PAKET : PRESERVASI REKONTRUKSI DAN RUTIN JEMBATAN RUAS SUNGAI DURI -

BTS MEMPAWAH - SEI PINYUH


KONTRAKTOR : PT. PUTRA SAMI JAYA
KONSULTAN : PT.EPADASCON PERMATA

LAPORAN PERCOBAAN PENGHAMPARAN DAN PEMADATAN LAPANGAN


TRIAL COMPACTION AC - BC
Tanggal :

Tanggal
Tebal Berat (Gram) Volume Density ( Cm³ ) Kepadatan ( % )
Core Nomor Lokasi Trial
Hampar Test
Drill Contoh Gembur Padat Udara SSD Dalam Air ( Cm³ ) Trial Lab Trial (%) Spek (%)

A 7.40 6.40 1342 1346.4 747.8 598.6 2.242 2.332 96.14 98.00%
segmen 1
B 7.00 6.00 1201.8 1205.8 669.6 536.2 2.241 2.332 96.11 98.00%

G 10 Passing 7.60 6.50 1072.8 1080.6 608.2 472.4 2.271 2.332 97.38 98.00%

H 8.30 7.10 1250.2 1259.4 705.8 553.6 2.258 2.332 96.84 98.00%
Rata - Rata 7.58 6.50
Los Rata-Rata : 14.19
C 9.40 8.00 1508.8 1515.5 853.4 662.1 2.279 2.332 97.72 98.00%
segmen 2
06 Juni 2018

07 Juni 2018

08 Juni 2018

D 9.90 8.40 1499.2 1509.5 804.3 705.2 2.126 2.332 91.16 98.00%

I 12 Passing 7.30 6.20 1055.2 1066.6 603.8 462.8 2.280 2.332 97.77 98.00%

J 7.20 6.10 967.8 970.0 543.4 426.6 2.269 2.332 97.28 98.00%
Rata - Rata 8.45 7.18
Los Rata-Rata : 15.09
E 7.20 6.00 1096.4 1110.9 635.7 475.2 2.307 2.332 98.94 98.00%
segmen 3
F 7.40 6.20 1038 1059.2 609.2 450 2.307 2.332 98.91 98.00%

K 14 Passing 7.10 5.90 1083.4 1091.2 619.6 471.6 2.297 2.332 98.51 98.00%

L 9.10 7.50 1246.8 1256.8 711.6 545.2 2.287 2.332 98.06 98.00%
Rata - Rata 7.70 6.40
Los Rata-Rata : 16.88 98.61
Bina Marga Konsultan Supervisi Penyedia Jasa
Project Officer PT. Epadascon Permata PT. Putra Sami Jaya

PARTOMUAN BATUBARA SYAHBANY KURNIAWAN DESMAN JEHA


NIP. 1968191011200711006 Quality Enginer Quality Control
Berita Acara Trial Compaction Asphalt Concrete Wearing Course
di Lapangan

Pada Kamis, 2 MEI 2019 telah diadakan Trial Compaction Asphal Concrate Wearing Coarse ( AC-WC) untuk Pekerjaan Paket
PRESERVASI JALAN RUAS SUNGAI DURI - BATAS KOTA MEMPAWAH DAN SEI PINYUH PONTIANAK 2019
yang mengacu pada hasil Jobmix Formula ( JMF ), yang telah dilaksanakan secara bersama-sama oleh pihak Kontraktor dengan
di awasi oleh pihak Konsultan Supervisi dan Direksi Pekerja ( PU ) Dengan Hasil Sebagai Berikut ,(Rincian Terlampir)

MARSHALL TEST

URAIAN UNIT Hasil Test Trial SPESIPIKASI

PENYERAPAN ASPAL % 0.373 Max. 1.2

KIADAR ASPAL % 5.4 -

ANTI STRIPING AGENT % 0.2 -

STABILITAS ASPAL Kg 954 MIN.800

PELELEHAN mm 3.2 2-4

MARSHALL QUINTEN Kg/mm 299 Min. 250

RONGGA DALAM CAMPURAN ( VIM ) % 4.06 3-5

RONGGA DALAM AGGREGAT ( VMA ) % 17.72 Min. 15

RONGGA TERISI ASPAL ( VFB ) % 77.08 Min. 65

STABILITAS MARSHALL SISA SETELAH PERENDAMAN


% 96.3 min. 90
SELAMA 24 JAM 60˚C
RONGGA DALAM CAMPURAN PADA KEPADATAN
% 2.35 Min. 2
MEMBAL ( REFUSAL)

RATIO PARTIKEL # 200 % 1.0 0.6 - 1.2

PEMADATAN DI LAPANGAN

JENIS ALAT JUMLAH PASSING TEMPERATUR KEPADATAN SPESIPIKASI

TANDEM 2 Passing
125 -145 Derajat
99 %' Min.98.0 %
PTR 14 Passing 100 - 125 Derajat

LOSS 18 %

Demikian Berita Acara ini Dibuat, untuk acuan kerja selanjutnya pada Pekerjaan , PRESERVASI JALAN SUI DURI - BATAS KOTA
MEMPAWAH DAN SEI PINYUH - PONTIANAK 2019

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
REPUBLIK INDONESIA
KEMENTRIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKOTRAT JENDERAL BINA MARGA

PRESERVASI REKONTRUKSI DAN RUTIN JEMBATAN


RUAS SEI. DURI - BTS KOTA MEMPAWAH - SEI. PINYUH - SEBADU

KALIMANTAN BARAT

TRIAL COMPACTION ASPHALT WEARING COARSE ( AC-WC )

KONSULTAN KONTRAKTOR
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING

LAPORAN PERCOBAAN PENGHAMPARAN DAN KEPADATAN LAPANGAN


TRIAL COMPACTION AC - WC
Tanggal Nomor Tebal Berat (gram) Volume Density (Cm³) Kepadatan (%)
Lokasi Trial :
Hampar Core dill Test Contoh Gembur Padat udara Air Jenuh (Cm³) TRIAL LAB TRIAL (%) Spek (%)
A 7.3 6.5 1205.2 1211.4 685.2 526.2 2.290 2.306 99.3 98.00%
segmen 1
B 7.3 6.0 1123.2 1129.2 635.4 493.8 2.275 2.306 98.6 98.00%
C PASSING 14 7.2 6.2 1165.4 1171.6 660.4 511.2 2.280 2.306 98.9 98.00%
D 7.5 6.6 1227.6 1234.0 696.6 537.4 2.284 2.306 99.1 98.00%
Rata - rata 7.3 6.3 2.282 2.306 99.0 98.00%
Loss thickness : 18.0%
A 7.1 5.8 1078.0 1083.2 612.8 470.4 2.292 2.306 99.4 98.00%
segmen 2
B 7.7 6.4 1161.2 1166.0 662.2 503.8 2.305 2.306 100.0 98.00%
02 Mei 2019

03 Mei 2019

04 Mei 2019

C PASSING 16 7.5 6.2 1141.6 1146.2 648.6 497.6 2.294 2.306 99.5 98.00%
D 7.4 6.1 1113.4 1118.2 632.6 485.6 2.293 2.306 99.4 98.00%
Rata - rata 7.4 6.1 2.296 2.306 99.6 98.00%
Loss thickness : 20.0%

A 7.5 6.6 1169.6 1171.2 685.2 486 2.407 2.306 104.4 98.00%
segmen 3
B 8.0 7.1 1306.2 1310.2 750.4 559.8 2.333 2.306 101.2 98.00%
C PASSING 18 7.3 5.8 1061.0 1065.2 604.6 460.6 2.304 2.306 99.9 98.00%
D 7.8 6.3 1155.6 1159.4 662.6 496.8 2.326 2.306 100.9 98.00%
Rata - rata 7.7 6.5 2.342 2.306 101.6 98.00%
Loss thickness : 22.0%

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING

Tanggal : 2-May-2109

Laporan Hasil Test Marshal Lab. Trial AC-WC


Gs Bitumen, Gb = 1.035
Proving Ring Calibration, Cal = 30.6 kg/dev Gs Eff Agg Comb., Gse = 2.677
Asphalt Absorption, Pba = 0.373 Gs Bulk Agg Comb., Gsb = 2.652

Berat Benda uji (Gram) Berat Rongga Rongga Stabilitas


Rongga Hasil Bagi Kadar Ratio
Isi Benda Kepadatan Jenis Terhadap Terisi Pelelehan
Kadar Aspal (%) dalam agg Marshall Aspal Partikel
Uji (Cm3) (gr/cm3) Campuran Campuran Aspal Bacaan Proving Setelah Dikoreksi (mm)
VMA (%) (kg/mm) Efektif (%) #200
Kering SSD Dalam Air Maksimal VIM (%) VFB (%) Pada Alat Rnig Kg
No.
a b c d e f g h i j k l m n o p q r
100-((100- 100- b-(Pba(100-
By Wt of Agg By Wt of Mix Lab Lab Lab d-e c/f 100x(i-j)/i From Lab l x Cal Adjust From Lab n/o -
b)xg)/Gsb (100xg/h) b))/100

1 5.40 1199.2 1205.8 686.2 519.6 2.308 30 918 918 3.1 296
2 1196.8 1201.8 683.0 518.8 2.307 32 979 979 3.0 326
3 1197.8 1203.6 685.4 518.2 2.311 31 949 949 3.4 279
4 1198.8 1204.0 683.6 520.4 2.304 33 1010 1010 3.2 316
5 1194.4 1210.2 692.2 518.0 2.306 31 949 949 3.3 287
6 1199.2 1204.2 683.4 520.9 2.302 30 918 918 3.2 287

2.306 2.404 17.72 4.06 77.08 31 954 954 3.2 299 5.05 1.0
Min. 15 3-5 Min. 65 Min.800 2-4 Min. 250 0.6 - 1.2

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING
Tanggal : 2-May-2109

BERAT JENIS CAMPURAN MAKSIMUM TRIAL AC-WC

Kadar Aspal : 5.40 %

N0 Keterangan 1 2

1 Berat Material + Pan Gram 964.4 966.6


2 Berat Pan Gram 373.4 373.4
3 Berat Material Gram 591.0 593.2
4 Berat Picno + Material +Air Gram 2089.2 2090.8
5 Berat Picno +Air Gram 1744.2 1744.2
6 Berat Air (4-5) Gram 345 346.6
7 Volume Material (3-6) Gram 246.0 246.6
8 Max Specific Gravity (GMM) (3:7) Gram 2.402 2.406
0
9 Temperatur Air T C Gram 25 25
10 Koreksi Suhu Gram 1 1
11 Max Specific Gravity (GMM) ( 8 X 10 ) Gram 2.402 2.406 2.404

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


Nip. 1968191011200711006 Quality Qontrol
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING
Tanggal : 2-May-2109

TAKE COAT TRIAL AC-WC


DISKRISITION SEGMEN 1 SEGMEN 2 SEGMEN 3
1 2 3 1 2 3 1 2 3 REMARK
1 Weight paper + sample ( gram ) 53.4 52.2 52.4 51.4 50.4 50.8 53.6 53.0 49.3
2 Weight paper 23.2 22.4 22.4 21.0 21.0 21.0 23.0 21.4 22.8 Paper standart =
3 Weight sample 30.2 29.8 30.0 30.4 29.4 29.8 30.6 31.6 26.5 0,25 x 0,25 m =
4 Paper area ( m2 ) 0.0625 0.0625 0.0625 0.0625 0.0625 0.0625 0.0625 0.0625 0.0625 0,0625 m2
5 Capacity ( gr / m2 ) 483.2 476.8 480 486.4 470.4 476.8 489.6 505.6 424
6 Specific grafity ( kg / ltr ) 1.019 1.019 1.019 1.019 1.019 1.019 1.019 1.019 1.019
7 Volume ( ltr / m2 ) 0.474 0.468 0.471 0.477 0.462 0.468 0.480 0.496 0.416
8 Total Volume 1+2+3 0.471 0.469 0.464

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING

Tanggal : 2-May-2109

Marshall Sisa Trial AC-WC


SNI 06-2489-1991 Gs Bitumen, Gb = 1.0347
Proving Ring Calibration, Cal = 30.6 kg/dev Gs Eff Agg Comb., Gse = 2.677
Asphalt Absorption, Pba = 0.373 Gs Bulk Agg Comb., Gsb = 2.652

Effective
Gs Bulk of Marshall Retained
Weight (Gram) Vol of Mix Gmm Stability Flow Asphalt
Bitument Content (%) Mix VMA (%) VIM (%) VFB (%) Quotient Marshall
(Cm3) maxs (mm) Content
In Air SSD In Water (gr/cm3) Read Load Kg (kg/mm) Stab (%)
No. (%)
a b c d e f g h i j k l m n o p q s
100-((100- 100- b-(Pba(100-
By Wt of Agg By Wt of Mix From Lab From Lab From Lab d-e c/f 100x(i-j)/i From Lab l x Cal Adjust From Lab n/o
b)xg)/Gsb (100xg/h) b))/100

1 5.40 1199.4 1205.4 687.4 518.0 2.315 2.404 17.40 3.68 78.83 30 918 918 3.1 296.1
2 1199.2 1204.2 685.2 519.0 2.311 2.404 17.57 3.88 77.89 30 918 918 3 306.0

2.313 2.404 17.49 3.78 78.36 918 3.1 301 5.40 96.3

MIN. 90

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING

Tanggal : 2-May-2109

Marshall Refusal Trial AC-WC


Gs Bitumen, Gb = 1.035
Proving Ring Calibration, Cal = 30.6 kg/dev Gs Eff Agg Comb., Gse = 2.677
Asphalt Absorption, Pba = 0.373 Gs Bulk Agg Comb., Gsb = 2.652

Gs Bulk of Marshall Asphalt


Weight (Gram) Vol of Mix Gmm Stability Flow
Bitument Content (%) Mix VMA (%) VIM (%) VFB (%) Quotient Content
(Cm3) maxs (mm)
In Air SSD In Water (gr/cm3) Means Load Kg (kg/mm) Eff
No. a b c d e f g h i j k l m n o p q
b-
By Wt of By Wt of 100-((100- 100-
From Lab From Lab From Lab d-e c/f 100x(i-j)/i From Lab l x Cal Adjust From Lab n/o (Pba(100-
Agg Mix b)xg)/Gsb (100xg/h)
b))/100

1 5.40 1198.8 1203.4 692.4 511.0 2.346 2.404 2.41


2 1196.6 1200.6 691.2 509.4 2.349 2.404 2.29

2.348 2.404 2.35

MIN. 2

Bina Marga Konsultan Supervisi Penyedia Jasa


Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control
PAKET : PRESERVASI JALAN RUAS SEI DURI - BATAS KOTA MEMPAWAH & SEI PINYUH -
PONTIANAK
KONTRAKTOR : PT. TRANS BORNEO LESTARI
KONSULTAN : PT. PLANOSIP NUSANTARA ENGINEERING
Tanggal : 2-May-2109

STREEP MAP

1 3 5 7
14 PASSING 16 PASSING
2 4 6 8
ARAH PINYUH 9 11 ARAH PONTIANAK
18 PASSING
10 12
Bina Marga Konsultan Supervisi Penyedia Jasa
Project Officer PT. Planosip Nusantara Engineering PT. Trans Borneo Lestari

PARTOMUAN BATUBARA DESMAN JEHA


NIP. 1968191011200711006 Quality Control