DAFTAR ISI
Daftar Isi............................................................................................................................................ 1
1. Pendahuluan.............................................................................................................................. 2
2. Lokasi dan jenis pekerjaan dan lingkup pekerjaan..................................................................... 2
3. Jalan Akses dan Persiapan Pekerjaan ........................................................................................ 4
4. Material dan Spesifikasi yang digunakan ................................................................................... 5
5. Uji Coba Kontruksi..................................................................................................................... 6
6. Alat yang digunakan .................................................................................................................. 7
8. Flow Chart .............................................................................................................................. 8
9. Action plan ........................................................................................................................... 10
8. Methode Konstruksi ............................................................................................................. 10
9. Personil dan Manpower........................................................................................................... 16
10. Quality Assurance.................................................................................................................... 17
11. Safety Assurance...................................................................................................................... 17
1
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
1. Pendahuluan
2
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
beam
TANGGUL
TANGGUL
3
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
4
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
7. Flow chart
8. Action plant
Action Plant Pekerjaan Fabrication and instalation of concrete block, 1.00m x1.00m x
0.07m dapat dilihat dalam lampiran.
2. Use the concrete vibrator to ensure that the pour is free of air bubbles and are
5
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
even
6
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
7
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
5. Formwork removal
6. Mobilisation precast
7. Mobilisation on stockyard
8
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
8. Mobilisation to site
9
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
10
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
11
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT
Method Statement
Manager Proyek
Kepala Pelaksana
Quality Control
Man Power
No. Manpower Unit Total
1. Kepala Pelaksana orang 1
2. Pelaksana orang 3
3. Pekerja grup 3
6. SHE grup 1
7. Surveyor grup 2
Membuat Garis keamanan di setiap batas pekerjaan dan pasang rambu himbauan untuk
memperingatkan bahaya yang dapat terjadi dalam pekerjaan tersebut.
Safety officer dilapangan akan memastikan para pekerja tidak menemui kondisi
berbahaya dengan briefing sebelum memulai pekerjaan.
Setiap accident akan di tangani oleh tim medis lapangan, jika itu berbahaya dan
membutuhkan penanganan lebih lanjut pekerja akan di bawa ke rumah sakit terdekat.
Make sure the vertical and horizontal alignment form is straight and neat
Coat formwork with oil
Make sure the formwork is strong to hold liquid concrete
On the formwork connection, make sure that there is no leak
13
ICB PACKAGE LSS-06 RENTANG IRRIGATION PROJECT