Jurnal Perhitungan Pondasi Gedung Menggunakan Program Etabs 18
Jurnal Perhitungan Pondasi Gedung Menggunakan Program Etabs 18
PROGRAM ETABS 18
JURNAL
Diajukan untuk melengkapi
Madya (D3)
Disusun Oleh :
ABSTRAC
Foundation work is one of the important works in a construction
development, because the foundation has the function of transmitting all
superstructure loads that occur due to the superstructure load and will be
channeled into a layer of hard soil that can carry the construction load.
Foundation design must be designed to be able to support loads up to a
certain safety limit. In the case study of the Indramayu Hajj Dormitory
building, a soil investigation was carried out with the aim of determining
the compactness or density of the soil, the structure of the soil layer, the
type of soil, and the physical and mechanical properties or parameters of
the soil. The data will be used for the analysis of determining the type and
1
depth of the foundation as well as the bearing capacity of the soil in the
Indramayu Haji Dormitory building project. After analyzing soil
characteristics, superstructure loads, the construction of the Indramayu
Hajj Dormitory building can use pile foundations, so the author wants to
try to do a review of the resistance on the existing foundations.
2
KATA PENGANTAR
Penulis
3
1. Pendahuluan
meneruskan semua beban struktur atas yang terjadi akibat beban struktur
atas tersebut dan akan disalurkan ke dalam lapisan tanah keras yang dapat
dukung yang cukup untuk memikul berat bangunan dan seluruh beban
yang bekerja pada lapisan yang sangat dalam dari permukaan tanah
didasarkan oleh fungsi bangunan atas yang akan dipikul oleh pondasi
4
dapat digunakan untuk menentukan jenis tanah.
terhadap regangan. Nilai ini bisa didapatkan dari Triaxial Test. Dengan
Qu = Qb + Qs
Dengan,
perhitungan :
Qp = Ap qp = Ap N* q’
5
c) Menentukan nisbah Lb/D tiang
6
1.2.5 Menentukan Nilai N*q
p=Ap.N*.q’≤ Ap . qt (5)
7
1.2.7 Tahanan Gesek Kulit (Qs)
ditulis sebagai :
Qs = Σ p ∆L f (7)
Dimana :
∆L = Panjang tiang
Dimana,
Ab = Luas Penampang
Qs = As fs (11)
0
fs = K dp′ tg δ (12)
8
Kd = Koefisien tekanan tanah
Tahanan Gesek
Qs = Σ p ∆L f (17)
Penetration Test)
fb = ω1 ω2 qca (18)
Tahanan Gesek
Qu = Ab ω qca + As Kf qf (20)
9
Tahanan Ujung Satuan
fs = Kc qc (kg/cm2 (22)
eh = Efisiensi palu/pemukul
Eh = Besaran energi
Wr = Berat ram
n = Koefisen restitusi
pancang
1
Q = Beban yang bekerja
tanah keras
2. Metode Penelitian
1
3. Hasil Penelitian dan Pembahasan
bertingkat terlebih dahulu harus dihitung beban tetap dan beban gempa.
3. Memasukan beban mati (D), beban hidup (L), beban gempa (E) dan
jepit-jepitagar tidak terjadi pergeseran pada struktur. Beban mati terdiri dari
berat tiap lantai dan atap. Berat struktur dan gempa langsung otomatis
dihitung ETABS, hasil analisa beban aksial dan momen berdasarkan analisa
1
Base 10 146 PONDASI -1.22 0.79 80.29 3.39 2.77 0.00
Base 11 151 PONDASI 1.35 -0.70 85.85 -2.12 0.74 0.00
Base 12 156 PONDASI -0.04 -1.26 114.54 0.97 -0.03 0.00
Base 13 161 PONDASI 0.01 -1.26 108.02 0.96 0.04 0.00
Base 14 166 PONDASI 0.01 -1.26 108.09 0.96 0.04 0.00
Base 15 171 PONDASI -0.01 -1.26 108.06 0.97 0.01 0.00
Base 16 176 PONDASI 0.02 -1.26 108.12 0.96 0.06 0.00
Base 17 181 PONDASI 0.01 -1.26 107.84 0.96 0.04 0.00
Base 18 186 PONDASI 0.01 -1.26 108.01 0.95 0.04 0.00
Base 19 191 PONDASI 0.05 -1.26 114.60 0.95 0.11 0.00
Base 20 201 PONDASI -1.34 -0.70 85.97 -2.14 -0.68 0.00
Base 21 206 PONDASI 1.44 0.85 90.11 3.28 -1.10 0.00
Base 22 211 PONDASI 0.03 1.21 112.91 -1.01 0.08 0.00
Base 23 216 PONDASI 0.00 1.28 108.00 -1.13 0.03 0.00
Base 24 221 PONDASI 0.00 1.27 107.76 -1.11 0.02 0.00
Base 25 226 PONDASI -0.09 1.20 108.30 0.33 -1.74 0.00
Base 26 231 PONDASI -0.07 1.34 121.60 0.02 1.62 0.00
Base 27 236 PONDASI -0.10 1.56 113.53 -1.59 -0.13 0.00
Base 28 241 PONDASI 0.02 1.28 107.87 -1.14 0.05 0.00
Base 29 246 PONDASI -0.02 1.22 112.91 -1.04 -0.01 0.00
Base 30 253 PONDASI -1.42 0.85 92.40 3.27 1.18 0.00
Base 31 258 PONDASI 1.11 -0.67 75.84 -4.85 -4.66 0.00
Base 32 263 PONDASI -0.10 -1.14 123.20 -0.58 1.40 0.00
Base 33 268 PONDASI 0.00 -1.19 119.40 0.37 0.03 0.00
Base 34 273 PONDASI 0.00 -1.18 119.27 0.35 0.02 0.00
Base 35 278 PONDASI 0.03 -1.44 130.63 -0.90 -2.02 0.00
Base 36 283 PONDASI 0.22 -1.67 147.36 1.13 0.38 0.00
Base 37 288 PONDASI -0.24 -1.57 128.49 0.98 -0.37 0.00
Base 38 293 PONDASI 0.02 -1.20 119.23 0.36 0.06 0.00
Base 39 298 PONDASI 0.11 -1.13 124.45 -0.60 -1.33 0.00
Base 40 303 PONDASI -1.10 -0.67 76.92 -4.88 4.74 0.00
Klasifikasi pondasi dibagi menjadi dua tipe yang didasarkan dari nilai
tertinggi dari Fz yang di dapat dari hasil running program Etabs 18.
1
Tabel 3.2 Kriteria Klasifikasi Pondasi
BANYAK
NO TIPE PONDASI FZ (TON) MX MY
PONDASI
DATA PONDASI
BAHAN STRUKTUR
Kuat tekan beton, fc' = 25 MPa
Tegangan leleh baja (deform) untuk tulangan lentur, fy = 400 MPa
Tegangan leleh baja (polos) untuk tulangan geser, fy = 280 MPa
DIMENSI PONDASI TIANG PANCANG
Diameter tiang pancang d= 30 cm
Berat volume tanah = 1.71 T/m3
Sudut gesek = 6 °
Kedalaman tanah L= 30 M
MOMEN DAN GAYA GESER RENCANA
Berat Bangunan (Dari Output Beban Etabs) P= 1000 kN
MENGHITUNG DAYA DUKUNG TIANG PANCANG DENGAN
METODE MEYERHOF DENGAN DATA SONDIR
Nilai Qc pada Uji Sondir Qc = 250 kg/cm2
Nilai JHL pada Uji Sondir JHL = 562 kg/cm2
𝑄𝑐 𝑥 𝐴𝑝
𝑄𝑢 𝑖𝑗𝑖𝑛 =
3
Qu Ijin =
Dimana :
Ap = ¼ π D2 = 707 cm2
Ka = πD = 94 cm2
1
Qu Ijin = 69498.31268 kg = 70.87 Ton
Data Bahan Pile Cap
Kuat Tekan Beton fc' = 25.00 MPa
Kuat leleh baja tulangan deform ( Æ > 12 mm ) fy = 400 MPa
Kuat leleh baja tulangan polos ( Æ ≤ 12 mm ) fy = 280 MPa
Berat beton bertulang wc = 24 kN/m3
Data Dimensi Pondasi
Lebar kolom arah x bx = 0.60 m
Lebar kolom arah y by = 0.70 m
Jarak tiang pancang tepi terhadap sisi luar beton a= 0.450 m
Tebal pilecap h= 0.50 m
Tebal tanah di atas pilecap z= 1.00 m
Berat volume tanah di atas pilecap ws = 1.72 T/m3
Posisi kolom (dalam = 40, tepi = 30, sudut = 20) s = 40
Data Beban Pondasi
Gaya Aksial kolom akibat beban terfaktor * Pn = 101.97 Ton
Momen arah x akibat beban terfaktor Mux = 19.75 T/m
Momen arah y akibat beban terfaktor Muy = 16.61 T/m
Tahanan aksial tiang pancang * Hn = 70.8685 Ton
1
GAYA AKSIAL PADA TIANG PANCANG
Berat tanah di atas pilecap W s = L x * Ly * z * w s = 5.56 Ton
Berat pilecap W c = L x * Ly * h * w c = 3.96 Ton
Lengan maksimum tiang pancang arah x thd. Pusat xmax = 0.45 m
Lengan maksimum tiang pancang arah y thd. Pusat ymax = 0.45 m
Pu = Puk + 1.2 * Ws + 1.2
Total gaya aksial terfaktor * Wc = 113.44 Ton
Gaya aksial pada 1 tiang pancang
pumax = Pu / n + Mux* xmax / x2 + Muy* ymax / y2 = 22.68 Ton
Syarat : pumax ≤ * Pn
22.68 70.86 → AMAN
0.6 ≤ S ≤ 0.75
Dimana :
S <
1
Setelah dihitungan efisiensi dari group pile tersebut, nilai dari 2TP memenuhi
syarat, 134.39 T lebih besar daripada 113.40 T, yaitu beban perpilecapnya. Maka
jumlah TP yang memenuhi syarat group dan memiliki selisih dengan beban
DATA PONDASI
BAHAN STRUKTUR
Kuat tekan beton, fc' = 25.00 MPa
Tegangan leleh baja (deform) untuk tulangan lentur, fy = 400 MPa
Tegangan leleh baja (polos) untuk tulangan geser, fy = 280 MPa
DIMENSI PONDASI TIANG PANCANG
Diameter tiang pancang d= 30 cm
Sudut gesek = 6 °
Kedalaman tanah L= 30 m
1
Dimana
:
Ap = ¼ π D2 = 707 cm2
Ka = πD = 94 cm2
Qu Ijin = 69498.3127 Kg = 7.22 kN
1
GAYA AKSIAL PADA TIANG PANCANG
Berat tanah di atas pilecap W s = L x * Ly * z * w s = 6.19 Ton
Berat pilecap W c = L x * Ly * h * w c = 3.49 Ton
Lengan maksimum tiang pancang arah x thd. Pusat xmax = 0.5 m
Lengan maksimum tiang pancang arah y thd. Pusat ymax = 0.5 m
Pu = Puk + 1.2 * Ws +
Total gaya aksial terfaktor 1.2 * Wc = 165.69 Ton
Gaya aksial pada 1 tiang pancang
pumax = Pu / n + Mux* xmax / x2 + Muy* ymax / y2 = 41.42 Ton
Syarat : pumax ≤ * Pn
41,42 70,86 → AMAN
S <
1
Setelah dihitungan efisiensi dari group pile tersebut, nilai dari 4TP memenuhi syarat,
268.7872 T lebih besar daripada 165.69 T, yaitu beban perpilecapnya. Maka jumlah TP
yang memenuhi syarat group dan memiliki selisih dengan beban keseluruhan, yaitu
4. Kesimpulan
tipe pondasi tiang pancang. Pondasi tipe satu digunakan untuk menopang
beban 134,43 Ton yang satu grup nya terdiri dari 2 tiang pancang yang
beban sebanyak 268,86 Ton yang satu grup nya terdiri dari 4 tiang
sebagai berikut.
2
12 TIPE PONDASI 2 114.57 32 TIPE PONDASI 2 123.23
13 TIPE PONDASI 2 108.05 33 TIPE PONDASI 2 119.44
14 TIPE PONDASI 2 108.12 34 TIPE PONDASI 2 119.30
15 TIPE PONDASI 2 108.09 35 TIPE PONDASI 2 130.67
16 TIPE PONDASI 2 108.15 36 TIPE PONDASI 2 147.40
17 TIPE PONDASI 2 107.87 37 TIPE PONDASI 2 128.53
18 TIPE PONDASI 2 108.04 38 TIPE PONDASI 2 119.26
19 TIPE PONDASI 2 114.63 39 TIPE PONDASI 2 124.48
20 TIPE PONDASI 1 85.99 40 TIPE PONDASI 1 76.94
2
DAFTAR PUSTAKA
Bangunan Gedung
Nasional.
Permana, PA. dan Mila KA. 2019. Pengaruh Kontribusi Pile Cap
Manyar.
Standarisasi Nasional