By SALMAN
Mgr BIM Divisi Infrastruktur PT.PP
Latar Belakang Implementasi BIM
Customer
Satisfaction
Approach Span Side Span Main Span Side Span Approach Span
4 SPAN 3 SPAN
@ I-GIRDER 30.0 METER @ I-GIRDER 40.0 METER
Clearance 19 m
ABT-1 P1 P2 P3 P4 P5 PYL-1 PYL-2 P6 P7 P8 P9 ABT-2
APPROACH (ABT.1 – P5) APPROACH (P6 – ABT.2)
SIDE SPAN 94 METER MAIN SPAN 200 METER SIDE SPAN 94 METER
188.27 METER 169.64 METER
▪ LINGKUP PEKERJAAN
A. Main Bridge B. Approach Span C. Oprit
1. Bor Pile + Casing Baja 2m 1. Bor Pile + Casing Baja 1,5m 1. Dinding Segmental
2. Pylon 2. Pier & Abutmen 2. Galian & Timbunan
3. Deck Jembatan 3. Slab (Precast Girder + Diafragma Post Tension) 3. Perkerasan Berbutir
4. Install Stayed Cable 4. Aksesoris Pendekat 4. Perkerasan Aspal
5. Aksesoris Jembatan 5. Drainase
BAHTERAMAS BRIDGE
Detailing..
Detailing Main Span
BAHTERAMAS BRIDGE
Detailing..
Others…..”
Other benefits….