Anda di halaman 1dari 1

OPNAME PEKERJAAN ELECTRICAL INDOCOOL MADIUN

VOLUME HARGA SATUAN


NO URAIAN PEKERJAAN ELECTRICAL SAT JUMLAH HARGA UPAH
BARU UPAH
A PEKERJAAN LANTAI 1
1 REVISI TARIKAN SKT AC 3.00 ttk 130,000.00 390,000.00
2 REVISI TARIKAN SKT UTAMA 5.00 ttk 50,000.00 250,000.00
3 REVISI TARIKAN SKT LINE POWER PENERANGAN 5.00 ttk 50,000.00 250,000.00
4 REVISI PANEL MDP 2 KWH METER 1.00 ls 1,800,000.00 1,800,000.00
5 BALANCING R-S-T DISTRIBUSI 3 PHASE 1.00 ls 400,000.00 400,000.00
6 SETTING DAN PERAKITAN PANEL ATS 2 KWH METER 1.00 ls 1,200,000.00 1,200,000.00

B PEKERJAAN LANTAI 2
1 REVISI TARIKAN SKT AC 2.00 ttk 130,000.00 260,000.00
2 WIRING LINE POWER 12.00 ttk 50,000.00 600,000.00
JUMLAH TOTAL 5,150,000.00

MADIUN,03 MEI 2024

IWAN SUPRIANTO TRI ANANG S. SONY


PENANGGUNG JAWAB TEKNIK PELAKSANA TEKNIK