3.10 Perhitungan Pondasi-4
3.10 Perhitungan Pondasi-4
Beban Mati
- ND Portal Melintang = 533,782 KN
- ND Portal Memanjang = 1216,024 KN
- VD Sloof Memanjang = 48,46 KN
- VD Sloof Melintang = 30,249 KN +
PD = 1828,515 KN
Beban Hidup
- NL Portal Memanjang = 625,945 KN
- NL Portal Melintang = 234,738 KN +
PL = 860,683 KN
P = PD + PL
= 1828,515 KN + 860,683 KN
= 2689,198 KN
Pu = 1,2PD + 1,6PL
= 1,2 1828,515 KN + 1,6 860,683 KN
= 3571,318 KN
Momen
Momen Portal Melintang
- MD portal melintang = 12,079 KN/m
- ML portal meintang = 5,159 KN/m +
Mtotal portal melintang = 17,238 KN/m
− 36
𝑁 = = 5,182
6,947
= 634,621 Ton
= 6346,21 KN
Qult
Qizin
F
6346,21 KN
= 3
= 2115,403 KN
Maka diambil nilai yang terkecil yaitu 2115,403 KN
Menentukan Jumlah tiang
514
= 0,898
515
Q M y. X maks M X . Ymaks
Q1
n X 2 Y 2
3044,5178 KN (6,676 KN) .0 (17,238𝐾𝑁).0,75
= − −
2 0 1,125 𝑚2
= 1510,7669 KN
Q M y. X maks M X . Ymaks
Q2
n X 2 Y 2
3044,5178 KN (6,676 KN) .0 (17,238𝐾𝑁).0,75
= + +
2 0 1,125 𝑚2
= 1533,7509 KN
Qtot = Q1 + Q2
= 1510,7669 KN + 1533,7509 KN
= 3044,5178 KN < Qizin grup (OK)
516
Dmaks = 1/2. q. L
= 1/2. 600 kg/m. 6 m
= 1800 kg
Mx = R1x – ½ qx2
Syarat Ekstrim :
𝑑𝑚𝑥
=0
𝑑𝑥
R1 - qx = 0
𝑅1 𝐿2 −2𝑎𝐿
x = =
𝑞 2 ( 𝐿−𝑎 )
𝐿2 .2𝑎𝐿 1 𝐿2 −2𝑎𝐿
Mmax = M2 = R1 2 ( 𝐿−𝑎 ) − 2 𝑞 ( 2(𝐿−𝑎) )2
1 𝐿2 −2𝑎𝐿
= 2 𝑞 ( 2(𝐿−𝑎) )
M1 = M 2
𝐿2 −2𝑎𝐿
½ qa2 = ½ q ( 2(𝐿−𝑎) )2
𝐿 − 2𝑎𝐿
a = 2 ( 𝐿−𝑎 )
2a2 + 4aL + L2 =0
2a2 + 4a(6) + 62 =0
2a2 + 24a - 36 =0
.a1 = 1,348 m atau a2 = -13,348 m ( Diambil )
- Momen yang timbul
M1 = M2 = ½ qa2
518
= 0,0258
𝑃𝑢
- Absis Y = ∅. 𝐴𝑔 .0,85 .𝑓𝑐 ′
1785,659 𝑥 1000
= 0,65 500.500 .0,85 .30
= 0,430
Didapat pg dari grafik gideon dibawah
Pg = 0,001 < 𝜌 min = 0,01, 𝑚𝑎𝑘𝑎 𝑑𝑖𝑎𝑚𝑏𝑖𝑙 𝜌𝑚𝑖𝑛
519
= 0,835
𝜌. 𝑝𝑎𝑘𝑎𝑖 = 𝜌 min 𝑥 𝛽 = 0,01 𝑥 0,835 = 0,00835
Astotal = 0,00835 x b x h
= 0,00835 x 500 x 500
= 2087,5 mm2
As Total = 2087,5 mm2 (𝑑𝑖𝑝𝑎𝑠𝑎𝑛𝑔 𝑑𝑒𝑛𝑔𝑎𝑛 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 16𝐷13 =
2123,717) 𝑑𝑎𝑟𝑖 𝑇𝑎𝑏𝑒𝑙 3. 𝑃𝑒𝑛𝑢𝑙𝑎𝑛𝑔𝑎𝑛 𝐵𝑎𝑗𝑎
Dipasang 4D13 tiap sisi
Dengan demikian ukuran tiang pancang adalah 50 x 50 cm
dengan dipasang tulangan 4D13 = 530,929 mm2 Dapat digunakan
𝑀𝑢 𝑓𝑦 2 𝜌2
= 𝑓𝑦𝜌 −
∅𝑏𝑑 2 1,7𝑓′𝑐
𝑓𝑦 2 𝜌2 𝑀𝑢
− 𝑓𝑦 𝜌 + =0
1,7𝑓′𝑐 ∅𝑏𝑑 2
−𝑏 ± √𝑏 2 − 4𝑎𝑐
𝜌1,2 =
2𝑎
= 0,0319
𝑓𝑦
0,003+
𝐸𝑠
𝜌𝑚𝑎𝑘𝑠 = ( ) 𝑥 𝜌𝑏
0,008
400
0,003+
200000
=( ) 𝑥 0,0319
0,008
= 0,019
521
1,4 1,4
𝜌. 𝑚𝑖𝑛 = = = 0,0035 ( 𝐷𝑖𝑎𝑚𝑏𝑖𝑙 )
𝑓𝑦 400
√𝑓𝑐′ √30
𝜌. 𝑚𝑖𝑛 = = = 0,034
4. 𝑓𝑦 4. 400
Astotal = 𝜌 . 𝑏 . ℎ
= 0,0035 . 500 . 500
= 875 mm2
As’ = Astotal/4
=218,75 mm2
Karena As dengan beban P lebih besar dari As dengan momen
pengangkatan (530,929 mm2 > 218,75 mm2), maka tetap gunakan
Tulangan 4D13 dengan As = 530,929 mm2 setiap sisi tiang pancang.
c. Perhitungan Sengkang
𝑞𝐿2 −2.𝑎.𝑞.𝐿
Vu = R1= 2(𝐿−𝑎)
545,1312.62 −2.1,348.545,1312.6
= = 1161,509 𝑘𝑔~ 11615,09 𝑁
2(6−1,348)
1
∅𝑉𝑐 = ∅ . √𝑓𝑐′. 𝑏𝑤 . 𝑑
6
1
= 0,75. . √30. 500 . 413,5
6
= 141552,048 N
½ ∅𝑉𝑐 = ½ 141552,048 N
= 70776,024 N
Vu < ∅𝑉𝑐 → tidak diperlukan tulangan geser. Namun untuk mengikuti
tulangan pokok masih digunakan tulangan geser dan jarak tulangan
geser ditentukan dari nilai Smaks ;
1
Av = 4 . 𝜋. 𝑑𝑠 2
1
= 4 . 𝜋. 102
= 78,539 mm2
522
3 . 𝐴𝑣 . 𝑓𝑦
S = 𝑏
3 . 78,539 . 400
= 500
= 188,493 mm ≈ 150 𝑚𝑚
Smaks = ½ deff
= ½ 413,5 mm
= 206,75 mm ≈ 200 mm
S < Smaks. Jadi, dipilih tulangan sengkang dengan tulangan ∅10 −
200 𝑚𝑚
= 9098334,424 N
d
Vc 2 0,083 1 2 f ' c .bo .d
bo
40.705
= 0,083 ( 4620 + 2) 1. √30. 4620.705
= 11999514,55 N
𝑉𝑐3 = 0,33𝜆√𝑓𝑐′. 𝑏𝑜 . 𝑑 = 0,33. 1 √30. 4620. 705 = 5887157,569 𝑁
Maka, ϕVn = 0,75 Vn = 0,75 (5887159,569 N)
= 4415368,177 N → 4415,368 KN > Vu (OKE)
524
= 4342386,884 N
d
Vc 2 0,083 1 2 f ' c .bo .d
bo
40.705
= 0,083 ( + 2) 1. √30. 2705 .705
2205
= 10451500,26 N
𝑉𝑐3 = 0,33𝜆√𝑓𝑐′. 𝑏𝑜 . 𝑑 = 0,33. 1 √30. 2705.705 =
2809779,749 𝑁
Maka, ϕVn = 0,75 Vn = 0,75 (2809779,749N) = 2107334,812 N
= 2107,334 KN > Vu= 1785,5 KN (OK)
525
Vu = Pu/n
= 738,501 KN
Mu = Vu . x
x = Jarak dari As tiang pancang ke tepi luas kolom
= 1275 mm – 750 mm = 525 mm
= Vu . x = 1785,659 KN x 0,525 m = 937,471 KN
Fc’ = 30 Mpa
Fy = 400 Mpa
Tulangan Utama = D25
Tulangan sengkang = D20
Tebal = 800 mm
B = 3000 mm
L = 1500 mm
Selimut beton (p) = 70 mm
Tinggi Efektif (deff) = h – p – ½ diameter tulangan
= 800 mm – 70 mm – ½ 25 mm
= 717,5 mm
a). Tulangan Pokok Pile Cap
1,4 1,4
𝜌. 𝑚𝑖𝑛 = = = 0,0035 ( 𝐷𝑖𝑎𝑚𝑏𝑖𝑙 )
𝑓𝑦 400
√𝑓𝑐′ √30
𝜌. 𝑚𝑖𝑛 = = = 0,0034
4. 𝑓𝑦 4. 400
𝑓𝑦 𝑀𝑢 1,7.𝑓𝑐 ′
𝜌 = ½ (1- √1 − 4 (1,7 . ) (∅.𝑏.𝑑2 .𝑓𝑦) ( )
𝑓𝑐 ′ 𝑓𝑦
𝜌 = 0,0038
Karena 𝜌𝑝𝑎𝑘𝑎𝑖 = 0,0038
𝜌𝑝𝑎𝑘𝑎𝑖 > 𝜌.𝑚𝑖𝑛
Astotal = 𝜌 . 𝑏 . 𝑑
= 0,0038 . 1500 . 717,5
= 4104 mm2
Diambil As Pakai 9D25 = 4417.865 mm2 (Dari Tabel 3. Penulangan Baja)
527
Jarak Tulangan
𝐴𝑠 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛
S = . 𝑙𝑒𝑏𝑎𝑟 𝑝𝑖𝑙𝑒 𝑐𝑎𝑝
𝐴𝑠 𝑃𝑎𝑘𝑎𝑖
490,873
= 4417,865 . 1500 𝑚𝑚
= 166,66 ≈ 150 𝑚𝑚
Jadi, digunakan tulangan 9D25 – 150 (As = 4417,865 mm2)
b). Tulangan Sengkang Pile Cap
= 1473,716 KN
1
∅𝑉𝑠 < ∅𝑉𝑠 = ∅ . 3 . √𝑓𝑐. 𝑏 . 𝑑
Dengan syarat :
S < 600 mm
𝑑
S =2
717,5 𝑚𝑚
= = 358,75 mm ≈ 350 𝑚𝑚
2
Gambar
528
= 14415 mm2
Untuk Jarak tulangan sengkang per meter
𝐴𝑣
Av = 𝐿
14415 m𝑚2
= 3 𝑚2
= 4805 mm2/m2
𝑏.𝑠
Avmaks = 0,35. 𝑓𝑦
1500 𝑚𝑚 .1000𝑚𝑚
= 0,35. 400 𝑀𝑝𝑎
= 1312,5 mm2/m2
Maka dipakai Av per meter = 4805 mm2/m2
1 1
Av1 = (4 . 𝜋. 𝑑𝑠 2 ) 𝑥 2 = (4 . 𝜋. 202 ) 𝑥 2 = 628,318 𝑚𝑚2
𝐴𝑣1 628,318
S = 𝐴𝑣 . 1000 𝑚𝑚 = . 1000 𝑚𝑚 = 130,76 𝑚𝑚 ≈ 130 𝑚𝑚
4805
As = 1256,637 mm2/4
= 314,159 mm2 (1D20)
Dipasang di keempat sisi kolom pasak (Dari Tabel 3. Penulangan baja)
Karena jumlah tulangan kolom dengan D20.
Kontrol panjang penyaluran pasak
Panjang penyaluran pasak
0,25.𝑓𝑦.𝑑𝑏
Ldb = ≥ 0,04.fy.db
√𝑓𝑐′
0,25.400.20
= ≥ 0,04.400.20
√30
= 365,148 mm ≥ 320 mm
L1 = h – p – (2∅𝑃𝑜𝑛𝑑𝑎𝑠𝑖) - ∅𝑝𝑎𝑠𝑎𝑘
= 800 mm – 70 mm – (2.13) – (2.20)
= 664 mm> 365,148 mm (𝑂𝐾𝐸)
530