Project Cost
1 Material cost Rp. 6,505,069,000.00
2 Consumable Cost Rp. 87,107,000.00
3 Labor cost Rp. 1,520,880,000.00
4 Inspection Cost Rp. 165,505,000.00
5 Packaging cost Rp. 60,666,000.00
6 Approval Drawing cost Rp. 15,150,000.00
7 Project cost Rp. 7,809,000.00
8 Transportation cost Rp. 55,066,000.00
SALDO AWAL KAS (184,136,667) (585,446,183) (993,318,200) (1,082,499,267) (1,228,765,233) (1,381,593,700) (1,540,984,667) (2,032,191,583) (2,653,502,000)
PENERIMAAN PEMBAYARAN :
1 Turn key 8,720,000,000 8,720,000,000
TOTAL KAS TERSEDIA 8,720,000,000 - (184,136,667) (585,446,183) (993,318,200) (1,082,499,267) (1,228,765,233) (1,381,593,700) (1,540,984,667) (2,032,191,583) 6,066,498,000
BEBAN OPERASIONAL
1 Material cost 6,505,069,000 975,760,350 975,760,350 650,506,900 650,506,900 650,506,900 650,506,900 975,760,350 975,760,350
2 Consumable Cost 87,107,000 17,421,400 17,421,400 17,421,400 17,421,400 17,421,400
3 Labor cost 1,520,880,000 168,986,667 168,986,667 168,986,667 168,986,667 168,986,667 168,986,667 168,986,667 168,986,667 168,986,667
4 Inspection Cost 165,505,000 33,101,000 33,101,000 33,101,000 33,101,000 33,101,000
5 Packaging cost 60,666,000 60,666,000
6 Approval Drawing cost 15,150,000 15,150,000
7 Project cost 7,809,000 7,809,000
8 Transportation cost 55,066,000 55,066,000
Total Beban Operasional 8,417,252,000.00 184,136,667 1,144,747,017 1,144,747,017 819,493,567 870,015,967 870,015,967 870,015,967 1,195,269,417 1,318,810,417 -
SURPLUS (DEFISIT) 66,498,000 (184,136,667) (1,335,446,183) (1,743,318,200) (1,832,499,267) (1,978,765,233) (2,131,593,700) (2,290,984,667) (2,782,191,583) (3,403,502,000) 6,066,498,000
1 Penarikan (Pembayaran) Pinjaman Ba - 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 (6,000,000,000)
2 Self Financing -
- - 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 750,000,000 (6,000,000,000)
SALDO AKHIR KAS 66,498,000 (184,136,667) (585,446,183) (993,318,200) (1,082,499,267) (1,228,765,233) (1,381,593,700) (1,540,984,667) (2,032,191,583) (2,653,502,000) 66,498,000
Catatan :
Nilai Proyek (excl PPN) 8,720,000,000
PPN 10% 872,000,000
Total 9,592,000,000
Jangka Waktu kontrak
Masa Pekerjaan = 28 minggu `
Total
8,720,000,000
8,720,000,000
8,720,000,000
6,505,069,000
87,107,000
1,520,880,000
165,505,000
60,666,000
15,150,000
7,809,000
55,066,000
8,417,252,000
-
236,250,000
236,250,000
66,498,000
-
-
-
66,498,000
TAHUN 2021
Total
-
-
-
-
-