Anda di halaman 1dari 10

PERMOHONAN SURAT PENUNJUKAN

PEMERIKSAAN TEKNIS PIPA


PENYALUR
DASAR HUKUM
 Keputusan Direktur Jenderal Minyak dan Gas Bumi Nomor
:84.K/38/DJM/1998 tentang Pedoman dan Tatacara Pemeriksaan
Keselamatan Kerja Atas. Instalasi, Peralatan dan Teknik Yang
Dipergunakan Dalam Usaha Pertambangan Minyak dan Gas Bumi
dan Pengusahaan Sumber Daya Panas Bumi.

 Keputusan Menteri Pertambangan dan Energi Nomor :


300.K/38/M.PE/ 1997 tentang Keselamatan Kerja Pipa Penyalur
Minyak dan Gas Bumi .

 SNI 13 – 3473 – 1994 / ASME B31.4 tentang Sistem Transportasi


Cairan Untuk Hidrokarbon ( Liquid Transportation System For
Hydrocarbon )
LINGKUP PEMERIKSAAN TEKNIS

A. Review Document
B. Site Inspection and Verification
C. Hydrotest

D. Reporting

3
A. REVIEW DOCUMENT

 Kontraktor QA/QC Manual


 Spesifikasi Owner
 RKL/RPL
 Pipeline Route Map / R.O.W
 Design Calculation / Design Basis
 Prosedur Instalasi Pipeline
 Sertifikat Material
 Sertifikat Personnel
 Laporan Instalasi Pipeline

4
B. SITE INSPECTION & VERIFICATION

 Verifikasi material
 Verifikasi rute pipeline
 Visual inspeksi welding
 Verifikasi NDT report
 Visual Inspeksi coating pipa
 Verifikasi pemasangan sistem perlindungan korosi

5
C. HYDROTEST

 Hydrostatic Test & Pigging Procedure


 Hydrostatic Test Equipment & Certificate
 Pressure/Temperature Recorder & Cert.
 DWT & Certificate
 Pressure/Temperature Gauge & Certificate
 Ambient Temperature Gauge & Certifcate
 Hydrostatis Test & Pigging Report

6
D. REPORTING

1. Migas Appointment Letter


2. Pt. Depriwangga Certificate Of Inspection
3. General Executive Summary
4. Drawing
5. Material Certificate
6. Welding Traceability Report
7. Welding Procedure Specification
8. Minutes Of Meeting
9. Hydrostatic Test Procedure
10. Cathodic Protection Design Calculation
11. Design Basic And Calculation

7
E. PROSEDUR DAN CHECKLIST

PROSEDUR
605-P-001 - Procedure For Inspection of Onshore Pipeline

CHECKLIST
605-F-002 - Form For Pipeline Document Check list
F. KELENGKAPAN PERSYARATAN

1. LIST of EQUIPMENT

2. ITP

3. MANDAYS SCHEDULE

4. LIST PERSONNEL
PENUTUP

Anda mungkin juga menyukai