Efisiensi dari pondasi grup

d 0.6 m
S 1.5 m
m 4
n 2
tan (d/s) 0.422793
arc tan 0.380506
Ce 0.697202646022892

c. Daya dukung pondasi tiang dengan d=60cm berdasarkan N-SPT dgn kedalaman 16m

Cara 1 Cara 2
diameter 0.6 m
d 16 m
penampang 0.282743 m2
keliling 1.884956 m
selimut 30.15929 m2
Nbottom 34
NSPT 17.90909
Qu 492.556 ton

d. Safety Factor

Sf 2.09628
Sf 3
Data
M 4
N 2
m 8
V 348 ton
My 184 ton.m
Mx 344 ton.m

a. Beban yang diterima masing2 tiang

Sb x (m) Perhitungan nilai P


x1 0.75 0.5625 1 -10.366667
x2 0.75 0.5625 2 234.96667
sigma Xn2 1.125 3 -56.233333
Sb y (m) 4 189.1
y1 2.25 5.0625 5 -102.1
y2 0.75 0.5625 6 143.23333
y3 0.75 0.5625 7 -147.96667
y4 2.25 5.0625 8 97.366667
sigma Yn2 11.25
Pmax 234.96667
Ketentuan
Tekan Positif (+)
Tarik Negatif (-)
KODE Sb. X Sb. Y
Upper 1
1- +
2+ +
Upper 2
3- +
4+ +
Bottom1
5- -
6+ -
Bottom 2
7- -
8+ -
Data
el 0.3 m
eb 0.15 m
L 1.5 m
B 1.5 m
Y Beton 2.4 ton/m3
Φ 30 derajat
C 0
Y sand 18 kN/m3
Df 0.7 m
SF 3
t 0.25 m2 Menentukan Kasus
P 25 ton el/L 0.2
F horizontal 1 ton eb/B 0.1
Momen 1 ton m Kasus 2

a. Menentukan daya dukung ultimate pondasi


L1/L 0.85
L1 1.275 m
L2/L 0.21
L2 0.315 m

A' 1.1925 m2
L' 1.275 m
B' 0.935294118 m2

Bearing capacity

c 0 Shape Factors Square Footing


Nc 30.14 Fcs 1.610484
q 12.6 ton/m2 Fqs 1.58
Nq 18.4 Fys 0.6
Y 18 kN/m3 Depth Factors
NY 22.4 Fcd 1.135333
Tan Φ 0.58 Fqd 1.148014
Sin Φ 0.5 Fyd 1
Df/B 0.467 <1 Inclination Factors
Fci 1
Fqi 1
Fyi 1

Ultimate Bearing Capacity


qU 601.9659744 kN/m3

Total Ultimate Load


Qult 717.8444245 kN
B. Menghitung Kemampuan Pondasi
Q Kerja 245 kN M Horizontal 6.86 kN.m
1.4175 ton 1 ton.m
Q Pondasi M Momen
13.8915 kN 9.8 kN.m
Q Tanah 17.71875 kN M total 16.66 kN.m
1 ton
Q Horizontal
9.8 kN
Q Total 276.61025 kN

q max 152.5556667

q allow 239.2814748

Maka,
q allow > q max
239.28147482 > 152.5557 (OK)
pondasi mampu menerima beban
2:00 Diketahui
l = 0.3 m Beban
b = 0.4 m Kerja
ϒ sat = 1.55 ton/m³
ϒ moist = 1.35 ton/m³
Φ' = 5 Nc'
c' = 0.6 ton/m² Nq'
Φ = 7.47 Ny'
cu = 0.9 ton/m²
B = 1.6 m
L = 1.6 m
ϒ beton = 2.4 ton/m³ Nc
Df = 1.1 m Nq
t = 0.3 m Ny
SF = 3
q = 1.545 ton/m²
q' = 1.245 ton/m²
tinggi = 0.8 m

Jawab
a. Short Term
q ult s 1,3.cu.Nc + q.Nq + 0,4.ϒ.B.Ny
= 13.3305857
q all = 4.443528567
Q all = 11.37543313

Long Term
q ult = 1,3.c'.Nc' + q'.Nq' + 0,4.ϒ'.B.Ny'
= 7.81628
q all = 2.605426667 ton/m2
Q all = 6.669892267 ton

b. Beban Kerja
Q Pondasi = 2.0736 ton
Q Kerja = 29.76 ton
Q Tanah = 2.6352 ton
Q Total 34.4688 ton

q max = 13.464375 ton/m2


q max > q all (short & long)
Maka, pondasi tidak mampu menerima beban (NOT OK)

Beban max = q all . A


= 6.669892267 ton
Beban max net (Wor
= 1.961092267 ton
= 29.76 ton

= 7.34
= 1.64
= 0.14

= 8.3615
= 2.0987
= 0.3076