RENCANA ANGGARAN BIAYA - HARGA PERKIRAAN SENDIRI (HPS)

TAHUN : 2017

NO URAIAN PEKERJAAN VOLUME ST HARGA SATUAN JUMLAH HARGA

A INSTALASI PENGKABELAN
A.1 PEKERJAAN PERSIAPAN
1 Pembersihan lapangan / Bongkaran 1.00 Ls 2,500,000.00 2,500,000.00
Jumlah A.I 2,500,000.00
A.II INSTALASI STOP KONTAK
1 Instalasi Stop Kontak Dinding (bawah) 55.00 titik 234,638.90 12,905,139.50
2 Instalasi Stop Kontak Dinding (atas) 14.00 titik 234,638.90 3,284,944.60
3 Instalasi Stop Kontak AC 17.00 titik 234,638.90 3,988,861.30
Jumlah A.II 20,178,945.40
A.III INSTALASI PENERANGAN
1 Instalasi Lampu LED 15 watt + Fitting Plafond 82.00 titik 229,935.00 18,854,670.00
2 Instalasi Lampu SL 18 watt + Armateur Lampu Taman 1.00 titik 556,610.00 556,610.00
Jumlah A.III 19,411,280.00
A.IV INSTALASI PENERANGAN
1 Instalasi Saklar Tunggal 11.00 titik 201,922.90 2,221,151.90
2 Instalasi Saklar Ganda 16.00 titik 246,038.90 3,936,622.40
Jumlah A.III 6,157,774.30

B TAMBAH DAYA & PANEL


B.I TAMBAH DAYA PLN
1 Tambah Daya PLN dan Kelengkapan Perijinannya 1.00 ls 18,400,000.00 18,400,000.00
Jumlah B.I 18,400,000.00
B.II PANEL dan KELENGKAPANNYA
1 Panel SDP Ruang Pertemuan 1.00 unit 1,413,250.00 1,413,250.00
2 Panel SDP Ruang Staff & Sekretariat 1.00 unit 9,438,500.00 9,438,500.00
3 Surge Arester 1.00 unit 4,700,000.00 4,700,000.00
Jumlah B.II 15,551,750.00

C INSTALASI KABEL FEEDER dan LAIN-LAIN


C.I MAIN LINE PANEL
1 Kabel feeder NYM 4 x 4 mm 122.00 m' 67,810.00 8,272,820.00
2 Kabel feeder NYY 4 x 16 mm 3.00 m' 173,060.00 519,180.00
Jumlah C.I 8,792,000.00
C.II FIRE ALARM SYSTEM
1 Instalasi Kabel FA + Smoke Detector 5.00 titik 2,750,000.00 13,750,000.00
2 Instalasi Kabel FA + ROR/Heat Detector 10.00 titik 2,150,000.00 21,500,000.00
3 Modul Fire Alarm 1.00 unit 8,682,500.00 8,682,500.00
Jumlah C.II 43,932,500.00

D INSTALASI KABEL TRAY


D.I KONSTRUKSI KABEL TRAY
1 Tray Kabel 4.00 m' 120,000.00 480,000.00
Jumlah D.I 480,000.00
R E K A P I T U L A S I - RAB - HARGA PERKIRAAN SENDIRI (HPS)
TAHUN : 2017

NO URAIAN PEKERJAAN RP

A INSTALASI PENGKABELAN
A.1 PEKERJAAN PERSIAPAN Rp 2,500,000.00
A.II INSTALASI STOP KONTAK Rp 20,178,945.40
A.III INSTALASI PENERANGAN Rp 19,411,280.00
A.IV INSTALASI PENERANGAN Rp 6,157,774.30
48,247,999.70

B TAMBAH DAYA & PANEL


B.I TAMBAH DAYA PLN Rp 18,400,000.00
B.II PANEL dan KELENGKAPANNYA Rp 15,551,750.00
33,951,750.00

C INSTALASI KABEL FEEDER dan LAIN-LAIN


C.I MAIN LINE PANEL Rp 8,792,000.00
C.II FIRE ALARM SYSTEM Rp 43,932,500.00
52,724,500.00

D INSTALASI KABEL TRAY


D.I KONSTRUKSI KABEL TRAY Rp 480,000.00
480,000.00

JUMLAH TOTAL Rp 135,404,249.70


PPN 10 % Rp 13,540,424.97

JUMLAH AKHIR Rp 148,944,674.67


DIBULATKAN Rp 148,944,000.00

Terbilang : Seratus Empat Puluh Delapan Juta Sembilan Ratus Empat Puluh Empat Ribu Rupiah

Malang, 2017
Dibuat Oleh,
garasi R. Rapat R. Klarifikasi KM/ Wudlu R. Staff 1 musholla Irban 1 Irban 2
stop kontak dinding (bawah) 9.00 5.00 15.00 1.00 1.00 1.00
stop kontak dinding (atas) 1.00 1.00 1.00 2.00 1.00
stop kontak AC 1 pk 3.00 1.00 1.00 1.00 1.00
stop kontak AC 2 pk 1.00 2.00
Fitting + LED 15 watt 1.00 8.00 5.00 3.00 16.00 2.00 1.00 1.00
Fitting/Downlight + LED 9 watt
RMI 2x11 watt
saklar tunggal 1.00 1.00 1.00 1.00 1.00
saklar ganda 2.00 1.00 1.00 2.00 1.00

R.
R.
Irban 3 Irban 4 R. Staff 2 R. Kasubag lorong Inspektu dapur + KM teras
Sekretaris
r + KM
stop kontak dinding (bawah) 1.00 1.00 12.00 4.00 2.00 3.00
stop kontak dinding (atas) 2.00 1.00 1.00 1.00 1.00
stop kontak AC 1 pk 1.00 1.00
stop kontak AC 2 pk 2.00 1.00 1.00 1.00
Fitting + LED 15 watt 1.00 1.00 10.00 4.00 2.00 3.00 2.00 4.00
Fitting/Downlight + LED 9 watt 5.00 13.00
RMI 2x11 watt 2.00
saklar tunggal 1.00 1.00 1.00 1.00 1.00 1.00
saklar ganda 1.00 1.00 1.00 2.00 1.00 3.00

jumlah estimasi
beban per item faktor ф beban daya
titik beban puncak
stop kontak dinding (bawah) 55.00 6,600.00 100 watt x 20% = 120.00
stop kontak dinding (atas) 12.00 1,440.00 100 watt x 20% = 120.00
stop kontak AC 1 pk 9.00 9,450.00 750 watt x 40% = 1,050.00
stop kontak AC 2 pk 8.00 17,920.00 1,600 watt x 40% = 2,240.00
Fitting + LED 15 watt 64.00 1,056.00 15 watt x 10% = 16.50
Fitting/Downlight + LED 9 watt 18.00 178.20 9 watt x 10% = 9.90
RMI 2x11 watt 2.00 48.40 22 watt x 10% = 24.20
saklar tunggal 11.00
saklar ganda 16.00
36,692.60
29,354.08
ANALISA HARGA SATUAN

KODE ANALISA : P.001


JENIS PEKERJAAN : Pemasangan stop kontak
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.5000 65,000.00 32,500.00


2 Tukang Listrik L13 Org/hr 0.5000 80,000.00 40,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0500 106,000.00 5,300.00
4 Mandor L01 Org/hr 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 83,550.00

B BAHAN

1 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00


2 Stop Kontak M439 bh 1.0000 38,500.00 38,500.00
3 T dos PVC M443 bh 1.0000 2,028.00 2,028.00
4 Pipa PVC 5/8" M444 Ljr 0.6500 9,986.00 6,490.90
5 Las doof M441 bh 3.0000 10,810.00 32,430.00

JUMLAH HARGA BAHAN 151,088.90

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 234,638.90

ANALISA HARGA SATUAN

KODE ANALISA : P.001a


JENIS PEKERJAAN : Pemasangan stop kontak AC
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Page 10 of 18
JENIS PEKERJAAN : Pemasangan stop kontak

A. TENAGA

1 Pekerja L27 Org/hr 0.5000 65,000.00 32,500.00


2 Tukang Listrik L13 Org/hr 0.5000 80,000.00 40,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0500 106,000.00 5,300.00
4 Mandor L01 Org/hr 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 83,550.00

Page 11 of 18
JENIS PEKERJAAN : Pemasangan stop kontak

B BAHAN

1 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00


2 Stop Kontak AC M439a bh 1.0000 135,000.00 135,000.00
3 T dos PVC M443 bh 1.0000 2,028.00 2,028.00
4 Pipa PVC 5/8" M444 Ljr 0.6500 9,986.00 6,490.90
5 Las doof M441 bh 3.0000 10,810.00 32,430.00

JUMLAH HARGA BAHAN 247,588.90

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 331,138.90


ANALISA HARGA SATUAN

KODE ANALISA : P.002


JENIS PEKERJAAN : Pemasangan saklar tunggal
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.5000 65,000.00 32,500.00


2 Tukang Listrik L13 Org/hr 0.5000 80,000.00 40,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0500 106,000.00 5,300.00
4 Mandor L01 Org/hr 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 83,550.00

B BAHAN

1 Kabel NYA 2.5 mm M437 m¹ 6.0000 7,164.00 42,984.00


2 Saklar Broco Tunggal M440 bh 1.0000 45,250.00 45,250.00
3 T dos PVC M443 bh 1.0000 2,028.00 2,028.00
4 Pipa PVC 5/8" M444 Ljr 0.6500 9,986.00 6,490.90
5 Las doof M441 bh 2.0000 10,810.00 21,620.00

JUMLAH HARGA BAHAN 118,372.90

C PERALATAN
Page 12 of 18
JENIS PEKERJAAN : Pemasangan stop kontak

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 201,922.90

Page 13 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.003


JENIS PEKERJAAN : Pemasangan saklar ganda
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.5000 65,000.00 32,500.00


2 Tukang Listrik L13 Org/hr 0.5000 80,000.00 40,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0500 106,000.00 5,300.00
4 Mandor L01 Org/hr 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 83,550.00

B BAHAN

1 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00


2 Saklar Broco Ganda M440.a bh 1.0000 49,900.00 49,900.00
3 T dos PVC M443 bh 1.0000 2,028.00 2,028.00
4 Pipa PVC 5/8" M444 Ljr 0.6500 9,986.00 6,490.90
5 Las doof M441 bh 3.0000 10,810.00 32,430.00

JUMLAH HARGA BAHAN 162,488.90

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 246,038.90

Page 14 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.006a


JENIS PEKERJAAN : Pemasangan titik lampu TL LED 2x11 Watt (RMI)
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.2500 65,000.00 16,250.00


2 Tukang Listrik L13 Org/hr 0.2500 80,000.00 20,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0250 106,000.00 2,650.00
4 Mandor L01 Org/hr 0.0250 115,000.00 2,875.00

JUMLAH HARGA TENAGA 41,775.00

B BAHAN

1 Lampu TL LED 2x11 Watt (RMI) M449a bh 1.0000 350,000.00 350,000.00


2 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00
3 Isolator M442 m¹ 4.0000 1,100.00 4,400.00
4 Las doof M441 bh 2.0000 10,810.00 21,620.00

JUMLAH HARGA BAHAN 447,660.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 489,435.00

Page 15 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.010a


JENIS PEKERJAAN : Pemasangan titik lampu LED 14 Watt
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.2500 65,000.00 16,250.00


2 Tukang Listrik L13 Org/hr 0.2500 80,000.00 20,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0250 106,000.00 2,650.00
4 Mandor L01 Org/hr 0.0250 115,000.00 2,875.00

JUMLAH HARGA TENAGA 41,775.00

B BAHAN

1 Lampu LED 15 Watt M453a bh 1.0000 75,000.00 75,000.00


2 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00
3 Isolator M442 m¹ 4.0000 1,100.00 4,400.00
4 Fiting Flafond M445 bh 1.0000 15,500.00 15,500.00
5 Las doof M441 bh 2.0000 10,810.00 21,620.00

JUMLAH HARGA BAHAN 188,160.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 229,935.00

Page 16 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.011


JENIS PEKERJAAN : Pemasangan titik lampu SL 18 Watt + Armateur Lampu Taman
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.2500 65,000.00 16,250.00


2 Tukang Listrik L13 Org/hr 0.2500 80,000.00 20,000.00
3 Kepala Tukang Listrik L07 Org/hr 0.0250 106,000.00 2,650.00
4 Mandor L01 Org/hr 0.0250 115,000.00 2,875.00

JUMLAH HARGA TENAGA 41,775.00

B BAHAN

1 Lampu XL (Lilin) 18 Watt M454 bh 1.0000 52,175.00 52,175.00


2 Kabel NYA 2.5 mm M437 m¹ 10.0000 7,164.00 71,640.00
3 Isolator M442 m¹ 4.0000 1,100.00 4,400.00
4 Kap Lampu Taman M445b bh 1.0000 365,000.00 365,000.00
5 Las doof M441 bh 2.0000 10,810.00 21,620.00

JUMLAH HARGA BAHAN 514,835.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 556,610.00

Page 17 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.017


JENIS PEKERJAAN : Memasang Panel SDP per buah ( 23 group )
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 1.8000 65,000.00 117,000.00


2 Tukang Listrik L13 Org/hr 2.5000 80,000.00 200,000.00
3 Kepala Tukang Listrik L07 Org/hr 2.5000 106,000.00 265,000.00
4 Mandor L01 Org/hr 1.5000 115,000.00 172,500.00

JUMLAH HARGA TENAGA 754,500.00

B BAHAN

1 Box Panel 40 x 50 x 20 Bh 1.0000 1,500,000.00 1,500,000.00


2 MFB 20 A 3 phase MG Bh 1.0000 1,320,000.00 1,320,000.00
3 MCB 1 phase 6 + 10 A Bh 22.0000 120,000.00 2,640,000.00
4 Fuse + Sekering 2 A Bh 3.0000 15,000.00 45,000.00
5 Ampere Meter Bh 3.0000 90,000.00 270,000.00
6 CT 50 / 5 Bh 3.0000 90,000.00 270,000.00
7 Volt Meter Bh 1.0000 114,000.00 114,000.00
8 Selector Switch / Volt Bh 1.0000 300,000.00 300,000.00
9 Rel Cooper 1.5 m 4 x 2.5 Bh 3.0000 240,000.00 720,000.00
10 Rel MCB 1.5 m Bh 1.0000 27,500.00 27,500.00
11 Terminal Nol Bh 1.0000 42,000.00 42,000.00
12 Terminal Arde Bh 1.0000 42,000.00 42,000.00
13 Secum Cable 10 mm Bh 10.0000 1,500.00 15,000.00
14 Kabel Trey 5 x 7 Ljr 1.0000 42,000.00 42,000.00
15 Grounding + Instalasi PMD unit 1.0000 1,336,500.00 1,336,500.00

JUMLAH HARGA BAHAN 8,684,000.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 9,438,500.00

Page 18 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.018


JENIS PEKERJAAN : Memasang Panel Box ( 4 group )
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.8000 65,000.00 52,000.00


2 Tukang Listrik L13 Org/hr 1.8000 80,000.00 144,000.00
3 Kepala Tukang Listrik L07 Org/hr 1.8000 106,000.00 190,800.00
4 Mandor L01 Org/hr 0.5000 115,000.00 57,500.00

JUMLAH HARGA TENAGA 444,300.00

B BAHAN

1 Box Panel Bh 1 1.0000 125,000.00 125,000.00


2 MFB 16 A 1 phase MG Bh 1 1.0000 357,500.00 357,500.00
3 MCB 1 phase 6 + 10 A Bh 3 3.0000 41,400.00 124,200.00
4 Rel MCB 1.5 m Bh 1 1.0000 28,750.00 28,750.00
5 Terminal Nol Bh 1 1.0000 42,000.00 42,000.00
6 Terminal Arde Bh 1 1.0000 42,000.00 42,000.00
7 Secum Cable 10 mm Bh### 10.0000 1,500.00 15,000.00
8 Kabel Trey 5 x 7 Ljr 1 1.0000 42,000.00 42,000.00
9 Grounding + Instalasi PMD unit 1 1.0000 192,500.00 192,500.00

JUMLAH HARGA BAHAN 968,950.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1,413,250.00

Page 19 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
ANALISA HARGA SATUAN

KODE ANALISA : P.019


JENIS PEKERJAAN : Kabel feeder NYM 4 x 4 mm
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.1000 65,000.00 6,500.00


2 Tukang Listrik L13 Org/hr 0.0200 80,000.00 1,600.00
3 Kepala Tukang Listrik L07 Org/hr 0.0100 106,000.00 1,060.00
4 Mandor L01 Org/hr 0.0100 115,000.00 1,150.00

JUMLAH HARGA TENAGA 10,310.00

B BAHAN

1 Kabel NYM Feeder 4x4 mm Bh 1 1.0000 57,500.00 57,500.00

JUMLAH HARGA BAHAN 57,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 67,810.00

ANALISA HARGA SATUAN

KODE ANALISA : P.019


JENIS PEKERJAAN : Kabel feeder NYM 4 x 4 mm
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

Page 20 of 18
JENIS PEKERJAAN : Pemasangan stop kontak
1 Pekerja L27 Org/hr 0.1000 65,000.00 6,500.00
2 Tukang Listrik L13 Org/hr 0.0200 80,000.00 1,600.00
3 Kepala Tukang Listrik L07 Org/hr 0.0100 106,000.00 1,060.00
4 Mandor L01 Org/hr 0.0100 115,000.00 1,150.00

JUMLAH HARGA TENAGA 10,310.00

Page 21 of 18
JENIS PEKERJAAN : Pemasangan stop kontak

B BAHAN

1 Kabel NYM Feeder 4x4 mm Bh 1 1.0000 57,500.00 57,500.00

JUMLAH HARGA BAHAN 57,500.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 67,810.00

ANALISA HARGA SATUAN

KODE ANALISA : P.019


JENIS PEKERJAAN : Kabel feeder NYM 4 x 16 mm
SATUAN PEMBAYARAN : Unit

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja L27 Org/hr 0.2000 65,000.00 13,000.00


2 Tukang Listrik L13 Org/hr 0.0200 80,000.00 1,600.00
3 Kepala Tukang Listrik L07 Org/hr 0.0100 106,000.00 1,060.00
4 Mandor L01 Org/hr 0.0100 115,000.00 1,150.00

JUMLAH HARGA TENAGA 16,810.00

B BAHAN

1 Kabel NYM Feeder 4x16 mm Bh 1 1.0000 156,250.00 156,250.00

JUMLAH HARGA BAHAN 156,250.00

C PERALATAN

JUMLAH HARGA PERALATAN -

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 173,060.00

Page 22 of 18
XX. BAHAN PERALATAN LISTRIK
1 Lampu TL 20 W/220 V Komplit Rp 65,000 Bh
2 Lampu TL 40 W/220 V Komplit Rp 102,000 Bh
3 Lampu Pijar 25,40,75/220 V Rp 18,000 Bh
4 Lampu XL 20 Watt Rp 40,000 Bh
5 Stop Kontak (Broco) Rp 27,500 Bh
6 Saklar (Broco) Tunggal Rp 35,000 Bh
7 Saklar (Broco) Ganda Rp 40,000 Bh
8 Zekering lengkap Rp 71,000 Bh
9 Fitting plafon Rp 11,000 Bh
10 Isolator Rp 850 Bh
11 T Doos PVC Rp 1,000 Bh
12 Paralon 5/8" Rp 7,500 ljr
13 Las doof Rp 650 bh
14 Stater lampu TL Rp 6,000 bh

XXI. BAHAN KABEL


1 Kabel NYA 1 x 2,5 mm2 Rp 4,500 m1
DAFTAR HARGA SATUAN UPAH KERJA KOTA - 2017

TAHUN 2017

No. URAIAN TENAGA KERJA HARGA SATUAN SATUAN

1 Mandor Rp 115,000.00 Orang / Hari

2 Kepala tukang batu Rp 106,000.00 Orang / Hari

3 Kepala tukang kayu Rp 106,000.00 Orang / Hari

4 Kepala tukang besi Rp 106,000.00 Orang / Hari

5 Kepala tukang cat Rp 106,000.00 Orang / Hari

6 Kepala tukang listrik Rp 106,000.00 Orang / Hari

7 Tukang batu Rp 80,000.00 Orang / Hari

8 Tukang kayu Rp 80,000.00 Orang / Hari

9 Tukang besi Rp 80,000.00 Orang / Hari

10 Tukang cat Rp 80,000.00 Orang / Hari

11 Tukang plitur Rp 65,000.00 Orang / Hari

12 Tukang pipa Rp 65,000.00 Orang / Hari

13 Tukang listrik Rp 80,000.00 Orang / Hari

14 Pekerja Rp 65,000.00 Orang / Hari

15 Penjaga Rp 70,000.00 Orang / Hari

Anda mungkin juga menyukai