I PEKERJAAN PERSIAPAN
1 1 m' Pagar sementara dari seng gelombang tinggi 2 m
Dolken kayu dia.8-10/400 1.250 Btg 18,150.00 22,687.50 225,171.15
Semen Portland 2.500 Kg 1,522.50 3,806.25
Seng Gelombang BJLS 30 1.200 Lbr 78,500.00 94,200.00
Pasir beton 0.005 M3 136,000.00 680.00
Koral Beton 0.009 M3 287,000.00 2,583.00
Kayu 5/7 0.072 M3 905,700.00 65,210.40
Paku 0.060 Kg 18,400.00 1,104.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 50,000.00 20,000.00
~ Tukang Kayu 0.200 Oh 60,000.00 12,000.00
~ Kepala Tukang 0.020 Oh 70,000.00 1,400.00
~ Mandor 0.020 Oh 75,000.00 1,500.00
2 1 m Pengukuran dan Pemasangan Bouwplank 50,666.90
- Patok Kayu 0.012 M3 2,657,000.00 31,884.00
- Paku 0.020 Kg 18,400.00 368.00
- Kayu Papan 3/20 0.007 M3 905,700.00 6,339.90
- Upah Pekerjaan
~ Pekerja 0.100 Oh 50,000.00 5,000.00
~ Tukang Kayu Text 0.100 Oh 60,000.00 6,000.00
~ Kepala Tukang 0.010 Oh 70,000.00 700.00
~ Mandor 0.005 Oh 75,000.00 375.00
3 1 m2 Pembuatan gudang semen dan alat-alat 566,488.25
- Dolken kayu dia.8-10/400 1.700 Btg 18,150.00 30,855.00
- Kayu 0.210 M3 905,700.00 190,197.00
- Paku 0.300 Kg 18,400.00 5,520.00
- Semen Portland 10.500 Kg 1,522.50 15,986.25
- Pasir beton 0.030 M3 136,000.00 4,080.00
- Koral Beton 0.050 M3 287,000.00 14,350.00
- Seng Gelombang BJLS 30 1.500 Lbr 78,500.00 117,750.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 50,000.00 50,000.00
~ Tukang Kayu 2.000 Oh 60,000.00 120,000.00
~ Kepala Tukang 0.200 Oh 70,000.00 14,000.00
~ Mandor 0.050 Oh 75,000.00 3,750.00
4 1 m2 Pembuatan rumah jaga/konstruksi kayu 589,303.20
- Dolken kayu dia.8-10/400 3.000 Btg 18,150.00 54,450.00
- Kayu 0.276 M3 905,700.00 249,973.20
- Paku 0.700 Kg 18,400.00 12,880.00
- Seng Gelombang BJLS 30 1.500 Lbr 78,500.00 117,750.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 50,000.00 50,000.00
~ Tukang Kayu 1.500 Oh 60,000.00 90,000.00
~ Kepala Tukang 0.150 Oh 70,000.00 10,500.00
~ Mandor 0.050 Oh 75,000.00 3,750.00
5 1 m2 Pembuatan Stegger dari bambu, ukuran (40x50x20) cm 36,935.00
- Bambu Ø 6-8 / 600 cm 1.000 Btg 20,000.00 20,000.00
- Tali ijuk 0.250 Kg 9,200.00 2,300.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 50,000.00 12,500.00
~ Tukang Kayu 0.017 Oh 60,000.00 1,020.00
~ Kepala Tukang 0.002 Oh 70,000.00 140.00
~ Mandor 0.013 Oh 75,000.00 975.00
6 1 m3 Bongkaran Beton Bertulang 365,530.00
- Pekerja 6.667 Oh 50,000.00 333,350.00
- Mandor 0.333 Oh 75,000.00 24,975.00
Alat
- Bodem 0.025 unit 135,000.00 3,375.00
- Keranjang 0.050 unit 11,500.00 575.00
- Gergaji Besi 0.068 unit 35,000.00 2,380.00
II PEKERJAAN TANAH
1 1 m3 Galian Tanah biasa sedalam 1 meter 39,375.00
- Pekerja 0.750 Oh 50,000.00 37,500.00
- Mandor 0.025 Oh 75,000.00 1,875.00
2 1 m3 Galian Tanah biasa 2 meter 48,375.00
- Pekerja 0.900 Oh 50,000.00 45,000.00
- Mandor 0.045 Oh 75,000.00 3,375.00
3 1 m3 Galian Tanah biasa 3 meter 57,525.00
- Pekerja 1.050 Oh 50,000.00 52,500.00
- Mandor 0.067 Oh 75,000.00 5,025.00
4 1 m3 Galian Tanah keras 1 meter 52,400.00
- Pekerja 1.000 Oh 50,000.00 50,000.00
- Mandor 0.032 Oh 75,000.00 2,400.00
5 1 m3 Galian cadas Keras 1 meter 79,500.00
- Pekerja 1.500 Oh 50,000.00 75,000.00
- Mandor 0.060 Oh 75,000.00 4,500.00
6 1 m3 Galian Lumpur sedalam 1 meter 63,375.00
- Pekerja 1.200 Oh 50,000.00 60,000.00
- Mandor 0.045 Oh 75,000.00 3,375.00
7 1 m' Galian bor Strouze (Dia =30 cm ) 67,225.00
- Pekerja 0.735 Oh 50,000.00 36,750.00
- Mandor 0.073 Oh 75,000.00 5,475.00
- Sewa Peralatan bor 1.000 ls 25,000.00 25,000.00
8 1 m' Pengeboran air tanah (sumur pompa) 49,400.00
- Pekerja 0.750 Oh 50,000.00 37,500.00
- Mandor 0.072 Oh 75,000.00 5,400.00
- Sewa Peralatan bor / tradisionil 1.000 ls 6,500.00 6,500.00
9 1 m3 Urugan kembali 13,125.00
- Pekerja 0.250 Oh 50,000.00 12,500.00
- Mandor 0.008 Oh 75,000.00 625.00
10 1 m3 Pemadatan tanah ( per 20 cm ) 28,750.00
- Pekerja 0.500 Oh 50,000.00 25,000.00
- Mandor 0.050 Oh 75,000.00 3,750.00
11 1 m3 Urugan Pasir Padat 105,750.00
- Pasir Urug 1.200 M3 75,000.00 90,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Mandor 0.010 Oh 75,000.00 750.00
12 1 m3 Urugan Sirtu Padat 140,550.00
- Sirtu 1.200 M3 104,000.00 124,800.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Mandor 0.010 Oh 75,000.00 750.00
13 1 m3 Urugan Sirtu Padat untuk peninggian lantai bangunan 139,175.00
- Sirtu 1.200 M3 104,000.00 124,800.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 50,000.00 12,500.00
~ Mandor 0.025 Oh 75,000.00 1,875.00
14 1 m3 Urugan Tanah Padat 99,750.00
- Tanah urug 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Mandor 0.010 Oh 75,000.00 750.00
15 1 m3 Urugan Paras Padat 105,750.00
- Tanah Paras 1.200 M3 75,000.00 90,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Mandor 0.010 Oh 75,000.00 750.00
IV PEKERJAAN PLESTERAN
1 1 m2 Plesteran 1 Pc : 2 Ps, tebal 15 mm 43,941.04
- Semen Portland 10.224 Kg 1,522.50 15,566.04
- Pasir Pasang 0.020 M3 110,000.00 2,200.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Tukang Batu 0.150 Oh 60,000.00 9,000.00
~ Kepala Tukang 0.015 Oh 70,000.00 1,050.00
~ Mandor 0.015 Oh 75,000.00 1,125.00
2 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm 40,543.96
- Semen Portland 7.776 Kg 1,522.50 11,838.96
- Pasir Pasang 0.023 M3 110,000.00 2,530.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Tukang Batu 0.150 Oh 60,000.00 9,000.00
~ Kepala Tukang 0.015 Oh 70,000.00 1,050.00
~ Mandor 0.015 Oh 75,000.00 1,125.00
3 1 m2 Plesteran 1 Pc : 5 Ps, tebal 15 mm 36,927.64
- Semen Portland 5.184 Kg 1,522.50 7,892.64
- Pasir Pasang 0.026 M3 110,000.00 2,860.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 50,000.00 15,000.00
~ Tukang Batu 0.150 Oh 60,000.00 9,000.00
~ Kepala Tukang 0.015 Oh 70,000.00 1,050.00
~ Mandor 0.015 Oh 75,000.00 1,125.00
V PEKERJAAN LANTAI
1 1 m2 Pasang Lantai Keramik 30 X 30 cm Putih KW I 120,618.50
- Keramik 30 x 30 cm 1.080 M2 49,450.00 53,406.00
- Semen Portland 10.000 Kg 1,522.50 15,225.00
- Pasir Pasang 0.045 M3 110,000.00 4,950.00
- Semen Warna 1.500 Kg 11,000.00 16,500.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 50,000.00 17,500.00
~ Tukang Batu 0.175 Oh 60,000.00 10,500.00
~ Kepala Tukang 0.018 Oh 70,000.00 1,225.00
~ Mandor 0.018 Oh 75,000.00 1,312.50
2 1 m2 Pasang Lantai Keramik 40 x 40 cm putih KW I 126,809.00
- Keramik 40 x 40 cm 1.105 M2 56,200.00 62,101.00
- Semen Portland 9.800 Kg 1,522.50 14,920.50
- Pasir Pasang 0.045 M3 110,000.00 4,950.00
- Semen Warna 1.300 Kg 11,000.00 14,300.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 50,000.00 17,500.00
~ Tukang Batu 0.175 Oh 60,000.00 10,500.00
~ Kepala Tukang 0.018 Oh 70,000.00 1,225.00
~ Mandor 0.018 Oh 75,000.00 1,312.50
3 1 m2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm 128,771.50
- Keramik 20 x 20 cm 1.060 M2 57,500.00 60,950.00
- Semen Portland 10.400 Kg 1,522.50 15,834.00
- Pasir Pasang 0.045 M3 110,000.00 4,950.00
- Semen Warna 1.500 Kg 11,000.00 16,500.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 50,000.00 17,500.00
~ Tukang Batu 0.175 Oh 60,000.00 10,500.00
~ Kepala Tukang 0.018 Oh 70,000.00 1,225.00
~ Mandor 0.018 Oh 75,000.00 1,312.50
4 1 m2 Pasang Lantai Keramik 30 x 30 cm Warna KW I 128,070.50
- Keramik 30 x 30 cm 1.080 M2 56,350.00 60,858.00
- Semen Portland 10.000 Kg 1,522.50 15,225.00
- Pasir Pasang 0.045 M3 110,000.00 4,950.00
- Semen Warna 1.500 Kg 11,000.00 16,500.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 50,000.00 17,500.00
~ Tukang Batu 0.175 Oh 60,000.00 10,500.00
~ Kepala Tukang 0.018 Oh 70,000.00 1,225.00
~ Mandor 0.018 Oh 75,000.00 1,312.50
5 1 m2 Pasang Lantai Keramik 30 x 30 cm Motif Kasar KW1 134,280.50
- Keramik 30 x 30 cm Kasar 1.080 M2 62,100.00 67,068.00
- Semen Portland 10.000 Kg 1,522.50 15,225.00
- Pasir Pasang 0.045 M3 110,000.00 4,950.00
- Semen Warna 1.500 Kg 11,000.00 16,500.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 50,000.00 17,500.00
~ Tukang Batu 0.175 Oh 60,000.00 10,500.00
~ Kepala Tukang 0.018 Oh 70,000.00 1,225.00
~ Mandor 0.018 Oh 75,000.00 1,312.50
VI PEKERJAAN ATAP
1 1 m3 Pasang Konstruksi Kuda-kuda Ekspose Kayu Kelas Kuat I 22,293,865.00
- Kayu Jati, balok 1.200 M3 16,905,000.00 20,286,000.00
- Besi Strip 15.00 Kg 13,200.00 198,000.00
- Paku Biasa 2" - 5" 5.60 Kg 18,400.00 103,040.00
- Upah Pekerjaan
~ Pekerja 6.700 Oh 50,000.00 335,000.00
~ Tukang Kayu 20.100 Oh 60,000.00 1,206,000.00
~ Kepala Tukang 2.010 Oh 70,000.00 140,700.00
~ Mandor 0.335 Oh 75,000.00 25,125.00
2 1 m3 Pasang Konstruksi Kuda-kuda konvensional kayu kelas I 19,915,540.00
- Kayu Jati, balok 1.100 M3 16,905,000.00 18,595,500.00
- Besi Strip 15.00 Kg 13,200.00 198,000.00
- Paku Biasa 2" - 5" 5.60 Kg 18,400.00 103,040.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 50,000.00 200,000.00
~ Tukang Kayu 12.000 Oh 60,000.00 720,000.00
~ Kepala Tukang 1.200 Oh 70,000.00 84,000.00
~ Mandor 0.200 Oh 75,000.00 15,000.00
3 1 m3 Pasang Konstruksi Kuda-kuda Kayu kelas II 8,277,540.00
- Kayu Meranti Asli, balok 1.100 M3 6,325,000.00 6,957,500.00
- Besi Strip 15.00 Kg 13,200.00 198,000.00
- Paku Biasa 2" - 5" 5.60 Kg 18,400.00 103,040.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 50,000.00 200,000.00
~ Tukang Kayu 12.000 Oh 60,000.00 720,000.00
~ Kepala Tukang 1.200 Oh 70,000.00 84,000.00
~ Mandor 0.200 Oh 75,000.00 15,000.00
PEKERJAAN
X PENGECATAN
1 1 m2 mendempul dan menggosok kayu 8,311.50
- Plamir Kayu 0.080 Kg 33,200.00 2,656.00
- Minyak Cat 0.020 kg 37,400.00 748.00
- Kertas gosok 0.010 Lbr 4,000.00 40.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 50,000.00 2,000.00
~ Tukang Cat 0.040 Oh 60,000.00 2,400.00
~ Kepala Tukang 0.004 Oh 70,000.00 280.00
~ Mandor 0.0025 Oh 75,000.00 187.50
2 1 m2 Pengecatan bidang kayu lama 17,602.30
- Cat Kayu 0.142 Kg 57,600.00 8,179.20
- Minyak cat 0.019 Lt 37,400.00 710.60
- Upah Pekerjaan
~ Pekerja 0.070 Oh 50,000.00 3,500.00
~ Tukang Cat 0.075 Oh 60,000.00 4,500.00
~ Kepala Tukang 0.0075 Oh 70,000.00 525.00
~ Mandor 0.0025 Oh 75,000.00 187.50
3 1 m2 Pengecatan bidang kayu baru 35,368.50
- Cat Kayu 0.260 Kg 57,600.00 14,976.00
- Plamir 0.150 Kg 33,200.00 4,980.00
- Cat Meni 0.200 Kg 33,300.00 6,660.00
- Kertas gosok 0.010 Lbr 4,000.00 40.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 50,000.00 3,500.00
~ Tukang Cat 0.075 Oh 60,000.00 4,500.00
~ Kepala Tukang 0.0075 Oh 70,000.00 525.00
~ Mandor 0.0025 Oh 75,000.00 187.50
4 1 m2 Pengecatan besi baru 39,143.50
- Cat besi Emco 0.260 Kg 57,600.00 14,976.00
- Cat Meni 0.200 Kg 43,100.00 8,620.00
- Kertas gosok 0.010 Lbr 4,000.00 40.00
- Plamir 0.150 Kg 45,300.00 6,795.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 50,000.00 3,500.00
~ Tukang Cat 0.075 Oh 60,000.00 4,500.00
~ Kepala Tukang 0.0075 Oh 70,000.00 525.00
~ Mandor 0.0025 Oh 75,000.00 187.50
5 1 m2 Pengecatan besi Finishing baru (Tanpa Cat dasar) 20,143.50
- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 57,600.00 14,976.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 50,000.00 1,750.00
~ Tukang Cat 0.053 Oh 60,000.00 3,180.00
~ Kepala Tukang 0.0020 Oh 70,000.00 140.00
~ Mandor 0.0013 Oh 75,000.00 97.50
6 1 m2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter 11,470.00
- Residu atau Ter 0.350 Ltr 17,200.00 6,020.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 50,000.00 5,000.00
~ Mandor 0.006 Oh 75,000.00 450.00
7 1 m2 Pelaburan Bidang Kayu dengan Politur 38,947.50
- Politur 0.372 Ltr 70,000.00 26,040.00
- Ampelas 2.000 Lbr 4,000.00 8,000.00
- Upah Pekerjaan
~ Tukang Cat 0.060 Oh 60,000.00 3,600.00
~ Kepala Tukang 0.016 Oh 70,000.00 1,120.00
~ Mandor 0.0025 Oh 75,000.00 187.50
8 1 m2 Pelaburan Bidang Kayu dengan Vernis 35,320.00
- Vernis 0.150 Ltr 92,000.00 13,800.00
- Dempul 0.050 Kg 40,250.00 2,012.50
- Ampelas 0.100 Lbr 4,000.00 400.00
- Kuas 0.010 Bh 20,000.00 200.00
- Upah Pekerjaan
~ Pekerja 0.160 Oh 50,000.00 8,000.00
~ Tukang Cat 0.160 Oh 60,000.00 9,600.00
~ Kepala Tukang 0.016 Oh 70,000.00 1,120.00
~ Mandor 0.0025 Oh 75,000.00 187.50
XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset duduk / monoblok 1,780,070.00
- Kloset duduk / monoblok 1.000 Bh 1,450,000.00 1,450,000.00
- Perlengkapan 0.060 hrg 1,450,000.00 87,000.00
- Upah Pekerjaan
~ Pekerja 3.300 Oh 50,000.00 165,000.00
~ Tukang Batu 1.100 Oh 60,000.00 66,000.00
~ Kepala Tukang 0.001 Oh 70,000.00 70.00
~ Mandor 0.160 Oh 75,000.00 12,000.00
2 Memasang 1 buah kloset jongkok porselen 417,235.00
- Kloset jongkok porselen 1.000 Bh 150,000.00 150,000.00
- Semen portland 6.000 Kg 1,522.50 9,135.00
- Pasir pasang 0.010 M3 110,000.00 1,100.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 50,000.00 50,000.00
~ Tukang Batu 1.500 Oh 60,000.00 90,000.00
~ Kepala Tukang 1.500 Oh 70,000.00 105,000.00
~ Mandor 0.160 Oh 75,000.00 12,000.00
3 Memasang 1 buah urinoir 1,473,735.00
- Urinoir 1.000 Bh 1,030,000.00 1,030,000.00
- Perlengkapan 0.300 hrg 1,030,000.00 309,000.00
- Semen portland 6.000 Kg 1,522.50 9,135.00
- Pasir pasang 0.010 M3 110,000.00 1,100.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 50,000.00 50,000.00
~ Tukang Batu 1.000 Oh 60,000.00 60,000.00
~ Kepala Tukang 0.100 Oh 70,000.00 7,000.00
~ Mandor 0.100 Oh 75,000.00 7,500.00
4 Memasang 1 buah wastafel 521,285.00
- Wastafel 1.000 Bh 315,000.00 315,000.00
- Perlengkapan 0.120 hrg 315,000.00 37,800.00
- Semen portland 6.000 Kg 1,522.50 9,135.00
- Pasir pasang 0.010 M3 110,000.00 1,100.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 50,000.00 60,000.00
~ Tukang Batu 1.450 Oh 60,000.00 87,000.00
~ Kepala Tukang 0.150 Oh 70,000.00 10,500.00
~ Mandor 0.010 Oh 75,000.00 750.00
5 Memasang 1 buah bak cuci stainless 266,212.50
- Bak cuci stainless 1.000 Bh 213,000.00 213,000.00
- Water drain dan accessories 1.000 set 31,500.00 31,500.00
- Upah Pekerjaan
~ Pekerja 0.030 Oh 50,000.00 1,500.00
~ Tukang Batu 0.300 Oh 60,000.00 18,000.00
~ Kepala Tukang 0.030 Oh 70,000.00 2,100.00
~ Mandor 0.0015 Oh 75,000.00 112.50
6 Memasang 1 buah bak mandi fiber glass 689,810.00
- Bak fiberglass 1.000 Bh 332,000.00 332,000.00
- Perlengkapan 0.180 hrg 332,000.00 59,760.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 50,000.00 90,000.00
~ Tukang Batu 2.700 Oh 60,000.00 162,000.00
~ Kepala Tukang 0.540 Oh 70,000.00 37,800.00
~ Mandor 0.1100 Oh 75,000.00 8,250.00
7 Memasang 1 pintu KM PVC 618,050.00
- Pintu PVC 1.000 Bh 320,000.00 320,000.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 50,000.00 90,000.00
~ Tukang Batu 2.700 Oh 60,000.00 162,000.00
~ Kepala Tukang 0.540 Oh 70,000.00 37,800.00
~ Mandor 0.1100 Oh 75,000.00 8,250.00