PROJECT :
A. FASA 1
B. FASA 2
• 106 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12798 - PT 13241,
• PT 13242 & PT 13305, 13243 & PT 13306, PT113244 & PT 13307, PT
13245 & PT 13308, PT 13246 & PT 13309, PT 13247 & PT 13310, PT
13248 & PT 13311, PT 13249 & PT 13312, PT 13250 & PT 13313, PT
13251 & PT 13314, PT 13257 & PT 12832, PT 13258 & PT 12831, PT
13259 & PT 13315 & PT 12830 PT 13260 - PT 13300, PT 13301 & PT
12829, PT 13302 & PT 12828, PT 13303 & PT 12827, PT 13304 & PT
12826.
• 1 UNIT PENCAWANG TNB (JENIS 'DOUBLE CHAMBER') DI ATAS
PETAK 83 (SEBAHAGIAN PT 12842)
C. FASA 3
• 63 UNIT RUMAH TERES 2 TINGKAT DI ATAS PT 12861- PT 12976.
Page 1 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
D. FASA 4a
• 30 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 70') DI ATAS PETAK 43- 53,
PETAK 61 - 69, PETAK 70 - 79.
• 7 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 80') DI ATAS PETAK 54 - 60.
• 1 UNIT BANGUNAN PASARAYA 1 TINGKAT DI ATAS PETAK 80
E. FASA 4b
• 42 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 70') DI ATAS PETAK 1 - 42
• 1 UNIT RESTORAN PANDU LALU 1 TINGKAT DI ATAS PETAK 81.
• 1 UNIT KEDAI PEJABAT 2 TINGKAT (30' X 70') DI ATAS PETAK 82
F. FASA 5
• 105 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12722 - PT 13221,
PT 13253 & PT 12836. PT 13254 & PT 12835, PT 13255 & PT 12834,
PT 13256 & PT 12833.
G. FASA 6
• 66 UNIT RUMAH TERES 2 TINGKAT DI ATAS PT 12848 - PT 12939.
H. FASA 7
• 89 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12669 – PT 12745,
PT 13162 – PT 12745, PT 13162 – PT 13181, PT 13252 & PT 12837.
I. FASA 8
• 108 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12561 – PT 12668.
Page 2 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
ATTENDANCE DISTRIBUTION
1. Amir Ikram Bin Ariffin Kumpulan Perunding (1988) Sdn Bhd KP88
(Chairman)
2. Rustun B. Sulaiman Exsim Halaman (BSTM) Sdn Bhd EHSB
3. Muhammad Yasiin Azmi Ditto
4. Nur Faiqah Binti Abdul Hisham Ditto
5. Ryan Chong Ditto
6. Tuan Norsyaliena Bt Tuan Ramli Ditto
7. Mazila Abdullah Ditto
8. Ir Chung Yof Consult Sdn Bhd YC
9. Shaiful KNS Consult Sdn Bhd KNS
10. Muhd Aiman Bin Ibrahim Ditto
11. Mohd Ridzuwan Salleh DZI Planner DZI
12. Mohd Zuriman Hashim WAW MDP Services Sdn Bhd WAW
13. Engku Fatimah Dayani Stratascape Design SD
Page 3 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
1.1 The Minute of Meeting No: 2022/23 was confirmed correct. All Noted
Based on the Minutes of the Council Meeting dated 30/1/2023, MDTM has All Noted
no objection to approve the application for amended KM (LCP) with
conditions that all comments by external technical authorities must be
complied as follows; -
2.2 JKR: to submit the requirements for TIA and RSA (Stage 1 & 2).
• YC informed that they are coordinating with RSA consultant for RSA YC
report stage 3.
Page 4 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
3.1 Based on letter from MDTM dated 12/12/2022, full BP Approval will be issued All Noted
subject to payment of RM182,205.00 that need to be made to MDTM.
• EHSB has made payment to MDTM via cheque on 19/3/2023. All Noted
• However, MDTM has mentioned that some of the cheque was bounced. KP88/EHSB
KP88 to liaise with EHSB on the bounced cheque as follows;
i. ISF Contribution: RM 84,695.00 – bounced cheque.
ii. Deposit Kebersihan: RM 30,000.00 – bounced cheque.
• EHSB is currently preparing new cheques for the above & the payment will EHSB
be made ASAP.
4.1 KP88 informed that based on the letter issued by MDTM on 8/2/2023, the All Noted
application was given Conditional Approval. Conditions imposed; -
i. Amend proposed ‘Nama Taman’ to BANDAR HALAMAN TANAH
MERAH
ii. To get confirmation from DBP in term of the correct spelling
iii. To comply with the standard ‘papan tanda Majlis’ in term of colour
& size.
• Condition i & iii; KP88 has submitted to comply with condition i & iii to KP88
MDTM on 20/3/23. KP88 to follow up with the approval.
• Condition ii; KP88 informed that MDTM will arrange for internal meeting to KP88
check the jawi spelling. KP88 to follow up with the approval.
5.1 EHSB informed that a further direction will be given after the Amended KM EHSB
Approval is issued. Status remained - 11
6.0 EARTHWORKS
6.1 YC informed that on MDTM letter dated 1/1/2023 full approval will be issued All Noted
once payment is done as follows; -
i. Processing fees : RM 6,988.00
ii. Site visit fee : RM 120.00
iii. Deposit : RM 215,668.00 (Got discount 50%)
6.2 EHSB has received official letter from MDTM on their appeal (on 19/2/23) for YC/EHSB
reduction in earthwork deposit. Based on MDTM letter dated 12/2/23 ref:
MDTM/KJ/2022/028(07), MDTM has granted 50% discount on the Deposit
Kerja Tanah.
6.3 EHSB has made payment on 19/3/2023 via cheque but was bounced as EHSB
informed by MDTM. EHSB is currently preparing new cheques & the payment
will be made ASAP.
6.4 The above Earthwork approval is for phase 1. YC to submit the updated YC
Earthworks for overall Phases to MDTM as required. Target to be submitted
on 27/3/23 after payment for phase 1 been made & approved by MDTM.
Status remained – 7
Page 5 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
8.1 Based on OSC ‘Pemakluman Mesyuarat’ 19/12/2022, the application was All Noted
given FULL APPROVAL by MDTM, official letter to be issued subject to total
payment of RM 22,555.00.
8.2 MDTM via official letter dated 12/3/23 ref: MDTM/KJ/2022/028(09) has EHSB/KNS
granted EHSB 50% discount for deposit Lampu Jalan. KNS to liaise with EHSB
on the payment.
9.0 ROADWORKS
10.1 YC informed that their submission to JPS Negeri Kelantan has been rejected All Noted
and commented on 20/2/23.
For phase 1, YC to submit the Drawing to get the approval for PDC 2. Target YC
to be on April 2023 after all STP design/details etc. are finalized from the
successful supplier/D&B contractor. Status remained – 2
14.2 KNS has emailed the revised drawing on 29/3/23 to EHSB. EHSB to check & EHSB
confirm.
Page 6 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
New date for confirmation & Award Tender to be extended as EHSB needs All Noted
time to review the revised quotation from tenderers. The timeline for Tendering
STP & Sewer reticulation to be updated; -
Items Ori Target Ext. No.3 Ext. No.4 Ext. No.5
1. Calling Tender 25/09/22 - - -
2. Closed Tender 16/10/22 - - -
3. Tender Report 23/10/22 - - -
13/02/23
4. Tender
30/10/22 & - -
interview
14/02/23
5. Confirmation & To be
13/11/22 28/02/23 14/03/23
Award updated
6. Preparing
Drawing & To be
06/12/22 21/03/23 11/04/23
Submit for updated
Approval
16.0 LANDSCAPE
17.0 MODEL-MAKING
Page 7 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023
18.1 KP88 has revised the SPA Drawings & 4th schedule as per commented by EHSB
EHSB (email dated 16/1/2023). All has been emailed on 30/1/2023. EHSB to
check for confirmation. Status remained – 4
19.2 EHSB to confirm the building finishes for phase 1 as soon as possible so not EHSB
to delay the preparation of detail drawings for tender. Status remained – 1
20.1 EHSB to coordinate with other consultants on the target date for BP All
Submission Phase 2. Status remained –2
21.1 Permohonan Kelulusan Pelan Hoarding & Papan Tanda Projek has been KP88
submitted to MDTM on 21/2/23. KP88 to follow up with the official latter for the
payment.
21.1 CCM No. 2023/24 was adjourned at 12.15 pm and CCM No. 2023/25 shall be All Noted
on 12/4/2023 at 10.30 am
Prepared by :
Page 8 of 8
BHTM - AUTHORITIES STATUS & ADDITIONAL INFO - (NO. 8) 30/03/2023
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
KM APRROVAL
MDTM informed all technical department to comments by 05/01/22. If no response
30/1/2023
or answer, they will proceed with approval before 12/01/23. Letter Kelulusan 15/8/22, DZI Consultants to comply all the
1 Jabatan Perancang MDTM KM Approval. Ref:MDTM/M/530 Jilid 1/2/2023 - -
Bersyarat KM by MDTM released on 30/01/23. Full KM approval will be approved 24/11/2022 (rev1) Planner comments by authorities
3(3)
after all conditions are comply. The conditions are as below:-
22/8/2022
Suruhanjaya Komunikasi
9 KM Approval Approved. - Ref:SKMM(T)/05- 30/8/2023 KNS Approved. - Approved
dan Multimedia (SKMM)
KSO/70/002/02/Jld.1(30)
Ulasan :- (letter Bil ( )JPS.KN.TM.149/4015)
1. Kapasiti Kolam Takungan (wet pond) yang dicadang tidak mencukupi dengan
keluasan pembangunan. Keluasan kolam takungan hendaklah 3% - 5% daripada 1/1/2023 YC submitted the letter to JPS
15/8/22,
10 JPS Tanah Merah KM Approval keluasan kawasan pembangunan. Ref:Bil()JPS.KN.TM.149/40 1/2/2023 YC 27/2/2023 on 27/02/23. Waiting for JPS -
24/11/2022 (rev)
2. Semua aliran semulajadi hendaklah dikekalkan, sekiranya memerlukan lencongan 15 Offical comments/approval.
pihak pemohon perlu mendapatkan kelulusan daripada JPS Negeri Kelantan terlebih
dahulu
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
Ulasan :-
IWK through their letter dated
05/02/23 Ref:
IWK/C/KEL12/22/0123 stated
19 comments need to comply.
IWK request NPS to move to
6/12/2023
another place in order for
11 IWK KM Approval - Ref:IWK/C/KEL12/22/01 6/12/2023 YC 14/12/2023 -
1. 28 nos of comments. buffer zone comply. DZI has plot
23
the area for NPS nearby Drive-
Thru. YC has comments due
insufficient buffer zone area. YC
re-sent to DZI the drawing to be
overlay on master plan.
BP APPROVAL
Approved with condition :-
1. Payment ISF RM 84,695.00 to be made. EHSB reply with an appeal
2. Deposit Kebersihan RM 71,200.00 to be made. letter to MDTM for reducing ISF
and Deposit Kebersihan. MDTM
12/12/2022 In 30 days (12/03/23)
KP88 / reply with letter dated
1 Jabatan Bangunan MDTM BP Approval 3/11/2022 Ref:MDTM/OSC/PB/22/2 12/12/2022 13/12/2022 19/03/23 (ext. date)
EHSB 12/02/23 ref;
10(6) 02/04/23 (ext. date)
3. Misc. payment RM 26,310.00 to be made. MDTM/OSC/PB/22/210(11)
confirmed ISF maintain, deposit
kebersihan reduced to RM 30k.
3/1/2023
STRATAS
5 Jabatan Perancangan MDTM BP - Landscape Drawing Approved. 6/11/2022 Ref:MDTM/OSC/PL/22/07 - - - Approved
CAPE
(5)
Approved with conditions :- EHSB reply with an appeal
1/1/2023
Jabatan Pembangunan letter on 19/01/23 to MDTM
6 BP - Earthwork Drawing (Phase 1) 1. Payment processing fees RM 6,988.00 to be made. 23/11/2022 Ref:MDTM/KJ/2022/028( 18/1/2023 YC 19/1/2023 Approved
Kejuruteraan MDTM for reducing Deposit Kerja
2. Payment site visit RM 120.00 tp be made. )
Tanah.
3. Payment Deposit Kerja-Kerja Tanah RM 215,668.00 to be made
EHSB reply with an appeal
letter on 19/01/23 to MDTM
for reducing Deposit Kerja
12/2/2023 In 30 days (12/03/23)
Jabatan Pembangunan Letter to MDTM for reducing Deposit Kerja Tanah with 75% discount. As verbal Tanah. MDTM reply with letter
7 BP - Earthwork Drawing (Phase 1) 19/1/2023 Ref:MDTM/KJ/2022/028/ 16/2/2023 EHSB In 30days 19/03/23 (ext. date)
Kejuruteraan MDTM confirmed, 50% discount given to EHSB. Waiting official letter for MDTM. dated 12/02/23 ref;
(07) 02/04/23 (ext. date)
MDTM/KJ/2022/028(07)
confirmed 50% discount
approved.
BP - Revise Earthwork Drawing Target submission date on
Jabatan Pembangunan Submission of revised earthworks drawings after payment for phase 1 been made
8 Phase 1 & Overall Phases - - - - - 27/03/23. Extended date to be -
Kejuruteraan MDTM and approved by MDTM.
(encroachment neighbour land) 12/04/23.
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
Approved with condition :- JKR through letter dated
21/02/23 invites for TIA & RSA
Jabatan Pembangunan 19/12/2022 Pemakluman
9 BP - Road & Drainage 1/11/2022 19/12/2022 YC 12/2/2023 Report Presentation on Approved
Kejuruteraan MDTM Mesyuarat OSC
1. To submit TIA & RSA Reports Stage 1 & 2. 02/03/23. Offial approval letter
by JKR dated 08/03/23.
18/1/2023
17 TELEKOM BP Approval Approved. 8/8/2022 - KNS Approved - Approved
Ref:4415A/TAM/2022/07
Additional Info
2 Cost Plan Single Storey Terrace House - 2 option to EHSB 15/3/2023 - WAW
3 Model Making drawing. The drawings email to EHSB on 16/02/23. 16/2/2023 To confirm the cost plan EHSB
9 Temporary Hoarding Permit Approval by MDTM. Verbal approved. Waiting official letter from MDTM. To update - KP88
11 Overall Infrastructure Drawing draft for costing. As mentioned by YC, need to confirm overall layout master plan. 28/3/2023 TBC YC