I Preliminary Wokrs
- Mobilisasi dan Demobiliasi alat 1.00 ls 2,000,000
- Koordinasi Keamanan 1.00 ls 500,000
- Pembersihan lahan 1.00 ls 500,000
- Pekerjaan Stek out 1.00 ls 500,000
Sub Total Preliminary
II Foundation Works
a Galian
- Pondasi Setempat 1.80 m3 85,800
- Sloof 3.48 m3 55,000
b Pemadatan Tanah bekas galian
- Pondasi Setempat 1.80 m2 42,900
- Sloof 11.60 m2 27,500
c Buang tanah bekas galian 1.80 m3 50,000
d Pondasi Setempat K-175
- Bekisting bata 24.00 m2 91,012
- Pembesian 213.70 kg 16,348
- Beton 1.80 m3 721,889
f Sloof 200x300 K-175
- Bekisting bata 34.81 m2 91,012
- Pembesian 293.43 kg 16,348
- Beton 3.48 m3 721,889
Sub Total Foundation Works
III Gate Cluster
a - Pekerjaan Pagar area Gerbang fin. 58.01 m' 1,660,584
Zincromate
Sub Total Gate Cluster
Total
PPn 11%
Grand Total
1
OE NEGOSIASI
Amount Unit Price Amount
Item
Bekisting Bata
Pembesian
Beton
Pekerjaan pagar
Item
Bekisting Bata
Pembesian
Beton
Pekerjaan pagar
Pondasi Setempat
Jumlah pondasi setempat Lebar Tinggi Tebal Beton
20.00 0.3 1.00 0.3 1.8
Pondasi Setempat
Panjang besi Jumlah Panjang besi panjang besi /btg Qty (Btg)
4D10 2.25 9.00 12 0.75
mbersian Sloof Panjang besi Jumlah Panjang besi panjang besi /btg Qty (Btg)
3D10 58.01 174.03 12 14.50
2D10 58.01 116.02 12 9.67
Berat Besi /btg Qty Besi / unit pondasi Jumlah Pondasi Total Besi
7.4 5.55 20.00 111
Qty (Btg) Berat Besi /btg Qty Besi / unit pondasi Jumlah Pondasi Total Besi
1.08 4.74 5.14 20 102.70 213.70
Berat Besi /btg Qty Besi / unit pondasi Total Besi Total Besi Sloof
7.4 107.32 178.86 293.43
7.4 71.55