Tugas Critical Path Method

Critical Path Method Pembangunan Pabrik Garam Analis

Aktivitas untuk pembangunan pabrik garam analis secara detail dapat dilihat pada Tabel 1.

Table 1. Detail Activity of Analytic Salt Production Plant Construction

Time
Activity Name Code Activity Details Predecessor
(Days)
Process Flow
A - 40
Diagram
Engineering
Piping and
Design
B Instrumentation A 40
Diagram
Project
C - 30
Design Preparation
Construction Plant
D A, B 200
Construction

Equipment
E D 10
Installation

Piping
F E 10
Installation
Safety
G Component F 3
Equipment Installation
Testing and
Office
Finalization H D 10
Installation

I Process Testing G 5

Non-process
J H 3
Testing
Safety
K I, J 3
Procedure
Commisioning
Commisioning L K 30
and Start-Up
Kombinasi aktivitas yang mungkin terjadi adalah:

1. A-B-D-E-F-G-I-K-L : 343 Days (CRITICAL PATH)


2. A-B-D-H-J-K-L : 326 Days
3. C-D-E-F-G-I-K-L : 291 Days
4. C-D-H-J-K-L : 276 Days

Maka, kita dapat membuat alur scheduling network pembangunan pabrik garam analis dengan metode critical pathway sebagai berikut:

Table 2. Critical Path Methods of Analytic Salt Production Plant Construction

Dapat dilihat bahwa hanya terdapat dua aktivitas yang dapat dijalankan secara bersamaan, yaitu engineering design, khususnya pada process flow
diagram design, dan project preparation pada design construction. Adapun waktu tersingkat untuk membangun pabrik produksi garam analis adalah
276 hari.