Jawab # 2: (Projek)

B E

A C I
F

D G

Critical Path : ADGHI, dengan waktu normal proyek = 19 minggu


Total Cost = 19 x 600 = Rp11.400,-

Aktivitas StDev Waktu Ic/week


Kritis s2 t'sedia
A (2/6)2=0,11 1 50
D 0 0
G (8/6)2=1,78 4 120
H 0 0
I 0 0
Ss2 = 1.89
s= 1.37
CP n=0 n=1 n-2 n=3 n=4 n=5
ADGHI 19 18 17 16 15 14
ACFHI 17 16 16 16 15 14
ABEI 14 13 13 13 13 13
Cost to crash - A G G G,F G,C
Act to crash - 50 50+120 170+120 290+120+80 490+120+200
TC 11400 10850 10370 9890 9490 9210

(a). Waktu optimal projek = 14 minggu


(b). Kemungkinan projek selesai dalam 17 minggu:
Z = (17-19) / 1,37 = -1,46
P (Z= -1,46) = 7,21%
(c ). Projek selesai 90% dalam waktu:
P(Z=…) = 0.90 Z = 0.82

X  19 X = 20.12 minggu
Z   0 .82
1,37
(d). Tidak ada pengaruhnya, karena akt. E bukan akt kritis & keterlambatannya masih
dalam batas (tdk melebihi) toleransi slack.

Jawab #1: Perencanaan Kapasitas


SOAL 3 - EOQ
D=7200
Co= 2000
Cc= 8%

Q (m3) Harga ($) eoq ket tc


0-499 1400
500 - 999 1300 526.2348 ok 9,414,728
1.000- 1.799 1200 547.7226 not 8,702,400
1.800-2.399 1100 572.0776 not 8,007,200
>=2.400 1000 600 not 7,302,000 optimal

EOQ 2400
F 3
d 20

A. JUMLAH PEMESANAN YANG OPTIMAL ADALAH 2.400 M3 120


PEMESANAN DILAKUKAN 3KALI DALAM 1 TAHUN

B. BESARNYA TOTAL BIAYA PERSEDIAAN SEBESAR $ 7.302.000


C. BESARNYA SAFETY STOCK = 1.89 * 2 * √20 = 16.9046739 17 M3
ROP = 5*20 + 17 = 117 M3

D. GAMBAR EOQ

Q
EOQ = 2.400

1200

ROP = 100
0
120 240 360
SS = 17 hari
TABEL MRP
1 2 3 4 5 6 7 8
Item ID: FM Gross Requirement 300 250
Level code: 0 Scheduled Receipts
On hand: 50 Projected On Hand 50 50 50 50 50 50 50 50
Lot Size: LFL Net Requirements 250 200
LT: 2 Planned Order Receipts 300 250
SS: 50 Planned Order Releases 300 250
Item ID: PP Gross Requirement 400
Level code: 0 Scheduled Receipts
On hand: 30 Projected On Hand 30 30 30 30 30 30 30 30
Lot Size: LFL Net Requirements 370
LT: 3 Planned Order Receipts 400
SS 30 Planned Order Releases 400
Item ID: DCV Gross Requirement 300 250
Level code: 1 Scheduled Receipts
On hand: 70 Projected On Hand 70 70 70 70 20 20 20 20
Lot Size: 250 Net Requirements 230 230
LT: 3 Planned Order Receipts 250 250
SS: 20 Planned Order Releases 250 250

Item ID: ACT Gross Requirement 600 500


Level code: 1 Scheduled Receipts
On hand: 0 Projected On Hand 0 0 0
Lot Size: LFL Net Requirements 600 500
LT: 2 Planned Order Receipts 600 500
SS: 0 Planned Order Releases 600 500
#4
Item ID: FT Gross Requirement 600 900
Level code: 2 Scheduled Receipts
On hand: 200 Projected On Hand 200 200 350 350 200 200 200 200
Lot Size: 750 Net Requirements 400 550
LT: 1 Planned Order Receipts 750 750
SS: 200 Planned Order Releases 750 750
Item ID: SP Gross Requirement 600 2100
Level code: 2 Scheduled Receipts
On hand: 600 Projected On Hand 600 600 750 750 150 150 150 150
Lot Size: 750 Net Requirements 0 1350
LT: 1 Planned Order Receipts 750 1500
SS: 150 Planned Order Releases 750 1500

RINGKASAN MRP:
ITEM Mg-ke Unit
DCV 1 250
3 250
FT 1 750
3 750
SP 1 750
2 1500
Institut Bisnis dan Informatika Indonesia - UAS Genap '08/09