Contoh Hps Jembatan
Contoh Hps Jembatan
TOTAL BIAYA
NO URAIAN
(Rp)
JUMLAH 155,820,875.00
PPN 10 % 15,582,087.50
TOTAL 171,402,962.50
DIBULATKAN 171,400,000.00
TERBILANG :
Manado, 2012
PT.
PEKERJAAN : PERENCANAAN RUAS JALAN TAMAKO - ENEMAWIRA
I PROFESIONAL STAF
a. Team Leader / Ahli Jembatan OB 1 x 2.00 13,425,000.00 26,850,000.00
e. Ahli Survey dan Pengukuran OB 1 x 0.50 11,948,250.00 5,974,125.00
f. Ahli Estimasi Kuantitas Biaya OB 1 x 1.00 11,948,250.00 11,948,250.00
Sub Jumlah 44,772,375.00
1 OPERASIONAL KANTOR
ANALISA DATA, DRAWING, COST & QUANTITY
1. Komputer + Printer (Sewa) Set/Bln 1 x 2.00 1,611,000.00 3,222,000.00
2. ATK dan Bahan Habis Pakai Bln 2.00 2,148,000.00 4,296,000.00
Sub Jumlah 7,518,000.00
3 BIAYA LAPORAN
Kontrak Perencanaan Set 5 1,250,000.00 6,250,000.00
Laporan Perencanaan Set 5 300,000.00 1,500,000.00
Gambar Rencana Uk. A3 Set 5 250,000.00 1,250,000.00
Dokumen Tender (RKS, EE, BOQ) Set 5 250,000.00 1,250,000.00
Disket / CD Buah 10 50,000.00 500,000.00
Sub Jumlah 10,750,000.00