Lampiran 1
Kondisi Proyeksi Naik / Turun
URAIAN
Seb. Kredit Set. Kredit Nominal %
1. Aktiva Lancar
a. Kas dan bank (Bulldozer) 5,560,088,035 4,673,588,035 (886,500,000) -15.94%
b. Kas & bank (dana termijn proyek) 0 0 0 #DIV/0!
c. Piutang 7,075,085,700 7,428,839,985 353,754,285 5.00%
d. Piutang Pada Pemegang Saham 0 0 0 #DIV/0!
e. Piutang 0 0 0 #DIV/0!
f. Persediaan Onderdil, minyak, oli, dll 1,023,567,800 1,074,746,190 51,178,390 5.00%
g. Sewa Dibayar Dimuka 0 0 0 #DIV/0!
Total Aktiva Lancar 13,658,741,535 13,177,174,210 (481,567,325) -3.53%
2. Aktiva Tetap
a. Bulldozer 2,386,500,000 4,773,000,000 2,386,500,000 100.00%
b. Kendaraan 35,020,432,431 35,020,432,431 0 0.00%
c. Mesin-mesin 0 0 0 #DIV/0!
d. Peralatan 0 0 0 #DIV/0!
e. Inventaris 53,000,000 53,000,000 0 0.00%
f. Akumulasi Penyusutan Aktiva Tetap (202,441,329) (389,132,658) (186,691,329) 92.22%
3. Hutang Lancar
a. Hutang Usaha 7,525,812,565 7,525,812,565 0 0.00%
b. Hutang Piha 0 0 0 #DIV/0!
c. Hutang BRI 0 0 0 #DIV/0!
d. Hutang Pajak 0 0 0 #DIV/0!
Total Hutang Lancar 7,525,812,565 7,525,812,565 0 0.00%
Pendapatan Sewa Alat Berat 1,209,600,000 1,192,320,000 1,166,400,000 1,249,920,000 1,252,800,000 1,223,040,000 1,385,440,000
Harga Pokok Penjualan 0 0 0 0 0 0 0
Laba Kotor 1,209,600,000 1,192,320,000 1,166,400,000 1,249,920,000 1,252,800,000 1,223,040,000 1,385,440,000
Pendapatan lainnya 0 0 0 0 0 0 0
Laba Setelah Pendapatan Lain 1,209,600,000 1,192,320,000 1,166,400,000 1,249,920,000 1,252,800,000 1,223,040,000 1,385,440,000
Biaya Operasional :
a. Gaji Operator 26,880,000 25,920,000 25,920,000 26,880,000 27,840,000 26,880,000 30,800,000
b. Gaji Pembantu Operator 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 18,000,000 19,500,000
c. Gaji Pengurus 48,000,000 48,000,000 48,000,000 48,000,000 48,000,000 48,000,000 52,000,000
d. Biaya Bahan Bakar 102,835,200 109,262,400 102,835,200 102,835,200 96,408,000 102,835,200 111,404,800
e. Listrik, Air dan Telepon 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,200,000
f. Perawatan Bulldozer 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,000,000 6,500,000
g. Biaya Mobilisasi Alat 32,400,000 32,400,000 32,400,000 32,400,000 32,400,000 32,400,000 35,100,000
h. Biaya Umum dan adm kantor 250,000 250,000 250,000 250,000 250,000 250,000 250,000
i. Biaya Lain-lain 130,000 130,000 130,000 130,000 130,000 130,000 130,000
Total Biaya Operasional 236,495,200 241,962,400 235,535,200 236,495,200 231,028,000 236,495,200 257,884,800
Laba Operasional 973,104,800 950,357,600 930,864,800 1,013,424,800 1,021,772,000 986,544,800 1,127,555,200
Penyusutan 175,941,329 175,941,329 175,941,329 175,941,329 175,941,329 175,941,329 186,691,329
Laba Seb. Bunga dan Pajak 797,163,471 774,416,271 754,923,471 837,483,471 845,830,671 810,603,471 940,863,871
Bunga bank 96,278,018 96,278,018 96,278,018 96,278,018 96,278,018 96,278,018 113,069,685
Laba Sebelum Pajak 700,885,453 678,138,253 658,645,453 741,205,453 749,552,653 714,325,453 827,794,187
Pajak 77,097,400 74,595,208 72,451,000 81,532,600 82,450,792 78,575,800 91,057,361
Laba Bersih 623,788,053 603,543,045 586,194,453 659,672,853 667,101,861 635,749,653 736,736,826
Kas Masuk dari Penjualan 1,209,600,000 1,192,320,000 1,166,400,000 1,249,920,000 1,252,800,000 1,223,040,000 1,385,440,000
Kas Masuk dari pendapatan lain-lain 0 0 0 0 0 0 0
Kas Keluar :
a. Harga Pokok Penjualan - - - - - - -
b. Biaya Operasional 236,495,200 241,962,400 235,535,200 236,495,200 231,028,000 236,495,200 257,884,800
c. P a j a k 77,097,400 74,595,208 72,451,000 81,532,600 82,450,792 78,575,800 91,057,361
Total Kas Keluar 313,592,600 316,557,608 307,986,200 318,027,800 313,478,792 315,071,000 348,942,161
Saldo Kas seb. Kewajiban Kpd Bank 896,007,400 875,762,392 858,413,800 931,892,200 939,321,208 907,969,000 1,036,497,839
Lampiran 2
Naik / Turun
Nominal %
162,400,000 13.28%
0 #DIV/0!
162,400,000 13.28%
0 #DIV/0!
162,400,000 13.28%
3,920,000 14.58%
1,500,000 8.33%
4,000,000 8.33%
8,569,600 8.33%
200,000 10.00%
500,000 8.33%
2,700,000 8.33%
0 0.00%
0 0.00%
21,389,600 9.04%
141,010,400 14.29%
10,750,000 6.11%
130,260,400 16.07%
16,791,667 17.44%
113,468,733 15.88%
12,481,561 15.88%
100,987,173 15.88%
Naik / Turun
Nominal %
162,400,000 13%
0 #DIV/0!
- #DIV/0!
21,389,600 9%
12,481,561 16%
33,871,161 11%
128,528,839 14%
79,291,667 21%
62,500,000 23%
16,791,667 17%
49,237,173 9%
Direktur Utama Lucy Herlima
Nama Usaha PT. SINAR JAYA ABADI
Rugi/Laba Periode Agustus 2022 sd Januari 2023
Lampiran 3
Kondisi
URAIAN
sd Des 2021
Biaya Operasional :
a. Biaya bahan 0
b. Biaya upah dan honor personil lapangan 0
c. Biaya peralatan dan transportasi 0
d. Biaya administrasi dan operasional proyek 0
#DIV/0!
Direktur Utama Lucy Herlima
Nama Usaha PT. SINAR JAYA ABADI
Rugi/Laba Periode Agustus 2022 sd Januari 2023
Gabungan
Lampiran 4
Jumlah Jumlah
URAIAN
Agus 2022 sd Jan 2023 Rata-rata per bln
Usaha Sewa Bulldozer
Pendapatan Sewa Alat Berat 7,294,080,000 1,215,680,000
Harga Pokok Penjualan - -
Laba Kotor 7,294,080,000 1,215,680,000
Pendapatan lainnya - -
Laba Setelah Pendapatan Lain 7,294,080,000 1,215,680,000
Biaya Operasional :
a. Gaji Operator 160,320,000 26,720,000
b. Gaji Pembantu Operator 108,000,000 18,000,000
c. Gaji Pengurus 288,000,000 48,000,000
d. Biaya Bahan Bakar 617,011,200 102,835,200
e. Listrik, Air dan Telepon 12,000,000 2,000,000
f. Perawatan Bulldozer 36,000,000 6,000,000
g. Biaya Mobilisasi Alat 194,400,000 32,400,000
h. Biaya Umum dan adm kantor 1,500,000 250,000
i. Biaya Lain-lain 780,000 130,000
Total Biaya Operasional 1,418,011,200 236,335,200
Laba Operasional 5,876,068,800 979,344,800
Penyusutan 1,055,647,973 175,941,329
Laba Seb. Bunga dan Pajak 4,820,420,827 803,403,471
Bunga bank 577,668,108 96,278,018
Laba Sebelum Pajak 4,242,752,719 707,125,453
Pajak 472,697,227 78,782,871
Laba Bersih 3,770,055,492 628,342,582
Usaha Kontraktor
Penerimaan bersih dari proyek 0 0
0 0
Laba Kotor 0 0
Pendapatan lainnya 0 0
Laba Setelah Pendapatan Lain 0 0
Biaya Operasional :
a. Biaya bahan 0 0
b. Biaya upah dan honor personil lapangan 0 0
c. Biaya peralatan dan transportasi 0 0
d. Biaya administrasi dan operasional proyek 0 0
URAIAN Periode
Biaya Operasional :
a. Gaji Operator 3,920,000
b. Gaji Pembantu Operator 1,500,000
c. Gaji Pengurus 4,000,000
d. Biaya Bahan Bakar 8,569,600
e. Listrik, Air dan Telepon 500,000
f. Perawatan Excavator 500,000
g. Biaya Mobilisasi Alat 2,700,000
h. Biaya Umum dan adm kantor 250,000
i. Biaya Lain-lain 130,000
Total Biaya Operasional 22,069,600
Laba Operasional 140,330,400
Penyusutan 10,750,000
Laba Seb. Bunga dan Pajak 129,580,400
Bunga bank 16,791,667
Laba Sebelum Pajak 112,788,733
Pajak 12,406,761
Laba Bersih 100,381,973
61.81%
Direktur Utama Lucy Herlima
Cash Flow
URAIAN Periode
3. Solvabilitas
a. Aktiva Thd. Total Hutang (Aset to liability ratio) 314.29% 302.01% -12.28%
b. Total Hutang thd. Modal (debt to equity ratio) 46.67% 49.50% 2.84%
4. Aktivitas
a. Perputaran Piutang (Collection periode) 174 161 -13
b. Perputaran Asset (Aset turn over) 1,249 1,140 -109
5. Profitabilitas
a. Profit Margin 51.98% 53.18% 1.20%
b. Return On Asset (R O A) 1.25% 1.40% 0.15%
c. Return On Equity (R O E ) 1.83% 2.09% 0.26%
Penyst
Lampiran 7
DAFTAR PENYUSUTAN AKTIVA TETAP
PT. SINAR JAYA ABADI
Per 31 Januari 2023
Nilai Buku Tahun Perk. Umur Perk. Nilai Penyusutan Penyusutan Jumlah
No. Aktiva tetap
(Perolehan) Perolehan Teknis Residu Per- bulan Per- tahun Penyusutan
1 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
2 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
3 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
4 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
5 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
6 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
7 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
8 DT MITSUBISHITRONTON 625,000,000 2011 10 40% 3,125,000 37,500,000 3,125,000
9 DT MITSUBISHITRONTON 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
10 DT MITSUBISHITRONTON 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
11 DT MITSUBISHITRONTON 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
12 DT MITSUBISHITRONTON 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
13 DT MITSUBISHITRONTON 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
14 DT MITSUBISHITRONTON 675,000,000 2013 10 40% 3,375,000 40,500,000 3,375,000
15 DT MITSUBISHITRONTON 675,000,000 2013 10 40% 3,375,000 40,500,000 3,375,000
16 DT MITSUBISHITRONTON 675,000,000 2013 10 40% 3,375,000 40,500,000 3,375,000
17 SANY PC 200 650,000,000 2012 10 40% 3,250,000 39,000,000 3,250,000
18 KOMATSU D 85 ES 450,000,000 2012 10 40% 2,250,000 27,000,000 2,250,000
19 KOMATSU D 85 ES 450,000,000 2012 10 40% 2,250,000 27,000,000 2,250,000
20 HAMM 311 D 575,000,000 2012 10 40% 2,875,000 34,500,000 2,875,000
21 HITACHI PC 300 800,000,000 2015 10 40% 4,000,000 48,000,000 4,000,000
22 HITACHI PC 300 800,000,000 2015 10 40% 4,000,000 48,000,000 4,000,000
23 HITACHI PC 300 800,000,000 2015 10 40% 4,000,000 48,000,000 4,000,000
24 SANY DUMP TRUCK SYZ326C-BWR SN : HNZX2631036147 1,235,000,000 2022 10 40% 6,175,000 74,100,000 6,175,000
25 SANY DUMP TRUCK SYZ326C-BWR SN : HNZX2631036151 1,235,000,000 2022 10 40% 6,175,000 74,100,000 6,175,000
26 SANY DUMP TRUCK SYZ326C-BWR SN : HNZ2631036149 1,235,000,000 2022 10 40% 6,175,000 74,100,000 6,175,000
27 SANY DUMP TRUCK SYZ326C-BWR SN : HNZ2631036148 1,235,000,000 2022 10 40% 6,175,000 74,100,000 6,175,000
28 SANY DUMP TRUCK SYZ326C-BWR SN : HNZX2631036146 1,235,000,000 2022 10 40% 6,175,000 74,100,000 6,175,000
29 KABELCO HYDRAULIC EXCAVATOR SK200-10/SK200XDL-10L 1,425,000,000 2022 10 40% 7,125,000 85,500,000 7,125,000
30 KABELCO HYDRAULIC EXCAVATOR SK200-10/SK200XDL-10L 1,425,000,000 2022 10 40% 7,125,000 85,500,000 7,125,000
31 KABELCO HYDRAULIC EXCAVATOR SK330-10/SK200XDL-10L 1,425,000,000 2022 10 40% 7,125,000 85,500,000 7,125,000
32 KABELCO HYDRAULIC EXCAVATOR SK330-10/SK200XDL-10L 1,425,000,000 2022 10 40% 7,125,000 85,500,000 7,125,000
33 HITACHI ZX210F-5G 1,520,000,000 2022 10 40% 7,600,000 91,200,000 7,600,000
34 SANY SINGLE ROLLER DRUM (2022), TYPE : SSR220C-BH,S/N 945,945,945 2022 10 40% 4,729,730 56,756,757 4,729,730
35 SANY EXCAVATOR SY215C SN SY021HCBB7198 1,190,000,000 2022 10 40% 5,950,000 71,400,000 5,950,000
36 SANY MOTOR GRADER, TYPE :STG1900C-8S 1,243,243,243 2022 10 40% 6,216,216 74,594,595 6,216,216
37 SANY MOTOR GRADER 190HP (2022), TYPE : STG190C-8S, S/N :P 1,243,243,243 2022 10 40% 6,216,216 74,594,595 6,216,216
38 LIUGONG BULLDOZER MODEL CLGB230/ SN : LGCB23OZLN C00 2,150,000,000 2022 10 40% 10,750,000 129,000,000 10,750,000
Page 8
Penyst
Page 9
67,813
162,400,000
PT. SINAR JAYA ABADI
PERHITUNGAN / PROYEKSI LABA / RUGI KI-MG YANG DIBIAYAI Lampiran 8
1.025 1.025
Total Tahun Tahun Tahun
URAIAN
Ke 1 Ke 2 Ke 3
101,721,933 114,401,416 -
PT. SINAR JAYA ABADI
PERHITUNGAN / PROYEKSI LABA / RUGI KI-MG YANG DIBIAYAI
Sesitivitas Pendapatan Turun 5% 0.95 0.950 0.950
Total Tahun Tahun Tahun
URAIAN
Ke 1 Ke 2 Ke 3
TAHUN NET CASH INFLOW CAPITAL NET DF PRESENT DF PRESENT NET CASH INFLOW
(PROCEED) OUTLAYS PROCEED 12.00% VALUE 17.65% VALUE DISCOUNTED
12.00% 17.65%
0 - 2,386,500,000 (2,386,500,000) 1.0000 (2,386,500,000) 1.0000 (2,386,500,000) -
1 1,489,453,823 - 1,489,453,823 0.8929 1,329,869,485 0.8500 1,266,005,222 1,329,869,485
2 1,550,932,618 - 1,550,932,618 0.7972 1,236,393,988 0.7225 1,120,494,778 1,236,393,988
3 - - - - - -
Jumlah 3,040,386,441 2,386,500,000 653,886,441 179,763,473 - 2,566,263,473
NPV 179,763,473
IRR 17.65% 17.64989569%
B/C ratio 1.08
TAHUN NET CASH INFLOW CAPITAL NET DF PRESENT DF PRESENT NET CASH INFLOW
(PROCEED) OUTLAYS PROCEED 12.00% VALUE 13.00% VALUE DISCOUNTED
12.00% 13.00%
0 - 2,386,500,000 (2,386,500,000) 1.0000 (2,386,500,000) 1.0000 (2,386,500,000) -
1 1,402,732,223 - 1,402,732,223 0.8929 1,252,439,485 0.8500 1,192,293,639 1,252,439,485
2 1,462,042,978 - 1,462,042,978 0.7972 1,165,531,711 0.7225 1,056,275,110 1,165,531,711
3 - - - - - -
Jumlah 2,864,775,201 2,386,500,000 478,275,201 31,471,196 (137,931,250) 2,417,971,196
NPV 31,471,196
IRR 13.00% 12.99520228%
B/C ratio 1.01
Lampiran 11
NET CAPITAL OUTLAYS
DISCOUNTED
2,386,500,000
-
-
-
2,386,500,000
2,386,500,000
-
-
-
2,386,500,000
PERHITUNGAN KEBUTUHAN INVESTASI PEMBELIAN
PT. SINAR JAYA ABADI
Lampiran 12
Uraian Harga Total
Harga 1 (satu) unit Liugong Bulldozer B230 2,150,000,000 2,150,000,000
PPN (11%) 236,500,000 236,500,000
Total Kebutuhan 2,386,500,000
Dana sendiri 37.15% 886,500,000
Fasilitas KI-MG yang diusulkan 62.85% 1,500,000,000
Lampiran 13
PLAFOND 1,500,000,000
JANGKA WAKTU (BULAN) 24 2 TAHUN
SUKU BUNGA SLIDING 13.00%
Capital Outlay DF
Tahun Net Cashflow (NCF) NCF - CO
(CO)
14.25%
0 0 2,386,500,000 -2,386,500,000 1.0000
1 1,489,453,823 0 1,489,453,823 0.8753
2 1,550,932,618 0 1,550,932,618 0.7661
3 0 0 0 0.6706
4 #REF! 0 #REF! 0.5869
5 #REF! 0 #REF! 0.5137
6 #REF! 0 #REF! 0.4496
7 #REF! 0 #REF! 0.3936
8 #REF! 0 #REF! 0.3445
9 #REF! 0 #REF! 0.3015
10 #REF! 0 #REF! 0.2639
NPV =
IRR
B/C Ratio
#REF!
#REF!
#REF!
250,000
103,000
353,000
1 Hari 8 jam kerja
1 ha 20 jam
1 ha ; 2.5 hari 10.00 2.5 25
30 2.5 12.00
BBM
5,150
No Nama Debitur & Grup Jenis Kredit Plafond Baki Debet
1 PT. Asiva Mandiri Pratama KI-MG 1,039,000,000 1,039,000,000
2 PT. Sangir Putra Reksindo KRK 1,150,000,000 1,150,000,000
3 Wandra Yunaldi KUR 245,000,000 224,583,332
4 Jumlah 2,434,000,000 2,413,583,332
5 Permohonan PT. Asiva Mandiri Pratama KI-MG 1,039,000,000 1,039,000,000
6 Total Kredit Debitur & Grup Set Permohonan 3,473,000,000 3,452,583,332