RENCANA ANGGARAN BIAYA

NAMA PROYEK : PESANTREN MA'HAD FAHMUSSALAM ALAZIZIYAH


LOKASI : JL.KARYA MARENDAL I - DELI TUA - SUMATERA UTARA
BANGUNAN : PEMBANGUNAN GEDUNG PESANTREN
TAHUN : Januari 2021
SUB-PEKERJAAN : 8 KELAS 1 LANTAI

Total Harga
No REKAPITULASI
Rp.

1 PEKERJAAN STRUKTUR 262.170.000

2 PEKERJAAN ARSITEKTUR 235.150.000

3 PEKERJAAN ELEKTRIKAL 2.680.000

TOTAL 500.000.000
RENCANA ANGGARAN BIAYA

NAMA PROYEK : PESANTREN MA'HAD FAHMUSSALAM AL AZIZIYAH


LOKASI : JL.KARYA MARENDAL I - DELI TUA - SUMATERA UTARA
TAHUN : 2020
BANGUNAN : PEMBANGUNAN GEDUNG PESANTREN
SUB-PEKERJAAN : STRUKTUR 8 KELAS 1 LANTAI

Koef per Harga Satuan Total Harga


No ANALISA URAIAN PEKERJAAN Sat Volume
lantai Rp. Rp.

ELEVASI + 0.000 S/D + 4.000

A PEKERJAAN KOLOM
1 Kolom K 1Uk. 400 x 300 per titik
- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 - - -
- Pembesian ( 200 kg / m3) 1,000 kg - - -
- Bekisting 1,000 m2 - - -
-
80 titik ( All ) -
30 titik -

2 Kolom K 2 Uk. 300 x 300


- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 - - -
- Pembesian 1,000 kg - - -
- Bekisting 1,000 m2 - - -
-
20 titik ( All ) -
10 titik ( Tahap 1 ) -

B PEKERJAAN BALOK
1 B - 1 uk. 500 x 250 per mtr
- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,02 860.000 13.438
- Pembesian ( 150 kg/m3 ) 1,000 kg 2,35 10.000 23.500
- Bekisting 1,000 m2 0,15 115.000 17.250
54.188
18 mtr 975.375

2 B - 2 uk. 400 x 200 per mtr


- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,01 860.000 8.600
- Pembesian ( 170 kg/m3 ) 1,000 kg 1,70 10.000 17.000
- Bekisting 1,000 m2 0,15 115.000 17.250
42.850
660 mtr ( All Lt 2 ) 28.281.000
169mtr ( Tahap 1 ) 7.241.650

3 B - 3 uk. 300 x 200 per mtr


- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,01 860.000 6.450
- Pembesian ( 170 kg/m3 ) 1,000 kg 1,30 10.000 13.000
- Bekisting 1,000 m2 0,10 115.000 11.500
30.950
228 mtr ( All Lt.2 ) 7.056.600
128,5 mtr ( Tahap 1 ) 3.977.075

4 B - 4 uk. 200 x 200 per mtr


- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,01 860.000 4.300
- Pembesian ( 150 kg/m3 ) 1,000 kg 0,75 10.000 7.500
- Bekisting 1,000 m2 0,08 110.000 8.250
( All Lt.2 / Tahap 1 ) 20.050

20,6 mtr 413.030

C PEKERJAAN PLAT LANTAI


1 Pek. Plat Lantai 15 cm per m2
- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,02 860.000 16.125
- Pembesian (125 kg / m3 ) 1,000 kg 2,35 10.000 23.500
- Bekisting 1,000 m2 0,12 110.000 13.200
52.825
0 m2 -

2 Pek. Plat Lantai 12 cm2 per m2


- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,02 860.000 12.900
- Pembesian 1,000 kg 1,90 10.000 19.000
- Bekisting 1,000 m2 0,12 110.000 13.200
45.100
1232 m2 ( All Lt.2 ) 55.563.200
431 m2 19.438.100

D PEK. STRUKTUR TANGGA DARI LT 01 KE LT 02


1 Pek. Tangga A ( 1 unit )
- Beton Ready Mix f'c = 24.90 Mpa (K-225) 1,000 m3 0,40 860.000 344.000
- Pembesian ( 125 kg /m3 ) 1,000 kg 50,00 10.000 500.000
- Bekisting 1,000 m2 2,50 110.000 275.000
1.119.000
1 unit ( Lt 1 ) 1.119.000

PEK.STRUKTUR 1 KELAS Sub total Rp. 32.771.250

PEK.STRUKTUR 8 KELAS 262.170.000


RENCANA ANGGARAN BIAYA

NAMA PROYEK : PESANTREN MA'HAD FAHMUSSALAM ALAZIZIYAH


LOKASI : JL.KARYA MARENDAL I - DELI TUA - SUMATERA UTARA
TAHUN : 2020
BANGUNAN : PEMBANGUNAN RUANG BELAJAR
SUB-PEKERJAAN : ARSITEKTUR 8 KELAS 1 LANTAI

KOEF
HARGA SATUAN TOTAL HARGA
No. ANALISA URAIAN PEKERJAAN BANG PER SAT VOLUME
(Rp.) (Rp.)
LANTAI

PEKERJAAN ARSITEKTUR LANTAI - 1

A PEKERJAAN DINDING
1 Pek. Dinding Bata 1,000 m2 460,00 100.000,00 46.000.000,00
2 Pek. Plesteran + acian, campuran mortar tebal 10 mm 1,000 m2 920,00 80.000,00 73.600.000,00
3 Pek. Cat tembok 1,000 m2 920,00 25.000,00 23.000.000,00
4 Batu angin 1,000 m2 18,00 - -
5 Ruang pengasuh 1,000 set - - -
142.600.000,00

B PEKERJAAN LANTAI
1 Pek. Lantai Homogenous Tile 40x40 cm (un-polish) 1,000 m2 429,00 130.000,00 55.770.000,00
2 Pek. Plin lantai Tile 40x10 cm (un-polish) 1,000 m2 21,00 130.000,00 2.730.000,00
3 Pek. Lantai K.Mandi Tile 30x30 cm 1,000 m2 16,00 - -
4 Pek. dinding K.Mandi Tile 30x30 cm 1,000 m2 27,00 - -
5 Tanah timbun level 1,000 m3 115,00 - -
58.500.000,00

C PEKERJAAN PLAFOND
1 Pek. Plafond Gypsum Board tebal 9 mm, termasuk
rangka hollow galvanized 40x40 mm berikut gantungan. 1,000 m2 445,00 - -
2 Pek. Cat tembok plafond 1,000 m2 445,00 - -
-

D PEKERJAAN BESI
1 Pek. Railing Tangga, dari bahan, ukuran serta detail sesuai
dengan gambar untuk itu.
- Tangga Depan (dari lantai-1 ke lantai-2) 1,000 m 7,00 - -
- Tangga Belakang (dari lantai-1 ke lantai-2) 1,000 m - - -
-

E PEKERJAAN KUSEN, PINTU, JENDELA DAN PARTISI


Pek. Kosen, Pintu & Jendela
1 Kosen Pintu (Type P-01) 1,000 unit 9,00 800.000,00 7.200.000,00
2 Kosen Jendela 4 lobang + kaca naco (Type J-01) 1,000 unit 16,00 1.200.000,00 19.200.000,00
3 Daun Pintu Panel 1,000 unit 9,00 850.000,00 7.650.000,00
4 Daun pintu pvc 1,000 unit 4,00 - -
34.050.000,00

F PEKERJAAN SANITARY DAN TAMBAHAN


Perlengkapan Toilet
1 Pas. Closed Jongkok 1,000 unit 4,00 - -
2 Pas. Jet Shower 1,000 bh - - -
3 Plumbing + Accessories 1,000 Ls 1,00 - -
4 Septik Tank uk. 1x2x1,5 mtr 1,000 unit 4,00 - -
5 Kanopy ( genteng ) 1,000 unit 1,00 - -
-

SUB-TOTAL PEKERJAAN ARSITEKTUR, 8 KELAS 1 LANTAI 235.150.000,00