E. PEKERJAAN ELEKTRIKAL - -
SAMSUL KOMAR, ST
RINCIAN
RENCANA ENGINEER ESTIMATE ( EE )
RUMAH TOKO RUMAH BEKU CABANG GARUT
Jl. Otto Iskandar Dinata Garut - Tarogong Paseban Garut
TAHUN ANGGARAN 2022
Strausspile ( 400x0,40)M
1 Pembesian 1.777,60 Kg 24.082,45 42.808.956,54
2 Beton Readymix K-250 12,06 M3 1.431.984,97 17.266.301,96
Pekerjaan Sloof
Beton Sloof SL1 20/40
1 Bekisting Multipleks 12 mm 74,40 M2 56.858,57 4.230.277,64
2 Pembesian 878,40 Kg 24.082,45 21.154.020,83
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
(RP.) (RP.)
1 2 3,00 4 5 6=5X3
3 Beton Readymix K-250 7,44 M3 1.431.984,97 10.653.968,17
2 Pekerjaan Balok
Balok (B1) - IWF 300.150.6,5.9 1.761,60 Kg 33.777,92 59.503.188,28
Vute - IWF 300.150.6,5.9 249,56 Kg 33.777,92 8.429.618,34
Joint T - IWF 300.150.6,5.9 176,16 Kg 33.777,92 5.950.318,83
Steffener - Plat 8 mm 46,75 Kg 33.777,92 1.579.117,88
Joint Plate - Plat 15 mm 175,00 Kg 33.777,92 5.911.136,44
4 Keranjang/Bucket :
Spesifikasi :
- IWF 200.100.5,5.8 42,67 Kg 33.777,92 1.441.191,36
- UNP 100.50.6 168,60 Kg 33.777,92 5.694.957,73
- UNP 65.42.5,5 84,00 Kg 33.777,92 2.837.345,49
- Hollow 40.40.2 158,95 Kg 33.777,92 5.369.000,78
- Plat 12 mm 9,72 Kg 33.777,92 328.396,47
- Plat 19 mm 13,84 Kg 33.777,92 467.613,11
- Plat Bordes 171,88 M2 33.777,92 5.805.580,43
- Kawat Mesh 12,00 M2 80.000,00 960.000,00
11 - Kawat Mesh #REF! M' 54.166,67 #REF!
-Pintu Railing Bucket 1,68 M2 550.000,00 924.000,00
JUMLAH - II 23.828.085,38
SUB JUMLAH PEKERJAAN STR BAJA, BETONISASI DAN ATAP 746.429.833,27
C. PEKERJAAN ARSITEKTUR
I.a LANTAI DASAR /1
1 Pasangan dinding 1/2 bata 215,07 M2 170.768,55 36.727.192,12
2 Pekerjaan plester dan acian dinding 1 : 5 / finishing acian 430,14 M2 148.059,47 63.686.301,36
4 Kolom praktis 15/15 96,80 M' 174.925,81 16.932.818,27
5 Balok 15/30 40,00 M' 466.468,82 18.658.752,91
6 Urugan pasir bawah lantai t=5 cm 16,55 M3 256.864,76 4.251.111,78
7 Lantai kerja t = 5 cm 331,00 M2 195.213,81 64.615.770,14
10 Openingan kusen pIntu dan jendela 76,50 M' 45.000,00 3.442.500,00
11 Pekerjaan dinding keramik 30X60 h= 2m 14,20 M2 249.413,14 3.541.666,53
12 Pekerjaan Lantai keramik 30x30 ( Toilet ) 3,50 M2 249.413,14 872.945,98
13 Pekerjaan Lantai keramik 60x60 214,84 M2 348.305,15 74.829.877,77
Pekerjaan Lantai keramik 30x60 anak tangga 8,76 M2 348.305,15 3.051.153,09
Pekerjaan Lantai keramik 20x60 tangga 5,04 M2 348.305,15 1.755.457,94
15 Pekerjaan Railling Tangga Ranggka hollo 40x40 , 20x40 t=3 mm M'
Pekerjaan roster 0,44 M2 450.000,00 198.000,00
Pekerjaan glass box 10,80 M2 650.000,00 7.020.000,00
18 Pekerjaan gutter d 20 x20 26,00 M' 130.500,00 3.393.000,00
SUB JUMLAH 302.976.547,88
I.b LANTAI 2
1 Pasangan dinding 1/2 bata hebel 216,06 M2 149.208,16 32.237.915,48
2 Pekerjaan plester dan acian dinding 1 : 5 / finishing acian 432,12 M2 148.059,47 63.979.459,11
4 Kolom praktis 15/15 96,80 M' 174.925,81 16.932.818,27
5 Balok lintel 15/15 104,00 M' 174.925,81 18.192.284,09
6 Urugan pasir bawah lantai t=2 cm 6,12 M3 314.283,18 1.923.413,06
10 Openingan kusen pIntu dan jendela 43,10 M' 45.000,00 1.939.500,00
11 Pekerjaan dinding keramik 30X60 h= 2m 14,20 M2 249.413,14 3.541.666,53
12 Pekerjaan Lantai keramik 30x30 ( Toilet ) 3,50 M2 249.413,14 872.945,98
13 Pekerjaan Lantai keramik 60x60 194,86 M2 348.305,15 67.870.740,93
SUB JUMLAH 207.490.743,45
JUMLAH - I 510.467.291,33
II. PEK. KUSEN PINTU/JENDELA , LENGKAP ASSESORIES
II.a LANTAI DASAR / 1
1 Pasang Kusen+Pintu Type PHD @ 8 daun /unit 2,00 Unit 16.521.600,00
2 Pasang Kusen+Pintu Type PDG 2 @ 4 daun /unit 2,00 Unit 18.657.100,00
3 Pasang Kusen+Pintu Type PT 1,00 Unit
4 Pasang Kusen+Pintu Jndla Type PJS 1,00 Unit 14.925.680,00
5 Pasang Kaca temper 18 mm 1,00 Unit 3.777.100,00
SUB JUMLAH
II.b LANTAI 2
3 Pasang Kusen+Pintu Type PDG 2 @ 4 daun /unit 2,00 Unit 18.657.100,00
Pasang Kusen+jendela Type CW 1,00 Unit 23.740.000,00
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
(RP.) (RP.)
1 2 3,00 4 5 6=5X3
Pasang Kusen+Pintu Type PK 2,00 Unit
4 Pasang Kusen+Pintu Type PT 2,00 Unit 2.374.000,00
SUB JUMLAH
JUMLAH - II -
III. PEKERJAAN PLAFOND
LANTAI 1
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 40,00 M2 109.306,00 4.372.240,00
Pek. Plafond multy 9mm finish hpl +Rangka Hollow 40x40 4,80 M2 218.612,00 1.049.337,60
Pek. Plafond GRC 9mm+Rangka Hollow 40x40 16,80 M2 98.375,40 1.652.706,72
Pek. list Plafond 29,60 M2 27.689,07 819.596,41
2 Pek. Plafond black hollow Rangka 40x60, 40x40 187,20 M2 350.000,00 65.520.000,00
SUB JUMLAH 73.413.880,73
LANTAI 2
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 208,86 M2 109.306,00 22.829.651,16
Pek. Plafond GRC 9mm+Rangka Hollow 40x40 3,50 M2 98.375,40 344.313,90
Pek. Plafond conwood 200.15 10,00 M2 300.000,00 3.000.000,00
2 Pek. Rangka hollow 60.40.40 Plafond conwood 12,00 M2 700.000,00 8.400.000,00
Pek. Penutup Multy 18 MM 10,00 M2 106.142,26 1.061.422,57
SUB JUMLAH 35.635.387,63
JUMLAH - III 109.049.268,36
IV. PEKERJAAN FINISHING & PENGECATAN
V.a LANTAI DASAR/1
1 Pekerjaan Finishing Opening Kusen pada dinding bata 76,50 M' 17.500,00 1.338.750,00
2 Pekerjaan pengecatan dinding Exterior Watershiel 215,07 M2 51.970,71 11.177.339,98
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 322,61 M2 30.459,24 9.826.302,11
4 Pekerjaan pengecatan plafond 56,80 M2 30.459,24 1.730.084,65
SUB JUMLAH SUB JUMLAH 24.072.476,75
IV.b LANTAI 2
1 Pekerjaan pengecatan dinding Exterior Watershiel 216,06 M2 50.384,87 10.886.154,74
2 Pekerjaan pengecatan dinding bata & partisi (Interior) 324,09 M2 30.459,24 9.871.534,08
3 Pekerjaan pengecatan plafond 213,20 M2 30.459,24 6.493.909,30
4 Pekerjaan pengecatan plitur conwood/ multyplek 22,00 M2 63.829,78 1.404.255,12
SUB JUMLAH SUB JUMLAH 27.251.598,13
JUMLAH - IV 52.026.202,44
SUB TOTAL ARSITEKTURE 671.542.762,13
D. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
1. LANTAI - 1
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 24,00 M' 87.131,39 2.091.153,46
- PPR dia 3/4 inc 24,00 M' 105.202,49 2.524.859,86
- PPR dia 1 inc 24,00 M' 148.610,39 3.566.649,46
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 2,00 Unit 100.000,00 200.000,00
- Gate valve dia 1 inc 2,00 Unit 160.000,00 320.000,00
c. TORN
Torn air bersih 1000 liter 2,00 unit 2.379.000,00 4.758.000,00
JUMLAH I 13.460.662,77
II. PEKERJAAN INSTALASI AIR KOTOR
1. LANTAI - 1
c. PIPA AIR KOTOR (PVC Class 10 Kg/cM2)
b PP-Atas/LP-Atas
- Panel box (400x300x250) mm 1,00 Bh 364.000,00
- Busbar+Wiring Material 2,00 lot 105.000,00
Input
- MCCB 3P 32 A 1,00 Bh 274.300,00
- Pilot Lamp Tlmq+MCB 1P 16A 3,00 set 19.320,00
Output -
- MCB 1P 6A 2,00 Bh 116.200,00
- MCB 3P 16A 2,00 Bh 151.060,00
SUB JUMLAH -
2 PASANG KABEL TRAY
kabel tray elektrikal (100 x 50) mm 50,00 M' 266.400,00
2 Material
TKI 1X40 W 8,00 Bh 162.500,00
Down Light 18 W 8,00 Bh 195.000,00
Down Light 6 W 9,00 Bh 195.000,00
Stop kontak 3p 30,00 Bh 36.150,00
Stop kontak 30,00 Bh 24.100,00
Saklar ganda 6,00 Bh 24.100,00
Saklar tunggal 6,00 Bh 19.910,00
SUB JUMLAH
II. ELEKTRIKAL LANTAI 2
1 PASANG KABEL TRAY
kabel tray elektrikal (100 x 50) mm 50,00 M' 266.400,00
2 Material
TKI 1X40 W 16,00 Bh 162.500,00
Down Light 18 W 4,00 Bh 195.000,00
Stop kontak 10,00 Bh 36.150,00
Saklar ganda 4,00 Bh 24.100,00
Saklar tunggal 4,00 Bh 19.910,00
SUB JUMLAH
SUB TOTAL PEK.ELEKTRIKAL
TOTAL JUMLAH PEKERJAAN RUKO 1.753.284.909,50
TOTAL JUMLAH
HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SAT HARGA KETERANGAN
(RP.) (RP.)
1 2 3 4 5,00 6=5X3
II. PEKERJAAN BANGUNAN PENUNJANG DAN LANDSCAPE
I. BANGUNAN MUSHOLA 2,5X2,5
1 Pekerjaan bowplank 14,00 M' 63.041,17 882.576,34
2 Pekerjaan galian pondasi pasangan batukali 0,60 M3 55.382,24 33.229,34
3 Pekerjaan urugan tanah t. 20 cm 12,00 M3 20.218,28 242.619,36
4 Pekerjaan urugan pasir t. 3 cm 1,80 M3 221.985,20 399.573,36
5 Pekerjaan Beton Sloof 15/20 10,00 M' 125.858,55 1.258.585,55
6 Pekerjaan dinding pasangan 1/2 bata 6,12 M2 117.465,94 718.891,55
7 Pekerjaan plester dan acian dinding 1 : 5 12,24 M2 53.332,89 652.794,61
8 Pekerjaan dinding krawang / roster 14,08 M2 450.000,00 6.336.000,00
9 Pekerjaan lantai rabat beton K175 t. 5 cm 3,00 M3 1.232.885,52 3.698.656,56
10 Pekerjaan Plapis lantai vinyl 5,06 M2 348.305,15 1.762.424,04
11 Pekerjaan dinding keramik 30X60 h= 2m 5,60 M2 249.413,14 1.396.713,56
12 Pekerjaan lantai keramik 30x30 1,20 M2 249.413,14 299.295,76
13 Pekerjaan dak atap 2,35 M2 4.098.716,04 9.640.180,13
-
14 Pekerjaan instalasi dan pemasangan lampu Tl 20 W 2,00 Unit 511.260,22 1.022.520,44
15 Pekerjaan instalasi dan pemasangan stop kontak 1,00 Unit 171.295,17 171.295,17
16 Pekerjaan instalasi dan pemasangan saklar ganda 1,00 Unit 171.295,17 171.295,17
2 PEKERJAAN TAMAN
1 Pekerjaan Taman -
1 - Urugan Tanah Subur 20 cm 2,88 M3 75.000,00 216.000,00
2 - Bibit Tanaman sayuran ( disesuaikan dgn Kebutuhan ) 1,00 Ls 1.000.000,00 1.000.000,00
3 - Bibit tanaman bunga (disesuaikan dengan Kebutuhan ) 1,00 Ls 1.000.000,00 1.000.000,00
4 pot dan peralatan lainnya ( disesuaikan dengan kebutuhan ) 1,00 Ls 1.000.000,00 1.000.000,00
6 Lampu taman 2,00 Unit 511.260,22 1.022.520,44