PENAWARAN HARGA

PEMBUATAN ABUTMENT & PIER KALIBONE

HARGA SATUAN JUMLAH


NO URAIAN PEKERJAAN SAT VOLUME
(Rp) (Rp)
A Abutment A1 & A2
1 Pancang Sheet Pile m' 348,00 70.000 24.360.000
2 Pemasangan Strut & Sabuk Hbeam 200 + Material ls 1,00 17.000.000 17.000.000
3 Potong Tiang Bored Pile titik 12,00 1.000.000 12.000.000
4 Galian Tanah s.d Lumpur m3 540,64 45.000 24.328.800
5 Coble Stones + Material m3 13,27 150.000 1.990.500
6 Cor Lantai Kerja K-175 m3 6,63 60.000 397.800
7 Bekisting + Material (Triplek 15 mm) m2 263,17 170.000 44.738.900
8 Pembesian (Upah + Kawat bendrat) kg 22.934,03 1.400 32.107.642
9 Beton K-350 m3 175,75 60.000 10.544.899

TOTAL 1 ABUTMENT : 167.468.541


TOTAL UNTUK 2 ABUTMENT : 334.937.081
B Pier
1 Bekisting + Material (Triplek 15 mm) m2 114,30 170.000 19.431.000
2 Pembesian Bored Pile (Upah + Kawat bendrat) kg 26.106,45 1.400 36.549.030
3 Pembesian Pier (Upah + Kawat bendrat) kg 29.384,84 1.400 41.138.776
4 Beton K-175 & K-350 m3 227,43 60.000 13.645.800

TOTAL PIER : 110.764.606


TOTAL UNTUK 2 ABUTMENT & 1 PIER : 445.701.687

Makasar, 24 Mei 2022

( Mas Mantep )