Ref : K14212/BHTM/MM/CCM/2023/24

Date : 29 March 2023

NO. 3&5, 2ND FLOOR, JALAN 2116D, KUCHAI ENTREPRENEURS’ PARK, OFF JALAN KUCHAI LAMA,
58200 KUALA LUMPUR, MALAYISA. TEL : 6(03) 7981 4638 (6 LINES) FAX : 6 (03) 7982 6121

NO 44, TINGKAT 1, JALAN SULTAN ISMAIL, 20200 KUALA TERENGGANU, TERENGGANU DARUL IMAN, MALAYSIA
TEL : 6(09) 622 3582, 622 3755 FAX : 6 (09) 623 1412

LOT PT 539, TINGKAT 1, JLN. ABDUL KADIR ADABI, CHERANG, SEKSYEN 50, PETI SURAT 310, 15730 KOTA BHARU,
KELANTAN. TEL : 6(09) 748 50609, 747 7316 FAX : 6 (09) 748 3062

Developer : EXSIM HALAMAN (BSTM) SDN BHD

PROJECT :

CADANGAN MEMBINA DAN MENYIAPKAN PROJEK PERUMAHAN DAN


KOMERSIL (BANDAR HALAMAN @ TANAH MERAH) SECARA BERFASA (FASA
1 - FASA 8) DI ATAS PECAHAN LOT ASAL, PT 12289 (10.2957 HA), LOT 886
(13.476 HA), LOT 7113 (2.1520 HA) & LOT 7115 (2.024 HA), MUKIM MAKA,
DAERAH KUSIAL, JAJAHAN TANAH MERAH, KELANTAN DARUL NAIM YANG
MENGANDUNGI: -

A. FASA 1

• 178 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12977 - PT 13154


• 1 UNIT PENCAWANG TNB (JENIS SSU) - DI ATAS PT12847
• 1 UNIT PENCAWANG TNB (JENIS 'DOUBLE CHAMBER') DI ATAS PT 13159.
• 1 UNIT TANGKI AIR SEDUTAN DI ATAS PT 12839
• 1 UNIT MENARA TANGKI AIR DI ATAS PT 13158
• 1 UNIT KOLAM TAKUNGAN AIR (OSD) DI ATAS PT 12845 & PT 13316
• 1 UNIT LOJI KUMBAHAN (STP) DI ATAS PT 12846 & PT 13317

B. FASA 2
• 106 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12798 - PT 13241,
• PT 13242 & PT 13305, 13243 & PT 13306, PT113244 & PT 13307, PT
13245 & PT 13308, PT 13246 & PT 13309, PT 13247 & PT 13310, PT
13248 & PT 13311, PT 13249 & PT 13312, PT 13250 & PT 13313, PT
13251 & PT 13314, PT 13257 & PT 12832, PT 13258 & PT 12831, PT
13259 & PT 13315 & PT 12830 PT 13260 - PT 13300, PT 13301 & PT
12829, PT 13302 & PT 12828, PT 13303 & PT 12827, PT 13304 & PT
12826.
• 1 UNIT PENCAWANG TNB (JENIS 'DOUBLE CHAMBER') DI ATAS
PETAK 83 (SEBAHAGIAN PT 12842)

C. FASA 3
• 63 UNIT RUMAH TERES 2 TINGKAT DI ATAS PT 12861- PT 12976.

Page 1 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

D. FASA 4a
• 30 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 70') DI ATAS PETAK 43- 53,
PETAK 61 - 69, PETAK 70 - 79.
• 7 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 80') DI ATAS PETAK 54 - 60.
• 1 UNIT BANGUNAN PASARAYA 1 TINGKAT DI ATAS PETAK 80

[KESEMUANYA DI ATAS TANAH SELUAS 2.180 HEKTAR (5.389 EKAR),


ASALNYA SEBAHAGIAN PT 12472, PT 12473, PT 12474 - PT 12483, PT
12489 - PT 12494, SEBAHAGIAN PT 12450, PT 12451 - PT 12458, PT
12495 - PT 12500, PT 12501 - PT 12506, PT 12507 - PT 12515, PT 12516
- PT 12524, PT 12525 - PT 12533, PT 12534 - PT 12542, PT 12543 - PT
12551, PT 12552 - PT 12560 DAN SEBAHAGIAN TANAH KERAJAAN].

E. FASA 4b
• 42 UNIT KEDAI PEJABAT 2 TINGKAT (20' x 70') DI ATAS PETAK 1 - 42
• 1 UNIT RESTORAN PANDU LALU 1 TINGKAT DI ATAS PETAK 81.
• 1 UNIT KEDAI PEJABAT 2 TINGKAT (30' X 70') DI ATAS PETAK 82

[KESEMUANYA DI ATAS TANAH SELUAS 1.377 HA (3.40 EKAR), ASALNYA PT


12838 (TNB), PT 12843, PT 12844, 12424 - PT 12436, PT 12459 - PT 12466, PT
12467 - PT 12471, SEBAHAGIAN PT 12472, PT 12437 - PT 12447, PT 12448, PT
12449, SEBAHAGIAN PT 12450, PT 12484 - PT 12488, DAN SEBAHAGIAN TANAH
KERAJAAN].

F. FASA 5
• 105 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12722 - PT 13221,
PT 13253 & PT 12836. PT 13254 & PT 12835, PT 13255 & PT 12834,
PT 13256 & PT 12833.
G. FASA 6
• 66 UNIT RUMAH TERES 2 TINGKAT DI ATAS PT 12848 - PT 12939.
H. FASA 7
• 89 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12669 – PT 12745,
PT 13162 – PT 12745, PT 13162 – PT 13181, PT 13252 & PT 12837.
I. FASA 8
• 108 UNIT RUMAH TERES 1 TINGKAT DI ATAS PT 12561 – PT 12668.

(NOTE : The above project Title was updated on 15/02/2023)

Page 2 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

CLIENT CONSULTANT MEETING – CCM NO: 2023/24

DATE : 29 MARCH 2023


TIME : 10:30 AM
VENUE : OFFICE @ EXSIM HALAMAN SDN BHD – KOTA BHARU

ATTENDANCE DISTRIBUTION

1. Amir Ikram Bin Ariffin Kumpulan Perunding (1988) Sdn Bhd KP88
(Chairman)
2. Rustun B. Sulaiman Exsim Halaman (BSTM) Sdn Bhd EHSB
3. Muhammad Yasiin Azmi Ditto
4. Nur Faiqah Binti Abdul Hisham Ditto
5. Ryan Chong Ditto
6. Tuan Norsyaliena Bt Tuan Ramli Ditto
7. Mazila Abdullah Ditto
8. Ir Chung Yof Consult Sdn Bhd YC
9. Shaiful KNS Consult Sdn Bhd KNS
10. Muhd Aiman Bin Ibrahim Ditto
11. Mohd Ridzuwan Salleh DZI Planner DZI
12. Mohd Zuriman Hashim WAW MDP Services Sdn Bhd WAW
13. Engku Fatimah Dayani Stratascape Design SD

Page 3 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

ITEM PARTICULARS ACTION BY


1.0 MINUTE OF MEETING NO: 2022/23

1.1 The Minute of Meeting No: 2022/23 was confirmed correct. All Noted

2.0 AMENDED KM(LCP) SUBMISSION

Based on the Minutes of the Council Meeting dated 30/1/2023, MDTM has All Noted
no objection to approve the application for amended KM (LCP) with
conditions that all comments by external technical authorities must be
complied as follows; -

2.1 AKSB: commented on 11/9/2022 (DZI received on 30/1/2023); -


i. Tee-off point at existing 450 diameter AKSB mild steel pipe All Noted
located about 4.0 km from BHTM site.
ii. Proposed suction tank size to be at 36m x 41m, and elevated tank
size at 42m x 42m.
iii. To complete the water tank at phase 1 (complied)
• YC informed that based on their discussion with Pn Syida from AKSB on YC
12/3/23, the size mentioned in the letter is the size of the required lands
not the size of the tanks. YC to follow up with the official revised letter
from AKSB

2.2 JKR: to submit the requirements for TIA and RSA (Stage 1 & 2).
• YC informed that they are coordinating with RSA consultant for RSA YC
report stage 3.

2.3 JMG: commented on 5/12/2022 (DZI received on 30/1/2023) YC


• YC missed original target to comply with the four JMG requirements
before 27/3/2023. New target to be submitted by 12/4/2023

2.4 TNB: 2nd comment on 5/1/2023; - All Noted


i. To propose site/land (46mx46m) for 1-unit PPU
ii. 1-unit SSU (complied)
iii. 2 units DC Sub-station (complied)
iv. To proposed 2 units single chamber sub-station for Hypermarket
& Drive Through Restaurant each.
• Pending TNB’s feedbacks on submitted appeal with updated calculation KNS
& project title on 23/2/23. KNS to follow up with TNB.

2.5 JPS Tanah Merah: commented on 1/1/2023; -


i. Proposed Wet Pond to be at least 3% from the development area
(5% total required for OSD from the development area).
• YC has submitted an appeal on 27/2/23. YC to follow up with JPS YC
• Failing which, YC to suggest proposals to comply with the said YC
requirements. Status remained - 3

2.6 IWK: commented on 5/2/2023.


• YC to comply with 19 new comments from IWK and obtain the approval YC
letter for PDC 1.
• YC has commented on DZI proposal for the new area for NPS at Phase YC
4b due to insufficient buffer zone. YC to forward their proposal for the
new location for NPS to DZI.

Page 4 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

ITEM PARTICULARS ACTION BY


3.0 BP SUBMISSION FOR PHASE 1.

3.1 Based on letter from MDTM dated 12/12/2022, full BP Approval will be issued All Noted
subject to payment of RM182,205.00 that need to be made to MDTM.
• EHSB has made payment to MDTM via cheque on 19/3/2023. All Noted
• However, MDTM has mentioned that some of the cheque was bounced. KP88/EHSB
KP88 to liaise with EHSB on the bounced cheque as follows;
i. ISF Contribution: RM 84,695.00 – bounced cheque.
ii. Deposit Kebersihan: RM 30,000.00 – bounced cheque.
• EHSB is currently preparing new cheques for the above & the payment will EHSB
be made ASAP.

4.0 PROPOSED ROAD NAMES FOR BANDAR HALAMAN @ TANAH MERAH.

4.1 KP88 informed that based on the letter issued by MDTM on 8/2/2023, the All Noted
application was given Conditional Approval. Conditions imposed; -
i. Amend proposed ‘Nama Taman’ to BANDAR HALAMAN TANAH
MERAH
ii. To get confirmation from DBP in term of the correct spelling
iii. To comply with the standard ‘papan tanda Majlis’ in term of colour
& size.
• Condition i & iii; KP88 has submitted to comply with condition i & iii to KP88
MDTM on 20/3/23. KP88 to follow up with the approval.
• Condition ii; KP88 informed that MDTM will arrange for internal meeting to KP88
check the jawi spelling. KP88 to follow up with the approval.

5.0 BUILDING PLAN PROPOSAL: COMMERCIAL UNITS (2 Story Shop


Office) @ PHASE 4a & 4b.

5.1 EHSB informed that a further direction will be given after the Amended KM EHSB
Approval is issued. Status remained - 11

6.0 EARTHWORKS

6.1 YC informed that on MDTM letter dated 1/1/2023 full approval will be issued All Noted
once payment is done as follows; -
i. Processing fees : RM 6,988.00
ii. Site visit fee : RM 120.00
iii. Deposit : RM 215,668.00 (Got discount 50%)

6.2 EHSB has received official letter from MDTM on their appeal (on 19/2/23) for YC/EHSB
reduction in earthwork deposit. Based on MDTM letter dated 12/2/23 ref:
MDTM/KJ/2022/028(07), MDTM has granted 50% discount on the Deposit
Kerja Tanah.

6.3 EHSB has made payment on 19/3/2023 via cheque but was bounced as EHSB
informed by MDTM. EHSB is currently preparing new cheques & the payment
will be made ASAP.

6.4 The above Earthwork approval is for phase 1. YC to submit the updated YC
Earthworks for overall Phases to MDTM as required. Target to be submitted
on 27/3/23 after payment for phase 1 been made & approved by MDTM.
Status remained – 7

Page 5 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

ITEM PARTICULARS ACTION BY


7.0 ROAD & DRAINAGE

7.1 Refer item 2.2 All Noted

8.0 STREET LIGHTING

8.1 Based on OSC ‘Pemakluman Mesyuarat’ 19/12/2022, the application was All Noted
given FULL APPROVAL by MDTM, official letter to be issued subject to total
payment of RM 22,555.00.

8.2 MDTM via official letter dated 12/3/23 ref: MDTM/KJ/2022/028(09) has EHSB/KNS
granted EHSB 50% discount for deposit Lampu Jalan. KNS to liaise with EHSB
on the payment.

9.0 ROADWORKS

9.1 Refer item 2.2 All Noted

10.0 DRAINAGE WORKS

10.1 YC informed that their submission to JPS Negeri Kelantan has been rejected All Noted
and commented on 20/2/23.

YC missed the original target to amend their application as per commented by YC


JPS Negeri Kelantan before 19/3/23. New target to submit before 6/4/23.

11.0 TENAGA NASIONAL BERHAD (TNB)

Refer item 2.4 All Noted

12.0 ELEVATED WATER TANK & WATER RETICULATION

12.1 Refer item 2.1 All Noted

13.0 SEWERAGE TREATMENT PLANT (STP) AND SEWERAGE


RETICULATION.
All Noted
13.1 Refer item 2.6

For phase 1, YC to submit the Drawing to get the approval for PDC 2. Target YC
to be on April 2023 after all STP design/details etc. are finalized from the
successful supplier/D&B contractor. Status remained – 2

14.0 MECHANICAL & ELECTRICAL WORKS

14.1 M&E Tender Drawings for Phase 1


EHSB has commented on the M&E tender drawing for phase 1 on 14/3/23. KNS
KNS has comply with EHSB comments on the M&E tender drawing for the
phase 1.

14.2 KNS has emailed the revised drawing on 29/3/23 to EHSB. EHSB to check & EHSB
confirm.

Page 6 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

ITEM PARTICULARS ACTION BY


15.0 QS MATTERS

15.1 Earthworks Tender

Timeline for retender Earthworks remained as follows; - All Noted


Items Ori. Target Date Ext. No. 1
a. Receive tender drawing from YC 08/02/23 14/02/23
b. Calling Tender 22/02/23 27/02/23
c. Closed Tender 08/03/23 15/03/23
d. Tender Report 15/03/23 22/03/23
e. Tender interview 22/03/23 29/03/23
f. Confirmation & Award 05/04/23 12/04/23

15.2 Sewerage Treatment Plan (Stp) & Sewer Reticulation

New date for confirmation & Award Tender to be extended as EHSB needs All Noted
time to review the revised quotation from tenderers. The timeline for Tendering
STP & Sewer reticulation to be updated; -
Items Ori Target Ext. No.3 Ext. No.4 Ext. No.5
1. Calling Tender 25/09/22 - - -
2. Closed Tender 16/10/22 - - -
3. Tender Report 23/10/22 - - -
13/02/23
4. Tender
30/10/22 & - -
interview
14/02/23
5. Confirmation & To be
13/11/22 28/02/23 14/03/23
Award updated
6. Preparing
Drawing & To be
06/12/22 21/03/23 11/04/23
Submit for updated
Approval

15.3 Cost Plan


WAW has forwarded to EHSB the revised cost plan for single story terrace EHSB
house (all type) on 8/3/23 with updated costing from KNS on the M&E and
based on updated structural drawing from YC. EHSB to review and comment.
Status remained – 1

16.0 LANDSCAPE

16.1 Main Entrance Archway


KP88 has revised the drawing of Main Entrance Archway and emailed to EHSB
EHSB 2 options to be considered on 25/02/23. EHSB to comment & confirm.
Status remained – 2

17.0 MODEL-MAKING

17.1 Overall Masterplan Model


• Model maker should not proceed yet until new KM approval issue. Unless EHSB
confirmed otherwise by EHSB. Status remained – 3

Page 7 of 8
Ref : K14212/BHTM/MM/CCM/2023/24
Date : 29 March 2023

ITEM PARTICULARS ACTION BY

17.2 Blow Up Unit Model


• EHSB to confirm all the finishes, paint color, size of tiles, etc. proposed by EHSB
KP88 so that the model can be done. Status remained – 3

18.0 SALE & PURCHASE AGREEMENT (SPA)

18.1 KP88 has revised the SPA Drawings & 4th schedule as per commented by EHSB
EHSB (email dated 16/1/2023). All has been emailed on 30/1/2023. EHSB to
check for confirmation. Status remained – 4

19.0 TENDER FOR PHASE 1

19.1 Target for tender phase 1 remained as follows; - All Noted


a. Final tender Drawing – 30/3/2023
b. Call for Tender – 30/4/2023

19.2 EHSB to confirm the building finishes for phase 1 as soon as possible so not EHSB
to delay the preparation of detail drawings for tender. Status remained – 1

20.0 BHTM PHASE 2

20.1 EHSB to coordinate with other consultants on the target date for BP All
Submission Phase 2. Status remained –2

21.0 TEMPORARY HOARDING PERMIT

21.1 Permohonan Kelulusan Pelan Hoarding & Papan Tanda Projek has been KP88
submitted to MDTM on 21/2/23. KP88 to follow up with the official latter for the
payment.

22.0 CCM NO.2023/25

21.1 CCM No. 2023/24 was adjourned at 12.15 pm and CCM No. 2023/25 shall be All Noted
on 12/4/2023 at 10.30 am

Prepared by :

For & on-behalf of


KUMPULAN PERUNDING (1988) SDN BHD

Amir Ikram Bin Ariffin


Graduate Architect

Page 8 of 8
BHTM - AUTHORITIES STATUS & ADDITIONAL INFO - (NO. 8) 30/03/2023
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
KM APRROVAL
MDTM informed all technical department to comments by 05/01/22. If no response
30/1/2023
or answer, they will proceed with approval before 12/01/23. Letter Kelulusan 15/8/22, DZI Consultants to comply all the
1 Jabatan Perancang MDTM KM Approval. Ref:MDTM/M/530 Jilid 1/2/2023 - -
Bersyarat KM by MDTM released on 30/01/23. Full KM approval will be approved 24/11/2022 (rev1) Planner comments by authorities
3(3)
after all conditions are comply. The conditions are as below:-

YC has submitted appeal letter


Ulasan :- (letter AKSB/MDTM/2022/LCP)
to AKSB on 27/02/23. As verbal
11/9/2022 informed by AKSB Pn. Syida on
1. Bekalan paip air paip AKSB saiz 450mm jenis mild steel yang berada sejauh 4.0km 15/8/22,
2 Air Kelantan Sdn. Bhd. KM Approval. Ref:AKSB/MDTM/2022/L 1/2/2023 YC 27/2/2023 12/03/23,, the sizes is for the -
dari tapak projek. 24/11/2022 (rev1)
CP area not for the tanks instead.
2. Saiz tangki sedutan 36m x 41m dan saiz tangki menara 42m x 42m.
Waiting official letter from
3. Membina dan menyiapkan sistem tangki pada fasa 1. AKSB.

JKR through letter dated


Ulasan :- (letter Bil (6) dlm.JKR.KN.R/RD/S04/886)
21/02/23 invites for TIA & RSA
30/8/2022 Report Presentation on
Jabatan Kerja Raya Negeri 15/8/22,
3 KM Approval Ref:Bil(6)dlm.JKR.KN.R/R 8/9/2022 YC 6/2/2023 02/03/23. JKR approval official Approved
Kelantan 24/11/2022 (rev1)
1. To submit TIA & RSA Reports Stage 1 & 2. D/S04/886 letter on 08/03/23.
Ref:Bil(3)dlm.JKR.KN.R/RD/S04
/886 Jld.1
12/12/2022
15/8/22,
4 BOMBA KM Approval Approved. Ref:JBPM/KN/ZMG:700- 22/12/2022 KP 88 Approved - Approved
24/11/2022 (rev1)
2/1/4/341/0858(6)
1/1/2023
15/8/22, Ref:JBPD.KN.KP/006/12/P
5 JPBD Negeri Kelantan KM Approval Approved. 1/2/2023 DZI Approved - Approved
24/11/2022 (rev1) T12289,886,7113&7115(4
)
Ulasan :- (letter JMG.KLT.(GS)/040 (50)
YC to comply all comments and
1. Di peringkat pelan kerja tanah, pemaju perunding hendaklah menyertakan submit together with revised
5/12/2022 27/03/23 (target)
Jabatan Mineral dan keratan rentas serta kaedah-kaedah pengukuhan cerun yang akan dilakukan. 15/8/22, earthwork drawing. Target
6 KM Approval Ref:JMG.KLT.(GS)/040(050 1/2/2023 YC 12/04/23 (new -
Geosains Malaysia, kelantan 2. Langkah-langkah kawalan dan mitigasi yang sewajarnya ke atas faktor-faktor 24/11/2022 (rev) submission date to MDTM on
) target)
bahaya geologi dan natural hazards yang dijangka akan memberi kesan kepada 27/03/23. New target
pembangunan dan juga kesan pelaksanaan pembangunan ke atas kawasan dan lot submission date 12/04/23.
berhampiran.
Approved. 5/10/2022
KM Approval (Layout Plan,
7 TNB 1. 1 unit Stesen Suis Utama (SSU) 15/8/2022 Ref:TNB(B)/KELA/TMER/ 10/10/2022 KNS Approved - Approved
calculation & system)
2. 2 unit Double Chamber MER/0174
Ulasan :- (letter TNB(B)/KELA/KBHA.KBU.PE.1870) TNB through letter reply date
1. Menyediakan 1 tapak Pencawang Pembahagian Utama 33/11kv (PPU) saiz 46m x 02/02/23 Ref:
46m KNS/2014/D/SPNBASB/TMER
5/1/2023
KM Approval (Layout Plan, 2. 1 unit SSU (SSU) 11kv dengan 2 transformer saiz 20m x 14.8m. 15/8/22, AH/28 rejected the appeal. KNS
8 TNB (New Comments) Ref:TNB(B)/KELA.KBHA.K 8/1/2023 KNS 19/1/2023 -
calculation & system) 3. 2 unit tapak pencawang double chamber saiz 14.8m x 16.6m. 24/11/2022 (rev) issued another appeal with
BU.PE.1870
calculation to TNB on
4. 2 unit tapak pencawang single chamber saiz 14.8m x 13.6m ( termasuk pasaraya 23/02/23. Waiting for TNB
dan kawasan komersil pandu lalu). reply/Approval.

22/8/2022
Suruhanjaya Komunikasi
9 KM Approval Approved. - Ref:SKMM(T)/05- 30/8/2023 KNS Approved. - Approved
dan Multimedia (SKMM)
KSO/70/002/02/Jld.1(30)
Ulasan :- (letter Bil ( )JPS.KN.TM.149/4015)
1. Kapasiti Kolam Takungan (wet pond) yang dicadang tidak mencukupi dengan
keluasan pembangunan. Keluasan kolam takungan hendaklah 3% - 5% daripada 1/1/2023 YC submitted the letter to JPS
15/8/22,
10 JPS Tanah Merah KM Approval keluasan kawasan pembangunan. Ref:Bil()JPS.KN.TM.149/40 1/2/2023 YC 27/2/2023 on 27/02/23. Waiting for JPS -
24/11/2022 (rev)
2. Semua aliran semulajadi hendaklah dikekalkan, sekiranya memerlukan lencongan 15 Offical comments/approval.
pihak pemohon perlu mendapatkan kelulusan daripada JPS Negeri Kelantan terlebih
dahulu
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
Ulasan :-
IWK through their letter dated
05/02/23 Ref:
IWK/C/KEL12/22/0123 stated
19 comments need to comply.
IWK request NPS to move to
6/12/2023
another place in order for
11 IWK KM Approval - Ref:IWK/C/KEL12/22/01 6/12/2023 YC 14/12/2023 -
1. 28 nos of comments. buffer zone comply. DZI has plot
23
the area for NPS nearby Drive-
Thru. YC has comments due
insufficient buffer zone area. YC
re-sent to DZI the drawing to be
overlay on master plan.

BP APPROVAL
Approved with condition :-
1. Payment ISF RM 84,695.00 to be made. EHSB reply with an appeal
2. Deposit Kebersihan RM 71,200.00 to be made. letter to MDTM for reducing ISF
and Deposit Kebersihan. MDTM
12/12/2022 In 30 days (12/03/23)
KP88 / reply with letter dated
1 Jabatan Bangunan MDTM BP Approval 3/11/2022 Ref:MDTM/OSC/PB/22/2 12/12/2022 13/12/2022 19/03/23 (ext. date)
EHSB 12/02/23 ref;
10(6) 02/04/23 (ext. date)
3. Misc. payment RM 26,310.00 to be made. MDTM/OSC/PB/22/210(11)
confirmed ISF maintain, deposit
kebersihan reduced to RM 30k.

EHSB reply with an appeal


12/12/2022 In 30 days (12/03/23)
KP88 / letter to MDTM for reducing ISF
2 Jabatan Bangunan MDTM KM Bangunan Approved with condition. To make payment for ISF, Deposit Kebersihan & Misc. 3/11/2022 Ref:MDTM/OSC/PB/22/2 12/12/2022 13/12/2022 19/03/23 (ext. date)
EHSB and Deposit Kebersihan.
10(6) 02/04/23 (ext. date)
Approved.
8/1/2023
3 Jabatan Bangunan MDTM BP - Tong Sampah Approved. 3/11/2022 Ref:MDTM/OSC/PB/22/2 8/1/2023 KP88 Approved - Approved
10(9)
Approved with condition.
1. To change name to Bandar Halaman Tanah Merah. Without @ Online submission done but
rejected by DBP. It is said
Bandar Halaman Tanah Merah
8/2/2023 Name not appropriate. KP88
4 Jabatan Lanskap MDTM BP - Nama Taman dan Nama Jalan 8/11/2022 Ref:MDTM/OSC/PN/22/0 14/2/2023 KP88 22/2/2023 will appeal another submission. -
2. To get confirmation in term of correct spelling. 3 (04) Online submission 15/03/23.
Hardcopy submission on
20/3/23. Target approval on
06/04/23.

3/1/2023
STRATAS
5 Jabatan Perancangan MDTM BP - Landscape Drawing Approved. 6/11/2022 Ref:MDTM/OSC/PL/22/07 - - - Approved
CAPE
(5)
Approved with conditions :- EHSB reply with an appeal
1/1/2023
Jabatan Pembangunan letter on 19/01/23 to MDTM
6 BP - Earthwork Drawing (Phase 1) 1. Payment processing fees RM 6,988.00 to be made. 23/11/2022 Ref:MDTM/KJ/2022/028( 18/1/2023 YC 19/1/2023 Approved
Kejuruteraan MDTM for reducing Deposit Kerja
2. Payment site visit RM 120.00 tp be made. )
Tanah.
3. Payment Deposit Kerja-Kerja Tanah RM 215,668.00 to be made
EHSB reply with an appeal
letter on 19/01/23 to MDTM
for reducing Deposit Kerja
12/2/2023 In 30 days (12/03/23)
Jabatan Pembangunan Letter to MDTM for reducing Deposit Kerja Tanah with 75% discount. As verbal Tanah. MDTM reply with letter
7 BP - Earthwork Drawing (Phase 1) 19/1/2023 Ref:MDTM/KJ/2022/028/ 16/2/2023 EHSB In 30days 19/03/23 (ext. date)
Kejuruteraan MDTM confirmed, 50% discount given to EHSB. Waiting official letter for MDTM. dated 12/02/23 ref;
(07) 02/04/23 (ext. date)
MDTM/KJ/2022/028(07)
confirmed 50% discount
approved.
BP - Revise Earthwork Drawing Target submission date on
Jabatan Pembangunan Submission of revised earthworks drawings after payment for phase 1 been made
8 Phase 1 & Overall Phases - - - - - 27/03/23. Extended date to be -
Kejuruteraan MDTM and approved by MDTM.
(encroachment neighbour land) 12/04/23.
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT
Approved with condition :- JKR through letter dated
21/02/23 invites for TIA & RSA
Jabatan Pembangunan 19/12/2022 Pemakluman
9 BP - Road & Drainage 1/11/2022 19/12/2022 YC 12/2/2023 Report Presentation on Approved
Kejuruteraan MDTM Mesyuarat OSC
1. To submit TIA & RSA Reports Stage 1 & 2. 02/03/23. Offial approval letter
by JKR dated 08/03/23.

Approved with condition :- EHSB reply with an appeal


letter to MDTM for omission
1. Payment processing fees RM 420.00 to be made. deposit. Official approval letter
Jabatan Pembangunan 2. Payment site visit RM 120.00 to be made. 1/1/2023
11 BP - Lampu Jalan 24/11/2022 31/1/2023 KNS 5/2/2023 MDTM dated 12/03/23 -
Kejuruteraan MDTM Ref:MDTM/OSC/LJ/22/12
ref:MDTM/KJ/2022/ 028(09)
3. Payment Deposit Lampu Jalan RM 22,015.00 stated RM10,000 + RM540.00
processing fees to pay.

JKR through letter dated


30/8/2022 21/02/23 invites for TIA & RSA
12 JKR Tanah Merah BP - Road & Drainage 1. To submit TIA & RSA Reports Stage 1 & 2. 15/8/2022 Ref:Bil.(6)dlm.JKR.KN.R/R 8/9/2022 YC 6/2/2023 Report Presentation on Approved
D/S04/886 02/03/23. Offial approval letter
by JKR dated 08/03/23.

Target submission date on


JKR Tanah Merah / Negeri
13 Road Safety Audit (Stage 3) 1. To submit RSA Stage 3 to JKR Tanah Merah / Negeri Kelantan 29/03/23. Extended date
Kelantan
04/04/23.
Rejected. To comply all the comments by JPS Negeri Kelantan :- JPS through their letter dated
20/02/23 rejected.
1. To submit Pelan Kerja Tanah & Pelan Kawalan Hakisan.
30/11/2022 Ref:Bil(4)dlm.JPS.KN.BPBSMA/
BP - Permohonan Kelulusan Pelan 2. To submit a detailed / comprehensive pelan sistem perparitan.
Ref:Bil(2)dlm.JPS.KN.BPBS 149/665/TM/2022/01/02. YC
13 JPS Negeri Kelantan Kerja Tanah / ESCP dan Sistem 26/10/2022 5/12/2023 YC 29/1/2023 -
3. To ensure if there existing alur that need to divert, must get approval from JPS. MA/149/665/TM/2022/0 to re-submit the application for
Perparitan
1/02 approval. Target submission
4. To re-design the drainage so as to have control structure at source before final date to JPS on 19/03/23. Ext.
discharge & all drainage cover over 600mm need to be well covered and to provide date 06/04/23.
sump every 10mtr.
Approved. 5/10/2022
BP Approval (Layout Plan,
14 TNB 1. 1 unit Stesen Suis Utama (SSU) 2/8/2022 Ref:TNB(B)/KELA/TMER/ 10/10/2022 KNS Approved - Approved
calculation & system)
2. 2 unit Double Chamber MER/0174
Ulasan :- TNB through letter reply date
1. Menyediakan 1 tapak Pencawang Pembahagian Utama 33/11kv (PPU) saiz 46m x 02/02/23 Ref:
46m KNS/2014/D/SPNBASB/TMER
5/1/2023
BP Approval (Layout Plan, 2. 1 unit SSU (SSU) 11kv dengan 2 transformer saiz 20m x 14.8m. AH/28 rejected the appeal. KNS
15 TNB (New Comments) 24/11/2022 Ref:TNB(B)/KELA.KBHA.K 8/1/2023 KNS 19/2/2023 -
calculation & system) 3. 2 unit tapak pencawang double chamber saiz 14.8m x 16.6m. issued another appeal with
BU.PE.1870
calculation to TNB on
4. 2 unit tapak pencawang single chamber saiz 14.8m x 13.6m ( termasuk pasaraya 23/02/23. Waiting TNB official
dan kawasan komersil pandu lalu). reply/approval.
12/12/2022
16 BOMBA BP Approval Approved. 6/11/2022 Ref:JBPM/KN/ZMG:700- 22/12/2022 KP 88 Approved - Approved
2/1/4/341/0858(6)

18/1/2023
17 TELEKOM BP Approval Approved. 8/8/2022 - KNS Approved - Approved
Ref:4415A/TAM/2022/07

Ulasan :- YC has submitted appeal letter


to AKSB on 27/02/23. As verbal
1. Bekalan paip air paip AKSB saiz 450mm jenis mild steel yang berada sejauh 4.0km 19/1/2023 informed by AKSB Pn. Syida on
18 Air Kelantan Sdn. Bhd. BP Approval dari tapak projek. 7/11/2022 Ref:AKSB/MDTM/2022/L 19/1/2022 YC 27/2/2023 12/03/23,, the sizes is for the -
2. Saiz tangki sedutan 36m x 41m dan saiz tangki menara 42m x 42m. CP/MAKLUMAT area not for the tanks instead.
Waiting official letter from
3. Membina dan menyiapkan sistem tangki pada fasa 1. AKSB.
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT

IWK through their letter dated


05/02/23 Ref:
IWK/C/KEL12/22/0123 stated
19 comments need to comply.
IWK request NPS to move to
6/12/2023
another place in order for
19 IWK BP Approval IWK has come out the letter with 19 comments need to comply. 25/11/2022 Ref:IWK/C/KEL12/22/01 6/12/2022 YC 14/12/2023 -
buffer zone comply. DZI has plot
23
the area for NPS nearby Drive-
Thru. YC has comments due
insufficient buffer zone area. YC
re-sent to DZI the drawing to be
overlay on master plan.
DATE REPLY
SUBMISSION AUTHORITY DATE RE-SUBMITTED
NO AUTHORITIES PARTICULARS DESCRIPTION PIC BY REMARKS
DATE LETTER DATE RECEIVED DATED
CONSULTANT

Additional Info

No. Particulars Deadline Ext. Date PIC


Cost Plan for Single Storey Terrace House - 2 options. M&E Cost plan submitted to WAW on 05/03/23. YOF drawing R.C Wall between unit & road to
1 21/2/2023 27/2/2023 (08/03/23) WAW/YOF
submit to WAW by 08/03/23.

2 Cost Plan Single Storey Terrace House - 2 option to EHSB 15/3/2023 - WAW

2 Main Entrance Archway - Confirmed. 20/2/2023 9/3/2023 (15/03/23) EHSB

3 Model Making drawing. The drawings email to EHSB on 16/02/23. 16/2/2023 To confirm the cost plan EHSB

To submit after payment


4 Earthwork revised drawing for authority approval 22/2/2023 made & approved by YC
MDTM
5 Earthworks Closed Tender 8/3/2023 15/3/2023 Info

6 STP Confirmation & Award Contractor - TBC Info

7 Sales and Purchase Agreement (SPA) 15/3/2023 - EHSB

8 Building Plan Submission (Phase 2) TBC - -

9 Temporary Hoarding Permit Approval by MDTM. Verbal approved. Waiting official letter from MDTM. To update - KP88

10 M&E Electrical tender drawing. Re-submitted on 29/03/23 22/3/2023 29/3/2023 KNS

11 Overall Infrastructure Drawing draft for costing. As mentioned by YC, need to confirm overall layout master plan. 28/3/2023 TBC YC

Anda mungkin juga menyukai