P e m b a n g u n a n J a l a n T o l K a m a l - T e l u k n a g a - R a j e g ( K A T A R A J A )

T a h a p 1 : S t a . 0 + 0 0 0 – S t a . 6 + 7 0 0

Metode Kerja
Dinding Pracetak
Bangunan Clarifier
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Desember 2020
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Mulai

Persiapan
1. Gambar dan metode sudah di approve
2. Alat kerja sudah approve
3. Kelengkapan dokumen HSE sudah
approve
4. Persiapan lokasi stockyard precast dan
lokasi pemasangan precast
5. Mobilisasi alat dan material ke site

FLOWCHART Unloading komponen precast


ke stockyard
PEKERJAAN
Lifting precast untuk dipasang

Pengaturan posisi precast


sesuai dengan shop drawing

Pemasangan shoring untuk


menyangga dinding precast

A
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Mulai A
Persiapan
1. Gambar dan metode sudah di approve Grouting sambungan
2. Alat kerja sudah approve dinding precast-
3. Kelengkapan dokumen HSE sudah dinding insitu
approve
4. Persiapan lokasi stockyard precast dan
lokasi pemasangan precast Pemasangan Plat siku
5. Mobilisasi alat dan material ke site untuk sambungan dinding
precast-plat lantai

FLOWCHART Unloading komponen precast


ke stockyard Pengelasan plat siku
PEKERJAAN untuk sambungan dinding
precast-plat lantai
Lifting precast untuk dipasang

Pengecoran lapisan
Pengaturan posisi precast
lantai t=3 cm
sesuai dengan shop drawing

Pemasangan shoring untuk Curing Beton


menyangga dinding precast

Selesai
A
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Alat yang Digunakan

Truck Trailer Crawler Crane Mesin Las Perlengkapan Welder

Concrete Pump Concrete Mixer Blower Full Body Harness


P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Lokasi Dinding Pracetak

Lokasi Dinding Precast


t1 d
Al yar

Stockyard
ck
Sto
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Rencana Siklus Pemasangan Dinding Pracetak


Urutan Kompartemen
• kompartemen 1
• kompartemen 2
• kompartemen 4
• kompartemen 3
1A 1B 1C 1D
2A 2B 2C 2D
3A 3B 3C 3D Urutan dinding
4A
5A
4B
5B
4C
5C
4D
5D
• 1A – 1D
6A 6B 6C 6D • 2A – 2D
7A 7B 7C 7D
• 3A – 3D
8A 8B 8C 8D
9A 9B 9C 9D
• dst
10A 10B 10C 10D
11A 11B 11C 11D

Komp. 1 Komp. 2 Komp. 3 Komp. 4


P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Alternatif 1
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Unloading Dinding Pracetak

• Dinding pracetak dimobilisasi dari pabrik ke site


menggunakan trailer
• Dinding pracetak diunloading dengan menggunakan
H-Beam /
crawler crane ke stockyard yang sudah disiapkan
Spreader beam

1m 3.48 m 1m

Titik Lifting
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Lifting Dinding Pracetak

Titik
Lifting

• Lifting untuk pemasangan pada bangunan clarifier


• Dinding diturunkan sedikit di belakang posisi rencana
Titik Lifting dinding
• Sesaat sebelum menyentuh plat lantai, plat dinding
ditarik ke depan hingga sampai pada posisi rencana

Tampak Isometri Tampak Atas


P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Pemasangan komponen sambungan


Dinding-Dinding

• Pemasangan shoring sementara pada dinding


• Pemasangan baja tulangan pada sambungan dinding
• Pemasangan bekisting
• Grouting sambungan dinding
• Lifting lug nantinya akan dipotong rata permukaan beton
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Pemasangan komponen sambungan


Lantai-Dinding

Sisi Dalam

• Pengelasan baja siku dan embedded plate yang sudah tertanam di


Sisi Luar
plat lantai
• Pengelasan sesuai dengan shop drawing
• Dengan menggunakan kawat las E70xx dilakukan pengelasan setebal
5mm serta 1 layer pengelasan sekeliling embedded dan disisakan
rongga 2cm pada area sudutan
• Pada saat pengelasan di ruang sempit, 1 orang akan standby di atas
dengan memegangi tali yang tersambung dengan body harness
welder untuk menarik welder jika terjadi sesuatu yang tidak aman
• Pada pengelasan di sisi dalam akan dipasang blower untuk
menyuplai udara karena merupakan kondisi pekerjaan di ruang
• Selesai pengelasan akan dilakukan pengecekan secara visual.
Pengelasan pada sisi luar Pengelasan dinyatakan lolos jika sesuai dengan shop drawing
Pengelasan pada sisi dalam
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Finishing Plat Lantai dan Penutupan Embedded


Plate Dinding

Sambungan plat baja difinish dengan


dilapisi dengan semen grouting
sehingga permukaan dinding rata
• Pengecoran finishing plat lantai setebal 3 cm dengan beton normal sehingga
t = 3 cm sesuai dengan elevasi rencana plat lantai
• Finishing menggunakan mortar grouting pada embedded plate dinding
• Mortar grouting ditambahkan dengan material bonding adhesive untuk
memastikan kerekatan struktur eksisting dengan material finishing
• Pengecoran finishing plat lantai dan mortar grouting sekaligus berfungsi untuk
pelindung sambungan baja siku dan embedded plate dari karat akibat air
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Alternatif 2
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Unloading Dinding Pracetak

• Dinding pracetak dimobilisasi dari pabrik ke site


menggunakan trailer
• Dinding pracetak diunloading dengan menggunakan
H-Beam /
crawler crane ke stockyard yang sudah disiapkan
Spreader beam
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Lifting Dinding Pracetak

• Lifting untuk pemasangan pada bangunan clarifier


• Dinding diturunkan pada lokasi yang sudah ditentukan
• Lifting lug nantinya akan dipotong rata permukaan beton
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Pemasangan komponen sambungan


Lantai-Dinding

• Pengelasan baja siku dan embedded plate yang


sudah tertanam di plat lantai
• Pengelasan sesuai dengan shop drawing
P E N G E M B A N G A N S I S T E M P E N Y E D I A A N A I R M I N U M
D E N G A N K A P A S I T A S 1 0 0 0 L I T E R / D E T I K
P A D A P E R U S A H A A N D A E R A H A I R M I N U M G I R I T I R T A
K A B U P A T E N G R E S I K

Finishing Plat Lantai dan Penutupan Embedded


Plate Dinding

Sambungan plat baja difinish dengan


dilapisi dengan semen grouting
sehingga permukaan dinding rata

• Pengecoran finishing plat lantai setebal 3 cm dengan beton normal


t = 3 cm sehingga sesuai dengan elevasi rencana plat lantai
• Finishing menggunakan mortar grouting pada embedded plate dinding
• Mortar grouting ditambahkan dengan material bonding adhesive untuk
memastikan kerekatan struktur eksisting dengan material finishing
• Pengecoran finishing plat lantai dan mortar grouting sekaligus berfungsi
untuk pelindung sambungan baja siku dan embedded plate dari karat
akibat air