ESTIMASI ENGINEERING (EE) PEKERJAN TULANGAN

HARGA JUMLAH
NO. URAIAN PEKERJAAN JUMLAH
SATUAN (Rp.) HARGA (Rp.)
1 Talud
1 Pasir Pasang 4 M3 200,000 800,000
2 Semen 7 Sak 100,000 700,000
3 Batu Kali 4 M3 200,000 800,000
1,600,000
2 Cor Jembatan
1 Pasir Cor 4 M3 200,000 800,000
2 Semen 8 Sak 100,000 800,000
3 Besi ø10 52 Kg 20,000 1,036,000
4 Kawat Bendrat 3 Kg 32,000 86,400
2 KOLOM 15 x 30 2,722,400
3 Bekisting
1 Balok kayu 5/5 10 Btg 25,000 250,000
2 Papan Bekisting 15 Btg 25,000 375,000
3 Paku Campur 1 Kg 25,000 25,000
650,000
4 Upah Kerja
1 Tukang 1 Org 185,000 185,000
2 Pekerja 1 Org 150,000 150,000
335,000
Total 4,657,400