I Pek. Persiapan
1 Pek. Bowplank 40.000 m'
Kaso Borneo 5/7 8.400 btg 22,500 189,000
Reng Borneo 3/4 10.000 btg 12,500 125,000
Total I 314,000
II Pek. Pondasi
Total II 4,432,388
Total IV 22,153,990
V Pek. Lantai
Total V 1,798,011
VI Pek. Plafond
Total VI 2,265,715
2 Listplank 11.040 m1
Listplank GRC 5.520 lbr 38,000 209,760
Paku 0.552 kg 12,000 6,624
2 Pintu
P4 @ 1 unit pintu PVC 1.000 unit 175,000 175,000
1 Pintu
Kunci Pintu 4.000 set 75,000 300,000
Engsel 4" 4.000 set 30,000 120,000
Total IX 420,000
3 Bak Kontrol
batako 5.000 bh 2,000 10,000
Semen 0.250 zak 47,000 11,750
Pasir 0.100 m3 200,000 20,000
4 Septic Tank
Buis Beton dia. 100 cm 1.000 bh 250,000 250,000
Total X 2,347,702
XI Pek. Instalasi Listrik
Total XI 982,000
1 Carport 0.450 m3
Semen 1.575 zak 47,000 74,025
Pasir 0.306 m3 200,000 61,200
Split 0.468 m3 245,000 114,660
XV Pek. Pengecatan
Total XV 1,625,217
TOTAL 95,100,122
REKAPITULASI
Rencana Anggaran Biaya
Perumahan Puri Delta Tigaraksa
Type : 30/60 mawar
A PEMBANGUNAN
1 Material Rp. 95,100,122
B TANAH
1 luas 60 m2 x Rp. 2.500.000,- Rp. 150,000,000