Anda di halaman 1dari 93

PETAK LUAS LUAS DAERAH IRIGASI FIX TOTAL

1 64.16 2321.84
2 75.53
3 104.35
4 84.33
5 116.29
6 114.44
7 62.36
8 118.52
9 87.37
10 92.36
11 85.79
12 72.36
13 62.23
14 67.86
15 97.09
16 115.16
17 64.32
18 113.65
19 123.03
20 103.38
21 128.67
22 62.36
23 78.42
24 72.09
25 70.94
26 84.78
DIKETAHUI

Efisiensi
Total = 0.7 0.075
NFR = 1.85 30.000
s = 0.0006

Kehilangan
Primer = 0.05
Sekunder = 0.05 30
E PS = 0.9
Tersier = 0.864198 0.001125

41.15714

Didapat 0.69997433
Efisiensi Primer = 0.075 0.925
Efisiensi Sekunder = 0.1 0.9
Efisiensi Tersier = 0.15 0.84081
Kehilangan Total = 30 %
Efisiensi = 70 %

PRIMER = 92.50%
SEKUNDER = 90%
TERSIER = 84%
0.1 0.15

0.840841

0.84
Tersier 84% Sekunder 90.000% Primer
Q Hidrologi

JENIS NAMA LUAS PAKAI (


DESA NFR Efisiensi Q ( l/dt ) Q ( m3/dt )
SALURAN SALURAN Ha )

KAS6-Kn 118.52 1.85 0.84 261.0262 0.26102619


TERSIER
KAS6-Kr 62.36 1.85 0.84 137.3405 0.13734048
SEKUNDER SSKAS5 180.88 1.85 0.9 371.8089 0.37180889
TERSIER KAS5-Kn 114.44 1.85 0.84 252.0405 0.25204048
SEKUNDER SSKAS4 295.32 1.85 0.9 607.0467 0.60704667
TERSIER KAS4-Kr 116.29 1.85 0.84 256.1149 0.25611488
DESA KRATON
AGUNG SEKUNDER SSKAS3 411.61 1.85 0.9 846.0872 0.84608722
SEJAGAT
TERSIER KAS3-Kn 84.33 1.85 0.84 185.7268 0.18572679
SEKUNDER SSKAS2 495.94 1.85 0.9 1019.432 1.01943222
TERSIER KAS2-Kr 104.35 1.85 0.84 229.8185 0.22981845
SEKUNDER SSKAS1 600.29 1.85 0.9 1233.929 1.23392944
TERSIER KAS1-Kn 75.53 1.85 0.84 166.3458 0.16634583
TERSIER KAS1-Kr 64.16 1.85 0.84 141.3048 0.14130476
RK5-Kn 115.16 1.85 0.84 253.6262 0.25362619
TERSIER
RK5-Kr 97.09 1.85 0.84 213.8292 0.21382917
SEKUNDER SSRK4 212.25 1.85 0.9 436.2917 0.43629167
RK4-Kn 67.86 1.85 0.84 149.4536 0.14945357
TERSIER
RK4-Kr 62.23 1.85 0.84 137.0542 0.13705417

DESA ROY SEKUNDER SSRK3 342.34 1.85 0.9 703.6989 0.70369889


KIYOSHI TERSIER RK3-Kn 72.36 1.85 0.84 159.3643 0.15936429
SEKUNDER SSRK2 414.7 1.85 0.9 852.4389 0.85243889
TERSIER RK2-Kr 85.79 1.85 0.84 188.9423 0.18894226
SEKUNDER SSRK1 500.49 1.85 0.9 1028.785 1.028785
TERSIER RK1-Kn 92.36 1.85 0.84 203.4119 0.2034119
TERSIER RK1-Kr 87.37 1.85 0.84 192.422 0.19242202
B5-Kn 70.94 1.85 0.84 156.2369 0.1562369
TERSIER
B5-Kr 72.09 1.85 0.84 158.7696 0.15876964
SEKUNDER SSB4 143.03 1.85 0.9 294.0061 0.29400611
B4-Kn 78.42 1.85 0.84 172.7107 0.17271071
TERSIER
B4-Kr 62.36 1.85 0.84 137.3405 0.13734048
SEKUNDER SSB3 283.81 1.85 0.9 583.3872 0.58338722
B3-Kn 128.67 1.85 0.84 283.3804 0.28338036
DESA BINOMO TERSIER
B3-Kr 103.38 1.85 0.84 227.6821 0.22768214
SEKUNDER SSB2 515.86 1.85 0.9 1060.379 1.06037889
DESA BINOMO

TERSIER B2-Kn 123.03 1.85 0.84 270.9589 0.27095893


SEKUNDER SSB1 638.89 1.85 0.9 1313.274 1.31327389
TERSIER B1-Kn 113.65 1.85 0.84 250.3006 0.2503006
TERSIER B1-Kr 64.32 1.85 0.84 141.6571 0.14165714
TERSIER B0 84.78 1.85 0.84 186.7179 0.18671786
PRIMER SPSE3 901.64 1.85 0.925 1803.28 1.80328
KABUPATEN
SUNDA PRIMER SPSE2 1581.86 1.85 0.925 3163.72 3.16372
EMPIRE
PRIMER SPSE1 2321.84 1.85 0.925 4643.68 4.64368
92.5000% ASUMSI SALURAN TANAH, KECUALI PRIMER BETON

Kemiringan
Talud ( 1 : b/h h/b b b pakai b Seharusnya h GoalSeek b/h aktual w
m)
1 1 1 0.581239 0.6 0.581239374 0.58123937 1 0.4
1 1 1 0.456583 0.5 0.456583498 0.4565835 1 0.4
1 1.5 0.666667 0.89235 0.9 0.5949 0.5949 1.5 0.4
1 1 1 0.573882 0.6 0.573881982 0.57388198 1 0.4
1 2 0.5 1.311 1.4 0.6555 0.6555 2 0.5
1 1 1 0.577128 0.6 0.577127541 0.57712754 1 0.4
1 2 0.5 1.4124 1.5 0.7062 0.7062 2 0.5
1 1 1 0.5116 0.6 0.5116 0.5116 1 0.4
1 2 0.5 1.514466 1.6 0.757233213 0.75723321 2 0.5
1 1 1 0.553757 0.6 0.553756627 0.55375663 1 0.4
1 2 0.5 1.627024 1.7 0.813512132 0.81351213 2 0.5
1 1 1 0.490864 0.5 0.490863967 0.49086397 1 0.4
1 1 1 0.461522 0.5 0.461522212 0.46152221 1 0.4
1 1 1 0.575145 0.6 0.575145119 0.57514512 1 0.4
1 1 1 0.539205 0.6 0.539205045 0.53920504 1 0.4
1 2 0.5 1.159024 1.2 0.579512187 0.57951219 2 0.5
1 1 1 0.472225 0.5 0.472224562 0.47222456 1 0.4
1 1 1 0.456197 0.5 0.456196566 0.45619657 1 0.4
1 2 0.5 1.3182 1.4 0.6591 0.6591 2 0.5
1 1 1 0.483266 0.5 0.483265917 0.48326592 1 0.4
1 2 0.5 1.489 1.5 0.7445 0.7445 2 0.4
1 1 1 0.5146 0.6 0.5146 0.5146 1 0.4
1 2 0.5 1.5198 1.6 0.7599 0.7599 2 0.5
1 1 1 0.529437 0.6 0.529436828 0.52943683 1 0.4
1 1 1 0.5189 0.6 0.5189 0.5189 1 0.4
1 1 1 0.479814 0.5 0.479814462 0.47981446 1 0.4
1 1 1 0.482612 0.5 0.482611954 0.48261195 1 0.4
1 1.5 0.666667 0.817295 0.9 0.544863507 0.54486351 1.5 0.4
1 1 1 0.497664 0.5 0.497664285 0.49766428 1 0.4
1 1 1 0.4569 0.5 0.4569 0.4569 1 0.4
1 2 0.5 1.292 1.3 0.646 0.646 2 0.5
1 1 1 0.599323 0.6 0.5993231 0.5993231 1 0.4
1 1 1 0.551843 0.6 0.551842734 0.55184273 1 0.4
1 2 0.5 1.537844 1.6 0.768922 0.768922 2 0.5
1 1 1 0.589333 0.6 0.589333 0.589333 1 0.4
1 2.5 0.4 1.93775 2 0.7751 0.7751 2.5 0.6
1 1 1 0.5718 0.6 0.5718 0.5718 1 0.4
1 1 1 0.462 0.5 0.462 0.462 1 0.4
1 1 1 0.513 0.6 0.513 0.513 1 0.4
1.5 2.5 0.4 1.684 1.7 0.6736 0.6736 2.5 0.25
1.5 3 0.333333 2.364 2.4 0.788 0.788 3 0.25
1.5 4 0.25 3.3258 3.4 0.83145 0.83145 4 0.3
PRIMER BETON 0.0174515207

Panjang P ( m^2 )
Sudut m h+w h+w pakai w pakai A (m^2) Basah R(m) k
M Basah

45 1 0.981239 1 0.418761 0.6756784203 2.2252325863 0.303644 35


45 1 0.856583 0.9 0.443417 0.4169369807 1.7479966473 0.238523 35
45 1 0.9949 1 0.4051 0.884765025 2.5749812965 0.343601 35
45 1 0.973882 1 0.426118 0.6586810595 2.1970653479 0.2998 35
45 1 1.1555 1.2 0.5445 1.28904075 3.1650339803 0.407275 35
45 1 0.977128 1 0.422872 0.6661523971 2.2094907323 0.301496 35
45 1 1.2062 1.3 0.5938 1.49615532 3.4098352355 0.438776 40
45 1 0.9116 1 0.4884 0.52346912 1.958623317 0.267264 35
45 1 1.257233 1.3 0.542767 1.7202064143 3.656245383 0.470484 40
45 1 0.953757 1 0.446243 0.613292804 2.1200168915 0.289287 35
45 1 1.313512 1.4 0.586488 1.9854059685 3.9279840462 0.505452 40
45 1 0.890864 0.9 0.409136 0.4818948681 1.8792369257 0.256431 35
45 1 0.861522 0.9 0.438478 0.4260055046 1.7669041556 0.241103 35
45 1 0.975145 1 0.424855 0.6615838152 2.2019011732 0.30046 35
45 1 0.939205 1 0.460795 0.58148416 2.0643072182 0.281685 35
45 1 1.079512 1.1 0.520488 1.0075031233 2.798132361 0.360063 35
45 1 0.872225 0.9 0.427775 0.4459920735 1.8078773214 0.246694 35
45 1 0.856197 0.9 0.443803 0.416230613 1.746515306 0.238321 35
45 1 1.1591 1.2 0.5409 1.30323843 3.1824163179 0.409512 40
45 1 0.883266 0.9 0.416734 0.4670918923 1.8501483437 0.252462 35
45 1 1.1445 1.2 0.4555 1.66284075 3.5947639944 0.462573 35
45 1 0.9146 1 0.4854 0.52962632 1.9701085984 0.268831 35
45 1 1.2599 1.3 0.5401 1.73234403 3.6691217721 0.472141 40
45 1 0.929437 1 0.470563 0.5606067107 2.0269103149 0.276582 35
45 1 0.9189 1 0.4811 0.53851442 1.986570835 0.271077 35
45 1 0.879814 0.9 0.420186 0.460443835 1.8369346993 0.250659 35
45 1 0.882612 0.9 0.417388 0.4658285964 1.8476446957 0.25212 35
45 1 0.944864 1 0.455136 0.7421906026 2.3584019821 0.314701 35
45 1 0.897664 0.9 0.402336 0.4953394809 1.9052714472 0.259984 35
45 1 0.8569 0.9 0.4431 0.41751522 1.7492083533 0.238688 35
45 1 1.146 1.2 0.554 1.251948 3.1191639226 0.401373 35
45 1 0.999323 1 0.400677 0.7183763564 2.2944648125 0.313091 35
45 1 0.951843 1 0.448157 0.6090608064 2.112689692 0.288287 35
45 1 1.268922 1.3 0.531078 1.7737231263 3.7126838416 0.477747 40
45 1 0.989333 1 0.410667 0.6946267698 2.2562184427 0.307872 35
45 1 1.3751 1.4 0.6249 2.102730035 4.1300638644 0.509128 40
45 1 0.9718 1 0.4282 0.65391048 2.1890946299 0.298713 35
45 1 0.862 0.9 0.438 0.426888 1.7687333316 0.241352 35
45 1 0.913 1 0.487 0.526338 1.963983115 0.267995 35
56.30993 0.666667 0.9236 1 0.3264 1.81494784 4.1126993392 0.441303 70
56.30993 0.666667 1.038 1.1 0.312 2.794248 5.2051744051 0.536821 70
56.30993 0.666667 1.13145 1.2 0.36855 3.8022000638 6.323635608 0.601268 70
i V Q Delta Q STATUS

0.0006 0.387305 0.261694 0.000668 OK


0.0006 0.329734 0.137478 0.000138 OK
0.0006 0.420578 0.372112 0.000304 OK
0.0006 0.38403 0.252953 0.000913 OK
0.0006 0.471052 0.607206 0.000159 OK
0.0006 0.385477 0.256786 0.000671 OK
0.0006 0.565759 0.846463 0.000375 OK
0.0006 0.355716 0.186206 0.00048 OK
0.0006 0.592697 1.01956 0.000128 OK
0.0006 0.374998 0.229984 0.000165 OK
0.0006 0.621711 1.234349 0.00042 OK
0.0006 0.346038 0.166754 0.000408 OK
0.0006 0.332107 0.14148 0.000175 OK
0.0006 0.384593 0.254441 0.000815 OK
0.0006 0.3684 0.214219 0.000389 OK
0.0006 0.433906 0.437162 0.00087 OK
0.0006 0.337222 0.150398 0.000945 OK 𝑷=𝒃+𝟐𝒉√(𝒎^𝟐+𝟏)
0.0006 0.329548 0.137168 0.000114 OK
0.0006 0.540315 0.704159 0.00046 OK
0.0006 0.342458 0.159959 0.000595 OK 𝑨=(𝒃+𝒎𝒉)𝒉
0.0006 0.512779 0.85267 0.000231 OK
0.0006 0.357106 0.189132 0.00019 OK
0.0006 0.594087 1.029164 0.000379 OK
0.0006 0.363937 0.204026 0.000614 OK
0.0006 0.359092 0.193376 0.000954 OK
0.0006 0.340826 0.156931 0.000694 OK
0.0006 0.342149 0.159383 0.000613 OK
0.0006 0.396651 0.294391 0.000385 OK
0.0006 0.349227 0.172986 0.000275 OK
0.0006 0.329886 0.137733 0.000392 OK
0.0006 0.46649 0.584021 0.000634 OK
0.0006 0.395298 0.283972 0.000592 OK
0.0006 0.374134 0.22787 0.000188 OK
0.0006 0.59878 1.062071 0.001692 OK
0.0006 0.390892 0.271524 0.000565 OK
0.0006 0.624722 1.313622 0.000348 OK
0.0006 0.383101 0.250514 0.000213 OK
0.0006 0.332337 0.14187 0.000213 OK
0.0006 0.356365 0.187568 0.000851 OK
0.0006 0.993875 1.803831 0.000551 OK
0.0006 1.132557 3.164645 0.000925 OK
0.0006 1.221478 4.644305 0.000625 OK
𝟐+𝟏)

=(𝒃+𝒎𝒉)𝒉
PERHITUNGAN HIDROLIKA CEK DIMENSI
h jagaan
SALURAN Luas Pakai NFR Efisiensi Q ( l/dt ) Q ( m3/dt ) ( 1 : m ) b/h k i h min h total Material b b h h total i k A ( m^2 ) P R V Q CEK SELISIH

RK1-Kr 87.37 1.85 0.84 192.4220238 0.192422024 1 1 35 0.0006 0.5179 0.4 1 Tanah 0.517938285 0.55 0.517938285 1 0.0006 35 0.553126124 2.014950695 0.274510997 0.362118045 0.200296951 OKE 0.0079
RK1-Kn 92.36 1.85 0.84 203.4119048 0.203411905 1 1 35 0.0006 0.5288 0.4 1 Tanah 0.528839164 0.6 0.528839164 1 0.0006 35 0.59697436 2.095783037 0.284845497 0.371150379 0.22156726 OKE 0.0182
TERSIER
KAS1-Kr 64.16 1.85 0.84 141.3047619 0.141304762 1 1 35 0.0006 0.4613 0.4 0.9 Tanah 0.461308303 0.5 0.461308303 0.9 0.0006 35 0.443459503 1.804776918 0.245714303 0.336328725 0.149148169 OKE 0.0078
KAS1-Kn 75.53 1.85 0.84 166.3458333 0.166345833 1 1 35 0.0006 0.4904 0.4 0.9 Tanah 0.490412968 0.55 0.490412968 0.9 0.0006 35 0.510232011 1.93709734 0.263400295 0.352279881 0.179744472 OKE 0.0134
SSRK1 500.49 1.85 0.9 1028.785 1.028785 1 2 40 0.0006 0.7598 0.5 1.75 Tanah 1.519590288 1.55 0.759795144 1.3 0.0006 40 1.754971135 3.699025195 0.47444152 0.5960153 1.045989648 OKE 0.0172
SEKUNDER
SSKAS1 600.29 1.85 0.9 1233.929444 1.233929444 1 2 40 0.0006 0.8134 0.5 1.85 Tanah 1.626816799 1.65 0.813408399 1.4 0.0006 40 2.003757083 3.95066638 0.507194709 0.623139707 1.248620602 OKE 0.0147
SPSE3 901.64 1.85 0.925 1803.28 1.80328 1.5 2 60 0.0006 0.7593 0.25 1.1 Pasangan 1.518642883 1.55 0.759321442 1.1 0.0006 60 2.041801812 4.287772392 0.476191744 0.896220313 1.829904259 OKE 0.0266
PRIMER SPSE2 1581.86 1.85 0.925 3163.72 3.16372 1.5 2 60 0.0006 0.9375 0.25 1.2 Pasangan 1.875021435 1.9 0.937510718 1.2 0.0006 60 3.099659882 5.280242964 0.587029783 1.030386831 3.193848724 OKE 0.0301
SPSE1 2321.84 1.85 0.925 4643.68 4.64368 1.5 2 60 0.0006 1.0826 0.3 1.4 Pasangan 2.165236446 2.25 1.082618223 1.4 0.0006 60 4.193984327 6.153435515 0.681567933 1.138237724 4.773751176 OKE 0.1301

Saluran Luas Pakai Dm Qd Q ( m3/dt ) ( 1 : m ) b/h k i h h jagaan h tot Material b b h h total i k A ( m^2 ) P R V Q CEK SELISIH
PEMBUANG

RK3-Kn 72.36 4 332.899911271553 0.332899911 1 1 30 0.0006 0.67399 0.4 1.1 Tanah 0.673992632 0.7 0.673992632 1.1 0.0006 30 0.92606091 2.606339041 0.355310992 0.368640157 0.341383239 OKE 0.00848

Top Notch
= 3.827964 1.913982162
= 4.85 2.425

𝑨=(𝒃+𝒎𝒉)𝒉 𝑷=𝒃+𝟐𝒉√(𝒎^𝟐+𝟏)
BSE2
Elevasi Muka Air = 14.1
Elevasi Dasar = 12.74068
SPSE3 = 12.74068
SPSE2 = 13.16249
Rk1 Kn = 13.17116
BSE1
SPSE2 = Jarak
I = 0.0006
Elevasi = 0.8964
4 Gorong = 0.05
1 Siphon = 0.1
Total = 1.1964

Elevasi SPSE2 Hulu


= 15.3

Elevasi Muka Air = 15.65


Elevasi Dasar = 13.18659
SSKAS 1 = 13.18659
KAS1-Kn = 13.40959
KAS1-Kr = 13.33869
SPSE2 = 14.36249
SPSE1 = 14.56738
m
SSRK1 = 13.0402
RK1-Kr = 13.38206

1494 m

m
15.55

13.04
13.17116

m
m
m
m
m
m
m
BANGUNAN

Jenis Elevasi a ( bukaan Hp ( ketinggian air


Bangunan Saluran Elevasi Air z Q g u √2gz h air b saluran n pintu b pilar b pintu B bruto Bahan Pintu
Saluran Dasar pintu ) bangunan sadap +0.1 )

RK1-Kn 13.7 0.2 0.203412 9.81 0.8 1.980909 0.528839 13.1711608 0.6 1 0 0.6 0.7 0.21392948 Baja 1.0375
Tersier
RK1-Kr 13.9 0.2 0.192422 9.81 0.8 1.980909 0.517938 13.3820617 0.55 1 0 0.55 0.65 0.22076875 Baja 0.8175
B SE 2
Sekunder SSRK1 13.8 0.2 1.028785 9.81 0.8 1.980909 0.759795 13.0402049 1.55 2 0.2 0.675 0.775 0.48087962 Baja 1.0375
Primer SPSE 3 13.5 0.3 1.80328 9.81 0.8 2.426108 0.759321 12.7406786 1.55 2 0.2 0.675 0.775 0.68822316 Baja 1.0375
Baja + Pelat
KAS 1 - Kn 13.9 0.2 0.166346 9.81 0.8 1.980909 0.490413 13.409587 0.55 1 0 0.55 0.65 0.19085114 0.290851136818091
Beton
Tersier
Baja + Pelat
KAS 1 - Kr 13.8 0.2 0.141305 9.81 0.8 1.980909 0.461308 13.3386917 0.5 1 0 0.5 0.6 0.17833324 0.278333242844878
Beton
B SE 1
Baja + Pelat
Sekunder SSKAS1 14 0.2 1.233929 9.81 0.8 1.980909 0.813408 13.1865916 1.65 2 0.2 0.725 0.825 0.53699203 0.636992028858501
Beton
Baja + Pelat
Primer SPSE 2 15.3 0.35 3.16372 9.81 0.8 2.620496 0.937511 14.3624893 1.9 2 0.2 0.85 0.95 0.88771919 0.98771918940069
Beton

0.4 2 0.7175
….. 0.2 0 0.34185686
0.3 1
0.6 3
13.04
13.24
Lapangan
L = 1626 m 13.5
Delta H = 2.25 m
SSRK1
Rencana 542
i = 0.0006
Delta L = 0.9756 m
1.28
Bangunan Terjun
H = 1.2744 m
Q = 1.028785 m3/s
Digunakan h = 0.6372 m
n bangunan terjun = 2
= 2 Buah

H1 = 0.759795 m
Delta H =
Hd = 1.268858
g = 9.81 m2/s
q = 1.028785
n =
RUMUS GA JELAS

h1 = 0.759795 m
V = 0.596015 m/s
g = 9.81 m2/s
H = 0.777901 m
Q = 1.028785 m3/s
m = 1
B = 0.88 m
dc = 0.538399 m
a = 0.2692 m
z = 0.6372 m
C1 = 3.851704 m
L = 1.571396

h' = 0.2692 m
L = 2.25602 m
Digunakan = 2.25602 m
0.379898

0.44
Gambar
t = 0.698498
L1 = 1.5 Digunakan 1.75
L2 = 2.25602 m
a = 0.2692 m
15.156
11.25 13.696 0.34
13.356 13.273
12.597 0.759 12.514 0.759

13.614
Sanggah 2%
Bukankah itu lebih menguntungkan kontraktor
Diketahui Aliran Tertutup
B SE 2a = KM 3.845
SPSE3
g = 9.81
h air = 0.75932144 m
b = 1.55 m
i = 0.0006
Q = 1.80328 m3/s
Direncanakan Gorong Gorong
D = 0.65 m
A = 0.3316625 m2
n gorong = 2
Q pakai = 0.90164 m3/s
u = 0.9 ( Bulat )
z = 0.46503922 m

Perencanaan Detail
Sig Masuk = 0.55
Sig Keluar = 1.1

Delta H Masuk
V2 = 1.5 m/s 1.5
V1 = 0.89622031 m/s
Delta H M = 0.01021929 m

Delta H f
V2 = 1.5 m/s
L = 8m
k = 70
R = 0.1625
C = 51.7098884
Delta H f = 0.02761727 m

Delta H Keluar
V3 = 0.89622031 m/s
V2 = 1.5
Delta H k = 0.02043858 m

Total Delta H
= 0.05827513 m
= 5.82751328 cm
I gor = 0.00728439

Kalau Gorong Gorong Segi Empat


Q = 1.80328 m3/s
V sal = 0.89622031 m/s
b = 1.55
h = 0.75932144
b box = 1.55
h box = 0.6 13.356
u = 0.8 0.1142
A = 0.93 13.2418
g = 9.81
Sig Masuk = 0.3
Sig Keluar = 0.6
K = 60
R = 0.21627907
c = 46.4858025
L = 8m
V gor = 1.93901075 m/s
Del H m = 0.01662709 m
Del H f = 0.06435692 m
Del H k = 0.03325419 m
Total Del = 0.1142382 m
= 11.4238202 cm
I gor = 0.00804462 0.00008
SIPHON

SKALA 1: 500
Bangunan D

KERTAS
cm cm
Titik Jarak REAL ACAD
47 0
46 1 0.1 50 500
45 2 0.05 25 250
44 3 0.04 20 200
43 4 0.025 12.5 125
42 5 0.025 12.5 125
41 6 0.04 20 200
40 7 0.02 10 100
39 8 0.2 100 1000
38 9 0.1 50 500
37 10 0.2 100 1000
36 11 0.25 125 1250
36 12 1.457 728.5 7285
37 13 0.8 400 4000
38 14 0.9 450 4500 Siphon Bangunan di Saluran SPSE
39 15 0.17 85 850
40 16 0.1 50 500 Q
41 17 0.12 60 600 b
42 18 0.1 50 500 h air
43 19 0.1 50 500 h saluran
44 20 0.001 0.5 5 A
45 21 0.1 50 500 v
46 22 0.002 1 10
47 23 0.1 50 500 Direncanakan Siphon
Penampang
2500 diameter
Luas
v

KISI KISI PENYARING

Beta
s
b
Cacing Alfa
c
delta Hf

1 0.25 1
Pemasukan

Sigma Masuk
Vo
V1
Delta Hm

Pengeluaran

Sigma Keluar
V2
Va
Delta Hk

Gesekan Sepanjang Pipa

Panjang
k
R
C
Delta Hf

Belokan pertama dan dua sama


Sudut
Kb
Va
delta Hb

TOTAL KEHILAGAN ENERGI

Delta H TOT

Maka Diperlukan Pompa untuk mengur


Bangunan di Saluran SPSE 2

= 3.16372 m3/s
= 1.9 m
= 0.937511 m
= 1.2 m
= 3.09966 m2 1
= 1.030387 m/s

DOBEL Hf = 𝒄 𝒗^𝟐/𝟐𝒈
= Double Lingkaran C= β 〖 (𝒔/𝒃) 〗 ^(𝟒/𝟑). Sin δ
= 1m
dimana :
= 0.785398 m2
hf = kehilangan tinggi energi, m
= 2.014087 m/s OKE OCE
v = kecepatan melalui kisi – kisi, m/dt
g = percepatan gravitasi, m/dt² (≈ 9,8)
c = koefisien berdasarkan :
= 1.8 β = fakor bentuk (2,4 untuk segi empat, dan 1.8 untuk
= 10 mm jeruji bulat)
= 100 mm s = tebal jeruji, m
b = jarak bersih antar jeruji, m
δ = sudut kemiringan dari bidang horisontal

 
c = koefisien berdasarkan :
β = fakor bentuk (2,4 untuk segi empat, dan 1.8 untuk
jeruji bulat)
s = tebal jeruji, m
= 75 derajat b = jarak bersih antar jeruji, m
= 0.080702
δ = sudut kemiringan dari bidang horisontal
= 0.016686 m
= 1.668554 cm  

= 0.1
= 1.030387 m/s
= 2.014087 m/s
= 0.004932 m/s dimana :
= 0.493204 cm ∆Hm = kehilangan energi pada pemasukan, m.
∆Hk= kehilangan energi pada pengeluaran, m.
= faktor kehilangan energi, yang tergantung pada bentuk hidrolis peralihan. (
=0.1-0.3, Koef Keluar = 0.5)
Va = kecepatan aliran rata-rata di dalam bangunan, m/dt.
V1,V2 = kecepatan aliran rata-rata di saluran hulu dan hilir, m/dt.
= 0.5 g = percepatan gravitasi, m/dt2
= 1.030387
= 2.014087
= 0.02466 m
= 2.466018 cm

anjang Pipa

= 28.85 m dimana : ∆Hf = kehilangan energi akibat gesekan, m.


= 70 V = kecepatan aliran di dalam bangunan.
= 0.25 L = panjang bangunan, m/dt2
= 55.55904 R = jari-jari hidrolis, m.
= 0.151654 m A = luas penampang basah, m2
= 15.16536 cm
P = keliling basah, m.
C = koefisien Chezy = k . R1/6
pertama dan dua sama
= 45 derajat k = koefisien kekasaran Strickler
= 0.24 0.24
= 2.014087
= 0.049621 m 67
= 4.962135 cm

AGAN ENERGI

= 29.71741 cm

ukan Pompa untuk mengurangi kehilangan energi


60 67 75
0.47 0.624 0.8
0.154
Z = ∆ hf + ∆ Hm+ ∆ Hf + ∆ Hb1 + ∆ Hb2 + ∆ Hk
 
Dimana :
∆ hf = Kehilangan energi akibat kisi-kisi
penyaring.
∆ Hm = Kehilangan energi akibat bagian
pemasukan
∆ Hf = Kehilangan energi akibat gesekan
sepanjang pipa
∆ Hb1 = Kehilangan energi akibat adanya
tikungan/belokan
∆ Hb2 = ∆ Hb1
∆ Hk= Kehilangan energi akibat bagian keluar
pipa

0.3 0.1 1 0.1 0.25 0.1

3.25

n 1.8 untuk
Itungan Elevasi Gambar
n 1.8 untuk

Intake SPSE 2

ung pada bentuk hidrolis peralihan. (Koef. Masuk

m bangunan, m/dt.
saluran hulu dan hilir, m/dt.

ekan, m.

15
0.33
1 0.1 0.3
i

Rating Curve 0.5

H air (m) A (mm2) A Kum A (m2) P (mm) P (m) R (m) n 1/n

5.5 12250000 1.12E+08 112.2713 55284.95 55.28 2.030774 0.04 25


5 11935000 1E+08 100.0213 52870.75 52.87 1.891807 0.04 25
4.5 11695000 88086250 88.08625 51551.65 51.55 1.708699 0.04 25
4 11487500 76391250 76.39125 49606 49.61 1.53996 0.04 25
3.5 11298750 64903750 64.90375 48460.6 48.46 1.33931 0.04 25
3 10967500 53605000 53.605 47613.1 47.61 1.125846 0.04 25
2.5 10617500 42637500 42.6375 44667.5 44.67 0.954553 0.04 25
2 10067500 32020000 32.02 42676.55 42.68 0.750295 0.04 25
1.5 9355000 21952500 21.9525 39351.4 39.35 0.557858 0.04 25
1 7642500 12597500 12.5975 36308.15 36.31 0.346961 0.04 25
0.5 4955000 4955000 4.955 25162.4 25.16 0.196921 0.04 25
0 0 0 0 0 0 0 0.04 25

Debit = 130 m 6
Didapatkan Tinggi Air adalah = 4.3 m

4
Kedalaman sungai (m)

0
0.00
2

Ke
1

0
0.00
= 1854 IKI HIL GARAPANE
4
0.002157 Area
H A Tiap A KumulatiP
5.5 49 449.085 110.5699
5 47.74 400.085 105.7415
4.5 46.78 352.345 103.1033
4 45.95 305.565 99.212
i Q (m3/s)
3.5 45.195 259.615 96.9212
0.002157 209.05 3 43.87 214.42 95.2262
0.002157 177.64 2.5 42.47 170.55 89.335
0.002157 146.18 2 40.27 128.08 85.3531
0.002157 118.28 1.5 37.42 87.81 78.7028
0.002157 91.56 1 30.57 50.39 72.6163
0.002157 67.36 0.5 19.82 19.82 50.3248
0.002157 47.99 0 0
0.002157 30.70
0.002157 17.27
0.002157 7.22
0.002157 1.95
0.002157 0

Rating curve
6

4
Kedalaman sungai (m)

0
0.00 50.00 100.00 150.00 200.00 250.00

Debit (m3/s)
2

Ke
1

0
0.00 50.00 100.00 150.00 200.00 250.00

Debit (m3/s)

4.77351 = 1.71 2.1 1.208933 1.5


4.7733

1.209326
1.329888
Estimasi Elevasi Muka Air Butuh

Air Pucuk B SE 1 masuk SPSE 2 = 15.3 m


Elevasi Pucuk = 15.5
L = 2350 m
I = 0.0006
= 1.41
Elevasi Air Butuh = 16.91 m Curam
Antisipasi Angin = m Tambahan Saluran Sepan
Jembatan = 0.1 m 1894
Alat Ukur = 0.272042 m
Pintu = 0.2 m Penampang Kontur saya
Elevasi Air Butuh = 17.48204 meter wakakaka

Alat Ukur SEK


〖 𝐐 =𝑪𝒅. 𝑪𝒗.(𝟐 )/𝟑 √(𝟐/𝟑.𝒈. )
Asumsi Pake alat ukur Drempel
𝒃.𝒉𝟏 〗 ^(𝟏.𝟓)
〖 𝐐 =𝑪𝒅. 𝑪𝒗.(𝟐 )/𝟑 √(𝟐/𝟑.𝒈. )
𝒃.𝒉𝟏 〗 ^(𝟏.𝟓)
Q sal = 4.773751 m3/s 〖𝐐 =𝟏,𝟕𝟏 𝒃.𝒉𝟏 〗 ^(𝟏.𝟓)
b = 2.25 m
h air = 1.082618 m Q = debit m3/dt
v = 1.138238 m/s Cd = koefisien debit
h = 1.15466 Cd adalah 0,93 + 0,10 H1/L, for 0,1 < H1/L < 1,0
= 115.466 cm
H1 adalah tinggi energi hulu, m
Cek Kemampuan Untuk ukur debit min L adalah panjang mercu, m
Q min = 1.432125 Cv = Koefisien kecepatan datang
h = 0.51745
= 51.74499 cm
g = percepatan gravitasi, m/dt2 (≈9,81)
Batas 5 Cm bc = lebar mercu, m
h1 = kedalaman air hulu terhadap ambang bangunan ukur, m
Kehilangan Energi Drempel
asumsi h = 0.2 m
z = 0.272042 m

Q = 4.773751
h air 〖 𝐐 =𝑪𝒅. 𝑪𝒗.(𝟐
bc = 2.1
Cv = 1
𝒃.𝒉𝟏 〗 ^(𝟏.𝟓)
Cd =
H1
L
g =
= Ambang Tajam, jangan dipake di daerah yang datar
Tambahan Saluran Sepanjang 1894 Meter
0.0006
1.1364 = 18.61844 +++ 842
Penampang Kontur saya sangat landai 335
FIX ANJAY ELEVASI 18 317
724
245
20 18.58 2463
√(𝟐/𝟑.𝒈. )
√(𝟐/𝟑.𝒈. )

𝒉𝟏 〗 ^(𝟏.𝟓)

1 < H1/L < 1,0

343
121
385
849
,81)

ambang bangunan ukur, m

=𝑪𝒅. 𝑪𝒗.(𝟐 )/𝟑 √(𝟐/𝟑.𝒈. )


^(𝟏.𝟓)
BENDUNG
Elevasi Muka Air Intake Butuh = 18.62 m
Elevasi Mercu Bendung = 18.72 m
Elevasi Tebing Bendung = 21 m
Tinggi Air Sungai = 4.3 m
Tinggi Sungai = 5.5 m
Tinggi Mercu Bendung = 3.22 meter

PINTU PEMBILAS ( Awal )


Direncanakan Pintu Pembilas = 2 Buah
Q pembilas = 19.5 m3/s
b pembilas = 1.25 m
h banjir = 4.3 m

LEBAR EFEKTIF BENDUNG


H1 mis = 2.021 m
b sungai = 25 Meter
Pintu Pembilas = 1.25 Meter
Lebar Pilar Pembilas = 1 Meter Bentuk pilar/tembok
Jumlah pilar pembilas = 1
 Pilar berujung segi empat dan
Banyak Pilar = 2 Buah
B Pilar = 1 dibulatkan dengan jari-jari y

Lebar Pangkal Bendung ( B ) = 19.5 Meter dengan 0.1 kali tebal pilar
Tipe Pilar = Pilar Berujung Bulat  Pilar berujung bulat
Kp = 0.01  Pilat berujung runcing
Beff = 19.41916 Meter
 Pangkal tembok segi empat den
arah aliran
Perhitungan H1 ITERASI 1
Rumus Pengaliran adalah sebagai berikut:  Pangkal tembok bulat dengan t
 
𝑸=𝟐/𝟑 𝑪𝒅√(𝟐/𝟑. 𝒈 )Be. H1 1.5
aliran di mana 0.5 H1 >r>0.15 H
 Pangkal tembok bulat di mana
dari 450 ke arah aliran
Q = 130 m3/s
Cd = 1.38
H1 = 2.008 Meter

Perhitungan Hd
V = 0.99465 m/s
Hd = 1.957547 m
H1 = 2.007971 Meter
H1/Hd = 1.025759
P/H1 = 1.603609
P/Hd = 1.644916

Direncanakan dengan Mercu Ogee

Co = 1.38
C1 = 0.99
Kemiringan Ogee Vertikal = 1:01
C2 = 1
Cd Tot = 1.3662

Perhitungan H1 ITERASI 2
Rumus Pengaliran adalah sebagai berikut:
 
𝑸=𝟐/𝟑 𝑪𝒅√(𝟐/𝟑. 𝒈 )Be. H11.5

Q = 130 m3/s
Cd = 1.3662
H1 = 2.021 Meter

Perhitungan Hd
V = 0.992088 m/s
Hd = 1.971305 m
H1 = 2.02147 Meter
H1/Hd = 1.025448
P/H1 = 1.5929
P/Hd = 1.633436

Direncanakan dengan Mercu Ogee

Co = 1.38
C1 = 0.99
Kemiringan Ogee Vertikal = 1:01
C2 = 1
Cd Tot = 1.3662

Perhitungan H1 ITERASI 3
Rumus Pengaliran adalah sebagai berikut:
 
𝑸=𝟐/𝟑 𝑪𝒅√(𝟐/𝟑. 𝒈 )Be. H11.5

Q = 130 m3/s
Cd = 1.3662
H1 = 2.021 Meter

Perhitungan Hd
V = 0.992088 m/s
Hd = 1.971305 m
H1 = 2.02147 Meter
H1/Hd = 1.025448
P/H1 = 1.5929
P/Hd = 1.633436
Direncanakan dengan Mercu Ogee

Co = 1.38
C1 = 0.99
Kemiringan Ogee Vertikal = 1--1
C2 = 1
Cd Tot = 1.3662

H1 pada Iterasi 2 & 3 Sudah sama, maka dapat disimpulkan

H1 = 2.02147 Meter
Cd = 1.3662
Hd = 1.971305 Meter

Cek Nilai Q
Rumus Pengaliran adalah sebagai berikut:
 
𝑸=𝟐/𝟑 𝑪𝒅√(𝟐/𝟑. 𝒈 )Be. H11.5

Q = 130 m3 YOI

Desain Mercu

hd = 1.971305 Meter
k = 2
n = 1.85

X^1.836= 1.939hd^0.836y
x = K/hd^(n-
y (m) 1).y (m)

0 0 0
0.2 0.8290179976 829.018
0.4 1.2158468493 1215.847 0 0.5 1 1.5
0.6 1.5211318581 1521.132 0

0.8 1.783174268 1783.174


0.5
1 2.0171362404 2017.136
1.2 2.2309085959 2230.909
1
1.4 2.4292317766 2429.232
1.6 2.6152228562 2615.223 1.5
1.8 2.7910638084 2791.064
2 2.9583540401 2958.354 2
2.2 3.1183081778 3118.308
2.4 3.2718749115 3271.875 2.5
2.6 3.4198123408 3419.812
2.8 3.5627378543 3562.738 3

3 3.7011623465 3701.162
3.2 3.8355144028 3835.514
3.22 3.8487401163 3848.74
3.4 3.9661578327 3966.158
3.6 4.0934046638 4093.405
3.8 4.2175249569 4217.525
4 4.3387543446 4338.754
4.2 4.45729991 4457.3

0.237hd = 0.467199 m
0.139hd = 0.274011 m
R 0.21 hd = 0.413974 m
R 0.68 hd = 1.340487 m

Desain Pintu Pembilas ( Lanjutan )


Direncanakan Pintu Pembilas = 2 Buah
Q pembilas = 19.5 m3/s
b pembilas = 1.25 m
h banjir = 4.3 m
H1 = 2.02147 m
z = 0.94147 m
a = 1.055672 m
Bentuk pilar/tembok Kp Ka
 Pilar berujung segi empat dan sudut-sudut yang
dibulatkan dengan jari-jari yang hampir sama
dengan 0.1 kali tebal pilar 0.02
 Pilar berujung bulat 0.01
 Pilat berujung runcing 0.00
0
 Pangkal tembok segi empat dengan tembok hulu pada 90 ke
arah aliran 0.20
 Pangkal tembok bulat dengan tembok hulu pada 90 0 ke arah
aliran di mana 0.5 H1 >r>0.15 H1 0.10
 Pangkal tembok bulat di mana r > 0.5 H1 dan tembok lebih
dari 450 ke arah aliran 0.00
Mercu Ogee
Tipe mercu ini pertama kali diperkenalkan oleh US Army
Corps of Engineers. Pembentukan mercunya didasarkan pada
persamaan berikut, lihat Gambar 2.14.
Xn = K . hdn-1 . Y
Keterangan
X dan Y = Koordinat permukaan hilir.
Hd = Tinggi muka air diatas mercu
K dan n = Parameter yang tergantung dari kemiringan
bidang hulu, lihat Tabel 1.3
Koefisien debit, diambil sebagai berikut:
C0 = Konstanta = 1,30
C1 = Fungsi dari p / hd dan H1 / hd
C2 = Faktor koreksi bidang hulu

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5


0

0.5

1.5

2.5

3
Menentukan Tipe Kolam Olak dengan menentukan bilangan Froude

P = 3.22 meter
Q banjir = 130 meter
Beff sungai = 19.41916 meter
H1 = 2.02147 meter
vu = 7.948358 m/s
q = 6.694419 m3/s
yu = 0.842239
Fr = 1.955286

Karena 2.5 < Fr < 4.5, digunakan kolam tipe USBR Tipe IV

d2 = 1.67H1 = 3.375855 m
L/d2 = 4.15
L = 14.0098 m
d1=yu = 0.842239 meter
1.25d1 = 1.052799 meter
2d1 = 1.684478 meter
2.5w = 2.105598 meter
Perhitungan Titik Pusat Konstruksi Bendung
Direncanakan bentuk konstruksi bendung seperti pada gambar di bawah
G Beton = 2.4 t/m2

Properties(mm)
Luas Area = 21708882 mm2 =
Horizontal= 3481 mm2 =
Vertikal = 2926 mm2 =
Berat = 50.69 t/m

Analisa Stabilitas Bendung - Muka Air Banjir


Gaya Tekan Air dalam ( Uplift Presure )
Hd = 1.971305130849 m
H2 = 3.37585523911 m
Delta H = 2.895449891738 m

0.5
0.5 0 3 4
0.5
1 2 5
6
0.5 23 1
1.13
7
0.3
1 3 1

Lv = 10.33 m
Lh = 45.17579924231 m
ΣLx = 25.38859974744 m

C = 3
Delta H = 2.895449891738 m

Gaya Uplift Presure


Panjang Rembesan
No Titik ∆H (m)
Lv (m) Lh (m) 1/3 Lh (m)
1 2 3 4 5
0 2.8954 0 0 0
1 2.8954 1 0 0
2 2.8954 1 0.5 0.1666666667
3 2.8954 1.5 0.5 0.1666666667
4 2.8954 1.5 23.500 7.8333333333
5 2.8954 2.5 23.500 7.833
6 2.8954 2.5 24.500 8.167
7 2.8954 3.5 24.500 8.167
8 2.8954 3.5 27.500 9.167
9 2.8954 4.5 27.500 9.167
10 2.8954 4.5 28.500 9.500
11 2.8954 5.63 28.500 9.500
12 2.8954 5.63 30.366 10.122
13 2.8954 5.93 30.366 10.122
14 2.8954 5.93 32.366 10.789
15 2.8954 7.03 44.376 14.792
16 2.8954 7.68 44.376 14.792
17 2.8954 7.68 45.176 15.059
18 2.8954 10.33 45.176 15.059

Lv + (1/3)Lh ≥ C x ΔH
22.472 ≥ 8.69 OK

Gaya gaya yang bekerja

hd

Ha
Plu

Gaya Tekan Air dari Luar

=1/2 𝛾_𝑤 ℎ^2


Ha
1
Ha = 5.1842 t

Mo = 𝐻_𝑎
(□(64&1/3)ℎ+𝑦_(0−1) )

= 15.8501292178 tm

Gaya Tekan Lumpur

Direncanakan
G = 2.65 ( Konstanta )
q = 30 Derajat
gtanah = 1.75 t/m3
gefektif = 0.75 t/m3

Sehingga
=𝛾_(𝑠^′ ) 1/𝐺(𝐺−1)
gs

= 0.466981132075 t/m3

= 〖 1/2 𝛾 〗 _𝑠 ℎ^2
((1−𝑠𝑖𝑛∅)/(1+𝑠𝑖𝑛∅))
= 〖 1/2 𝛾 〗 _𝑠 ℎ^2
Plumpur ((1−𝑠𝑖𝑛∅)/(1+𝑠𝑖𝑛∅))

= 1.613949056604 t

Mo = 〖 𝑃〗 _𝑙𝑢𝑚𝑝𝑢𝑟 P
(□(64&1/3)ℎ+𝑦_(0−1) ) Mo
= 5.803760807547 t/m

Gaya Tekan Tanah Aktif

Daya Duku= 2 kg/cm2


q = 30 Derajat
G = 2.65 ( Konstanta )
Ka = 0.333333333333
gtanah = 1.75 t/m3
gefektif = 0.75 t/m3
h = 2.63 m
c = 2 kg/cm2
Pa = 0,5𝑥𝛾_𝑒𝑓𝑓𝑒𝑘𝑡𝑖𝑓 𝑥𝐾𝑎𝑥ℎ^2
= 0.8646125 t
𝐻.1/3 𝑃𝑎
Mo =

= 0.75039718875 tm

Gaya Tekan Tanah Pasif

Kp = 3
c = 0.4 kg/cm2
Df = 2.63 meter
Pp = 13.8075 t
Mo = 12.1033645425 t.m

Gaya Gempa

Asumsi Menggunakan Tanah Aluvium


n = 1.56
m = 0.89
Ac = 0.85 cm/dt2
Asumsi Perencanaan
Kota = Upin Ipin Atuk
z = 0.56
ad = =𝑛.(𝐴𝑐.𝑍)𝑚
0.6608784
E = 0.067367828746 ( Koefisien Gempa )
He = 3.414875239144 t/m'
Me = 9.991924949735 tm

Perhitungan Gaya Uplift Vertikal Terhadap Titik Tinjau


No Uv (t/m') L Mv(tm/m')
1 6.574 6.366 41.84900001
2 16.151 4.366 70.516413301
3 6.194 2.366 3.0968393993
4 7.140 0.933 6.6619297636
TOT 122.12418247

Perhitungan Gaya Uplift Horizontal Terhadap Titik Tinjau


No Uh (t/m') L Mh (tm/m') Keterangan
1 5.900 2.63 15.517 Pendorong
2 5.998 1.63 9.776 Penahan
3 5.770 1.63 9.405 Pendorong
4 6.675 0.565 3.772 Pendorong
5 6.938 0.15 1.041 Penahan

Perhitungan Berat Terhadap Titik Tinjau

Berat Tota= 50.69 t


Titik Berat= 3481 mm
= 3.481 m
Momen To= 176.45189 tm

Kontrol Stabilitas Bendung

Kontrol Terhadap Guling


M Penaha= 199.372
M Pendor= 131.135
Mp/Md = 1.520364941761 > 1.3
OK
Kontrol Terhadap Gelincir
ΣH = -5.93767992007
Σ(V-U) = 26.560
Syarat -> ΣH/Σ(V-U) < 0,5 = -0.22355887189 OK f/s

Kontrol Eksentrisitas
e = L/2 - M/Rv <= L/6
L = 6.866
M guling = 68.238
Rv = 26.560
e = L/2 - M/Rv <= L/6 0.863786490344 OK 1.1443333333

Kontrol Tegangan Bawah Bendung


σ = Rv/L (1±6e/L) < σ = 20 t/m2
σ = 20
σ max = 6.78825500896
σ min = 0.948361492038 OK

Kontrol Kestabilan Kolam Olak


𝛾_𝑏𝑒𝑡𝑜𝑛== 2.4 t/m3
U9 = 6.771
U10 = 6.395
Wx = 3.37585523911
Px = 6.58263525153
S = 1.25 ( Ekstrim )
T kolam = 2
dx = 2
Sx(Px-Wx)/= 1.670197923136 < 1.95
5

4 6
1
7
SETTING
3
2 8

21.708882 m2
3.481 m
2.926 m

-3

-2 -1

14

2.65
0.65
11
1.1
8 12 13
9 10
1.866 2 12.009799 0.8

ft Presure
esan
ΣL (m) Lx.∆H/ΣL Hx (t/m2) Ux (t/m2)
Lx (m)
6=3+5 7 8=6x2/7 9 10=9-8
0 25.389 0.0000 6.271 6.271
1 25.389 0.1140 7.271 7.157
1.1666666667 25.389 0.1331 7.271 7.138
1.6666666667 25.389 0.1901 6.771 6.581
9.3333333333 25.389 1.0644 6.271 5.207
10.3333 25.389 1.1785 7.771 6.593
10.6667 25.389 1.2165 7.771 6.555
11.6667 25.389 1.3305 6.771 5.441
12.6667 25.389 1.4446 6.771 5.327
13.6667 25.389 1.5586 7.771 6.213
14.0000 25.389 1.5966 7.771 6.175
15.1300 25.389 1.7255 8.901 7.176
15.7520 25.389 1.7964 8.901 7.105
16.0520 25.389 1.8307 8.601 6.771
16.7187 25.389 1.9067 8.301 6.395
21.8219 25.389 2.4887 9.431 6.943
22.4719 25.389 2.5628 9.431 6.868
22.7386 25.389 2.5932 9.431 6.838
25.3886 25.389 2.8954 9.431 6.536

1.9713051 m
3.22 m

Diketahui
h1 = 4.5 m
p = 3.22 m
h2 = 1.28 m
a = 2.07 m
MAB Kanan = 3.3758552 m
b = 2.601 m

4 Luas
1 5.1842
2 4.1216
3 3.3327
3
4 2.6496
5
2 5 4.3902997
6 6 11.396399

Momen Total
=
= 1.556308
= 9.7191436 t/m -3.915383 t/m
= 0.4615385 OK

OK
2.4

Berat Bentuk Faktor Bentuk Panjang Lebar Berat


W1 Segitiga 0.5 2.072 3.22 8.006208
W2 Persegi 1 1 1 2.4
W3 Persegi 1 6.319 0.5 7.5828
W4 Persegi 1 0.469 3.22 3.624432
W5 Segitiga 0.5 1.507 0.6 1.08504
W6 Persegi 1 1.515 2.62 9.52632
W7 Segitiga 0.5 2.264 2.62 7.118016
W8 Persegi 1 2.866 1 6.8784
W9 Persegi 1 1.866 1 4.4784
50.699616

Berat Bentuk Berat Jarak X DariM Hori Jarak Y M Verti


W1 Segitiga 8.006208 5.734 45.907597 3.703 29.646988
W2 Persegi 2.4 6.415 15.396 1.63 3.912
W3 Persegi 7.5828 3.891 29.504675 2.3 17.44044
W4 Persegi 3.624432 4.608 16.701383 4.24 15.367592
W5 Segitiga 1.08504 3.963 4.3000135 5.45 5.913468
W6 Persegi 9.52632 3.64 34.675805 3.942 37.552753
W7 Segitiga 7.118016 2.246 15.987064 3.44 24.485975
W8 Persegi 6.8784 1.433 9.8567472 1.63 11.211792
W9 Persegi 4.4784 0.933 4.1783472 0.63 2.821392
TOT 50.699616 176.50763 148.3524

Mh = 3.4814392
M ver = 2.926105

0 4

1 5
6
23
7
8
9 10
9 10
Lengan Momen
3.596 18.642383
4.24 17.475584
6.245 20.812712
5.831 15.449818
0.7803 3.4257509
2.6140322 29.790553

Momen Total
-26.50936 tm
Berat Berat (t/m)Jarak x dariM akibat jaJarak y dariM akibat jarak vertikal (tm/m')
W1 30.36 1.375 41.745 2.3 69.828
W2 22.058364 4.0820268 90.042836 1.5333333 33.822826
W3 3.2381186 3.3730403 10.922305 -0.1 -0.323812
W4 0.6 0.1 0.06 -0.825 -0.495
W5 19.2 3.55 68.16 -0.825 -15.84
TOTAL 75.456483 210.93014 86.992014

-3

-2 -1

14

11
12 13
Perhitungan Titik Pusat Konstruksi Bendung
Direncanakan bentuk konstruksi bendung seperti pada gambar di bawah
G Beton =

Properties (mm)
Luas Area =
Horizontal =
Vertikal =
Berat =

Analisa Stabilitas Bendung - Muka Air Banjir


Gaya Tekan Air dalam ( Uplift Presure )
Hd =
H2 =
Delta H =

0.5
0.5
0.5

0.5 23 1
1.13
0.3
Lv =
Lh =
ΣLx =

C =
Delta H =

Gaya Uplift Presur


No Titik ∆H (m)

1 2
0 4.3000
1 4.3000
2 4.3000
3 4.3000
4 4.3000
5 4.3000
6 4.3000
7 4.3000
8 4.3000
9 4.3000
10 4.3000
11 4.3000
12 4.3000
13 4.3000
14 4.3000
15 4.3000
16 4.3000
17 4.3000
18 4.3000

Lv + (1/3)Lh ≥ C x ΔH
22.472 ≥

Gaya gaya yang bekerja

hd

Ha
Plu

Gaya Tekan Air dari Luar

=1/2 𝛾_𝑤 ℎ^2


Ha

Ha =

Mo 𝐻_𝑎 =
(□(64&1/3)ℎ+𝑦_(0−1) )

Gaya Tekan Lumpur

Direncanakan
G =
q =
gtanah =
gefektif =

Sehingga
=𝛾_(𝑠^′ ) 1/𝐺(𝐺−1)
gs

= 〖 1/2 𝛾 〗 _𝑠 ℎ^2
((1−𝑠𝑖𝑛∅)/(1+𝑠𝑖𝑛∅))
= 〖 1/2 𝛾 〗 _𝑠 ℎ^2
Plumpur ((1−𝑠𝑖𝑛∅)/(1+𝑠𝑖𝑛∅))

Mo = 〖 𝑃〗 _𝑙𝑢𝑚𝑝𝑢𝑟
(□(64&1/3)ℎ+𝑦_(0−1) )
=

Gaya Tekan Tanah Aktif

Daya Dukung =
q =
G =
Ka =
gtanah =
gefektif =
h =
c =
Pa =
=
𝐻.1/3 𝑃𝑎
Mo =

Gaya Tekan Tanah Pasif

Kp =
c =
Df =
Pp =
Mo =

Gaya Gempa

Asumsi Menggunakan Tanah Aluvium


n =
m =
Ac =
Asumsi Perencanaan
Kota =
z =
ad =
E =
He =
Me =

Perhitungan Gaya Uplift Vertikal Terhadap Titik Tinjau


No Uv (t/m') L
1 0.5 x ( Ux5 + Ux6 ) x 1 4.022 (0.5 x 1 ) + 3 + 1 + 1.866
2 0.5 x ( Ux7 + Ux8 ) x 3 8.218 (0.5 x 3 ) + 1 + 1.866
3 0.5 x ( Ux9 + Ux10 ) x 1 3.457 (0.5 x 1) + 1.866
4 0.5 x ( Ux10 + Ux11 ) x 1 4.315 (0.5 x 1.866)
TOT

Perhitungan Gaya Uplift Horizontal Terhadap Titik Tinjau


No Uh (t/m') L
1 0.5 x ( Ux4 + Ux5 ) 3.385 0.5 + 1 + 1.13
2 0.5 x ( Ux6 + ux7 ) 3.409 ( 0.5 x 1 ) + 1.13
3 0.5 x ( Ux8 + Ux9 ) 3.070 ( 0.5 x 1 ) + 1.13
4 0.5 x ( Ux10 + Ux11 ) 3.898 ( 0.5 x 1.13 )
5 0.5 x ( Ux12 + Ux13 ) 4.087 ( 0.5 x 0.3 )

Perhitungan Berat Terhadap Titik Tinjau

Berat Total =
Titik Berat X =
=
Momen Total =

Kontrol Stabilitas Bendung

Kontrol Terhadap Guling


M Penahan =
M Pendorong =
Mp/Md =
Kontrol Terhadap Gelincir
ΣH =
Σ(V-U) =
Syarat -> ΣH/Σ(V-U) < 0,5 =

Kontrol Eksentrisitas
e = L/2 - M/Rv <= L/6
L =
M guling =
Rv =
e = L/2 - M/Rv <= L/6

Kontrol Tegangan Bawah Bendung


σ = Rv/L (1±6e/L) < σ = 20 t/m2
σ =
σ max =
σ min =

Kontrol Kestabilan Kolam Olak


𝛾_𝑏𝑒𝑡𝑜𝑛= =
U9 =
U10 =
Wx =
Px =
S =
T kolam =
dx =
Sx(Px-Wx)/𝛾 =
2.4 t/m2

SETTING

21708882 mm2 = 21.708882 m2


3481 mm2 = 3.481 m
2926 mm2 = 2.926 m
50.699 t/m

m
m
4.3 m

-3

-2 -1

14
0 3 4

1 2 5
6
11
7 12 13
8
9 10
1 3 1 1.866 2 12.009799 0.8

10.33 m
45.175799242 m
25.388599747 m

3
4.3 m

Gaya Uplift Presure


Panjang Rembesan
ΣL (m) Lx.∆H/ΣL Hx (t/m2) Ux (t/m2)
Lv (m) Lh (m) 1/3 Lh (m) Lx (m)
3 4 5 6=3+5 7 8=6x2/7 9 10=9-8
0 0 0 0 25.389 0.0000 4.300 4.300
1 0 0 1 25.389 0.1694 5.300 5.131
1 0.5 0.1666666667 1.1666666667 25.389 0.1976 5.300 5.102
1.5 0.5 0.1666666667 1.6666666667 25.389 0.2823 4.800 4.518
1.5 23.500 7.8333333333 9.3333333333 25.389 1.5808 4.300 2.719
2.5 23.500 7.833 10.3333 25.389 1.7501 5.800 4.050
2.5 24.500 8.167 10.6667 25.389 1.8066 5.800 3.993
3.5 24.500 8.167 11.6667 25.389 1.9760 4.800 2.824
3.5 27.500 9.167 12.6667 25.389 2.1453 4.800 2.655
4.5 27.500 9.167 13.6667 25.389 2.3147 5.800 3.485
4.5 28.500 9.500 14.0000 25.389 2.3711 5.800 3.429
5.63 28.500 9.500 15.1300 25.389 2.5625 6.930 4.367
5.63 30.366 10.122 15.7520 25.389 2.6679 6.930 4.262
5.93 30.366 10.122 16.0520 25.389 2.7187 6.630 3.911
5.93 32.366 10.789 16.7187 25.389 2.8316 6.330 3.498
7.03 44.376 14.792 21.8219 25.389 3.6959 7.460 3.764
7.68 44.376 14.792 22.4719 25.389 3.8060 7.460 3.654
7.68 45.176 15.059 22.7386 25.389 3.8512 7.460 3.609
10.33 45.176 15.059 25.3886 25.389 4.3000 7.460 3.160

12.90 OK

1.9713051 m
3.22 m

Diketahui
h1 = 4.5 m
p = 3.22 m
h2 = 1.28 m
a = 2.07 m
MAB Kanan = 0m
b = 2.601 m

3
5
2
1 6
5.1842 t

15.850129218 tm

2.65 ( Konstanta )
30 Derajat
1.75 t/m3
0.75 t/m3

0.4669811321 t/m3
1.6139490566 t

P = 1.556308
Mo = 9.7191436 t/m -3.915383
5.8037608075 t/m

2 kg/cm2
30 Derajat
2.65 ( Konstanta )
0.3333333333
1.75 t/m3
0.75 t/m3
2.63 m
2 kg/cm2
0,5𝑥𝛾_𝑒𝑓𝑓𝑒𝑘𝑡𝑖𝑓 𝑥𝐾𝑎𝑥ℎ^2
0.8646125 t

0.7503971888 tm

3
2 kg/cm2
2.63 meter
13.8075 t
12.103364543 t.m

1.56
0.89
0.85 cm/dt2

Upin Ipin Atuk


0.56
0.6608784 =𝑛.(𝐴𝑐.𝑍)𝑚
0.0673678287 ( Koefisien Gempa )
3.4154815496 t/m'
9.9936990141 tm

L Mv(tm/m')
6.366 25.601777854
4.366 35.880187589
2.366 1.7285424575
0.933 4.0257071527
67.236215053

L Mh (tm/m') Keterangan
2.63 8.901 Pendorong
1.63 5.556 Penahan
1.63 5.004 Pendorong
0.565 2.202 Pendorong
0.15 0.613 Penahan

50.699 t
3481 mm
3.481 m
176.483219 tm

194.756
105.478
1.8464097081 > 1.3
OK
-17.333472205
35.576
-0.4872184089 OK f/s = 0.5384615 OK

6.866
89.278
35.576
0.9235350494 OK 1.1443333333

20
9.363288918
0.9997725882 OK

2.4 t/m3
3.911
3.498
0
3.7048594237
1.25 ( Ekstrim )
2
2
1.9296142832 < 1.95 OK
-1

14

2.65
0.65
1.1
13
Luas Lengan Momen
1 5.1842 3.596 18.642383
2 4.1216 4.24 17.475584
3 3.3327 6.245 20.812712
4 0 5.831 0
5 0 0.7803 0
6 6 0 1.5 0

Momen Total
= 15.305256 tm
t/m
Diketahui
a = 1.055672 m
b = 1.25 m
b bruto = 1.5 m
Tinggi daun Pintu ( Hp ) = 1.155672 m

Perencanaan Tebal Plat Pintu Air


h air depan pintu = 4.3 m
Lebar Pintu Air = 1.25 m
Tinggi Bukaan Air = 1.055672 m
Tinggi daun Pintu ( Hp ) = 1.2 m

Gaya Tekan Akibat Air


h2 = 3.1 m
P1 = 4.3 t/m2
P2 = 3.1 t/m2
F air = 3.083333 t/m2

Gaya Tekan Akibat Endapan


Endapan direncanakan setinggi daun pintu
Hp = 1.2 m
Endapan asumsi tanah lumpur
g endapan = 1.6 t/m2
Pe = 1.92 t/m2
Fe = 0.8 t/m
q = 3.883333 t/m

Momen Maximum yang Bekerja


M max = 0.699 t.m
= 69900 kgcm
Tebal pelat yang diperlukan
t = 1.18237
69900 < 2400 GOAL SEEK
29.1249997185994
Didapat t = 1.377838 cm
Digunakan t = 1.5 cm

Perencanaan Diameter Stang

Lebar Pintu = 1.5 m


Tinggi Daun Pintu = 1.2
= 1.2 m
Tebal Pintu = 1.5 cm
Volume Pintu = 0.027 m3
Berat pintu = 211.95 kg ( Disarankan menggunakan mesin )
Ag = 0.098125 cm2
d = 0.353553 cm
digunakan 1 cm

Maka Digunakan
h air = 4.3 m
Lebar Pintu Air = 1.25 m
a = 1.055672 m
Hp = 1.2 m
Pelat = 1.5 cm
Diameter Stang = 1 cm
unakan mesin )