METHODE STATEMENT
1
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
METHODE STATEMENT
Disetujui oleh ;
PT Harmas Jalesveva
Nagib Shahab
Engineering Manager
2
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
DAFTAR ISI
1. Pendahuluan
………………………………………………………………………………… 4
2. Definisi
……………………………………………………………………………………… 4
3. Pelaksanaan Pekerjaan
……………………………………………………………………… 4
4. Bahan
……………………………………………………………………………………….. 6
5. Alat
………………………………………………………………………………………….. 6
6. Brosur
……………………………………………………………………………………….. 7
7. Jaminan Mutu
………………………………………………………………………………. 15
8. Jaminan Keselamatan Kerja ………………………………………………………………... 15
9. Penutup ………………………………………………………………………………..…… 15
3
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
1. Pendahuluan
Material urugan / timbunan adalah material tanah yang layak digunakan sebagai material
timbunan yang layak dan memenuhi persyaratan yang di berikan. Dalam pekerjaan ini
diupayakan material timbunan berasal dari daerah yang dekat dengan lokasi proyek.
2. Definisi
Urugan atau timbunan merupakan bagian dari pekerjaan tanah dan fondasi. Urugan atau
timbunan itu menutup area yang kosong dengan tanah. Urugan harus dilakukan untuk memenuhi
elevasi yang diperlukan untuk melakukan suatu pekerjaan dan atau seperti tercantum dalam
gambar – gambar rencana.
3. Pelaksanaan Pekerjaan
4
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Mencapai kohesi minimum sebesar 1,0 kg/cm2 dan sudut geser dalam minimum sebesar
18o untuk soil – cement yang dipadatkan.
5
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
5. Alat
Alat – alat yang di gunakan antara lain :
a. Excavator
b. Stamper
6
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
6. Brosur
7
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Selected Dimensions
Dimensions
8
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Undercarriage
F. TRACK GAUGE 6.4 ft in 1960 mm
N. SHOE SIZE 19.7 in 500 mm
Specification
Engine
MAKE Komatsu
MODEL S4D102E
GROSS POWER 80.5 hp 60 kw
POWER MEASURED @ 2100 rpm
DISPLACEMENT 239.2 cu in 3.9 L
NUMBER OF CYLINDERS 4
Operational
OPERATING WEIGHT 23699.7 lb 10750 kg
FUEL CAPACITY 60.8 gal 230 L
HYDRAUILC SYSTEM FLUID CAPACITY 26.4 gal 100 L
HYDRAULIC SYSTEM RELIEF VALVE PRESSURE 4620 psi 31853.8 kPa
HYDRAULIC PUMP FLOW CAPACITY 57.1 gal/min 216 L/min
Swing Mechanism
SWING SPEED 12 rpm
Undercarriage
SHOE SIZE 19.7 in 500 mm
GROUND PRESSURE 5.4 psi 37.2 kPa
MAX TRAVEL SPEED 3.4 mph 5.5 km/h
TRACK GAUGE 6.4 ft in 1960 mm
Buckets
REFERENCE BUCKET CAPACITY 0.58 yd3 0.44 m3
MINIMUM BUCKET CAPACITY 0.24 yd3 0.18 m3
MAXIMUM BUCKET CAPACITY 0.72 yd3 0.55 m3
Boom/Stick Option (HEX) 1
BOOM/STICK OPTION (HEX) 1 Boom 14'0" (4260mm)/Stick 6'9" (2060mm)
9
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Product Description
10
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Tamming Rammer
Jumping stroke: 80 mm
Kecepatan: 10 – 13 m/menit
11
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
Dimensi: 1050x500x730 mm
12
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
13
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
14
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
15
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
7. Jaminan Mutu
Dengan melaksanakan metode ini kita akan mendapatkan hasil urugan tanah yang lebih baik
dari pada sebelumnya, sesuai dengan apa yang sesuai dengan dokumen kontrak (RKS) dan
owner / pemilik.
9. Penutup
Agar kita dapatkan hasil perbaikan urugan tanah yang baik, pelaksanaan di lapangan harus
sesuai dengan metode kerja urugan tanah yang telah ditentukan oleh tim ahli.
16
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva
PT. PULAUINTAN BAJA PERKASA METODE STATEMENT METODE URUGAN / TIMBUNAN TANAH
17
THE ASPEN recidence@ADMIRALTY PT. Harmas
Jalesveva