RANCANGAN EVAPORATOR
137
138
Direncanakan :
Sudut puncak tutup = 120o
bawa
Allowable sress (f) = 18750 (App.D brownell &
Young hal 342)
Type pengelasan = Double Welded Butt join
Faktor pengelasan (E ) = 0.8
= 0.5 × 1,5 OD ×
= 0.5 × 0.1875 × 0.1624
2
= 0.0152 ft = 0.1827 in2
Sehingga luas total Vrk
A Vrk = 2082 × 0.1827 = 380.3340 in2 = 31.6945 ft2
139
2(fE-0,6Pi)
59.6865 × 7.1055 1
ts = +
2(18750×0,8-0,6×58,7331) 16
16 1.2267 4
= 0.0767 × = in ≈ in
16 16 16
Standarisasi do :
do = di + 2ts
= 85.2663 + 2(4/16) = 85.3913 in