TAHUN : 2017
A INSTALASI PENGKABELAN
A.1 PEKERJAAN PERSIAPAN
1 Pembersihan lapangan / Bongkaran 1.00 Ls 2,500,000.00 2,500,000.00
Jumlah A.I 2,500,000.00
A.II INSTALASI STOP KONTAK
1 Instalasi Stop Kontak Dinding (bawah) 55.00 titik 234,638.90 12,905,139.50
2 Instalasi Stop Kontak Dinding (atas) 14.00 titik 234,638.90 3,284,944.60
3 Instalasi Stop Kontak AC 17.00 titik 234,638.90 3,988,861.30
Jumlah A.II 20,178,945.40
A.III INSTALASI PENERANGAN
1 Instalasi Lampu LED 15 watt + Fitting Plafond 82.00 titik 229,935.00 18,854,670.00
2 Instalasi Lampu SL 18 watt + Armateur Lampu Taman 1.00 titik 556,610.00 556,610.00
Jumlah A.III 19,411,280.00
A.IV INSTALASI PENERANGAN
1 Instalasi Saklar Tunggal 11.00 titik 201,922.90 2,221,151.90
2 Instalasi Saklar Ganda 16.00 titik 246,038.90 3,936,622.40
Jumlah A.III 6,157,774.30
NO URAIAN PEKERJAAN RP
A INSTALASI PENGKABELAN
A.1 PEKERJAAN PERSIAPAN Rp 2,500,000.00
A.II INSTALASI STOP KONTAK Rp 20,178,945.40
A.III INSTALASI PENERANGAN Rp 19,411,280.00
A.IV INSTALASI PENERANGAN Rp 6,157,774.30
48,247,999.70
Terbilang : Seratus Empat Puluh Delapan Juta Sembilan Ratus Empat Puluh Empat Ribu Rupiah
Malang, 2017
Dibuat Oleh,
garasi R. Rapat R. Klarifikasi KM/ Wudlu R. Staff 1 musholla Irban 1 Irban 2
stop kontak dinding (bawah) 9.00 5.00 15.00 1.00 1.00 1.00
stop kontak dinding (atas) 1.00 1.00 1.00 2.00 1.00
stop kontak AC 1 pk 3.00 1.00 1.00 1.00 1.00
stop kontak AC 2 pk 1.00 2.00
Fitting + LED 15 watt 1.00 8.00 5.00 3.00 16.00 2.00 1.00 1.00
Fitting/Downlight + LED 9 watt
RMI 2x11 watt
saklar tunggal 1.00 1.00 1.00 1.00 1.00
saklar ganda 2.00 1.00 1.00 2.00 1.00
R.
R.
Irban 3 Irban 4 R. Staff 2 R. Kasubag lorong Inspektu dapur + KM teras
Sekretaris
r + KM
stop kontak dinding (bawah) 1.00 1.00 12.00 4.00 2.00 3.00
stop kontak dinding (atas) 2.00 1.00 1.00 1.00 1.00
stop kontak AC 1 pk 1.00 1.00
stop kontak AC 2 pk 2.00 1.00 1.00 1.00
Fitting + LED 15 watt 1.00 1.00 10.00 4.00 2.00 3.00 2.00 4.00
Fitting/Downlight + LED 9 watt 5.00 13.00
RMI 2x11 watt 2.00
saklar tunggal 1.00 1.00 1.00 1.00 1.00 1.00
saklar ganda 1.00 1.00 1.00 2.00 1.00 3.00
jumlah estimasi
beban per item faktor ф beban daya
titik beban puncak
stop kontak dinding (bawah) 55.00 6,600.00 100 watt x 20% = 120.00
stop kontak dinding (atas) 12.00 1,440.00 100 watt x 20% = 120.00
stop kontak AC 1 pk 9.00 9,450.00 750 watt x 40% = 1,050.00
stop kontak AC 2 pk 8.00 17,920.00 1,600 watt x 40% = 2,240.00
Fitting + LED 15 watt 64.00 1,056.00 15 watt x 10% = 16.50
Fitting/Downlight + LED 9 watt 18.00 178.20 9 watt x 10% = 9.90
RMI 2x11 watt 2.00 48.40 22 watt x 10% = 24.20
saklar tunggal 11.00
saklar ganda 16.00
36,692.60
29,354.08
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 10 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
A. TENAGA
Page 11 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
B BAHAN
C PERALATAN
A. TENAGA
B BAHAN
C PERALATAN
Page 12 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
Page 13 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 14 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 15 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 16 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 17 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 18 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
Page 19 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN
A. TENAGA
B BAHAN
C PERALATAN
A. TENAGA
Page 20 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
1 Pekerja L27 Org/hr 0.1000 65,000.00 6,500.00
2 Tukang Listrik L13 Org/hr 0.0200 80,000.00 1,600.00
3 Kepala Tukang Listrik L07 Org/hr 0.0100 106,000.00 1,060.00
4 Mandor L01 Org/hr 0.0100 115,000.00 1,150.00
Page 21 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
B BAHAN
C PERALATAN
A. TENAGA
B BAHAN
C PERALATAN
Page 22 of 18
XX. BAHAN PERALATAN LISTRIK
1 Lampu TL 20 W/220 V Komplit Rp 65,000 Bh
2 Lampu TL 40 W/220 V Komplit Rp 102,000 Bh
3 Lampu Pijar 25,40,75/220 V Rp 18,000 Bh
4 Lampu XL 20 Watt Rp 40,000 Bh
5 Stop Kontak (Broco) Rp 27,500 Bh
6 Saklar (Broco) Tunggal Rp 35,000 Bh
7 Saklar (Broco) Ganda Rp 40,000 Bh
8 Zekering lengkap Rp 71,000 Bh
9 Fitting plafon Rp 11,000 Bh
10 Isolator Rp 850 Bh
11 T Doos PVC Rp 1,000 Bh
12 Paralon 5/8" Rp 7,500 ljr
13 Las doof Rp 650 bh
14 Stater lampu TL Rp 6,000 bh
TAHUN 2017