MATERIAL
Kuat tekan beton f’c = 35.0 Mpa
Kuat leleh baja tulangan, (D > 12 mm), fy = 400.0 Mpa
Kuat leleh baja tulangan, (D ≤ 12 mm), fy = 400.0 Mpa
Berat beton bertulang γc = 24.0 kN / m3
DIMENSI
Tebal plat pondasi h= 1.00 m
Posisi kolom pedestal, (dalam = 40, tepi = 30, sudut = 20) αs = 30.0
Lebar pilecap Lx = 1.2 m
Panjang pilecap Ly = 1.2 m
Diameter tiang Dp = 0.7 m
Jumlah tiang
arah-x nx = 1.0
arah-y ny = 1.0
Total n(pile) = 1.0 pile
Jarak antar tiang
arah-x sx = - m
arah-y sy = - m
1 of
Pemodelan dengan SAP2000:
Kontur Momen
2 of
Lebar bidang geser pons arah x Bx = bx + d = 1.2 m
Lebar bidang geser pons arah y By = by + d = 1.2 m
Gaya geser pons yang terjadi Puk = 1320 kN
Luas bidang geser pons Ap = 2 * (Bx +By) * d = 4.4 m2
Lebar bidang geser pons bp = 2 * (Bx + By) = 4.8 m
Rasio sisi panjang thd. sisi pendek kolom βc = bx / by = 1.0
Tegangan geser pons, diambil nilai terkecil dari fp yang diperoleh dari pers. sbb:
fp = (1 + 2 / βc) * sqrt (fc’) / 6 = 3.0 Mpa
fp = (αs * d / bp + 2) * sqrt(f’c) / 12 = 3.80 Mpa
fp = 1 / 3 * sqrt (fc’) = 1.97 Mpa
Tegangan geser pons yang disyaratkan fp = 1.97 Mpa
Faktor reduksi kekuatan geser pons φ= 0.8
Kuat geser pons φ * Vnp = φ * Ap * fp * 103 = 6478 kN
Syarat:
φ * Vnp > Puk
6478 > 1320 → AMAN
TULANGAN LENTUR
3 of
Luas tulangan yang diperlukan, As = ρ . b . d = 3675 mm2
Diameter tulangan yang digunakan D 25 mm
Jarak tulangan yang diperlukan, s = π / 4 . D 2 . B / As = 160 mm
Jarak tulangan maximum, smax = 450 mm
Jarak tulangan yang digunakan s= 150 mm
Digunakan tulangan, D 25 - 150 mm
Luas tulangan terpakai As = π / 4 * D2 * b / s = 3,927 mm2
4 of
MATERIAL
Kuat tekan beton f’c = 35.0 Mpa
Kuat leleh baja tulangan, (D > 12 mm), fy = 400.0 Mpa
Kuat leleh baja tulangan, (D ≤ 12 mm), fy = 400.0 Mpa
Berat beton bertulang γc = 24.0 kN / m3
DIMENSI
Tebal plat folder h= 0.30 m
Posisi kolom pedestal, (dalam = 40, tepi = 30, sudut = 20) αs = 30.0
Lebar folder B= 3.2 m
Tinggi muka air D= 5.3 m
TULANGAN ANGKUR
5 of