Lampiran 1 Total Keseluruhan Biaya Membagun Pembibitan Pre Nursery Kelapa Sawit

N HARGA
URAIANPEKERJAAN STN NORMA FISIK JUMLAH BIAYA
o SATUAN
Membangun Pembibitan Pre Nursery Kelapa Sawit Seluas 0,12 Ha (214.159 St =
178 bed)
A. Pengolahan Tanah / Persiapan Lapangan.

1 Membersihkan Areal Bedengan Bed 0,50 Hk/Bed 178 6.818 1.213.604

2 Menggali/Mengumpulkan Tanah (400 Plbg/M3) M3 1,50 M3/Hk 345 20.454 7.056.630

3 Transport Tanah Top Soil (400Plbg/M3) M3 21.000 Rp/M3 345 21.000 7.245.000

4 Bongkar/ Muat Tanah Top Soil M3 2,42 M3/Hk 345 5.634,71 1.943.975

5 Buat Bedengan & Naungan Bed 3 Hk/Bed 178 40.908 7.281.624

6 Mencari Pelepah Bed 2 Hk/Bed 178 27.272 4.854.416

7 Mengisi Pasir Kebedengan Bed 10 Bed/Hk 178 1.363,60 242.721

8 Mengayak Tanah Plbg 400 Plbg/Hk 137.962 34,09 4.703.125

9 Mengisi Tanah Ke polybag Plbg 400 Plbg/Hk 137.962 34,09 4.703.125

10 Mengangkat Polybag Plbg 700 Plbg/Hk 137.962 19,48 2.687.500

11 Menyusun Polybag Plbg 5.000 Plbg/Hk 137.962 2,73 376.636

12 Desin Feksi Bedengan Bed 30 Bed/Hk 178 454,53 80.906

13 Menyiram Bibit Di Bedengan(90 Hrx2 Rot) Plbg 10.000 Plbg/Hk 24.833.160 1,36 33.773.098

14 Menyiang Luar/Dalam Polybag(6 Rot) Plbg 10.000 Plbg/Hk 827.772 1,36 1.125.770

15 Pembrantasan Hama Penyakit (6 Rot) Bed 15 Bed/Hk/Apl 1.068 909,07 970.887

16 Memupuk (9 Rot) Plbg 3.000 Plbg/Hk 1.241.658 4,55 5.649.544

17 Mencampur Pupuk Unsur P Sebelum Tanam Plbg 3.000 Plbg/Hk 137.962 4,55 627.727

41
18 Menanam Kecambah Plbg 1.000 Plbg/Hk 137.962 13,64 1.881.802

19 Konsolidasi Bed 4 Bed/Hk 178 3.409 606.802

20 Mendalamkan Parit Ukuran 20 mtr x 4 mtr x 1 mtr BU 40 Mtr/BU 80 10.541 843.280

21 Membuat Rorak Ukuran 10x10x5Mtr BU 40 Mtr/BU 500 10.541 5.270.500

22 Thining Out &Seleksi umur 4-8 Minggu Plbg 5.000 Plbg/Hk 137.962 2,73 376.636

23 Thining Out &Seleksi Umur 10-12 Minggu Plbg 5.000 Plbg/Hk 137.962 2,73 376.636

24 Penjarangan/Buang Atap Umur 1,5 Bln Bed 10 Bed/Hk 178 1.363,60 242.721

25 Penjarangan/Buang Atap Umur 2 Bln Bed 15 Bed/Hk 178 909,07 161.814

26 Penjarangan/Buang Atap Umur 2,5 Bln Bed 20 Bed/Hk 178 681,80 121.360

27 Meratakan tanah Tanjaan Untuk Pipa Air Mtr 40 Mtr/BU 100 11.168 1.116.800

28 Membuat Pagar Kawat Duri Mtr 4 Mtr/Hk 2.525 3.409 8.607.725

29 Membuat Patok Persilangan Bed 4 Bed/Hk 178 3.409 606.802

30 Menulis Jenis Persilangan Bh 10 Bh/Hk 460 1.363,60 627.256

31 Membuat paret ukuran 1 x 1 x 1 x 400 mtr Mtr 40 Mtr / Bu 400 10.541 4.216.400

32 Mobilisasi alat berat 7.200.284

JUMLAH-A 116.793.106
B BAHAN & ALAT-ALAT

1 Bambu 4'' Untuk Tiang Btg 6 Btg/Bed 1.068 19.000 20.292.000

2 Bambu 3'' Untuk Penyangga Btg 5 Btg/Bed 890 14.000 12.460.000

3 Bambu 3'' Untuk Skat Bedeng Btg 4 Btg/Bed 712 14.000 9.968.000

4 Baby Polybag (+5%) Lbr 1.200 Plbg/Bed 144.860 185 26.799.100

5 Ayakan Tanah Bh 0,05 Plbg/Bed 39 66.000 2.574.000


42
6 Gembor Bh 0,07 Plbg/Bed 54 26.000 1.404.000

7 Selang Ukran 3/4'' Mtr 2,50 Mtr/Bed 445 4.000 1.780.000

8 Paku Campur Kg 0,25 Kg/Bed 45 22.200 999.000

9 Kawat Ukuran 1mm Kg 0,50 Kg/Bed 89 19.000 1.691.000

10 Pasir M3 0,33 M3/Bed 59 124.200 7.327.800

11 Drum isi 200 Ltr Bh 0,03 Bh/Bed 5 275.000 1.375.000

12 Timbangan Kecil Bh 0,01 Bh/Bed 2 65.000 130.000

13 Ember Plastik Ukuran 15 Ltr Bh 0,05 Bh/Bed 9 11.050 99.450

14 Hand Counter Bh 0,01 Bh/Bed 2 45.500 91.000

15 Angkong/Kereta Sorong Bh 0,01 Bh/Bed 2 343.000 686.000

16 Sprayer Solo Bh 0,01 Bh/Bed 2 275.000 550.000

17 Pembelian Pupuk Urea Zak 0,2 Gram/Plbg 230.221 3.000 690.663

18 Pembelian Pupuk NPK 15-15-6-4 Zak 0,2 Gram/Plbg 130.334 7.500 977.580

19 Pupuk Cair (Bambu Hijau) Bh 0,10 Bh/Bed 18 250.000 4.500.000

20 Solar Untuk Mesin Air Ltr 4 Ltr/Hari 360 8.382 3.017.520

21 Lampu Kapal Untuk Jaga Malam Bh 0,5 Bh/Ha 6 35.000 210.000

22 Minyak Tanah Ltr 4 Ltr/Hr 360 8.382 3.017.520

23 Seng Rata Untuk Plakat Persilangan Lbr 5 Bed/Lbr 23 86.250 1.983.750

24 Cat Minyak Warna Biru Kg 5 Bed/Kg 23 50.400 1.159.200

25 Cat Minyak Warna Putih Kg 5 Bed/Kg 23 50.400 1.159.200

26 Kuas 1'' Bh 0,03 Plbg/Bed 3 3.850 11.550


27 Tampah Bh 0,07 Bh/Bed 29.990
43
8 239.920

28 Bambu Penyangga Diatas Timur - Barat Btg 4 Btg/Bed 712 14.000 9.968.000

29 Bambu Penyangga Diatas Utara - Selatan Btg 4 Btg/Bed 712 14.000 9.968.000

30 Sevin Kg 3 Bed/Keep 7 90.000 630.000

31 Dithane-M 45 Kg 3 Bed/Keep 7 90.000 630.000

32 Baypolan Ltr 3 Bed/Keep 7 50.000 350.000

33 Kayu Laut Btg 8 Mtr/Btg 316 30.000 9.480.000

34 Kawat Duri Gulung 50 Mtr/glg 255 50.000 12.750.000

JUMLAH 148.969.253
C Membangun Gudang Ukuran 3x4 Meter

1 Semen @ 40 Kg Zak 35 52.000 1.820.000

2 Pasir M3 3 124.200 372.600

3 Krikil M3 4 140.000 560.000

4 Batu bata Bh 500 455 227.500

5 Broti Ukuran 4x4'' Btg 4 301.796 1.207.184

6 Broti Ukuran 2x3'' Btg 19 113.173 2.150.287

7 Broti Ukuran 2x4'' Btg 8 150.898 1.207.184

8 Broti Ukuran 1/2x3'' Btg 85 75.000 6.375.000

9 Papan Ukuran 3/4x8'' Kpg 6 122.265 733.590

10 Papan Ukuran 1x9'' Kpg 1 75.000 75.000

11 Besi Plat Strip40mmx4mmx6mtr Btg 8 15.000 120.000

12 Mur Baut @ 12 mmx5'' Bh 40 45.000 1.800.000


13 Seng Gelombang 6'' Lbr 31.200
44
2 62.400

14 Paku Seng Ktk 25 14.773 369.325

15 Paku Campur Kg 15 58.781 881.715

16 Engsel Ukuran 8'' Bh 6 21.450 128.700

17 Grendel Panjang Bh 1 35.750 35.750

18 Kuas Merk Eterna 4'' Bh 2 21.250 42.500

19 Cat Vinilex @ 5 Kg Klg 7 96.250 673.750

20 Cat Minyak Kg 3 50.400 151.200

21 Thinner Ltr 5 14.400 72.000

22 Upah 5.000.000

23 Transport 4.000.000

J U M L A H -C 28.065.685
D Pengadaan &Pemasangan Mesin Pompa Air

1 Mesin Pompa Air Merk Yanmar Type TS.230 Unit 1 23.500.000 23.500.000

2 Pipa Besi Ukuran 3'' tebal 3mm (Pakai Drat) Btg 4 812.500 3.250.000

3 Elbow Besi 3'' Bh 4 137.500 550.000

4 Klep Isap Komplit 3'' Bh 1 910.000 910.000

5 Upah Pemasangan & Transport 12.500.000

JUMLAH-D 40.710.000

JUMLAH (A+B+C+D) 334.538.044

Ppn 10 % 33.453.804

TOTAL 367.991.848

45
Lampiran 2. Total Keseluruhan Biaya Membagun Pembibitan Main Nursery Kelapa Sawit

HARGA JUMLAH
No URAIANPEKERJAAN STN NORMA FISIK
SATUAN BIAYA
PEMBIBITAN KELAPA SAWIT (MN) =194.011 ST LUAS
14,00 HA
A PERSIAPAN LAHAN

1 Membersihkan /Meratakan Areal Ha 25 Hk/Ha 14 340.900 4.772.600

2 Transport Tanah Top Soil Trip 4 M3/Trip 1.386 54.544 75.597.984

3 Mengumpul/Mengayak Tanah ( 194.011 : 35 Pb/M3) Pb 2 M3/Hk 2.467 6.818 16.820.006

4 Mengisi Tanah Ke Large Polybag Pb 60 Pb/Hk 194.011 227,27 44.092.880

5 Memberikan Mulching Pb 300 Pb/Hk 194.011 45,45 8.817.800

6 Memancang Letak Polybag Ha 17 Hk/Ha 14 231.812 3.245.368

7 Menyusun Large Polybag Pb 100 Pb/Hk 194.011 136,36 26.455.340

8 Menambah Tanah ke Polybag Pb 2.500 Pb/Hk 970.055 5,45 5.286.800

9 Menyiram Polybag Sebelum Tanam (5 Hari ) Pb 2.500 Pb/Hk 970.055 5,45 5.286.800

10 Mengangkat Bibit Dari PN Ke MN Pb 300 Pb/Hk 194.011 45,45 8.817.800


11 Menanam Bibit Pb Pb/Hk
46
200 194.011 68,18 13.227.670

Hk/Ha/Ro
12 Menyiang Dalam & Luar Polybag (18 Rot ) Ha 20 t 252 272.720 68.725.440

13 Menyiram Bibit Pagi / Sore (270 Hr) Pb 2.000 Pb/Hk 104.765.940 6,82 714.503.711

Pb/Hk/Ro
14 Inventaris Bibit (2 Rot) Pb 3.000 t 388.022 4,55 1.765.500

Pb/Hk/Ro
15 Memupuk Pb 2.500 t 2.716.154 5,45 14.803.039

16 Konsolidasi / Menambah Tanah Pb 2.500 Pb/Hk 194.011 5,45 1.057.360

17 Seleksi Umur 1-4 Bulan Pb 2.000 Pb/Hk 194.011 6,82 1.323.155

18 Seleksi Umur 4-6 Bulan Pb 2.000 Pb/Hk 194.011 6,82 1.323.155

19 Seleksi Umur 6-8 Bulan Pb 2.000 Pb/Hk 194.011 6,82 1.323.155

20 Seleksi Umur 8-12 Bulan Pb 2.000 Pb/Hk 194.011 6,82 1.323.155

21 Seleksi Pindah Ke Lapangan Pb 2.000 Pb/Hk 194.011 6,82 1.323.155

22 Memutar Bibit Pb 2.500 Pb/Hk 194.011 5,45 1.057.360

23 Menabur Bio Fungisida Pb 2.500 Pb/Hk 194.011 5,45 1.057.360

Hk/Ha/Ro
24 Pemberantasan Hama (24 Rot) Ha 2 t 252 27.272 6.872.544

25 Melangsir / Ecer Pupuk di lapangan Kg 500 Kg/Hk 24.509 27,27 668.360

26 Transport Mulching Trip 3 M3/Trip 1.848 40.908 75.597.984


27 Bongkar Muat Mulching M3 M3/Hk
47
2 2.467 6.818 16.820.006
JUMLAH - A
1.121.965.487
B BAHAN & ALAT-ALAT

01 Large Polybag (194.011 Pb + 105%) Uk.50x40Cmx0,13C Bh Bh/Ha 203.712 1.975 402.331.200

02 Ayakan Tanah Bh 1 Bh/Ha 14 66.000 924.000

03 Sprayer Solo Bh 0,25 Bh/Ha 4 275.000 1.100.000

04 Ember Plastik 15 Liter Bh 1 Bh/Ha 14 11.000 154.000

05 Selang Plastik 3/4'' Mtr 215 Mtr/Ha 3.010 4.000 12.040.000

06 Kepala Gembor Bh 5 Bh/Ha 70 11.000 770.000

07 Pipa PVC Ukuran 3'' Bh 24 Btg/Ha 336 234.221 78.698.256

08 Kran Air 1/2'' Btg 5 Bh/Ha 70 25.000 1.750.000

09 Bor Tanah Bh 0,50 Bh/Ha 7 19.500 136.500

10 Socket Drat 3'' Bh 5 Bh/Ha 70 4.650 325.500

11 Socket Drat 2'' Bh 5 Bh/Ha 70 2.520 176.400

12 T.Socket 3 x 1/2'' Bh 5 Bh/Ha 70 19.600 1.372.000

13 T.Socket 2 x 1/2'' Bh 5 Bh/Ha 70 15.800 1.106.000

14 Lem PVC Kg 1 Kg/Ha 14 31.200 436.800

15 Stop Drop 3'' Bh 1,25 Bh/Ha 18 7.500 135.000

16 Hand Counter Bh 0,12 Bh/Ha 2 45.500 91.000


48
17 Kereta Sorong Bh 0,50 Bh/Ha 7 343.000 2.401.000

18 Pipa Besi Ukuran 4'' Btg Btg/Ha 8 3.780.000 30.240.000

19 Pipa PVC Ukuran 4'' Btg Btg/Ha 101 74.232 7.497.432

20 Nepel Drat Bh Bh/Ha 122 20.592 2.512.224

21 Kran Ukuran 3/4'' Bh Bh/Ha 61 18.295 1.115.995

22 T.Sock Kran 3/4'' Bh Bh/Ha 61 15.048 917.928

23 Elbow Ukuran 4'' Bh Bh/Ha 3 10.944 32.832

24 Kran Penutup/Buka Ukuran 3'' Bh Bh/Ha 4 403.200 1.612.800

25 Socket Ukuran 3'' Bh Bh/Ha 165 75.816 12.509.640

26 Pipa Besi Ukuran 1/2'' Btg Btg/Ha 6 75.360 452.160

27 Gergaji Besi Bh Bh/Ha 4 24.960 99.840

28 Tutup Pipa 3'' Bh Bh/Ha 12 17.280 207.360

29 T.Socket 4/3'' Bh Bh/Ha 8 58.344 466.752

30 T.Socket 3/3'' Bh Bh/Ha 4 54.959 219.836

31 Solar Ltr 4 Ltr/Jam 8.640 8.382 72.420.480

32 Sevin (2 Rot x 9 Bulan) Kg 1 Kg/Ha 18 90.000 1.620.000

33 Dithane -M45 (2 rot x 9 Bulan) Kg 1 Kg/Ha 18 90.000 1.620.000

34 Baypolan (2 rot x 9 Bulan) Ltr 1 Ltr/Ha 18 50.000 900.000

49
Gram/Plb
35 Pembelian Pupuk NPK 15-15-6-4 Zak g 20.075 7.500 150.562.500

Gram/Plb
36 Pembelian Pupuk NPK 12-12-17-2 Zak g 15.176 7.300 110.784.800

Gram/Plb
37 Pembelian Pupuk Dolomit Zak g 19.195 700 13.436.500

Gram/Plb
38 Pembelian Pupuk Urea Zak g 8.289 3.000 24.867.000
JUMLAH - B
938.043.297
C. PENGADAAN & PEMASANGAN MESIN POMPA AIR

1 Mesin Pompa Air Yanmar TS 230 Unit 1 23.500.000 23.500.000

2 Pipa Besi Hisap Air Ukuran 4'' tebal 3 mm (pakai Drat) Btg 8 812.500 6.500.000

3 Elbow Besi 4'' Bh 8 98.841 790.728

4 Klep Isap Komplit 4'' Bh 1 910.000 910.000

5 Upah Pemasangan & Transport 12.500.000 12.500.000


JUMLAH - C
44.200.728

JUMLAH ( A+B+C ) 2.104.209.512

Ppn 10 % 210.420.951

TOTAL 2.314.630.463

50
51
Lampiran 3. Biaya Pembelian Pupuk untuk Pre Nursery
Asal Uraian Minggu Ke
Bibit 4 5 6 7 8 9 10 11 12 Total
PPKS Jumlah Bibit 72.167 72.167 72.167 72.167 72.167 67.932 67.932 67.932 67.932 67.932
Dosis (grm/bibit) C1-0,2 C1-0,2 C1-0,2 C1-0,2 C1-0,2 C1-0,2 C1-0,2 C1-0,2 C1-0,2
Jumlah Pupuk (kg) 14,433 14,433 14,433 14,433 14,433 13,586 13,586 13,586 13,586 126,509
Biaya Pupuk (Rp) 43.299 43.299 43.299 43.299 43.299 46.785 46.785 46.785 46.785 379.527
Socfindo Jumlah Bibit 133.163 133.163 133.163 133.163 133.163 126.121 126.121 126.121 126.121 126.121
Dosis (gram/bibit) C2-0,2 C1-0,2 C2-0,2 C1-0,2 C2-0,2 C1-0,2 C2-0,2 C1-0,2 C2-0,2
Jumlah Pupuk (kg) 26,632 26,632 26,632 26,632 26,632 25,224 25,224 25,224 25,244 234,05
Biaya Pupuk (Rp) 199.740 79.896 199.740 79.896 199.740 75.672 189.180 75.672 189.180 1.288.716
Total Pembelian Pupuk (Rp) 1.668.243

Keterangan C1= Urea

C2= NPK 15-15-6-4