Mendapatkan Konsep Nilai Akhir Minggu ke-5, untuk mencarinya diambil data sampai
minggu ke-5 :

Mencari BCWS
BCWS = Nilai Progress Rencana x Jumlah Total Biaya
BCWS = 20.084% x Rp. 987.870.000,-
BCWS = Rp. 198.403.810,8

Mencari BCWP
BCWP = Nilai Progress Aktual x Jumlah Total Biaya
BCWP = 20.89% x Rp. 987.870.000,-
BCWP = Rp. 206.366.043,-

Mencari ACWP (Diasumsikan 70%)


ACWP = 70% x Nilai BCWP
ACWP = 70% x Rp. 206.366.043,-
ACWP = Rp. 144.456.230,1

Mencari Schedule Variance (SV)


SV = BCWP BCWS
SV = Rp. 206.366.043 - Rp. 198.403.810,8
SV = Rp. 7.962.232,2

Mencari Cost Variance (CV)


CV = BCWP ACWP
CV = Rp. 206.366.043 - Rp. 144.456.230,1
CV = Rp. 61.909.812,9

Mencari Schedule Performance Index (SPI)


BCWP
SPI = BCWS
Rp . 206.366.043
SPI = Rp . 198.403.810,8
SPI = 1.040131448

Mencari Cost Performance Index (CPI)


BCWP
CPI = ACWP
Rp .206.366 .043
CPI = Rp . 144.456.230,1
CPI = 1.428571429
Mencari Estimate Completion Date (ECD)
ECD = (Sisa Waktu / SPI) + Waktu yang sudah dipakai
135
ECD = 1.040131448 +5
ECD = 12.69133557

Mencari Estimate Cost at Completion (EAC)


Biaya totalBCWP
EAC = + ACWP
CPI
Rp . 987.870 .000Rp .206.366 .043
EAC = 1.428571429 + Rp. 144.456.230,1

EAC = Rp. 691.508.999,8

Kesimpulan :
Didapatkan Parameter metode Konsep Nilai Hasil (Earn Value)

Mingg BCWS (Rp) BCWP (Rp) ACWP (Rp) SV (Rp) CV (Rp) SPI CPI
u Ke

5 198.403.810,8 206.366.043 144.456.230,1 7.962.232,2 61.909.812,9 1.040131448 1.4285

Didapatkan SPI 1.04 yang berarti proyek sesuai/lebih cepat dari rencana
Didapatkan CPI 1.42 yang berarti biaya proyek lebih kecil dari rencana