Pembuatan Program Aplikasi Simulasi Kinerja Backhoe-Dump Truck Pada


Pemindahan Tanah Mekanis

Article · June 2013

CITATIONS READS

0 132

3 authors, including:

Almuntofa Purwantoro Waluyo Nuswantoro


Universitas Palangka Raya Universitas Palangka Raya
4 PUBLICATIONS   0 CITATIONS    14 PUBLICATIONS   0 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Jurnal Manajemen Rekayasa Konstruksi View project

Rekayasa Jalan dan Pemanfaatan Material Lokal di Kalimantan Tengah View project

All content following this page was uploaded by Waluyo Nuswantoro on 28 April 2018.

The user has requested enhancement of the downloaded file.


J URNAL
REKAYASA RANCANG BANGUN, Volume 14 Nomor 1, Juni 2013: 16 - 23
_________________________________________________________________________

PEMBUATAN PROGRAM APLIKASI SIMULASI KINERJA BACKHOE - DUMP


TRUCK PADA PEMINDAHAN TANAH MEKANIS
Oleh : Rahmat Bangun Giarto1, Almuntofa Purwantoro dan Waluyo Nuswantoro 2

Abstraksi
Pekerjaan Pemindahan Tanah Mekanis dalam perencanaan jumlah Backhoe-Dump
Truck, waktu kerja dan anggaran biaya masih menggunakan Microsoft Execl. Pada Tugas Akhir
ini akan dirancang dan dibuat sebuah system informasi yang akan membantu merencanakan
jumlah Backhoe-Dump Truck, waktu kerja dan anggaran biaya, sehingga lebih mudah
mendapatkan hasil yang riil untuk digunakan dalam suatu proyek. Pembuatan system informasi
simulasi pemindahan tanah mekanis ini menggunakan metode waterfall. Dalam metodologi ini
dilakukan beberapa langkah untuk membangun sebuah perangkat lunak yaitu : analysis,
desaign, coding,testing dan maintenance. Metode pembutan simulasi pemindahan tanah mekanis
untuk perhitungan menggunakan metode yang digunakan Departemen Pekerjaan Umum
Direktorat Jendral Bina Marga ini menggunakan bahasa pemrograman Visual Basic 6.0 dan
Microsoft Acces sebagai databasenya. Hasil perhitungan menggunakan Program Aplikasi
Simulasi Kinerja Backhoe-Dump Truck Pada Pemindahan Tanah Mekanis didapatkan hasil
perhitungan pada proyek Lanjutan Pembangunan Jaringan Irigasi D.I. Hurung Bunut 600 Ha
(Rounding Up) yaitu nilai ultility factor yang tinggi dengan jumlah 1 Backhoe dan 6 Dump
Truck, artinya idle time yang ada hanya sedikit, sehingga Backhoe dan Dump truck lebih efektif
bekerja. Biaya pekerjaan pada proyek secara manual sebesar Rp.1.106.553.838,54, sedangkan
pada hasil program simulasi didapat biaya pekerjaan sebesar Rp. 171.7248,-

Kata kunci: Backhoe, Dump truck, Pemindahan Tanah Mekanis, Simulasi .

PENDAHULUAN mempunyai produktivitas dan waktu siklus


Dalam pekerjaan galian tanah pada proyek masing-masing yang berbeda, sehingga kinerja
konstruksi, misalnya untuk ruang basement dalam kedua alat merupakan hal yang sangat penting
pelaksanaannya sering kali menggunakan 2 jenis untuk mencapai suatu hasil yang optimum.
alat, yaitu Backhoe yang berfungsi untuk
menggali tanah dan Dump truck yang berfungsi Teknologi merupakan bagian dari media yang
untuk mengangkut tanah hasil galian dan digunakan untuk menyampaikan pesan pada
membawanya ketempat pembuangan (Dump Site), banyak orang. Kemajuan teknologi membawa
sehingga dalam sistem operasi ini Backhoe banyak dampak positif pada kehidupan manusia.
(sebagai server) melayani Dump truck (sebagai Salah satunya adalah komputer yang dapat
customer). Perhitungan yang tepat terhadap membantu dan mempermudah manusia
jumlah Backhoe dan Dump truck mempunyai menyelesaikan suatu pekerjaan. Kemampuan
peran yang sangat penting untuk durasi, biaya, komputer yang semakin meningkat merupakan
serta kelancaran pekerjaan pada pemindahan suatu pendorong untuk memanfaatkan teknologi
tanah mekanis. Backhoe dan Dump truck ini untuk mendukung kegiatan bisnis.

1 Rahmat Bangun Giarto, ST adalah alumni Jurusan/Program Studi Teknik Sipil Fakultas Teknik
Universitas Palangka Raya
2 Almuntofa Purwantoro, ST., MT dan Ir. Waluyo Nuswantoro, MT adalah dosen Jurusan/Program

Studi Teknik Sipil Fakultas Teknik Universitas Palangka Raya

_________________________________________________________________________
16
Rahmat Bangun Giarto, et al., Pembuatan Program Aplikasi Simulasi Kinerja Backhoe-Dump Truck…
_________________________________________________________________________________________________

Mengelola informasi yang dihasilkan oleh (7) Aplikasi hanya dapat menampilkan satu tipe
komputer berbeda dengan mengelola data-data Backhoe yang sama apabila jumlah Backhoe lebih
yang diperoleh secara manual. Sehingga untuk dari satu dalam satu kali simulasi. (8) Aplikasi
sebuah tujuan dibutuhkan sistem agar tidak memperhitungkan Idle Time untuk
meningkatkan sasaran kinerja yang hendak kebutuhan lain, seperti kelangkaan BBM,
dicapai. perubahan cuaca, faktor ketinggian, faktor
perubahan suhu, faktor lalu lintas, faktor social
Agar perusahaan dapat mencapai target yang (hubungan dengan warga disekitar lokasi proyek),
hendak dicapai maka diperlukan sistem informasi kerusakan dan perawatan pada alat berat. (9)
untuk mendukung operasi yang bersifat Untuk database pada Excavator yang digunakan
managerial. Jadi, sistem informasi bagi suatu dalam program hanya dua tipe, yaitu Komatsu
perusahaan merupakan salah satu faktor kritis dan Cat, sedangkan pada Dump Truck yang
dalam menetukan kesuksesan atau kegagalan digunakan adalah tipe Hino. Untuk spesifikasi
suatu usaha. diluar itu, bisa ditambahkan pada program. (10)
Seringkali perusahaan masih menggunakan sistem Standar Sprsifikasi perhitungan mengacu pada
manual sehingga menimbulkan masalah dalam Departemen Pekerjaan Umum Direktoral Jendral
hal : Bina Marga. (11) Aplikasi hanya dapat
1. Menghitung jumlah Backhoe-Dump truck menghitung output data dengan jumlah 2 Backhoe
secara manual. dan 16 Dump Truck.
2. Perhitungan anggaran masih menggunakan Adapun manfaat dari penelitian ini adalah sebagai
Microsoft Excel. berikut: (1) Aplikasi simulasi kinerja Backhoe-
3. Sering kehilangan link karena analisa Dump Truck memudahkan kontraktor
dilakukan dengan menghubungkan file menentukan jumlah Backhoe-Dump truck dengan
Microsoft Excel yang lain. cepat untuk mencapai suatu hasil yang optimal.
4. Untuk 1 paket pekerjaan perusahaan (2) Menentukan jumlah Backhoe-Dump truck
membutuhkan waktu minimal 2 minggu untuk secara mudah dan tepat. (3) Aplikasi simulasi
melakukan perkiraan anggaran (estimate) dan kinerja Backhoe-Dump Truck ini dapat membantu
penjadwalan proyek. manager dalam membuat keputusan. (4)
Memperluas pengetahuan dan wawasan
Konsep yang baik untuk menangani permasalahan akademisi mengenai sistem informasi dan
ini adalah dengan membuat sistem baru sehingga pemanfaatannya dalam bidang teknik sipil.
mampu menunjang kelancaran jalannya sistem
lama yang ada di perusahaan dan mempercepat PERUMUSAN MASALAH
kinerja perusahaan memperkecil segala kesalahan
yang sering dilakukan secara manual serta 1. Bagaimana perancangan pembuatan aplikasi
pembuatan rencana perincian kebutuhan program simulasi kinerja backhoe-dump truck
pelaksanaan proyek untuk mengatur keuangan pada pemindahan tanah mekanis?
yang dikeluarkan dalam pengerjaan proyek 2. Berapa jumlah Backhoe-Dump truck yang
tepat pada suatu proyek?
Batasan masalah yang digunakan : (1) Pembuatan
aplikasi dan program simulasi kinerja Backhoe-
TUJUAN STUDI
Dump truck pada pemindahan tanah mekanis
1. Menghasilkan sebuah program aplikasi
menggunakan bahasa pemrogram Visual Basic
simulasi kinerja backhoe-dump truck pada
6.0. (2) Dalam perhitungan produktivitas
pemindahan tanah mekanis
digunakan metode General Output Formula dan
2. Menentukan jumlah Backhoe-Dump truck
untuk perhitungan waktu kinerja menggunakan
secara mudah dan tepat .
model antrian First In First Serve. (3) Aplikasi
tidak menghitung volume pekerjaan. (4) Aplikasi
hanya dapat menganalisa Utility factor dengan
METODE PENELITIAN
menggunakan Backhoe, berapa jumlah Dump
truck yang diperlukan agar waktu bekerja lebih
Lokasi dan Waktu Penelitian
efektif. (5) Aplikasi hanya dapat menghitung
Working day dengan menggunakan Backhoe,
Penelitian ini mengambil lokasi pada pekerjaan
berapa jumlah Dump truck yang diperlukan untuk
Lanjutan Pembangunan Jaringan Irigasi D.I.
waktu yang paling cepat. (6) Aplikasi hanya dapat
Hurung Bunut 600 Ha (Rounding Up) yang
menghitung Cost yang paling murah dengan
menggunakan Backhoe dan jumlah Dump truck.

_________________________________________________________________________
17
J URNAL
REKAYASA RANCANG BANGUN, Volume 14 Nomor 1, Juni 2013: 16 - 23
_________________________________________________________________________
berlokasi di D.I. Hurung Bunut, Kabupaten 3. Analisis Sistem.
Gunung Mas. 4. Tahapan Perancangan Desain Sistem Usulan.
5. Implementasi
6. Uji Coba Sistem

ANALISA DAN DESAIN SISTEM

Berikut adalah desain arus data dalam sistem


Simulasi PTM :

Teknik Pengumpulan Data

Pengumpulan data terbagi dua yakni data primer


dan data sekunder. Data primer yang digunakan
dalam penelitian ini meliputi catatan hasil
wawancara dengan supervisor dan hasil
pengamatan/observasi di lapangan secara
langsung tentang situasi dan keadaan proyek.
Dalam penelitian ini data sekunder yang
digunakan antara lain meliputi data volume
pekerjaan, tipe backhoe dan dump truck, jarak
site ke dump site, kecepatan rata-rata dump truck
pada Lanjutan Pembangunan Jaringan Irigasi D.I.
Hurung Bunut 600 Ha (Rounding Up),
Kabupaten Gunung Mas..

Cara Pengolahan Data

Proses pengolahan data terbagi menjadi tiga Gambar DFD Level 0


tahapan, yang disebut dengan siklus pengolahan
data (Data Processing Cycle) yaitu :
1. Pada tahapan Input
Yaitu dilakukan proses pemasukan data ke
dalam komputer lewat media input (Input
Devices).
2. Pada tahapan Processing
Yaitu dilakukan proses pengolahan data yang
sudah dimasukkan, yang dilakukan oleh alat
pemproses (Process Devices) yang dapat
berupa proses perhitungan, perbandingan,
pengendalian, atau pencarian distorage.
3. Pada tahapan Output
Yaitu dilakukan proses menghasilkan keluaran
dari hasil pengolahan data ke alat (Output
Devices) yaitu berupa informasi.

Tahap Penelitian
Urutan dalam penyusunan penelitian ini
digunakan metodologi waterfall dengan beberapa
tahap, yaitu :
1. Tahap Pengumpulan Data.
2. Tahap Identifikasi Masalah.

_________________________________________________________________________
18
Rahmat Bangun Giarto, et al., Pembuatan Program Aplikasi Simulasi Kinerja Backhoe-Dump Truck…
_________________________________________________________________________________________________

Backhoe Data_Simulasi
Kode * Kode *
Backhoe_Brand Digging Depth
**
Backhoe_Model Dump Site
Tarvel_Speed Project Name
Swing_Speed Project Location
Backhoe_Notes Site Area
Overall_Width Working Time
Track_Shoe_Width Gate to Dump Site Distance
Overall_Cab_Height Average Dump Truck Travel Speed at
Overall_Boom_Height Site
Average Dump Truck Travel Speed at
Overall_Length Road
Factor Bucket
Swing_Radius Factor Bucket
Undercarriagel_Length Factor Efficiency
Arms Operator Efficiency
Bucket Backhoe_Brand **
Min_Swing_Radius Cost for BackHoe
Max_Culling_Height Cost Mob-Demob For 1 Backhoe
Max_Digging_Reach Cost Solar
Max_Digging_Depth Digging Depth
Dump Site
Dump_Truck Project Name
Kode * Project Location
Truck_Brand Site Area
**
Truck_Mudel Working Time
Dump_Time Gate to Dump Site Distance
Truck_Notes Average Dump Truck Travel Speed at
Overal_Width Site
Average Dump Truck Travel Speed at
Overal_Height Road
Truck_Brand **
Overal_Lenght Coct For Dump Truck
Dump_Capacity Cost Mob-Demob For 1 Dump Truck
Cost Solar
Cost Operator Dump Truck
Solar ( Liter / Km)
Start Day
T1
Keterangan : T2
* Primary Key T3
** Foreign Key T4
T5
T6
Utility Factor
Working Days
Total Cost
Gambar ERD

_________________________________________________________________________
19
J URNAL
REKAYASA RANCANG BANGUN, Volume 14 Nomor 1, Juni 2013: 16 - 23
_________________________________________________________________________
HASIL ANALISIS DAN IMPLEMENTASI Jumlah siklus Backhoe
= Kapasitas Dump Truck /
Hasil analisis merupakan tahapan KapasitasBackhoe
penggunaan/pemanfaatan Simulasi Pemindahan Jumlah siklus Backhoe = 4m3 / 0.93
Tanah Mekanis (PTM) dibuat untuk membuktikan Jumlah siklus Backhoe = 4,30
aplikasi dapat berfungsi dengan baik. Tahapan ini = 5 siklus
adalah membandingkan hasil perhitungan pada Waktu = 5 x Ts
program dan pada perhitungan manual. Untuk = 5 x 17
hasil output pada program dapat dilihat pada = 85 detik
gambar dibawah ini. = 1.41 menit
4. T3 (Waktu Dump Truck bergerak ketempat
1. Data Info pembuangan)
Pada bagian ini berisi proses pengisian data, T3 = (Jarak buang /
dimana data yang di perlukan adalah jarak Kec. DT Bermuatan) x 60
parkir, volume pekerjaan, kedalaman galian, T3 = (1km / 20km/jam) x 60
kecepatan dump truck, tipe backhoe dan dump T3 = 3 menit
truck yang dapat diambil melalui database, 5. T4 (Waktu untuk membuang galian)
T4 = 90 detik
6. T5 (Waktu Dump Truck kembali ketempat
penggalian)
T5 = (Jarak buang /
Kec. DT Kosong) x 60
T5 = ( 1km : 30km/jam) x 60
T5 = 2 menit
7. Total Siklus Dump Truck
Total Siklus Dump Truck = T1 + T2 + T3 +
T4 + T5 = 7.93 menit
8. Waktu efektif untuk Backhoe
Waktu Efektif = Waktu siklus Backhoe =
T2
Gambar Data Info Program Waktu Efektif = 1.41 Menit
9. Waktu tunggu Dump Truck (Idle time)
Waktu tunggu = Waktu Efektif Backhoe –
2. Perhitungan Pada Program Total siklus Dump Truck
Waktu tunggu = 1.41 – 7.93 = -6.52 menit
Kontrol Perhitungan Pada Program Apabila hasilnya negatif ( - ) maka tidak ada
Idle time pada Dump Truck dan terjadi Idle
Perhitungan berfungsi memberikan kontrol, time pada Backhoe.
dengan adanya perhitungan manual program ini 10. Waktu efektif untuk Dump Truck
dapat memperoleh data yang valid tanpa Waktu efektif untuk Dump Truck = Total
memanupulasi data. Siklus Dump Truck
Waktu efektif untuk Dump Truck = 7.93
1. Produktivitas Backhoe menit
Q = ( V x Fa x Fb x 60 x Operator Efisiensi)/ 11. Ultility Facktor Backhoe
(Ts x Fv) Total time = (Efektive time + Idle time) =
Q = (0.93 x 0.75 x 1.2 x 60 x 0.8333) / 1.41+(-6.52). Karena hasil tersebut negative
((17/60) x 0.7) (-), maka untuk total time diambil waktu
Q = 220.254 M3/Jam siklus Dump Truck, karena Dump Truck
2. T1 (Waktu dari tempat parkir ke tempat yang bekerja lebih efektif dari Backhoe.
penggalian) Ultility Facktor Backhoe = (Efektif time /
Jarak parkir = 10 m = 0,01 km Total time) x 100% =
T1 = Kecepatan Kosong / jarak parkir (1.41 / 7.93) x100% = 17.84 %
T1 = 30km/jam / 0,01km 12. Ultility Facktor Dump Truck
T1 = 0.02 Menit Total time = (Efektive time + Idle time) =
3. T2 (Waktu Backhoe untuk mengisi Dump 7.93 + 0 = 7.93 menit
Truck)

_________________________________________________________________________
20
Rahmat Bangun Giarto, et al., Pembuatan Program Aplikasi Simulasi Kinerja Backhoe-Dump Truck…
_________________________________________________________________________________________________

Ultility Facktor Dump Truck = (Efektif time Solar Dump Truck per jam = 8 liter
/ Total time) x 100% = Waktu kerja = 7 jam
(7.93 / 7.93) x100% = 100 % Siklus 1 jam = 60 menit / Siklus
13. Kapasitas Dump Truck per jam = 60 / 7.93
((Kapasitas Dump Truck x jumlah Dump = 7,556 siklus/jam
Truck) x efisiensi Dump Truck x 60) / Asumsi solar 7 liter/ km
(Waktu siklus Dump Truck) = ((4 x 1) x 0.75 1 siklus = jarak pembuangan (km) x 2
x 60) / 7.93) = 22.6986 m3 = 1 Km x 2
14. Kapasitas Dump Truck per hari = 2 Km
Kapasitas Dump Truck per jam x waktu Jarak tempuh = 2 x 7 ,556 siklus
kerja = 22.6986 x 7 = 158.89 m3 = 15,112 Km/jam
15. Waktu Kerja Jarak tempuh = 15,112 x 7 (waktu kerja)
Volume pekerjaan / Kapasitas Dump Truck = 105,784 Km/hari
per jam = 7654 / 158.89 = 48.17 hari Solar per hari = 105.784 / 8 = 13,223 liter
16. Harga Backhoe
Unit Cost Backhoe = Harga solar per hari
= 13,223 liter x Rp.12.000
= Rp.181.344,-
+ Cost Solar
= Harga Solar per hari
x Waktu Kerja (hari) x Jumlah DT
= Rp. 181.344 x 48,17 x 1
= + = Rp. 8.735.340.-
Cost Operator
= 0.0125868 + 0.0013065064
= Volume x HargaOperator
= 0.013893
x Jumlah Dump Truck
= Rp. 13.893.-
= 7654 x Rp. 2000 x 1
Cost Solar = Rp.12.000-
= Rp. 15.380.000.-
Solar Backhoe/jam = 22 liter
Total Cost Dump Truck
Waktu kerja = 7 jam
= (Unit Cost Dump Truck x Volume)
Solar yang di butuhkan Backhoe per hari
+ Cost Solar + Cost Operator
= 7 x 22 = 154 liter
= (Rp. 3146 x 7654) + Rp. 15.380.000
Cost Solar
+ Rp. 8.735.340.-
= (Harga Solar x Waktu Kerja (hari))
= Rp. 24.079.484 + Rp. 15.380.00
x Solar per hari
+ 8.735.340.-
= ( Rp.12.000,- x 48,17) x 154
= Rp. 48.194.824,-
= Rp. 89.018.160,-
Cost Operator = Volume x Harga Op.
18. Total Cost Backhoe Dump Truck
= 7654 x Rp. 1000,-
= Total Cost Backhoe
= Rp. 7.654.000.-
+ Total Cost Dump Truck
Total Cost Backhoe
= Rp.203.019.182,- + Rp. 48.194.824,-
= (Unit Cost Backhoe x Volume)
= Rp. 251.214.010,-
+ Cost Solar + Cost Operator
= (Rp. 13.893 x 7654) + Rp.89.018.160
+ Rp.7.654.000
= Rp.203.019.182,-
17. Harga Dump Truck
Unit Cost Dump Truck =

= +
= 0.003146
= Rp. 3146,-
Cost Solar = Rp.12.000-

_________________________________________________________________________
21
J URNAL
REKAYASA RANCANG BANGUN, Volume 14 Nomor 1, Juni 2013: 16 - 23
_________________________________________________________________________
Tabel Perbandingan Perhitungan Manual Dengan 5. Output Tabel
Program Ini adalah output pada table, dimana hasil
No Nama Manual Program pada semua perhitungan dapat dilihat disini.
1 Working Day (hari) 48.17 48
3
2 Produvtivity (m /jam) 211 210.164

3 Effektive Time Backhoe (%) 1.41 1.41

4 Idle Time (menit) -6.52 -6.52

5 Total Time Backhoe (menit) 7.93 7.93667

6 Utility Factor Backhoe (%) 17.84 17.84695

7 Unit Cost Backhoe (Rp/m3) 0.01389 0.01390

8 Total Cost Backhoe (Rp) 203.019182 199.1241

9 Effektive Time Dump Truck (%) 7.93 7.93667

10 Total Time Dump Truck (menit) 7.93 7.93667

11 Utility Factor Dump Truck (%) 100 100

12 Unit Cost Dump Truck (Rp/m3) 0.003 0.00308

13 Total Cost Dump Truck (Rp) 48.194824 47.950404

14 Total Cost Backhoe and Dump Truck (Rp) 251.214010 247.078200

Sumber : Hasil Analisa

3. Output Gambar
Ini adalah output pada gambar, dimana waktu
siklus dump truck dari T1 – T5 dan total
siklus dapat dilihat disini.

Output Tabel Program

KESIMPULAN DAN SARAN

Kesimpulan
Kesimpulan yang didapat dari hasil
Output Gambar Program penulisan Tugas Akhir dengan judul “Pembuatan
Program Aplikasi Simulasi Kinerja Backhoe –
4. Output Grafik Dump Truck Pada Pemindahan Tanah Mekanis
Ini adalah output grafik, dimana hasil pada adalah sebagai berikut :
perhitungan dapat dilihat perbandingan pada 1. Aplikasi tersebut dirancang dan dibuat
grafik. dengan menggunakan metodologi warterfall
dengan beberapa tahapan yaitu perancagan
analisis kebutuhan, desain sistem, penulisan
kode program, dan pengujian
program.Aplikasi dibuat dengan
menggunakan Visual Bsic 6.0 dan database
Microscoft Access 2007.
2. Berdasarkan hasil perhitungan menggunakan
Aplikasi Simulasi Pemindahan Tanah
Mekanis pada Lanjutan Pembangunan
Jaringan Irigasi D.I. Hurung Bunut600 Ha
(Rounding Up) kabupaten Gunung Mas
didapatkan nilai ultility factor yang tinggi,
Output Grafik Program dengan jumlah 1 Backhoe dan 6 Dump truck,

_________________________________________________________________________
22
Rahmat Bangun Giarto, et al., Pembuatan Program Aplikasi Simulasi Kinerja Backhoe-Dump Truck…
_________________________________________________________________________________________________

itu artinya idle time lebih sedikit, sehingga Departemen Pekerjaan Umun Direktora Jendral
Backhoe dan Dump Truck sedikit Bina Marga, 2009, Peralatan : Jakarta :
menganggur (bekerja lebih efektif). Departemen PU.
Dari segi harga terdapat perbedaan, pada
program ini didapat hasil perhitungan biaya Milana, P.T., Santoso. 2005. Pembuatan Dan
sebesar Rp. 171.7248,- Dan pada proyek Aplikasi Program Simulasi Kinerja
mempunyai nilai sebesar Backhoe – Dump Truck Pada Pemindahan
Rp.1.106.553.838,54. Tanah Mekanis. Tugas Akhir Universitas
Kristen Petra.
Saran
Berdasarkan penjelasan tentang Pembuatan Nguk, 2007, Waterfall Proces Model
Program Aplikasi Simulasi Kinerja Backhoe - http://tonyjustinus.wordpress.com. Diakses
Dump Truck Pada Pemindahan Tanah Mekanis, tanggal 1 Juli 2013.
dibawah ini ada beberapa saran yang diharapkan
dapat mendukung pengembangan system lebih Novia Miranda Kristiana, 2013, Perancangan
lanjut. dan Pembuatan Sistem Informasi Rencana
1. Pada saat ini program menggunakan Visual Anggaran Biaya (RAB) Proyek
Basic 6.0 sebagai pembuat aplikasi, dimana Pembangunan Gedung Laboratorium
terdapat kelemahan didalamnya, yaitu untuk Terpadu Tiga Lantai Tahap II STAIN
menampilkan dan membuat tampilan form Palangka Raya. Tugas Akhir Universitas
sangat terbatas, karena tidak bisa membuat Palangka Raya.
tampilan form, rumus dan menampilkan hasil
dalam jumlah banyak. Purwantoro Almuntofa, 2012 .Bahan Kuliah
2. Pada saat ini program menggunakan Pemindahan Tanah Mekanis.
Microsoft Access sebagai database PalangkaRaya : UniversitasPalangka Raya.
penyimpanan datanya, dimana terdapat
kelemahan didalamnya, yaitu kapasitas Rochmanhadi, 1992. Alat Alat Berat dan
penyimpanan data yang relative tidak banyak, Penggunaannya. Jakarta: Departemen PU.
dengan mengikuti perkembangan pekerjaan
yang lebih besar dan aspek kebutuhan, maka Rochmanhadi, 1992. Kapasitas dan Produksi
untuk kedepan dapat digunakan database Alat Berat. Jakarta: Departemen PU.
yang mempunyai kualitas dan fitur yang lebih
baik. Rochmanhadi, 1982. Pengantar dan dasar dasar
3. Untuk pengembangan program selanjutnya, pemindahan tanah mekanis. Jakarta:
digunakan aplikasi selain Visual Basic 6.0 Departemen PU.
yang dapat menampilkan dan membuat data-
data yang lebih banyak, Thabrabi Suryanto, 2007. Mudah dan Cepat
4. Memperketat sistem keamanan data demi Menguasai Visual Basic, Mediakita, Jakarta
kesempurnaan program. Selatan.
5. Aplikasi ini masih melakuakan perhitungan
volume secara manual. Yoso Haryanto Wigroho., Suryadharama Hendra,
Dalam aplikasi ini banyak faktor hambatan, seperti 1992. Pemindahan Tanah Mekanis.
: faktor kelangkaan BBM, perubahan cuaca, faktor Yogyakarta : Universitas Atma Jaya
ketinggian, faktor perubahan suhu, faktor lalu Yogyakarta.
lintas, faktor sosial (hubungan dengan warga .
disekitar lokasi proyek), kerusakan dan perawatan
pada alat berat. Bagi penulis selanjutnya
diharapkan melakukan analisa untuk mengatasi
faktor hambatan tersebut

DAFTAR PUSTAKA