1 2 3 4 5 6 7 8
PERKERASAN BERBUTIR
Lapis Pondasi Agregat Kls A M3 4,326.15 5,191.38
Lapis Pondasi Agregat Kls B M3 1,964.56 2,357.47 Stone Crusher 19.200 m3/jam 8.000 Jam 3.00 unit
Total 7,548.85
AC-BC dan AC-WC M3 7,062.57 8,475.08
Total kebutuhan Batu pecah 16,023.93 m3
Total
Sisa Volume Kebutuhan Alat yang Kapasitas Jam Kerja Jumlah
No URAIAN PEKERJAAN Sat
(Padat) Base A
(Gembur) digunakan Alat/ Jam / Hari Alat
1 2 3 4 5 6 7 8
V PERKERASAN BERBUTIR
5.1 Lapis Pondasi Agregat Kls A M3 4,326.15 5,191.38 Wheel Loader 18.68 m3/jam 8.000 Jam 4.00 unit
(1) Pada Badan Jalan dan Bahu Dump Truck 2.81 m3/jam 8.000 Jam 25.00 unit
Motor Greader 81.810 m3/jam 8.000 Jam 4.00 unit
Vibrator Roller 56.03 m3/jam 8.000 Jam 4.00 unit
Water Tank 47.43 m3/jam 8.000 Jam 4.00 unit
KAPASITAS PRODUKSI PERALATAN
SATKER : SKPD-TP Dinas Bina Marga dan Cipta Karya Aceh
PAKET : JNB 1 Construction Of Road Lueng Gayo - Arongan Lambalek
PENYEDIA JASA : PT. Waskita Karya (Persero)
V PERKERASAN BERBUTIR
5.1 Lapis Pondasi Agregat Kls B M3 1,964.56 2,357.47 Wheel Loader 18.68 m3/jam 8.000 Jam 4.00 unit
(2) Pada Badan Jalan dan Bahu Dump Truck 2.81 m3/jam 8.000 Jam 25.00 unit
Motor Greader 81.810 m3/jam 8.000 Jam 4.00 unit
Vibrator Roller 56.03 m3/jam 8.000 Jam 4.00 unit
Water Tank 47.43 m3/jam 8.000 Jam 4.00 unit
KAPASITAS PRODUKSI PERALATAN
SATKER : SKPD-TP Dinas Bina Marga dan Cipta Karya Aceh
PAKET : JNB 1 Construction Of Road Lueng Gayo - Arongan Lambalek
Laston AC-BC
Alat yang Produksi Jam Kerja Jumlah
No URAIAN PEKERJAAN SatuanSisa Volume
digunakan Alat/ Jam / Hari Alat
1 2 3 4 5 6 7 8
V PERKERASAN ASPAL
1 Laston - Lapis Pengikat M3 1,301.40 Wheel Loader 22.539 m3/jam 8.00 Jam 1.00 unit
(AC-BC) AMP 20.870 m3/jam 8.00 Jam 1.00 unit
Generator Set 17.391 m3/jam 8.00 Jam 1.00 unit
Dump Truck 1.635 m3/jam 8.00 Jam 15.00 unit
Asphalt Finisher 13.913 m3/jam 8.00 Jam 1.00 unit
Tandem Roller 20.000 m3/jam 8.00 Jam 1.00 unit
PTR 28.000 m3/jam 8.00 Jam 1.00 unit
KAPASITAS PRODUKSI PERALATAN
V PERKERASAN ASPAL
1 Laston - Lapis Aus M3 3,211.37 Wheel Loader 22.539 m3/jam 10.00 Jam 1.00 unit
(AC-WC) AMP 20.870 m3/jam 10.00 Jam 1.00 unit
Generator Set 17.391 m3/jam 10.00 Jam 1.00 unit
Dump Truck 1.635 m3/jam 10.00 Jam 15.00 unit
Asphalt Finisher 13.913 m3/jam 10.00 Jam 1.00 unit
Tandem Roller 20.000 m3/jam 10.00 Jam 1.00 unit
PTR 28.000 m3/jam 10.00 Jam 1.00 unit
WAKTU PELAKSANAAN PEKERJAAN
Jumlah Hari
SISA WAKTU PELAKSANAAN 112 HAR
No. Uraian Pekerjaan Sat. Sisa Volume
Kerja
Agustus September
10 - 31 1 - 30
9=(6x7x8) 10=(4/9) 11 12
16,023.93
460.80
460.8 m3 34.77 35 hr Memenuhi
Yulianto
Kepala Proyek
PRODUKSI PERALATAN
9=(6x7x8) 10=(4/9) 11 12
597.6 m3 8.69
561.1 m3 9.25 10 hr Memenuhi
2,617.9 m3 1.98
1,792.8 m3 2.90
1,517.7 m3 3.42
597.6 m3 3.94
561.1 m3 4.20 5 hr Memenuhi
2,617.9 m3 0.90
1,792.8 m3 1.31
1,517.7 m3 1.55
Yulianto
Kepala Proyek
PRODUKSI PERALATAN
Laston AC-BC
Produktivitas Jlh Hari Waktu
Pelaksa KET
/ Hari Kerja Alat naan
9=(6x7x8) 10=(4/9) 11 12
180.3 m3 7.217
167.0 m3 7.795
139.1 m3 9.354
196.2 m3 6.633
111.3 m3 11.692 12 hr Memenuhi
160.0 m3 8.134
224.0 m3 5.810
225.4 m3 14.248
208.7 m3 15.388
173.9 m3 18.465
245.3 m3 13.094
139.1 m3 23.082 24 Hr Memenuhi
200.0 m3 16.057
280.0 m3 11.469
Oktober November
1 - 30
PT. Waskita Karya
Yulianto
Kepala Proyek
RENCANA ACTION PLAN SAMPAI 30 SEPTEMBER 2012
Aspal AC-WC
Aspal AC-BC
Agregat Base A
Agregat Base B
Agregat Base A (Bahu)
Agregat Base B (Bahu)
1+050
Aspal AC-WC
Aspal AC-BC
Agregat Base A
Agregat Base B
Agregat Base A (Bahu)
Agregat Base B (Bahu)
Aspal AC-WC
Aspal AC-BC
Agregat Base A
Agregat Base B
Agregat Base A (Bahu)
Agregat Base B (Bahu)
0+000
Aspal AC-WC
Aspal AC-BC
Agregat Base A
Agregat Base B
Agregat Base A (Bahu)
Agregat Base B (Bahu)
SKETSA PELAKSANAAN HINGGA 24 SEPTEMBER 2012
1+050
EMBER 2012
16+325 18+000
Pel. Jembatan
Pel. Jembatan
Ke Meulaboh
TOBER 2012
Pel. Jembatan
Ke Meulaboh
16+250
EMBER 2012
7654.86
14+025 16+325 18+000
Jem
Jem
Pel.
Pel.
bat
bat
an
an
Ke Meulaboh
Pel. Jembatan
Pel. Jembatan
16+250
MBER 2012)
bata
Jem
Jem
Pel.
Pel.
n
Jem
Pel.
bat
an
Ke Meulaboh
Pel. Jembatan
Pel. Jembatan
16+250
EMBER 2012
16+325 18+000
13+125 17+575
Pel. Jembatan
Pel. Jembatan
Ke Meulaboh
37,831,666,035
52,809,764,492
101,433,668,000.00
14,978,098,457
48,623,903,508
REALISASI FISIK SAMPAI DENGAN 10 OKTOBER 2012
1+800 12+230
0+000 1+050 2+100 4+000 5+275 9+000 11+250
1+350 8+800
Aspal AC-WC
Aspal AC-BC
Agregat Base A
Agregat Base B
Guard Rail
1+400
10+100
15-Oct-12
16-Aug-11
426
474
OKTOBER 2012
Jembata
Pel.
n Ke Meulaboh
1.388
52,089,764,492
2 8,569,670,700
16-Aug-11 60,659,435,192
101433668000,00
426
474
48 #VALUE!
INFRASTRUCT
PACKAGE JN
ORIGINAL
DIVISION
CONTRACT
DESCRIPTION UNIT
EST.
NO.
Q'TITY
DIVISI - 1 GENERAL
1.2 Mobilization LS 1.00
1.8 Relocation of Utilities and service existing PLN, Telkom LS 1.00
DIVISI - 2 DRAINASE
2.1 Excavation for Drainage Dithes & Waterways Cu. M 2,219.00
2.3 (3) Reinforced Concrete Pipe, Inner diameter 75 - 120 cm L.M 386.00
DIVISI - 3 EARTHWORKS
3.1(1) Common Excavation Cu. M 15,717.53
3.1.(8) Excavatin on Existing Asphaltic Pavament Without CMM Cu. M 247.00
3.2.(2) Selected Embankment Cu. M 140,000.00
3.3 Grade Preparation Sq.M 11,250.00
DIVISI - 4 PAVEMENT WIDENING AND SHOULDERS
4.2.(1) Aggregat Base Class A Cu. M 11,460.00
4.2.(2) Aggregat Base Class B Cu. M 12,594.00
DIVISI - 5 GRANULAR PAVEMENT
5.1.(1) Aggregat Base Class A Cu. M 15,525.00
5.1.(2) Aggregat Base Class B Cu. M 20,700.00
DIVISI - 6 ASPHALT PAVEMENT
6.1(1) Prime Coat Litre 72,951.25
6.2(2) Tack Coat Litre 127,977.50
6.3 (5a) Asphaltic Concrete - Wearing Course (AC - WC) Sq.M 162,000.00
6.3 (6a) Asphaltic Concrete - Binder Course (AC - BC) Cu. M 5,175.00
6.3 (6c) Asphaltic Concrete - Binder Course (AC - BC) Leveling Tonne 518.00
DIVISI - 7 STRUCTURES
7.1 (5) Structural Concrete Class K 250 Cu. M 6,382.79
7.1 (8) Concrete Class K 125 Cu. M 21.60
7.3 (1) Reinforcing Steel Plain Bar U - 24 Kg 282,606.80
7.9 Stone Masonry Cu. M 1,253.79
SS7.10 (1) Geotextile Non Woven Sq.M 144,000.00
SS7.18 Geogrid Sq.M 7,500.00
DIVISI - 8 REINSTATEMENT AND MINOR WORKS
8.1 (5) Hot Asphaltic Mixture for minor works Cu. M 7.03
8.3 (1) Stabilization By Vegetation Sq.M 3,600.00
8.3 (3) Trees Each 1,766.57
8.4 (1) Pavement Marking Thermoplactic Type Sq.M 5,466.00
8.4 (4) Road Sign Single Arm With Refclector of High Instensity Grade Each 48.00
8.4 (5) Gulde Post Each 50.00
8.4 (6)a Hectometer Posts Each 162.00
8.4.(7) Guardrail L.M
DIVISI - 9 DAYWORKS
9.1 (1) Foreman Hour 40.00
9.1 (2) General Labour Hour 200.00
9.1 (3) Carpenter, Mason, etc Hour 80.00
9.1 (4) Dump Truck 3 - 4m3 Hour 40.00
9.1 (6) Water Tank 3000 - 4500 Liter Hour 40.00
9.1 (8) Motor Grader min 100 HP Hour 20.00
9.1 (9) Wheel Loader 1.0 - 1,6 M3 Hour 20.00
9.1 (11) Excavator 80 - 140 HP Hour 40.00
9.1 (13) Steel Wheel Roller 6 - 9 Ton Hour 20.00
9.1 (17) Compresor 4000 - 6500 Ltr/mnt Hour 20.00
9.1 (19) Water Pump 70 - 100 mm Hour 40.00
9.1 (20) Jack Hammer Hour 20.00
(A) Sum of division 1 to 10
(B1) Provisional Sum Environmental Mitigation Const. Works Ls 1.00
(B2) Lump Sum for Preparation of Environmental Action Plan,
Enviromental Agreement, Monitoring Equip and Testing Ls 1.00
(C) Total Cost (A + B1 + B2)
APPROVED BY
PPK 10 (TEUNOM - MEULABOH)
MONITOR
ADDENDUM CONTRACT -2
UP TO AUGUST 30, 2012
EST. Total Bid Price WIGHT EST. Total Bid Price WIGHT EST.
Q'TITY (IDR) (%) Q'TITY (IDR) % Q'TITY
- - - #REF! -
70,115.00 762,220,165.00 0.827 40,000.00 434,840,000.00 0.472 30,115.00
1,766.00 261,786,542.00 0.284 - - -
6,517.17 756,916,740.03 0.821 - - - -
82.00 161,200,274.00 0.175 - - - -
736.00 342,972,320.00 0.372 - - - -
182.00 42,665,714.00 0.046 - - - -
8,150.00 6,197,260,000.00 6.721 - - - 1,000.00
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
91,592,425,660.56 99.328 60,482,227,564.68 65.590
1.00 500,000,000.00 0.542 0.30 150,000,000.00 0.163 0.20
CHECKED BY
CONSULTANT SUPERVISION
Katahira & Engineers Interntional
ERIOD : Sept 01 to Sept 30, 2012 WEEK TO : 47 (Fourty Seven) 60 (SIXTY) WEEKS
ONTRACT (DAY) 479 PLANNING 86.518 %
SED (DAY) 133 REALIZATION 78.680 %
WIGHT (%) 28 DEVIATION (7.838) %
- #REF! -
327,380,165.00 0.355 70,115.00 762,220,165.00 0.827 100.00%
- - - - - 0.00%
- - - - - 0.00%
- - - - - 0.00%
- - - - - 0.00%
- - - - - 0.00%
760,400,000.00 0.825 1,000.00 760,400,000.00 0.825 12.27%
SUBMITTED BY
CONTRACTOR
Persero PT. WASKITA KARYA
YULIANTO
PROJECT MANAGER
INFRASTRUCTURE RECONSTR
PACKAGE JNB 1, CONSTRUCTION
PROG
DIVISION ADD.03
UNIT PRICE
DESCRIPTION UNIT
WEIGTHEST.
NO. (Rp.)
(%) Q'TITY
DIVISI - 1 GENERAL
1.2 Mobilization LS 1,833,430,500.00
### 1.00
1.8 Relocation of Utilities and service existing PLN, Telkom LS 350,000,000.00
### 1.00
DIVISI - 2 DRAINASE
2.1 Excavation for Drainage Dithes & Waterways Cu. M 23,524.00
### 432.00
2.3 (3) Reinforced Concrete Pipe, Inner diameter 75 - 120 cm L.M 1,398,958.18
### 590.00
DIVISI - 3 EARTHWORKS
3.1(1) Common Excavation Cu. M 21,474.00
### 38,633.51
3.1.(8) Excavatin on Existing Asphaltic Pavament Without CMM Cu. M 127,807.00
### -
3.2.(2) Selected Embankment Cu. M 116,314.00
### 181,997.73
3.3 Grade Preparation Sq.M 1,393.00
### 115,358.40
DIVISI - 4 PAVEMENT WIDENING AND SHOULDERS
4.2.(1) Aggregat Base Class A Cu. M 355,270.00
### 10,861.94
4.2.(2) Aggregat Base Class B Cu. M 302,030.00
### 10,906.94
DIVISI - 5 GRANULAR PAVEMENT
5.1.(1) Aggregat Base Class A Cu. M 327,473.00
### 16,504.21
5.1.(2) Aggregat Base Class B Cu. M 279,285.00
### 22,095.62
DIVISI - 6 ASPHALT PAVEMENT
6.1(1) Prime Coat Litre 12,459.00
### 180,771.59
6.2(2) Tack Coat Litre 12,323.00
### 38,016.80
6.3 (5a) Asphaltic Concrete - Wearing Course (AC - WC) Sq.M 97,787.00
### 162,929.16
6.3 (6a) Asphaltic Concrete - Binder Course (AC - BC) Cu. M 2,351,584.00
### 5,501.40
6.3 (6c) Asphaltic Concrete - Binder Course (AC - BC) Leveling Tonne 1,031,530.00
### -
DIVISI - 7 STRUCTURES
7.1 (5) Structural Concrete Class K 250 Cu. M 1,139,516.00
### 88.16
7.1 (8) Concrete Class K 125 Cu. M 808,766.00
### 309.42
7.3 (1) Reinforcing Steel Plain Bar U - 24 Kg 10,766.00
### 11,901.60
7.9 Stone Masonry Cu. M 555,853.00
### 9,652.81
SS7.10 (1) Geotextile Non Woven Sq.M 17,995.00
### 28,000.00
SS7.18 Geogrid Sq.M 32,808.00
### 37,250.00
DIVISI - 8 REINSTATEMENT AND MINOR WORKS
8.1 (5) Hot Asphaltic Mixture for minor works Cu. M 2,180,285.00
### -
8.3 (1) Stabilization By Vegetation Sq.M 10,871.00
### 70,115.00
8.3 (3) Trees Each 148,237.00
### 1,766.00
8.4 (1) Pavement Marking Thermoplactic Type Sq.M 116,142.00
### 6,517.17
8.4 (4) Road Sign Single Arm With Refclector of High Instensity Grade Each 1,965,857.00
### 82.00
8.4 (5) Gulde Post Each 465,995.00
### 736.00
8.4 (6)a Hectometer Posts Each 234,427.00
### 182.00
8.4.(7) Guardrail L.M 8,150.00
(A) Sum of division 1 to 10 ###
(B1) Provisional Sum Environmental Mitigation Const. Works Ls ### 1.00
(B2) Lump Sum for Preparation of Environmental Action Plan,
Enviromental Agreement, Monitoring Equip and Testing Ls ### 1.00
(C) Total Cost (A + B1 + B2) ###
PLANNING
KUMULATIF PLANNING
REALISATION
KUMULATIF REALISATION
DEVIATION
RECONSTRUCTION FINANCING FACILITY - ADDITIONAL FINANCING (IRFF-AF)
ONSTRUCTION OF ROAD : LUENG GAYO - ARONGAN LAMBALEK (KM. 198+000 TO KM. 216+000)
NANGGROE ACEH DARUSSALAM
- - -
0.20 70,000,000.00 0.076
- - -
-
6,997.73 813,934,319.15 0.883
- - -
-
30,115.00 327,380,165.00 0.355
- -
- - -
- - -
- - -
- - -
1,000.00 760,400,000.00 0.825
11,882,714,490.53 12.886 0.352 -
0.20 100,000,000.00 0.108
0.352 1.132
(2.782) (5.264)
NCING (IRFF-AF)
TO KM. 216+000)
G PHYSICAL PROGRESS
PENCAPAIAN PROGRES ACTION PLAN September 2012
REMARKS
Minggu III Minggu IV
Qtty % Q'TITY %
- -
-
-
-
-
-
-
300.000 0.116 -
600.00 0.197
11,250.00 0.152
-
15,367.500 1.630 -
712.50 1.817
-
-
-
-
-
-
-
-
-
-
-
-
-
2.849
-
-
1.905 2.849
3.293 3.325
9.689 13.014
1.905 2.849
3.037 5.885
(6.652) (7.129)