CONTIGUOUS PILE

Oleh : Raditya Andy K


PENDAHULUAN

•Basement
•Air Permukaan
•Dinding Penahan Tanah

•Contiguous Bentonite Cement Pile


• Contiguous Pila (CP)
•Bentonite Pili (BN)
MATERIAL
MATERIAL
 Bentonite Pile dibutuhkan material sebagai berikut :
Bentonite
Semen Portland
Air
 Untuk setiap pembuatan 1m3 volume Bentonite Pile,
dibutuhkan komposisi :
50 kg Bentonite
300 kg Semen Portland
1000 kg air
MATERIAL BENTONITE
Semen Bentonite @ 50 kg Sement Portland @ 50 kg
MATERIAL CONCRETE PILE

 Mix Desain Beton dengan f’c = 25 Mpa

 Besi Tulangan D-19 (dengan ulir)

 Besi Tulangan D-13 (dengan ulir)

 Styrofoam
MATERIAL CONCRETE PILE
Sement Portland yang digunakan
 Sement Tipe I dengan spesifikasi sbb :
 Kandungan C3S = 45 – 55%
 Kandungan C3A = 8 – 12%
 Kehalusan = 350 – 400 m2/kg
MATERIAL
CONTIGUOUS
PILE

Beton Holcim fc’25


Composition for 1CuM (SSD Condiyion)
Water = 196 lt
Cementious = 384 kg
=
Admixture
Retalder = 0.96 lt
Superplasticiser = - lt
Other = - lt

Volume of Aggregate
Fine aggregate = 674 kg
Coarse Aggregate = 1062 kg

TOTAL = 2316 kg
MATERIAL CONTIGUOUS PILE
Besi Ø 19 dan Ø 13 Styrofoam
PERALATAN
PERALATAN
 Bentonite Pile
 Seperangkat Bentonite Plant
 Seperangkat Instalasi Listrik dan Genset
 Pipa / selang penyaluran
 Mesin Bor
 Mata Bor Augher
 Drilling Bucket
 Pipa Tremie
 Crawler Crane
PERALATAN
Bentonite Plant Genset
PERALATAN
Pipa Selang Penyaluran Mesin Bor
PERALATAN
Mata Bor Augher Drilling Bucket
PERALATAN
Pipa Tremie Crane 35 Ton
PERALATAN
 Contiguous Pile :
 Mesin Bor SoilMec R-416
 Mata Bor Augher
 Drilling Bucket
 Cleaning Bucket
 Seperangkat alat las listrik
 Crawler Crane
 Pipa Tremie dan Kepala Tremie
 Casing
 Back Hoe
PERALATAN

Mesin Bor SoilMec R-416


PERALATAN

Augher Drilling Bucket Cleaning Bucket


PERALATAN
Genset 10 KVA Api Potong
PERALATAN
Back Hoe Crane 35 Ton
PERALATAN
Pipa & Kepala Tremie Casing
FLOW CHART PENGEBORAN
BENTONITE PLANT
URUTAN PENGERJAAN
FLOWCHART PEMBUATAN BENTONITE PILE

Start

Call :
Persiapan Kerja Semen Bentonite

Call :
Pengeboran Lobang Bentonite

Call :
Pembuatan Bentonite

Call :
Pengecoran Bentonite

TIDAK
Tunggu ± 1 hari
( hingga susut )

Susut < 2 meter

YA

Finish
FLOWCHART SUBROUTINE PERSIAPAN
KERJA SEMEN BENTONITE PILE

Pembuatan Sumur Untuk Air Gambar 2A


Kerja

Pembuatan Bentonite Plant Gambar 2B

Pemasangan Genset dan Instalasi Gambar 2C


Listrik

Instalasi Pipa Untuk Pengecoran Gambar 2D


Semen Bentonite
Gbr 2A Gbr 2D

Gbr 2C Gbr 2B
FLOWCHART SUBROUTINE
PENGEBORAN LOBANG BENTONITE

Penentuan Titik Bor oleh


Gambar 3A
Surveyor
Gambar 3B
Pengeboran oleh Mesin Bor
(R-10)

Gunakan
Tanah Lempung YA Mata Bor
Auger Gambar 3C

TIDAK
TIDAK Gunakan
Tanah Pasir YA Mata Bor
Drill Gambar 3D

Bucket
TIDAK
Kedalaman
Rencana Gambar 3E
atau
Tanah Keras
YA
Gbr 3A Gbr 3B1

Gbr 3B2
Gbr 3E
FLOWCHART SUBROUTINE PEMBUATAN BENTONITE
PER 6M3 (PALING SERING DILAKUKAN)

Gambar 4A

Air 6000 liter

Bentonite Bentonite
3 sak @ 50 kg 3 sak @ 50 kg
Gambar 4B

Feed Hopper 1 Feed Hopper 2


( Corong 1 ) Gambar 4C
( Corong 2 )

Tangki Aduk Gambar 4D

Aduk-aduk hingga merata Gambar 4E


selama ± 30 menit

Semen Portland Semen Portland


18 sak @ 50 kg 18 sak @ 50 kg

Gambar 4F

Feed Hopper 1 Feed Hopper 2


( Corong 1 ) ( Corong 2 )

Tangki Aduk
(Aduk-aduk hingga merata ± 15 menit)

Siap disalurkan ke lobang


pengeboran
Gbr 4B Gbr 4F2 Gbr 4C

Gbr 4F1
 NOTE :
 Urutan Pengeboran
 Untuk pengeboran semen bentonite yang berdekatan
atau bersebelahan disyaratkan semen bentonite
berumur minimal 3 hari.
 Untuk pengeboran contiguous pile yang berada
diantara semen bentonite pile disyaratkan bentonite
berumur minimal 9 hari, untuk mencegah
terjadinya kebocoran yang dikarenakan rusak atau
patah semen bentonite pile. Pada umur 9 hari semen
bentonite sudah cukup keras.
 Urutan Pengeboran semen Bentonite dan contiguous
pile terlihat pada gambar dibawah ini :

1 3 5 1 3 5 2 4 6 2 4 6

Dst………..

14 16 18 14 16 18 15 17 19 15 17 19

= Contiguous Pile

= Cement Bentonite Pile

 Contoh diatas menggunakan asusmi produktivitas


alat bor = 2 buah lobang per hari
FLOWCHART SUBROUTINE
PENGECORAN BENTONITE
Gambar 5A
Masukkan Pipa Tremie Pada Lobang Pengecoran
Dengan Ditahan oleh Crane

Panjang Pipa Penambahan Panjang


Tremie ≈ Kedalaman Pipa Tremie

Gambar 5B

Peletakan Ujung Selang Pengecoran Gambar 5C


pada Bagian Atas Pipa Tremie

Pelimpasan Bentonite dari Kolam


Aduk ke Lobang Tremie Melalui
Selang Pengecoran

Setelah Penuh, Tarik Pipa Tremie


Gambar 5D
dengan Crane
Gbr 5A Gbr 5B Gbr 5B2

Gbr 5C Gbr 5D
FLOW CHART PENGEBORAN
CONTIGUOUS PILE
FLOWCHART PENGERJAAN
CONTIGUOUS PILE
START

Call :
Fabrikasi Tulangan

Call :
Pengeboran

Pemasangan Casing,

Call :
Pemasangan Tulangan

Call :
Pemasangan Tremy dan
Pengecoran

FINISH
FLOWCHART SUBROUTINE FABRIKASI
TULANGAN CONTIGUOUS PILE

Pengerolan Baja Ulir Ø 13 GAMBAR 7a

Penyusunan Tulangan dalam Bentuk Silinder


dengan panjang 12 meter
Dengan Ø = 19 mm dan jarak antar tulangan GAMBAR 7b

dalam = 125 mm

Penambahan tulangan dalam sepanjang 4 meter GAMBAR 7c


dengan diameter yang sama
(panjang penyaluran = 760 mm)

Pemasangan Tulangan dan Sengkang menjadi


satu kesatuan

Pengerolan Spriral untuk sengkang dengan jarak 150


(over steak = 760 mm bebas dari pengerolan spiral)

Pemasangan Dowel sepanjang 8 meter dimulai GAMBAR 7d


dari jarak 1 meter dari ujung over steak
FLOWCHART SUBROUTINE PENGEBORAN CONTIGUOUS PILE

Penentuan Titik Bor oleh


Surveyor

Pengeboran oleh Mesin Bor


(R-416)

Gunakan
YA
Tanah Lempung Mata Bor
Auger

TIDAK TIDAK
Gunakan
YA
Mata Bor
Tanah Pasir
Drill Bucket
TIDAK

Kedalaman Rencana
atau
Tanah Keras

Cleaning menggunakan mata bor


Cleaning Bucket
FLOWCHART SUBROUTINE PEMASANGAN
TULANGAN CONTIGUOUS PILE

Pengangkatan Tulangan Hasil Fabrikasi oleh Crane

Dimasukan ke dalam Casing pada lubang


pengeboran Contiguous Pile disertai pemasangan GAMBAR 9a

Styrofoam pada Bagian muka Dowell

Pengelasan besi penggantung pada besi oversteak.


Panjang besi penggantung bervariasi bergantung
pada level COL CP tersebut

RETURN
Gbr7DC Gbr 9A
FLOWCHART SUBROUTINE PEMASANGAN TREMIE
DAN PENGECORAN CONTIGUOUS PILE

Masukkan Pipa Tremie Pada Lubang


Pengecoran BORED Pile

Panjang Pipa TIDAK Penambahan Panjang


Pengecoran ≈ Kedalaman Pipa Pengecoran

YA

Pemasangan kepala tremie pada Pipa


tremie

Pelimpasan Beton cair dari Mixer


kedalam Lubang Pengecoran, ujung
tremie digantung oleh crane

Setelah volume rencana didapat, Pipa


tremie ditarik dengan Crane
PRODUKTIVITAS
PRODUKTIVITAS BENTONITE
MINGGU PERTAMA

PERIODE
S/D 10 JUNI S/D 17 JUNI
11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun
JUMLAH
JML % SISA SENIN SELASA RABU KAMIS JUMAT SABTU MINGU JML % SISA
27 20 110 6 6 5 7 6 6 6 42 50 36% 87
8 6% 135 6 7 2 7 4 0 0 23 34 25% 103
BN-136 BN-128 BN-131 BN-130 BN-109
BN-132 BN-124 BN-92 BN-123 BN-102
BN-111 BN-121 BN-116 BN-100
BN-108 BN-117 BN-110 BN-107S
NO LOBANG
BN-104 BN-114 BN-107
BN-101 BN-98 BN-103
BN-95 BN-89
PRODUKTIVITAS BENTONITE
MINGGU KEDUA

PERIODE
S/D 17 JUNI S/D 24 JUNI
18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun
JUMLAH
JML % SISA SENIN SELASA RABU KAMIS JUMAT SABTU MINGU JML % SISA

55 40 87 7 7 7 7 7 7 7 49 83 61% 54

34 25% 103 6 6 5 6 7 7 6 30 64 47% 73

BN-85 BN-67 BN-52 BN-78 BN-57 BN-48 BN-59

BN-88 BN-70 BN-55 BN-81 BN-60 BN-51 BN-62

BN-91 BN-73 BN-58 BN-84 BN-63 BN-54 BN-65


NO LOBANG BN-94 BN-76 BN-61 BN-87 BN-66 BN-77 BN-68

BN-96 BN-79 BN-64 BN-90 BN-69 BN-80 BN-71

BN-99 BN-82 BN-93 BN-72 BN-83 BN-74

BN-75 BN-86
PRODUKTIFITAS BENTONITE
Lama waktu rata-rata kegiatan pengerjaan Bentonite Pile.

 Pengeboran 3 lobang Ø 600 = ± 4 – 4,5 jam


 Pembuatan Pasta Semen Betonite = ± 1 jam
 Setting alat pengecoran (pipa dan tremie) = ± 5-10 menit
 Pengecoran lubang bentonite = ± 10 menit
 Jumlah pekerja yang dibutuhkan = 7 pekerja
PRODUKTIVITAS CONTIGUOUS PILE
MINGGU PERTAMA

PERIODE
S/D 24 JUNI S/D 1 JULI
25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jun
JUMLAH
JML % SISA SENIN SELASA RABU KAMIS JUMAT SABTU MINGU JML % SISA

20 15 114 5 5 5 5 5 25 35 26 99

10 7 124 4 2 3 4 6 19 29 22 105

CP-123 CP-131 CP-118 CP-117 CP-107

CP-127 CP-113 CP-125 CP-120 CP-104

CP-132 CP-130 CP-114 CP-101

NO LOBANG CP-135 CP-110 CP- 98

CP- 95

CP- 92
PRODUKTIVITAS CONTIGUOUS PILE
MINGGU KEDUA

S/D 1 JULI S/D 1 JULI


S/D 1 JULI S/D 8 JULI
2-Juli 3-Juli 4-Juli 5-Juli 6-Juli 7-Juli 8-Juli
JUMLAH
JML % SISA SENIN SELASA RABU KAMIS JUMAT SABTU MINGU JML % SISA
35 26 99 5 5 8 8 3 3 8 40 75 56 59
29 22 105 6 5 5 5 5 5 8 39 68 51 66
CP-
112 CP-108 CP-89 CP-91 CP-94 CP-111 CP-75
CP-
109 CP-102 CP-86 CP-88 CP-90 CP-68 CP-72
CP-
106 CP-99 CP-83 CP-85 CP-87 CP-65 CP-69
NO LOBANG CP-
103 CP-96 CP-80 CP-82 CP-84 CP-62 CP-66
CP-
100 CP-93 CP-77 CP-79 CP-81 CP-78 CP-64
CP-97 CP-61
CP-58
CP-55
PRODUKTIFITAS CONTIGUOUS PILE

Lama waktu rata-rata kegiatan pengerjaan CP.

 Mobil mixer yang dibutuhkan = 2 buah truck (4,5 dan 4 m3)


 Proses pengecoran membutuhkan waktu = 15-20 menit / titik
 Jumlah pekerja pengecoran yang diperlukan = 4 orang
 Jumlah pekerja fabrikasi tulangan = 6 orang
 Waktu fabrikasi tulangan = 1 jam
WASTE MATERIAL
WASTE MATERIAL
Dalam Proyek Life Style ini untuk Contiguous Bentinte
Cement Pile diterapkan ukuran lubang sebagai berikut :

 Untuk Bentonite :
Diameter lobang = 600 mm
Kedalaman = 15000 mm
Volume Teori = 4,3 m3
 Untuk Contiguous Pile
Diameter lobang = 800 mm
Kedalaman = 15000 mm
Volume Teori = 7,5 m3 (min COL = 2 meter dari
tanah eksisting)
Waste Material Bentonite
TGL Titik Desain Elevasi Kedalaman Vol.aktual Durasi Bor Durasi Cor
No Elevasi Diameter Tanah Kedalaman
COR Bentonite Dasar asli Bor Akhir Bored (M3) Mulai Selesai Mulai selesai
1 11-Jun-07 BN 111 -18.00 600 -0.964 17.100 -18.064 8 8.30 9.10 10.00 10.25
2 11-Jun-07 BN 108 -18.00 600 -1.062 17.000 -18.062 10 9.15 9.45 10.55 11.25
3 11-Jun-07 BN 104 -18.00 600 -1.062 17.000 -18.062 6 9.55 10.35 13.15 13.40
4 11-Jun-07 BN 101 -18.00 600 -1.173 17.000 -18.173 6 10.40 11.15 14.25 14.50
5 11-Jun-07 BN 136 -18.00 600 -1.067 17.000 -18.067 6 16.10 16.50 17.35 17.50
6 11-Jun-07 BN 132 -18.00 600 -0.933 17.100 -18.033 5 16.55 17.35 18.40 18.55
7 11-Jun-07 BN 126 -18.00 600 -0.947 17.200 -18.147 6 17.45 18.20 19.50 20.15
8 12-Jun-07 BN 128 -18.00 600 -0.829 17.200 -18.029 6 8.30 9.30 11.00 11.20
9 12-Jun-07 BN 124 -18.00 600 -0.955 17.100 -18.055 6 9.30 10.30 12.00 12.20
10 12-Jun-07 BN 121 -18.00 600 -0.904 17.100 -18.004 6 10.30 11.30 13.00 13.20
11 12-Jun-07 BN 117 -18.00 600 -0.167 17.000 -17.167 6 11.30 12.30 14.00 14.30
12 12-Jun-07 BN 114 -18.00 600 -0.949 17.100 -18.049 6 13.30 14.30 15.00 15.20
13 12-Jun-07 BN 95 -18.00 600 -1.187 16.900 -18.087 6 14.30 15.30 16.00 16.30
14 12-Jun-07 BN 98 -18.00 600 -1.206 16.900 -18.106 6.0 16.30 17.30 18.00 18.30
15 13-Jun-07 BN 113 -18.00 600 -0.932 17.000 -17.932 6.5 13.15 14.10 16.10 16.30
16 13-Jun-07 BN 119 -18.00 600 -0.930 17.200 -18.130 6.0 11.35 12.15 15.10 15.35
17 13-Jun-07 BN 134 -18.00 600 -0.992 17.000 -17.992 8.0 10.40 11.25 14.00 14.20
18 13-Jun-07 BN 131 -18.00 600 -0.998 17.100 -18.098 12.0 8.15 9.00 10.25 10.40
19 13-Jun-07 BN 92 -18.00 600 -1.211 16.900 -18.111 12.0 9.40 10.25 12.15 12.40
20 13-Jun-07 BN 130 -18.00 600 -1.044 17.000 -18.044 6.0 8.00 8.50 10.20 10.35
21 13-Jun-07 BN 123 -18.00 600 -1.262 16.900 -18.162 6.0 8.55 9.35 11.20 11.45
22 14-Jun-07 BN 116 -18.00 600 -1.256 17.000 -18.256 6.0 10.35 11.10 13.50 14.15
23 14-Jun-07 BN 110 -18.00 600 -0.966 17.200 -18.166 5.0 13.00 13.40 15.10 15.25
24 14-Jun-07 BN 107 -18.00 600 -1.026 17.000 -18.026 6 14.10 14.50 16.35 16.45
25 14-Jun-07 BN 103 -18.00 600 -1.104 16.900 -18.004 6 15.05 15.50 17.50 18.00
26 14-Jun-07 BN 89 -18.00 600 -1.256 17.000 -18.256 5 17.00 17.45 19.20 19.40
Waste Material Bentonite
TANGGA Vol.aktua
Desain
L Titik Elevasi Kedalaman l Durasi Bor Durasi Cor
No Elevasi Diameter
Tanah Kedalaman Akhir
Dasar
COR Bentonite asli Bor Bored (M3) Mulai Selesai Mulai selesai
27 15-Jun-07 BN 109 -18.00 600 -0.954 17.200 -18.154 6 8.10 8.50 10.00 10.20
28 15-Jun-07 BN 102 -18.00 600 -1.192 17.000 -18.192 6 9.20 10.00 11.25 11.45
29 15-Jun-07 BN 100 -18.00 600 -1.215 16.900 -18.115 6 10.10 11.50 13.20 13.45
30 15-Jun-07 BN 107 -18.00 600 -1.224 16.900 -18.124 6 13.00 13.40 14.50 15.15
31 18-Jun-07 BN 106 -18.00 600 -1.020 17.000 -18.020 6 16.15 17.00 18.10 18.30
31 18-Jun-07 BN 99 -18.00 600 -1.216 -16.900 15.684 6 9.00 9.40 10.35 10.40
32 18-Jun-07 BN 96 -18.00 600 -1.158 17.000 -18.158 6 9.45 10.30 11.25 11.40
33 18-Jun-07 BN 94 -18.00 600 -1.139 17.000 -18.139 6 10.50 11.35 12.50 13.05
34 18-Jun-07 BN 91 -18.00 600 -1.221 18.000 -19.221 6 13.35 14.00 14.40 14.55
35 18-Jun-07 BN 88 -18.00 600 -1.238 17.000 -18.238 6 14.10 14.45 15.35 15.40
36 18-Jun-07 BN 85 -18.00 600 -1.296 17.000 -18.296 6 15.20 16.05 16.50 17.05
36 19-Jun-07 BN 82 -18.00 600 -1.296 17.000 -18.296 6 8.00 8.40 10.10 10.20
37 19-Jun-07 BN 79 -18.00 600 -1.224 17.000 -18.224 6 8.45 9.30 11.15 11.30
38 19-Jun-07 BN 76 -18.00 600 -1.145 17.000 -18.145 6 10.20 11.40 14.05 14.25
39 19-Jun-07 BN 73 -18.00 600 -1.173 17.000 -18.173 6 13.20 14.00 15.30 15.45
40 19-Jun-07 BN 70 -18.00 600 -0.076 17.000 -17.076 6 14.10 15.00 16.50 17.10
41 19-Jun-07 BN 67 -18.00 600 -1.125 17.000 -18.125 10 15.10 16.00 19.00 19.20
41 20-Jun-07 BN 105 -18.00 600 -1.086 17.000 -18.086 6 19.00 19.45 22.10 22.25
42 20-Jun-07 BN 112 -18.00 600 -0.911 17.200 -18.111 6.5 18.10 18.55 21.20 21.35
43 20-Jun-07 BN 64 -18.00 600 -0.993 17.200 -18.193 6 13.10 13.45 14.20 14.35
44 20-Jun-07 BN 61 -18.00 600 -1.060 17.000 -18.060 6 14.00 14.40 15.40 16.00
45 20-Jun-07 BN 58 -18.00 600 -1.058 17.000 -18.058 6 14.10 15.00 17.30 17.50
46 20-Jun-07 BN 55 -18.00 600 -1.055 17.000 -18.055 6 15.10 16.00 18.50 19.10
47 20-Jun-07 BN 52 -18.00 600 -0.985 17.100 -18.085 6 16.20 18.05 20.25 20.40
Waste Material Bentonite
TANGGA
Desain
L Titik Elevasi Kedalaman Vol.aktual Durasi Bor Durasi Cor
No Elevasi Diameter
Tanah Kedalaman Akhir
Dasar
COR Bentonite asli Bor Bored (M3) Mulai Selesai Mulai selesai
48 21-Jun-07 BN 93 -18.00 600 -1.171 17.000 -18.171 6 8.10 8.50 10.00 10.15
49 21-Jun-07 BN 90 -18.00 600 -1.221 17.000 -18.221 6 9.00 9.45 11.10 11.20
50 21-Jun-07 BN 87 -18.00 600 -1.231 17.000 -18.231 6 11.00 11.40 12.15 12.25
51 21-Jun-07 BN 84 -18.00 600 -1.326 16.800 -18.126 6 13.10 13.50 14.00 14.20
52 21-Jun-07 BN 81 -18.00 600 -1.278 17.000 -18.278 6 14.00 14.50 15.40 15.55
53 21-Jun-07 BN 78 -18.00 600 -1.215 17.000 -18.215 6 14.55 15.40 17.40 17.55
53 22-Jun-07 BN 75 -18.00 600 -1.146 17.000 -18.146 6 8.00 8.45 10.00 10.15
54 22-Jun-07 BN 72 -18.00 600 -1.115 17.000 -18.115 6 8.50 9.35 11.20 11.35
55 22-Jun-07 BN 69 -18.00 600 -1.159 17.000 -18.159 6 10.00 11.00 13.30 13.45
56 22-Jun-07 BN 66 -18.00 600 -1.118 17.000 -18.118 6 11.15 12.00 14.50 15.05
57 22-Jun-07 BN 63 -18.00 600 -1.073 17.000 -18.073 6 13.25 14.10 15.50 16.10
58 22-Jun-07 BN 60 -18.00 600 -1.026 17.000 -18.026 6 15.10 16.00 17.25 17.40
59 22-Jun-07 BN 57 -18.00 600 -1.078 17.000 -18.078 6 16.10 17.00 18.50 19.10
60 23-Jun-07 BN 86 -18.00 600 -1.286 17.000 -18.286 6 8.00 8.50 9.40 9.55
61 23-Jun-07 BN 83 -18.00 600 -1.321 17.000 -18.321 6 9.00 9.50 11.20 11.35
62 23-Jun-07 BN 80 -18.00 600 -1.244 17.000 -18.244 6 10.00 11.50 13.50 13.10
63 23-Jun-07 BN 77 -18.00 600 -1.166 17.000 -18.166 6 13.10 13.55 14.20 14.35
64 23-Jun-07 BN 54 -18.00 600 -1.067 17.000 -18.067 6 14.00 14.50 15.50 16.05
65 23-Jun-07 BN 51 -18.00 600 -0.928 17.200 -18.128 6 14.55 16.00 17.40 17.55
66 23-Jun-07 BN 48 -18.00 600 -0.881 17.200 -18.081 6 16.10 17.20 18.50 19.00
67 24-Jun-07 BN 74 -18.00 600 -1.158 17.000 -18.158 6 8.00 9.00 10.10 10.15
68 24-Jun-07 BN 71 -18.00 600 -1.102 17.000 -18.102 6 9.05 10.00 11.25 11.40
69 24-Jun-07 BN 68 -18.00 600 -1.132 17.000 -18.132 6 10.10 11.00 13.00 13.15
70 24-Jun-07 BN 65 -18.00 600 -1.114 17.000 -18.114 6 13.15 14.00 14.30 14.45
71 24-Jun-07 BN 62 -18.00 600 -1.047 17.000 -18.047 6 14.10 15.05 15.50 16.10
72 24-Jun-07 BN 59 -18.00 600 -1.060 17.000 -18.060 6 15.10 16.00 17.40 17.55
Waste Material Bentonite
Volume Pakai
12

10

0
121

109

105
111
108
104
101
136
132
126
128
124
117
114

113
119
134
131
130
123
116
110
107
103

102
100
107
106

112

63
95
98

92

89

99
96
94
91
88
85
82
79
76
73
70
67

64
61
58
55
52
93
90
87
84
81
78
75
72
69
66
60
57
86
83
80
77
54
51
48
74
71
68
65
62
59
BN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BNBN
BN
WASTE MATERIAL
 Waste material rata-rata BN = ±1.7 m3 = 39%

Beberapa hal yang menyebabkan waste material tinggi :


 Kondisi tanah jelek ( lapisan sampah)

 Cor Penuh hingga tanah eksisting

 Tingkat susut bentonite yang tinggi


Waste Material CP
Diameter = 800 mm
Panjang Casing = 4000 mm
Elevasi COL = variasi
Muka Air Tanah = -9400 mm
Volume Rencana = 7.4 m3
Batching Plant = Holcim

Permukaan
TANGGAL Titik Elevasi Elevasi Elevasi Kedalaman Vol.aktual Beton Durasi Pengecoran Elv.akhir
No
Tanah Beton
Bor / Cor Bore Pile Casing asli Desain Bor (M3) 1 2 Mulai selesai Beton
1 8-Jul-07 CP 73 -0.730 -1.163 3.000 16.367 8.0 8.40 1.50 11.50 12.10 -2.230
2 8-Jul-07 CP 76 -0.715 -1.145 3.000 16.270 8.0 8.90 2.00 11.10 11.30 -2.715
3 7-Jul-07 CP 52 -0.582 -0.892 3.000 16.490 8.0 8.20 1.00 11.25 11.40 -1.582
4 7-Jul-07 CP 55 -0.534 -0.985 3.000 16.449 8.0 8.60 1.10 12.25 12.40 -1.634
5 7-Jul-07 CP 58 -0.512 -1.055 3.000 16.357 8.0 8.60 1.10 15.25 15.45 -1.612
6 7-Jul-07 CP 61 -0.583 -1.060 3.000 16.423 8.0 8.60 1.00 17.20 17.35 -1.583
7 7-Jul-07 CP 64 -0.645 -0.993 3.000 16.452 8.0 8.30 1.20 10.15 10.30 -1.845
8 7-Jul-07 CP 66 -0.820 -1.118 3.000 16.302 8.0 8.20 1.40 18.10 18.30 -2.220
9 7-Jul-07 CP 69 -0.715 -1.159 3.000 16.256 8.0 8.60 1.50 16.45 16.50 -2.215
10 7-Jul-07 CP 72 -0.802 -1.115 3.000 16.287 8.0 8.80 1.10 14.35 14.50 -1.902
11 7-Jul-07 CP 75 -0.745 -1.146 3.000 16.399 8.0 9.00 1.30 11.55 12.20 -2.045
12 7-Jul-07 CP 78 -0.802 -1.215 3.000 16.287 8.0 8.50 1.20 10.30 10.45 -2.002
13 6-Jul-07 CP 62 -0.722 -1.047 3.000 16.475 8.0 9.00 1.30 18.35 19.00 -2.022
14 6-Jul-07 CP 65 -0.835 -1.114 3.000 16.421 8.0 8.90 1.30 17.35 17.50 -2.135
15 6-Jul-07 CP 68 -0.702 -1.132 3.000 16.370 8.0 8.00 1.00 16.00 16.20 -1.702
16 6-Jul-07 CP 111 -0.654 -0.964 3.000 19.290 8.0 11.80 3.50 12.15 12.30 -4.154
17 6-Jul-07 CP 81 -0.710 -1.278 3.000 16.232 8.0 9.20 1.00 19.25 19.40 -1.710
18 6-Jul-07 CP 84 -0.700 -1.326 3.000 16.174 8.0 9.10 1.00 18.55 19.10 -1.700
19 6-Jul-07 CP 87 -0.880 -1.231 3.000 16.349 8.0 8.80 1.00 18.05 18.20 -1.880
20 6-Jul-07 CP 90 -0.840 -1.214 3.000 16.308 8.0 8.20 1.10 14.05 14.25 -1.940
21 6-Jul-07 CP 94 -0.723 -1.139 3.000 15.384 8.0 7.20 1.00 11.15 11.50 -1.723
Waste Material CP
Permukaan
TANGGAL Titik Elevasi Elevasi Elevasi Kedalaman Vol.aktual Beton Durasi Pengecoran Elv.akhir
No
Tanah Beton
Bor / Cor Bore Pile Casing asli Desain Bor (M3) 1 2 Mulai selesai Beton
22 5-Jul-07 CP 79 -0.710 -1.224 3.000 16.286 7.5 3.40 1.00 16.15 16.30 -1.710
23 5-Jul-07 CP 82 -0.658 -1.296 3.000 16.162 12.0 12.10 8.00 15.00 16.45 -2.258
24 5-Jul-07 CP 85 -0.711 -1.294 3.000 16.217 8.0 8.20 1.00 13.15 13.30 -1.711
25 5-Jul-07 CP 88 -0.722 -1.138 3.000 16.284 8.0 7.80 2.00 12.00 12.25 -2.722
26 5-Jul-07 CP 91 -0.760 -1.223 3.000 16.337 8.0 8.80 1.10 10.15 10.30 -1.860
27 4-Jul-07 CP 77 -0.875 -1.166 3.000 16.499 8.0 8.90 1.10 16.05 16.25 -1.975
28 4-Jul-07 CP 80 -0.874 -1.244 3.000 16.330 8.0 8.90 1.20 15.00 15.15 -2.074
29 4-Jul-07 CP 83 -0.770 -1.321 3.000 16.249 8.0 8.70 0.90 12.00 12.15 -1.670
30 4-Jul-07 CP 86 -0.779 -1.286 3.000 16.293 8.0 8.80 1.10 11.05 11.20 -1.879
31 4-Jul-07 CP 89 -0.723 -1.256 3.000 16.167 8.0 8.80 1.60 10.00 10.45 -2.323
32 3-Jul-07 CP 93 -0.569 -1.171 1.800 15.298 8.0 8.90 0.80 19.15 19.30 -1.369
33 3-Jul-07 CP 96 -0.497 -1.196 2.323 15.801 8.5 7.90 0.80 18.35 18.50 -1.297
34 3-Jul-07 CP 99 -0.487 -1.216 2.845 16.271 8.0 9.70 2.00 16.55 17.10 -2.487
35 3-Jul-07 CP 102 -0.548 -1.192 3.372 16.856 8.0 9.70 2.30 15.20 15.35 -2.848
36 3-Jul-07 CP 108 -0.413 -1.012 4.520 18.001 8.0 11.20 3.00 11.40 11.50 -3.413
37 2-Jul-07 CP 97 -0.659 -1.224 2.496 15.735 9.5 7.70 0.60 19.00 19.20 -1.259
38 2-Jul-07 CP 100 -0.770 -1.215 3.000 16.555 10.0 7.60 1.00 17.15 17.30 -1.770
39 2-Jul-07 CP 103 -0.584 -1.104 3.548 17.180 8.5 11.20 2.30 16.40 17.00 -2.884
40 2-Jul-07 CP 106 -0.295 -1.026 4.147 17.748 10.5 10.80 5.80 15.30 16.40 -3.295
41 2-Jul-07 CP 109 -0.479 -0.954 4.706 18.025 8.0 10.00 4.50 12.10 12.25 -4.979
42 2-Jul-07 CP 112 -0.518 -0.964 5.324 18.554 11.0 11.20 6.10 11.35 12.05 -4.618
Waste Material CP
Permukaan
TANGGAL Titik Elevasi Elevasi Elevasi Kedalaman Vol.aktual Beton Durasi Pengecoran Elv.akhir
No
Tanah Beton
Bor / Cor Bore Pile Casing asli Desain Bor (M3) 1 2 Mulai selesai Beton
43 30-Jun-07 CP 92 -0.994 -1.211 1.800 16.783 8.0 8.40 0.20 16.00 16.30 -1.194
44 30-Jun-07 CP 95 -0.725 -1.187 2.151 16.538 8.0 7.00 1.00 15.05 15.20 -1.725
45 30-Jun-07 CP 98 -0.763 -1.206 2.668 16.857 8.0 7.80 1.00 14.30 14.45 -1.763
46 30-Jun-07 CP 101 -0.781 -1.173 3.195 17.108 8.0 9.00 1.00 12.10 12.25 -1.781
47 30-Jun-07 CP 104 -0.585 -1.062 3.725 17.223 8.0 10.20 3.00 10.40 10.55 -3.585
48 30-Jun-07 CP 107 -0.564 -1.206 4.333 18.038 8.0 10.40 2.80 9.55 10.05 -3.364
49 29-Jun-07 CP 110 0.880 0.966 4.892 19.314 10.0 8.10 2.75 17.35 17.50 -1.870
50 29-Jun-07 CP 114 -0.468 -0.949 5.700 19.189 9.5 11.20 4.00 15.45 16.05 -4.468
51 29-Jun-07 CP 120 -0.513 -0.904 5.700 19.309 9.0 13.70 4.00 14.35 15.00 -4.513
52 29-Jun-07 CP 117 -0.554 -1.006 -5.700 19.248 8.0 12.70 4.70 9.50 1.00 -5.254
53 28-Jun-07 CP 130 -0.505 -1.044 3.000 17.061 8.0 10.00 1.90 14.45 15.05 -2.405
54 28-Jun-07 CP 125 -0.519 -0.925 3.000 17.154 8.0 9.70 1.50 12.55 13.10 -2.019
55 28-Jun-07 CP 118 -0.440 -0.984 5.700 19.256 8.0 12.00 4.00 11.20 11.35 -4.440
56 27-Jun-07 CP 113 -0.580 -0.949 5.510 19.331 8.0 11.20 3.30 12.35 13.05 -3.880
57 27-Jun-07 CP 131 -0.571 -0.998 3.000 17.073 9.0 12.70 2.20 19.00 19.15 -2.771
58 26-Jun-07 CP 123 -0.562 -1.262 5.700 19.100 8.0 11.40 3.50 17.55 18.10 -4.062
59 26-Jun-07 CP 132 -0.593 -0.933 3.000 17.260 8.0 10.60 2.60 13.15 13.35 -3.193
60 26-Jun-07 CP 127 -0.569 -0.829 3.000 17.340 8.0 8.70 1.60 15.35 15.45 -2.169
Waste Material CP
Volume Pakai
12.0

10.0

8.0

6.0
Volume Pakai

4.0

2.0

0.0

113
111

102
108
100
103
106
109
112

101
104
107
110
114
120
117
130
125
118
131
123
132
127
73

78

82

99

98
76
52
55
58
61
64
66
69
72
75
62
65
68
81
84
87
90
94
79
85
88
91
77
80
83
86
89
93
96

97

92
95
CPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCPCP
WASTE MATERIAL
 Waste material rata-rata CP = ± 0.5 m3

 Waste material diatas termasuk dalam batas normal.


Karena setiap kali pengorderan material harus ada
cadangan material. Cadangan tersebut berkisar 0.5 m3

 Jika terjadi order material berlebih ( > 8 m3) maka kondisi


tanah pengeboran kemungkinan mengalami kelongsoran
atau menggembung di bagian ujung atau tengahnya.
METODE PELAKSANAAN
Tahap I – Pengecoran BN dan CP

- 1.00
URUTAN PENGERJAAN CP DAN GA
Tahap II – Pembobokan dan Caping Beam

- 3.00
URUTAN PENGERJAAN CP DAN GA
Tahap III – Galian Tanah dan Ground Anchor

- 6.00
URUTAN PENGERJAAN CP DAN GA
Tahap IV – Perimeter Beam
TERIMA KASIH