No. Uraian Pekerjaan Harga (Rp) (Minggu) Bobot (%)

I PEK. PONDASI 54,661,000.00 6 14.285

II PEK. BETON 97,237,000.00 6 25.411

III PEK. DINDING 26,656,000.00 7 6.966

IV PEK. KAP DAN ATAP 33,695,000.00 6 8.806

V PEK. PLAFOND 20,509,000.00 6 5.360

VI PEK. PLASTERAN DAN ACIAN 30,966,000.00 8 8.092

VII PEK. LANTAI 28,030,000.00 6 7.325

VIII PEK. PINTU DAN JENDELA 30,377,000.00 7 7.938

IX PEK. PENGECATAN 20,109,000.00 4 5.255

X PEK. INSTALASI & SANITASI 23,655,000.00 7 6.182

XI PEK. PERLENGKAPAN LUAR 16,761,000.00 9 4.380

JUMLAH BOBOT RENCANA 382,656,000.00 100.0001 2

KUMULATIF BOBOT RENCANA

JUMLAH BOBOT REALISASI

KUMULATIF BOBOT REALISASI

SELISIH

Nama : I Putu Bgaus Dananjaya Adi Luhur


No : 25
NIM : 2215113083
Kelas : 3C D3 Teknik Sipil
Min

1 2 3 4 5 6 7 8 9 10

2.381 2.381 2.381 2.381 2.381 2.381

4.235 4.235 4.235 4.235

0.995 0.995

1 2.38 2 2.38 3 2.38 4 2.38 5 2.38 6 2.38 7 4.24 8 4.24 9 5.23 10 5.23 11

2.38 4.76 7.14 9.52 11.90 14.28 18.52 22.75 27.99 33.22

2.14 2.14 2.14 2.14 2.86 7.94 5.08 6.13 6.13 6.13

2.14 4.29 6.43 8.57 11.43 19.37 24.45 30.58 36.70 42.83

0.24 0.48 0.71 0.95 0.48 5.08 5.93 7.82 8.72 9.61
Minggu ke

11 12 13 14 15 16 17 18 19 20

4.235 4.235

0.995 0.995 0.995 0.995 0.995

1.468 1.468 1.468 1.468 1.468 1.468

0.893 0.893 0.893 0.893 0.893 0.893

1.012 1.012 1.012 1.012 1.012 1.012 1.012 1.012

1.221 1.221 1.221 1.221 1.221 1.221

1.134 1.134 1.134 1.134 1.134 1.134 1.134

1.314 1.314 1.314 1.314

0.883 0.883 0.883 0.883 0.883 0.883

0.487 0.487 0.487 0.487 0.487 0.487

10 116.70 127.71 136.72 6.72


14 8.09
15 7.10
16 6.94
17 6.94
18 4.83
19 2.68
20 21

39.91 47.62 54.35 61.07 69.16 76.26 83.20 90.14 94.97 97.66

2.81 4.37 6.70 6.70 - - - - - -

45.64 50.00 56.70 63.41 63.41 63.41 63.41 63.41 63.41 63.41

5.72 2.38 2.36 2.34 5.75 12.85 19.79 26.74 31.57 34.25
21 22 23
100.00

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00
0.883
10.00
0.487 0.487 0.487
-
20 1.37
21 0.4922 0.4923

99.03 99.51 100.00

- - -

63.41 63.41 63.41

35.62 36.11 36.59


Durasi
No. Uraian Pekerjaan Harga (Rp) (Minggu) Bobot (%)

I PEK. PONDASI 54,661,000.00 6 14.285

II PEK. BETON 97,237,000.00 6 25.411

III PEK. DINDING 26,656,000.00 7 6.966

IV PEK. KAP DAN ATAP 33,695,000.00 6 8.806

V PEK. PLAFOND 20,509,000.00 6 5.360

VI PEK. PLASTERAN DAN ACIAN 30,966,000.00 8 8.092

VII PEK. LANTAI 28,030,000.00 6 7.325

VIII PEK. PINTU DAN JENDELA 30,377,000.00 7 7.938

IX PEK. PENGECATAN 20,109,000.00 4 5.255

X PEK. INSTALASI & SANITASI 23,655,000.00 7 6.182

XI PEK. PERLENGKAPAN LUAR 16,761,000.00 9 4.380

JUMLAH BOBOT REALISASI 382,656,000.00 100.000

KUMULATIF BOBOT REALISASI

Hitunglah bobot realisasi sesuai data progress di atas, kemudian tambahkan grafik rea
Min

1 2 3 4 5 6 7 8 9 10

15.0% 15.0% 15.0% 15.0% 20.0% 20.0%

20.0% 20.0% 20.0% 20.0% 20.0%

15.0% 15.0% 15.0%

1.150 2.150 3.150 4.150 5.200 6.400 7.200 8.350 9.350 10.350

1.150 3.300 6.450 10.600 15.800 22.200 29.400 37.750 47.100 57.450

ian tambahkan grafik realisasi pada Kurva-S rencana


Minggu ke

11 12 13 14 15 16 17 18 19 20

15.0% 20.0% 20.0%

20.0% 20.0% 20.0% 20.0%

15.0% 20.0%

15.0% 15.0% 15.0%

10.0% 20.0%

10.0% 15.0%

11.350 12.550 13.900 14.900

68.800 81.350 95.250 110.150


21 22 23
Waktu Pelaksanaan

Durasi
No. Uraian Pekerjaan Harga (Rp) Mulai Selesai (Minggu)
minggu ke minggu ke

I PEK. PONDASI 54,661,000.00 1 6 6

II PEK. BETON 97,237,000.00 7 12 6

III PEK. DINDING 26,656,000.00 9 15 7

IV PEK. KAP DAN ATAP 33,695,000.00 11 16 6

V PEK. PLAFOND 20,509,000.00 13 18 6

PEK. PLASTERAN DAN


VI 30,966,000.00 12 19 8
ACIAN

VII PEK. LANTAI 28,030,000.00 13 18 6

PEK. PINTU DAN


VIII 30,377,000.00 13 19 7
JENDELA

IX PEK. PENGECATAN 20,109,000.00 17 20 4

PEK. INSTALASI &


X 23,655,000.00 15 21 7
SANITASI
PEK. PERLENGKAPAN
XI 16,761,000.00 15 23 9
LUAR

JUMLAH BOBOT
382,656,000.00
REALISASI

KUMULATIF BOBOT
REALISASI
Bobot (%)
1 2 3 4 5 6 7 8 9

14.285 2.14 2.14 2.14 2.14 2.86 2.86 - - -

25.411 - - - - - 5.08 5.08 5.08 5.08

6.966 - - - - - - - 1.04 1.04

8.806 - - - - - - - - -

5.360 - - - - - - - - -

8.092 - - - - - - - - -

7.325 - - - - - - - - -

7.938 - - - - - - - - -

5.255 - - - - - - - - -

6.182 - - - - - - - - -
4.380 - - - - - - - - -

100.000 2.14 2.14 2.14 2.14 2.86 7.94 5.08 6.13 6.13

2.14 4.29 6.43 8.57 11.43 19.37 24.45 30.58 36.70


Minggu ke

10 11 12 13 14 15 16 17 18 19

- - - - - - - - - -

5.08 - - - - - - - - -

1.04 1.04 1.39 1.39 - - - - - -

- 1.76 1.76 1.76 1.76 - - - - -

- - - 0.80 1.07 - - - - -

- - 1.21 1.21 1.21 - - - - -

- - - 0.73 1.47 - - - - -

- - - 0.79 1.19 - - - - -

- - - - - - - - - -

- - - - - - - - - -
- - - - - - - - - -

6.13 2.81 4.37 6.70 6.70 - - - - -

42.83 45.64 50.00 56.70 63.41 63.41 63.41 63.41 63.41 63.41
20 21 22 23

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

63.41 63.41 63.41 63.41