LAPORAN KERJA PRAKTIK

“PENGUKURAN VOLUME CUT AND FILL MENGGUNAKAN


METODE PENAMPANG RATA-RATA PADA PEMBANGUNAN
EMBUNG SIGIT KABUPATEN SRAGEN”

Disusun oleh:

Enggar Saputro 18/426169/SV/15311


Muhammad Zulfa Irsyad 18/431868/SV/15839
Mohammad Dikhyak Alwi Z 18/432259/SV/16195

PROGRAM STUDI DIPLOMA-III TEKNIK GEOMATIKA


DEPARTEMEN TEKNOLOGI KEBUMIAN
SEKOLAH VOKASI
UNIVERSITAS GADJAH MADA
TAHUN 2021
LEMBAR PENGESAHAN

Laporan ini disusun berdasarkan hasil Kerja Praktik di CV. Karya Gemilang yang telah
dilaksanakan pada:
Tanggal : 15 Juli – 31 Agustus 2020 vdf

Lokasi : CV. Karya Gemilang Perum Jombang Citra Raya Block C-10 no. 6
Jombang Jawa Timur 081235428240

Yogyakarta, 15 Maret 2021

Menyetujui,

Dosen Pembimbing Kerja Praktik Pembimbing Kerja Praktik


CV. Karya Gemilang

Muhammad Iqbal Taftazani, S.T., M.Eng. Cahya Hardianta S.T., M.T.


NIKA. 111198504201706101

Mengetahui,

Ketua Program Studi Diploma III Teknik Geomatika

Ir. Waljiyanto, M.Sc.


NIP. 195805161985031003

i
KATA PENGANTAR

Puji syukur kami panjatkan kepada Allah SWT yang telah memberikan rahmat, nikmat,
dan karunianya sehingga kami dapat menyelesaikan penulisan laporan Kerja Praktik di CV.
Karya Gemilang pada pelaksanaan pembangunan Embung Sigit Kabupaten Sragen. Penulisan
laporan ini dimaksudkan untuk memenuhi syarat kelulusan pada mata kuliah magang program
studi Diploma III Teknik Geomatika SV UGM. Laporan Kerja Praktik ini dibuat berdasarkan
pengalaman kerja yang telah kami lakukan di CV. Karya Gemilang.
Pada proses penulisan laporan ini telah melibatkan banyak pihak yang memberikan
arahan, bimbingan, inspirasi, bantuan baik material maupun spiritual, dan lain sebagainya.
Oleh karena itu pada kesempatan ini kami mengucapkan terima kasih kepada:
1. Orang tua dan keluarga.
2. Dr. Taufik Hery Purwanto M.Si. selaku Ketua Departemen Teknologi Kebumian SV
UGM.
3. Ir. Waljiyanto, M.Sc. selaku Ketua Program Studi Diploma-III Teknik Geomatika
4. Muhammad Iqbal Taftazani, S.T., M.Eng. selaku dosen pebimbing magang
5. Cahya Hardianta S.T., M.T. selaku pebimbing magang di CV. Karya Gemilang
6. Serta pihak lain yang baik secara langsung maupun tidak langsung turut terlibat dalam
pembuatan laporan ini yang tidak dapat kami sebutkan satu per satu.

Kami sadar bahwa masih terdapat kekurangaan pada penulisan laporan ini, sehingga
kami dengan senang hati menerima kritik dan saran yang diberikan. Kami berharap laporan ini
dapat memberikan banyak manfaat.

Yogyakarta, 15 Maret 2021

Penulis

ii
DAFTAR ISI

LEMBAR PENGESAHAN ........................................................................................ i


KATA PENGANTAR ............................................................................................... ii
DAFTAR ISI ............................................................................................................ iii
DAFTAR GAMBAR ................................................................................................ iv
DAFTAR TABEL ..................................................................................................... v
BAB I PENDAHULUAN .......................................................................................... 1
I.1. Latar Belakang .................................................................................................... 1
I.2. Tujuan dan Manfaat Kegiatan .............................................................................. 2
I.2.1. Bagi Mahasiswa................................................................................................ 2
I.2.2. Bagi Instansi/Perusahaan .................................................................................. 2
I.2.3. Bagi Universitas ............................................................................................... 3
I.3. Landasan Teori .................................................................................................... 3
I.3.1. Kerangka Kontrol Horizontal ............................................................................ 3
1.3.2. Kerangka Kontrol Vertikal ............................................................................... 5
1.3.3. Staking Out ...................................................................................................... 6
1.3.4. Penampang Memanjang dan Melintang ............................................................ 6
1.3.5. Perhitungan Volume......................................................................................... 6
BAB II PELAKSANAAN ......................................................................................... 8
II.1. Tempat dan Waktu Pelaksanaan Kegiatan .......................................................... 8
II.2. Lingkup Kegiatan ............................................................................................... 8
II.3. Tatakala Pelaksanaan Kegiatan ........................................................................... 8
II.4. Persiapan .......................................................................................................... 10
II.4.1. Alat ............................................................................................................... 10
II.4.2. Bahan ............................................................................................................ 10
II.5. Tahapan Kerja .................................................................................................. 10
II.6. Proses Pengumpulan Data ................................................................................ 11
II.7. Proses Pengolahan Data.................................................................................... 11
II.7.1. Plotting Data Hasil Pengukuran Lapangan ..................................................... 11
II.7.2. Plotting Data Hasil Pengukuran Lapangan ..................................................... 13
BAB III HASIL DAN PEMBAHASAN .................................................................. 14
III.1 Hasil Pengumpulan dan Pengolahan Data......................................................... 14
III.1.1 Data Pengukuran dan Pengolahan Ukuran Lapangan ..................................... 14
III.1.2 Hasil Plotting Situasi Tampak Atas ............................................................... 26
III.1.3 Hasil Penggambaran Penampang Melintang .................................................. 29
III.1.4 Hitungan Volume Cut And Fill ..................................................................... 33
III.2 Analisis Pengukuran dan Perhitungan Volume Progres .................................... 48
BAB IV PENUTUP................................................................................................. 50
IV.1. Kesimpulan..................................................................................................... 50
IV.2. Saran .............................................................................................................. 50
DAFTAR PUSTAKA .............................................................................................. 51
LAMPIRAN ............................................................................................................ 52

iii
DAFTAR GAMBAR

Gambar 1.1. Poligon Tertutup.................................................................................... 3


Gambar 1.2. Poligon Terbuka .................................................................................... 4
Gambar 1.3. Poligon Kombinasi ................................................................................ 4
Gambar 1.4. Poligon Bercabang ................................................................................ 4
Gambar 1.5. Tahapan Kerja ..................................................................................... 10
Gambar 1.6. Shop Drawing Embung Sigit ............................................................... 12
Gambar 1.7. Progres Galian ..................................................................................... 12
Gambar 1.8. Progres Galian pada Profil Melintang .................................................. 13
Gambar 2.1. Plot Data Ukur Minggu 1 .................................................................... 26
Gambar 2.2. Plot Data Ukur Minggu 2 .................................................................... 26
Gambar 2.3. Plot Data Ukur Minggu 3 .................................................................... 26
Gambar 2.4. Plot Data Ukur Minggu 4 .................................................................... 28
Gambar 2.5. Plot Data Ukur Minggu 5 .................................................................... 28
Gambar 2.6. Progres Galian M1 pada STA 0+00 ..................................................... 29
Gambar 2.7. Progres Galian M1 pada STA 0+25 ..................................................... 29
Gambar 2.8. Progres Galian M1 pada STA 0+50 ..................................................... 29
Gambar 2.9. Progres Galian M1 pada STA 0+75 ..................................................... 29
Gambar 2.10. Progres Galian M2 pada STA 0+25 ................................................... 29
Gambar 2.11. Progres Galian M2 pada STA 0+50 ................................................... 29
Gambar 2.12. Progres Galian M2 pada STA 0+75 ................................................... 30
Gambar 2.13. Progres Galian M2 pada STA 1+00 ................................................... 30
Gambar 2.14. Progres Galian M3 pada STA 0+00 ................................................... 30
Gambar 2.15. Progres Galian M3 pada STA 0+10 ................................................... 30
Gambar 2.16. Progres Galian M3 pada STA 0+15 ................................................... 30
Gambar 2.17. Progres Galian M4 pada STA 0+00 ................................................... 31
Gambar 2.18. Progres Galian M4 pada STA 0+25 ................................................... 31
Gambar 2.19. Progres Galian M4 pada STA 0+50 ................................................... 31
Gambar 2.20. Progres Galian M4 pada STA 0+75 ................................................... 31
Gambar 2.21. Progres Galian M4 pada STA 1+00 ................................................... 31
Gambar 2.22. Progres Galian M5 pada STA 0+00 ................................................... 32
Gambar 2.23. Progres Galian M5 pada STA 0+15 ................................................... 32
Gambar 2.24. Progres Galian M5 pada STA 0+30 ................................................... 32

iv
DAFTAR TABEL

Tabel 1.1. Jadwal kegiatan per-hari............................................................................ 8


Tabel 1.2. Jadwal kegiatan per-minggu ...................................................................... 9
Tabel 1.3. Format Penyusunan di Ms. Excel ............................................................ 11
Tabel 1.4. Format Tabel Perhitungan Volume di Ms.Excel ...................................... 13
Tabel 1.5. Formula Perhitungan Volume.................................................................. 13
Tabel 2.1. Data Ukur Minggu 1 ............................................................................... 15
Tabel 2.2. Data Ukur Minggu 2 ............................................................................... 16
Tabel 2.3. Data Ukur Minggu 3 ............................................................................... 18
Tabel 2.4. Data Ukur Minggu 4 ............................................................................... 20
Tabel 2.5. Data Ukur Minggu 5 ............................................................................... 22
Tabel 2.6. Gambar Penampang Melintang Data Ukur Minggu 1 .............................. 29
Tabel 2.7. Gambar Penampang Melintang Data Ukur Minggu 2 .............................. 29
Tabel 2.8. Gambar Penampang Melintang Data Ukur Minggu 3 .............................. 30
Tabel 2.9. Gambar Penampang Melintang Data Ukur Minggu 4 .............................. 31
Tabel 2.10. Gambar Penampang Melintang Data Ukur Minggu 5 ............................ 32
Tabel 2.11. Perhitungan Luas Penampang M1 STA 0+00 ........................................ 33
Tabel 2.12. Perhitungan Luas Penampang M1 STA 0+25 ........................................ 33
Tabel 2.13. Perhitungan Luas Penampang M1 STA 0+50 ........................................ 34
Tabel 2.14. Perhitungan Luas Penampang M1 STA 0+75 ........................................ 34
Tabel 2.15. Rekapitulasi Perhitungan Volume Minggu 1.......................................... 35
Tabel 2.16. Perhitungan Luas Penampang M2 STA 0+25 ........................................ 35
Tabel 2.17. Perhitungan Luas Penampang M2 STA 0+50 ........................................ 36
Tabel 2.18. Perhitungan Luas Penampang M2 STA 0+75 ........................................ 36
Tabel 2.19. Perhitungan Luas Penampang M2 STA 1+00 ........................................ 37
Tabel 2.20. Rekapitulasi Perhitungan Volume Minggu 2 ......................................... 38
Tabel 2.21. Perhitungan Luas Penampang M3 STA 0+00 ........................................ 38
Tabel 2.22. Perhitungan Luas Penampang M3 STA 0+10 ........................................ 39
Tabel 2.23. Perhitungan Luas Penampang M3 STA 0+15 ........................................ 40
Tabel 2.24. Rekapitulasi Perhitungan Volume Minggu 3.......................................... 40
Tabel 2.25. Perhitungan Luas Penampang M4 STA 0+00 ........................................ 41
Tabel 2.26. Perhitungan Luas Penampang M4 STA 0+25 ........................................ 41
Tabel 2.27. Perhitungan Luas Penampang M4 STA 0+50 ........................................ 42
Tabel 2.28. Perhitungan Luas Penampang M4 STA 0+75 ........................................ 42
Tabel 2.29. Perhitungan Luas Penampang M4 STA 1+00 ........................................ 43
Tabel 2.30. Rekapitulasi Perhitungan Volume Minggu 4 ........................................ 43
Tabel 2.31. Perhitungan Luas Penampang M5 STA 0+00 ........................................ 44
Tabel 2.32. Perhitungan Luas Penampang M5 STA 0+15 ........................................ 45
Tabel 2.33. Perhitungan Luas Penampang M5 STA 0+30 ........................................ 46
Tabel 2.34. Rekapitulasi Perhitungan Volume Minggu 5.......................................... 47
Tabel 2.35. Hasil Volume 5 Minggu Pengukuran ..................................................... 48

v
BAB I
PENDAHULUAN

I.1. Latar Belakang


Indonesia merupakan negara yang memiliki wilayah luas dengan kekayaan
sumber daya alam didalamnya dan tersebar di berbagai penjuru daerah baik di
pedalaman maupun di perkotaan. Untuk menjadikan Indonesia yang lebih maju demi
adanya pemerataan fasilitas baik itu akses jalan, akomodasi, logistik dan lain
sebagainya, maka perlu adanya strategi pembangunan nasional guna mempercepat
pencapaian pembangunan insfrastruktur yang merata.
Dalam kegiatan pembangunan insfrastruktur, tenaga kerja yang dibutuhkan
tidak hanya berlatar belakang dari disiplin ilmu sipil dan arsitektur saja, tetapi juga
membutuhkan tenaga kerja dari disiplin ilmu lainnya, salah satunya adalah surveyor
dari Teknik Geodesi dan Geomatika. Bidang ilmu Teknik Geodesi dan Geomatika
merupakan bidang ilmu yang mempelajari segala hal yang berhubungan dengan survei
pemetaan. Secara umum, tahap survei pemetaan yaitu akuisisi data, pengolahan data,
penyajian data, dan penyimpanan data. Dalam survei pemetaan dikenal beberapa
metode akuisisi data, seperti Survei Terestris, GNSS (Global Navigation Satellite
System), Fotogrametri, Penginderaan Jauh, dan Hidrografi. Ilmu - ilmu dalam bidang
Teknik Geodesi dan Geomatika sangat berperan dalam kegiatan pekerjaan yang
membutuhkan keakurasian dalam penentuan posisi (positioning), salah satunya
kegiatan kontruksi seperti pada kegiatan kerja praktik ini.
Pemetaan Konstruksi dilakukan dalam perencanaan, pengawalan (monitoring),
dan pemeliharaan pembangunan infrastruktur dengan menggunakan peralatan survey
pemetaan sehingga seluruh proses pembangunan dapat dikontrol dengan baik.
Program Studi Diploma-III Teknik Geomatika Universitas Gadjah Mada
merupakan program vokasional terapan, dimana kurikulum dirancang lebih menitik
beratkan pada penerapan praktik. Sesuai dengan kompetensi yang ditargetkan oleh
Program Studi Teknik Geomatika yaitu menghasilkan lulusan yang mampu dan trampil
dalam menerapkan ilmu pengetahuan yang didapatkan selama perkuliahan. Dengan
demikian, tujuan kegiatan Kerja Praktik ini untuk mendapatkan lebih banyak
pengetahuan dan pengalaman yang sesuai dengan standar etos kerja di dunia kerja.
Adanya kegiatan Kerja Praktik, mahasiswa mampu mengaplikasikan antara teori dan

1
praktik dalam mata kuliah yang telah diajarkan serta mahasiswa memiliki gambaran
tentang kondisi nyata yang terjadi di dunia kerja.
CV Karya Gemilang merupakan perusahaan jasa yang bergerak di bidang
kontruksi, dapat mendukung untuk pengaplikasian hasil pembelajaran selama
perkuliahan pada kegiatan Kerja Praktik ini. Dengan berbekal ilmu yang diberikan
selama perkuliahan dan pengetahuan beberapa disiplin ilmu yang lain, diharapkan
program Kerja Praktik ini dapat memberikan pengalaman serta pengaplikasian secara
nyata yang berhubungan dengan ilmu Geodesi dan Geomatika.

I.2. Tujuan dan Manfaat Kegiatan


I.2.1. Bagi Mahasiswa
1. Menerapkan dan mengaplikasikan ilmu teori dan ilmu praktis yang didapatkan
di perkuliahan dalam kondisi lapangan di dunia kerja sehingga mahasiswa
mendapatkan gambaran yang nyata tentang berbagai hal mengenai dunia kerja
yang aplikatif.
2. Memperoleh pengalaman tentang kerja teknis di lapangan, mengenal dunia
pekerjaan dan diharapkan dari pengalaman kerja praktik ini akan dapat
memberikan gambaran tentang penggunaan ilmu Geodesi dan Geomatika
khususnya di CV. Karya Gemilang.
3. Menambah relasi dan hubungan yang baik terhadap mahasiswa dengan
individu maupun perusahaan dalam suatu pekerjaan.
4. Memenuhi syarat SKS dalam menyelesaikan studi di Teknik Geomatika,
Sekolah Vokasi, Universitas Gadjah Mada.
I.2.2. Bagi Instansi/Perusahaan
1. Memperoleh masukan serta saran dari mahasiswa yang mungkin dapat berguna
dalam penyelesaian masalah terkait pemetaan maupun sesuai judul kerja
praktik di perusahaan.
2. Sebagai salah satu sarana pertimbangan bagi perusahaan/instansi dalam
menilai kualitas mahasiswa Teknik Geomatika, Universitas Gadjah Mada
terkait penerimaan tenaga kerja lulusan baru atau fresh graduate.
3. Membantu pekerjaan atau proyek yang sedang dilakukan oleh CV. Karya
Gemilang.

2
I.2.3. Bagi Universitas
1. Terjalinnya hubungan baik antara Universitas Gadjah Mada Yogyakarta
dengan instansi/perusahaan terkait.
2. Sebagai sarana evaluasi kurikulum universitas dalam menyiapkan lulusan yang
lebih baik dan sesuai yang diharapkan.
I.3. Landasan Teori
I.3.1. Kerangka Kontrol Horizontal
Pemetaan detail situasi permukaan bumi secara terestris pada bidang datar
memerlukan Kerangka Kontrol Horizontal (KKH) untuk menunjukan letak satu titik
dengan titik yang lain diatas permukaan bumi pada bidang datar (Basuki, 2011). KKH
terdiri dari sekumpulan titik yang telah diketahui posisi yang tetap yang akan
melingkupi wilayah yang akan dipetakan untuk menentukan posisi horizontal dalam
satu sistem koordinat. Metode pengukuran KKH dapat dilakukan dengan beberapa
metode diantaranya yakni:
1. Poligon
Poligon atau Travers mserupakan serangkaian garis lurus yang menghubungkn
titik-titik yang terletak di permukaan bumi, dengan menentukan posisi titik yang
belum diketahui koordinatnya dari titik yang sudah diketahui koordinatnya, dengan
mengukur sudut horizontal dan jarak datar antar titik (Basuki, 2011). Macam-
macam polygon diantaranya sebagai berikut:
a. Poligon tertutup
Poligon tertutup memiliki titik awal dan titik akhir koordinat yang berhimpit
dimana titik awal dan titik akhir berada pada satu titik. Seperti disajikan pada
Gambar 1.1.

Gambar 1.1. Poligon Tertutup

3
c. Poligon Terbuka
Poligon terbuka memiliki titik awal dan titik akhir yang tidak saling berhimpit.
Seperti disajikan pada Gambar 1.2.

Gambar 1.2. Poligon Terbuka

d. Poligon Kombinasi
Poligon kombinasi memadukan antara polygon terbuka dan polygon tertutup
dengan tujuan mendekatkan kerangka ke obyek pemetaan serta dapat
melingkupi obyek yang akan dipetakan secara utuh. Seperti disajikan pada
Gambar 1.3.

Gambar 1.3. Poligon Kombinasi


e. Poligon Bercabang
Poligon bercabang memiliki memiliki cabang dalam rangkain titik yang dibuat.
Seperti disajikan pada Gambar 1.4.

1.4. Poligon Bercabang

4
Berdasarkan titik ikatnya poligon dibagi menjadi 2 diantaranya:
1. Poligon terikat sempurna
Poligon yang terikat sempurna memiliki koordinat dan sudut azimuth minimum 2
buah titik ikat dan tingkatnya berada di atas titik yang dihasilkan.
2. Poligon terikat tidak sempurna
Poligon terikat tidak sempurna karena titik ikat hanya diketahui koordinatnya atau
hanya jurusan atau azimuthnya saja
2. Pemotongan ke muka
Menentukan koordinat suatu titik dari 2 titik tetap yang telah diketahui kemudian
diukur sudut dan jarak dari setiap titik tetap kearah titik yang akan dicari
koordinatnya.
3. Pemotongan ke Belakang
Menentukan koordinat titik dengan membutuhkan minimal 3 titik tetap, dengan
meletakan alat ukur diatas titik yang akan dicari koordinatnya untuk diukur sudut
dan jarak kesetiap titik tetap yang diketahui.
4. Triangulasi
Menentukan posisi horizontal dari suatu titik dengan menggunakan konsep segitiga
dimana harus mengukur semua sudut dalam segitiga dan satu sisi segitiga harus
diketahui.
5. Trilaterasi
Metode trilaterasi menggunakan konsep segitiga yang harus diukur semua jarak
sisinya untuk mendapatkan posisi dari titik yang dicari.
6. Triangulaterasi
Menentukan posisi titik dengan menggunakan konsep segitiga akan tetapi metode
ini harus mengukur jarak dan sudut semua sisi.
1.3.2. Kerangka Kontrol Vertikal
Pengukuran kontrol vertikal atau kontrol tinggi (z), dilakukan dengan
pengukuran beda tinggi secara teliti antara titik-titik kontrol horizontal atau titik-titik
poligon yang berurutan dengan cara atau metode sipat datar, atau dengan cara
tachimetrik maupun trigonometrik, tergantung dari tingkat ketelitian yang
disyaratkan. Dengan kombinasi antara kontrol horizontal (X,Y) dan vertikal (Z),
maka titik-titik kerangka dasar pemetaan (TKDP) tersebut akan dapat ditentukan
posisinya dalam tiga dimensi (X,Y,Z) (Hidayat, 2014).

5
1.3.3. Staking Out
Pekerjaan staking out adalah pekerjaan memindahkan atau mentransfer titik-titik yang
ada di peta perencanaan ke lapangan (permukaan bumi) berdasarkan data yang ada
pada desain kontruksi dan perencanaan dengan menggunakan alat Total Station
(Susetyo, Yuniar, & Saputra, 2013).

1.3.4. Penampang Memanjang dan Melintang


Penampang memanjang merupakan gambar irisan vertical atau tegak pada
lapangan dengan mengukur jarak dan beda tinggi titik-titik di atas permukaan bumi.
Profil memanjang untuk melakukan pengukuran yang jaraknya jauh, contohnya;
pekerjaan membuat trace jalan, kereta api, saluran air, pipa air minum, dan lain
sebagainya.
Penampang melintang gambar irisan tegak kondisi topografi permukaan
tanah yang diukur jarak dan beda tinggi titik-titik diatas permukaan tanah dan tegak
lurus terhadap garis sumbu pada stasiun penuh dan stasiun plus yang menyatakan
batas-batas suatu galian atau timbunan rencana atau data existing (yang sudah ada)
(Adi, 2019).
1.3.5. Perhitungan Volume
Cut and fill merupakan suatu metode untuk menentukan volume galian atau
timbunan tanah pada suatu tempat. Juga dapat digunakan untuk menghitung material
(bahan) yang sifatnya padat. Prinsip hitungan volume adalah satu luasan x satu wakil
tinggi. Apabila ada beberapa luasan atau beberapa tinggi maka dibuat wakilnya,
misalnya dengan merata-ratakan luasan ataupun merata-ratakan tingginya (Gultom,
Rassarandi, & Siagian, 2020).
Volume mempunyai dimensi kubik, misalnya meter kubik (m3). Yang
dimaksud volume disini adalah volume timbunan. Sering terjadi bahwa bentuk
timbunan yang akan dihitung volumenya berubah-ubah, artinya dapat mengalami
penambahan ataupun pengurangan. Permukaan timbuanan yang tidak beraturan akan
dihitung volumenya dengan beberapa metode.
Perhitungan volume diperlukan suatu bidang referensi berupa bidang datar
atau bidang proyeksi. Volume tanah yang dimaksud disini adalah apabila ingin
menggali atau menimbun tanah pada suatu tempat (cut and fill) atau untuk
menghitung material (bahan) galian yang sifatnya padat. Pada kasus yang lain
apabila suatu daerah merupakan gundukan (tanah tinggi), sedangkan daerah tersebut

6
akan dibangun dengan ketinggian tertentu yang mengharuskan memangkas
(memotong) ketinggian daerah tersebut. Volume galian ini yang akan dihitung
besarnya. Perhitungan Volume (Cut and Fill) ini dapat dilakukan dengan metode
pengukuran detil tachimetri.

7
BAB II
PELAKSANAAN
II.1. Tempat dan Waktu Pelaksanaan Kegiatan
Tempat Pelaksanaan : CV. Karya Gemilang
Perum Jombang Citra Raya Block C-10 no. 6 Jombang Jawa
Timur.
Waktu pelaksanaan : 15 Juli – 31 Agustus 2020
II.2. Lingkup Kegiatan
Terkait dengan CV Karya Gemilang sebagai Badan Usaha penyedia jasa
konsultan perencana dan pengawas proyek, lingkup kegiatan yang kami lakukan pada
pelaksanaan kerja praktik ini adalah sebagai berikut :
1. Melakukan pengecekan dan pemantauan dalam pengerjaan proyek agar sesuai
dengan rencana kerja.
2. Melakukan penggambaran penampang melintang hasil pengerjaan infrastruktur
lapangan, berdasarkan pengambilan data yang telah diperoleh untuk dijadikan
bahan evaluasi pekerjaan yang dilakukan kontraktor proyek.
3. Melakukan perhitungan volume cut and fill pada item pekerjaan tanah guna
pelaporan pada instansi terkait pada waktu yang ditentukan.
II.3. Tatakala Pelaksanaan Kegiatan
Jadwal kegiatan magang dimulai pukul 07.00 dan diakhiri pukul 23.00, dengan
rincian seperti disajikan pada Tabel 1.1.
Tabel 1.1. Jadwal kegiatan per-hari

Pukul Kegiatan
07.00-08.00 Sarapan
08.00-09.00 Briefing persiapan kerja lapangan
09.00-12.00 Pelaksanaan kerja lapangan
12.00-13.30 ISHOMA
13.30-16.30 Pelaksanaan kerja lapangan
16.30-20.00 Bersih diri & ISHOMA
20.00-23.00 Pengolahan data

8
Jadwal kegiatan magang dilaksanakan pada tanggal 15 Juli – 31 Agustus 2020, dengan rincian seperti pada Tabel 1.2.
Tabel 1.2. Jadwal kegiatan per-minggu
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5
Minggu 6 Minggu 7
NO Kegiatan
1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7
1 Perkenalan
Orientasi
2
Lapangan
Analisis
3
Shop Drawing
Pengukuran
4
lapangan
Pengawasan
5
lapangan
Penggambaran
6
penampang
Perhitungan
7
volume

8 Laporan

Pelaporan akhir
9 & Penyerahan
cendera mata

9
II.4. Persiapan
II.4.1. Alat
a. Teodolit
b. Tripod
c. Bak ukur
d. Alat tulis kantor
e. Laptop
f. Printer
g. AutoCAD Civil 3D 2018
h. Microsoft Excel
II.4.2. Bahan
a. Penampang melintang area pembangunan Embung Sigit Kabupaten Sragen
b. Shop Drawing
II.5. Tahapan Kerja
Tahapan kerja untuk pelaksanaan kegiatan pengukuran volume cut and fill menggunakan
metode penampang rata-rata ditunjukkan seperti pada gambar 1.5.

Gambar 1.5. Tahapan Kerja

10
II.6. Proses Pengumpulan Data
Proses pengumpulan data dilakukan oleh surveyor dilapangan dengan
menggunakan alat Teodolit. Pengukuran lapangan dilakukan setiap hari kamis dan
jumat atau menyesuaikan perintah dari atasan jika akan melakukan pemantauan progres
pembuatan Embung Sigit Kabupaten Sragen.
Pengukuran lapangan dilakukan untuk mendapakan data koordinat X,Y dan Z
titik atau spot penggalian atau timbunan yang dilakukan kontraktor, sehingga dapat
dilakukan kontrol seberapa cepat pekerjaan lapangan yang dilakukan. Data yang
diperoleh kemudian dilakukan plotting pada AutoCAD Civil 3D 2018 diatas shop
drawing dan profil melintang untuk mengetahui hasil galian dan timbunan di lapangan.
II.7. Proses Pengolahan Data
II.7.1. Plotting Data Hasil Pengukuran Lapangan
1. Menyusun data lapangan kedalam Ms. Excel yang kemudian dilakukan
penyimpanan (Save As) dalam format CSV (Comma Delimated) dengan susunan
X,Y, Z. Seperti disajikan pada Tabel 1.3.
Tabel 1.3. Format Penyusunan di Ms. Excel
X Y Z
658.891 1112.113 148.695
659.508 1116.334 148.329
659.608 1124.954 147.988
660.312 1133.413 147.819
660.65 1141.661 147.701
654.853 1143.326 148.932
651.053 1143.576 149.926
644.664 1145.763 151.232
640.038 1147.927 151.68
628.57 1153.596 152.314
627.323 1146.65 152.154
626.652 1137.877 152.001
626.034 1126.896 152.039
624.698 1110.67 152.304
2. Membuka AutoCAD Civil 3D 2018 Civil 3D 2018

11
3. Membuka Shop Drawing dalam format DWG. Seperti disajikan pada Gambar 1.6.

Gambar 1.6. Shop Drawing Embung Sigit


4. Plotting data lapangan yang sudah disusun pada Ms. Excel dalam format CVS
dengan menggunakan Create From Point. Seperti disajikan pada Gambar 1.7.

Gambar 1.7. Progres Galian


5. Melakukan plotting pada profil melintang, dihubungkan dengan tanah existing agar
dapat diketahui luas penampangnya. Seperti disajikan pada Gambar 1.8. Progres
galian pada profil melintang

12
Gambar 1.8. Progres Galian pada Profil Melintang
II.7.2. Plotting Data Hasil Pengukuran Lapangan
1. Menghitung luas penampang setiap STA pada AutoCAD Civil 3D 2018
2. Membuka Ms. Excel membuat tabel dengan format seperti pada Tabel 1.4.
Tabel 1.4. Format tabel perhitungan Volume di Ms.Excel
JARAK LEBAR LEBAR
VOLUME
NO. PATOK ANTAR PATOK PENAMPANG RATA-RATA
(m3)
m' m2 m2
1.96
STA 0
25.00 7.59 189.75
STA 0+25 13.21
25.00 24.85 621.25
STA 0+50 36.49
25.00 32.94 823.50
STA 0+75 29.39

JUMLAH 2,036.25

3. Untuk formula yang digunakan pada tabel tersebut ialah sebagai beikut:

Tabel 1.5. Formula Perhitungan Volume


Lebar rata-rata =ROUND((D11+D13)/2,2)

Volume =ROUND((C12*E12),2)

Keterangan Round digunakan untuk membulatkan hasil


perhitungan ke sejumlah digit yang diinginkan

13
BAB III
HASIL DAN PEMBAHASAN
Dalam BAB ini akan diterangkan mengenai hasil perhitungan volume pekerjaan tanah
tiap minggu dan analisis hasil penggunaan metode perhitungan volume penampang rata-rata
selama pelaksanaan Kerja Praktik.

III.1 Hasil Pengumpulan dan Pengolahan Data


Hasil keluaran dari pelaksanaan pengukuran sebagai quantity surveyor Konsultan
Pengawas di Embung Sigit Kecamatan Tangen Kabupaten Sragen sebagai berikut:
1. Data Ukuran dan Olahan Ukuran Lapangan,
2. Gambar Plot Tampak Atas,
3. Gambar Penampang Melintang,
4. Hitungan Volume Cut and Fill.
III.1.1 Data Pengukuran dan Pengolahan Ukuran Lapangan
a. Pengukuran Minggu 1
Pada minggu pertama pengukuran lapangan, dilakukan kegiatan pengukuran
pengawalan (monitoring) penggalian sisi utara dari rencana pembangunan dengan
relief muka bumi berbentuk punggungan bukit. Penggalian dilakukan untuk
mendapatkan elevasi sesuai dengan shop drawing sebesar +152,00 m untuk
lintasan jogging track. Hasil data ukur disajikan pada Tabel 2.1

14
Tabel 2.1 Data Ukur Minggu 1
VA HA Azimuth Bacaan Bak Ukur Jarak ∆H D SIN Az D COS Az Koordinat
SA TA
DD DD D M S DD BA BB BT X Y Z
BM2 512.820 1012.820 160.164
214.4317
TL1 577.981 1107.873 155.720
1.295 K10A 94.6844 230.9778 85 24 34.26328 85.4095 1036 580 808 45.296 -3.225 45.15056331 3.625179518 623.132 1111.498 152.496
K10B 94.7008 232.2211 86 39 10.26328 86.6529 1490 1010 1250 47.678 -3.876 47.59628502 2.783683925 625.577 1110.656 151.845
K10' 94.6661 240.5025 94 56 3.263285 94.9342 1242 758 1000 48.080 -3.629 47.90152532 -4.135447039 625.883 1103.737 152.091
K9A 93.6933 229.0061 83 26 16.26328 83.4379 1280 1050 1165 22.905 -1.348 22.75450301 2.617553598 600.736 1110.490 154.372
K9B 96.6561 236.9831 91 24 53.26328 91.4148 2326 2080 2203 24.269 -3.740 24.26209764 -0.599221822 602.243 1107.273 151.980
J10 97.2192 249.7625 104 11 39.26328 104.1942 1582 1298 1440 27.952 -3.686 27.09815559 -6.853988851 605.079 1101.019 152.035
M10A 94.2483 232.5736 87 0 19.26328 87.0054 880 720 800 15.912 -0.687 15.89046628 0.831295954 593.872 1108.704 155.033
M10B 96.8650 245.8153 100 14 49.26328 100.2470 2690 2510 2600 17.743 -3.441 17.45982602 -3.15631232 595.441 1104.716 152.279
S10 96.9697 262.2036 116 38 7.263285 116.6354 2460 2250 2355 20.691 -3.589 18.49503268 -9.275899643 596.476 1098.597 152.131
L8A 95.6917 281.5361 135 58 4.263285 135.9679 1412 1328 1370 8.317 -0.904 5.781094015 -5.97977977 583.762 1101.893 154.816
L8B 101.4378 286.9656 141 23 50.26328 141.3973 2460 2340 2400 11.528 -3.437 7.192576662 -9.009112908 585.174 1098.863 152.283
L8' 103.6067 293.6172 148 2 56.26328 148.0490 984 816 900 15.870 -3.446 8.398422549 -13.4658779 586.380 1094.407 152.274
K8A 94.0058 344.2639 198 41 44.26328 198.6956 1234 1166 1200 6.767 -0.379 -2.169039779 -6.40976223 575.812 1101.463 155.341
K8B 98.6394 333.6597 188 5 29.26328 188.0915 3008 2892 2950 11.338 -3.378 -1.595900339 -11.22537147 576.385 1096.647 152.343
J9 98.7831 326.4061 180 50 16.26328 180.8379 2284 2116 2200 16.408 -3.440 -0.239934274 -16.40654815 577.741 1091.466 152.280
L9A 89.3022 17.1981 231 37 47.26328 231.6298 1556 1444 1500 11.198 -0.069 -8.779680989 -6.951258643 569.202 1100.921 155.652
L9B 98.1250 357.8667 212 17 54.26328 212.2984 2824 2676 2750 14.504 -3.526 -7.750102628 -12.26020502 570.231 1095.612 152.195
L9' 98.1081 346.2028 200 38 4.263285 200.6345 2248 2062 2155 18.230 -3.457 -6.424352906 -17.06049936 571.557 1090.812 152.263
L10A 91.4633 22.5231 236 57 17.26328 236.9548 873 627 750 24.584 -0.083 -20.60727106 -13.40564538 557.374 1094.467 155.637
L10B 94.3014 11.3564 225 47 17.26328 225.7881 3228 2972 3100 25.456 -3.720 -18.24599099 -17.75080793 559.735 1090.122 152.001
L10' 94.3097 3.8628 218 17 40.26328 218.2945 3240 2972 3106 26.649 -3.819 -16.51427624 -20.91481482 561.467 1086.958 151.901
L11' 93.4039 8.1133 222 32 42.26328 222.5451 3260 2940 3100 31.887 -3.702 -21.56116168 -23.49274877 556.420 1084.380 152.019
L11B 93.4481 15.4178 229 50 58.26328 229.8495 3352 3048 3200 30.290 -3.730 -23.15229698 -19.53093432 554.829 1088.342 151.990

15
a. Pengukuran Minggu 2
Pada minggu kedua pengukuran, dilakukan kegiatan pengukuran pengawalan (monitoring) penimbunan sisi selatan dari rencana
pembangunan dengan relief muka bumi lebih rendah dari relief sekitarnya. Penimbunan dilakukan untuk mendapatkan elevasi sesuai
dengan shop drawing sebesar +152,00 m pada lintasan jogging track. Hasil pengukuran disajikan pada Tabel 2.2
Tabel 2.2 Data Ukur Minggu 2
VA HA Azimuth Bacaan Bak Ukur Jarak ∆H D SIN Az D COS Az Koordinat
SA TA
DD DD D M S DD BA BB BT X Y Z

TL4 468.694 1062.969 160.574

318.6554
BM2 512.820 1012.820 160.164
1.18 101 96.0908 129.5817 88 14 13.26328 88.2370 1250 356 803 88.394 -9.055 88.35166935 2.719425718 601.172 1015.539 151.109
102 96.6283 126.9425 85 35 52.26328 85.5979 1840 952 1396 87.617 -10.398 87.35837392 6.725156639 600.178 1019.545 149.766
103 96.7506 124.7531 83 24 30.26328 83.4084 1740 864 1302 86.390 -10.348 85.81853598 9.916783706 598.639 1022.737 149.816
104 96.9308 123.6875 82 20 34.26328 82.3429 2434 1568 2001 85.339 -11.195 84.57801696 11.37099171 597.398 1024.191 148.969
105 97.2322 123.0333 81 41 19.26328 81.6887 2238 1362 1800 86.212 -11.560 85.30620525 12.46203627 598.126 1025.282 148.604
106 97.9367 122.2261 80 52 53.26328 80.8815 1944 1060 1502 86.715 -12.411 85.61874856 13.74231563 598.439 1026.562 147.753
107 97.9439 120.1694 78 49 29.26328 78.8248 1850 958 1404 87.496 -12.433 85.83726168 16.95763543 598.657 1029.778 147.731
108 97.9550 119.0631 77 43 6.263285 77.7184 3038 2162 2600 85.922 -13.427 83.95575617 18.27706387 596.776 1031.097 146.737
109 96.7033 132.8533 91 30 31.26328 91.5087 1528 872 1200 64.706 -7.625 64.68373348 -1.703613961 577.504 1011.116 152.539
110 96.7408 131.8194 90 28 29.26328 90.4748 1724 1080 1402 63.513 -7.729 63.51053438 -0.526307476 576.331 1012.294 152.435
111 96.7353 130.7169 89 22 20.26328 89.3723 2322 1678 2000 63.514 -8.321 63.51035873 0.695816383 576.330 1013.516 151.843
112 96.7592 128.3236 86 58 44.26328 86.9790 2420 1780 2100 63.113 -8.400 63.02573368 3.326244661 575.846 1016.146 151.764
113 98.5600 125.7781 84 26 0.263285 84.4334 1626 974 1300 63.756 -9.717 63.45484146 6.184450516 576.275 1019.004 150.447
114 90.5972 121.3356 79 59 27.26328 79.9909 2122 1478 1800 64.393 -1.291 63.41295336 11.19179221 576.233 1024.012 158.873
115 99.6728 117.3833 76 2 19.26328 76.0387 3030 2380 2705 63.165 -12.291 61.29901394 15.23960821 574.119 1028.060 147.873
116 102.3639 108.3592 67 0 52.26328 67.0145 2942 2468 2705 45.227 -11.439 41.63600195 17.66098507 554.456 1030.481 148.725
117 105.1903 78.2247 36 52 48.26328 36.8801 3268 2944 3106 30.176 -10.119 18.10958857 24.13718636 530.930 1036.957 150.045

16
118 105.2778 78.4544 37 6 35.26328 37.1098 1936 1664 1800 25.311 -7.534 15.27152491 20.18540173 528.092 1033.005 152.630
119 105.372 85.4611 44 6 59.26328 44.1165 2102 1898 2000 18.966 -6.035 13.20283838 13.61644181 526.023 1026.436 154.129
120 105.548 89.3464 48 0 6.263285 48.0017 904 704 804 18.563 -4.789 13.79531604 12.42059986 526.615 1025.241 155.375
121 105.746 96.2853 54 56 26.26328 54.9406 1674 1522 1598 14.081 -4.388 11.52571767 8.088206218 524.346 1020.908 155.776
122 104.009 98.4342 57 5 22.26328 57.0895 1366 1234 1300 12.426 -3.220 10.43221911 6.751612916 523.252 1019.572 156.944
123 94.7253 139.5708 98 13 34.26328 98.2262 2088 1712 1900 37.345 -3.807 36.96059703 -5.343346322 549.781 1007.477 156.357
124 96.1158 136.7630 95 25 6.263285 95.4184 2190 1810 2000 37.569 -4.845 37.40081116 -3.547540433 550.221 1009.272 155.319
125 96.1286 130.0122 88 40 3.263285 88.6676 2300 1910 2105 38.555 -5.065 38.54505984 0.89653608 551.365 1013.717 155.099
126 98.4131 128.4183 87 4 25.26328 87.0737 1598 1202 1400 38.752 -5.951 38.7017836 1.978369408 551.522 1014.798 154.213
127 98.4172 122.5558 81 12 40.26328 81.2112 2700 2300 2500 39.143 -7.112 38.68330412 5.980760087 551.503 1018.801 153.052
128 99.3958 121.1436 79 47 56.26328 79.7990 2604 2198 2401 39.518 -7.760 38.89324761 6.998727193 551.713 1019.819 152.404
129 100.832 113.1261 71 46 53.26328 71.7815 2420 1980 2200 42.446 -9.142 40.31810991 13.2703766 553.138 1026.090 151.022
130 101.725 111.5500 70 12 19.26328 70.2054 2328 1872 2100 43.717 -9.993 41.13376911 14.80472882 553.954 1027.625 150.171
131 101.835 109.4736 68 7 44.26328 68.1290 2428 1972 2200 43.682 -10.174 40.53780119 16.27229386 553.358 1029.092 149.990

b. Pengukuran Minggu 3
Pada minggu ketiga pengukuran, dilakukan kegiatan pengukuran pengawalan (monitoring) penimbunan area vasum (area bangunan
operasional embung) dan penggalian main dam sisi utara. Hasil pengukuran disajikan pada Tabel 2.3

17
Tabel 2.3 Data Ukur Minggu 3
VA HA Azimuth Bacaan Bak Ukur Jarak ∆H D SIN Az D COS Az Koordinat
SA TA
DD DD D M S DD BA BB BT X Y Z
BM 2 512.820 1012.820 160.164

CP 1 670.372 1089.563 148.157


1.271 244 1 46.263 244.0295
1 87.7367 88.516 332 32 45.263 332.5459 2000 1744 1872 25.560 0.409 -11.78415922 22.68151069 658.588 1112.244 148.566
2 87.7181 89.093 333 7 20.263 333.1223 1800 1544 1672 25.559 0.618 -11.55509551 22.79832048 658.817 1112.361 148.775
3 85.2969 82.130 326 9 34.263 326.1595 2500 2274 2387 22.448 0.731 -12.50093898 18.6451684 657.871 1108.208 148.888
4 85.3356 83.142 327 10 17.263 327.1715 2100 1880 1990 21.855 1.064 -11.8479187 18.36427666 658.524 1107.927 149.221
5 80.7428 75.482 319 30 42.263 319.5117 3900 3690 3795 20.457 0.810 -13.28228422 15.55801068 657.090 1105.121 148.967
6 82.6119 76.473 320 30 9.263 320.5026 2300 2100 2200 19.669 1.621 -12.51053051 15.17787581 657.862 1104.741 149.779
7 82.6397 66.666 310 41 43.263 310.6954 3100 2904 3002 19.278 0.759 -14.61658483 12.57018302 655.756 1102.133 148.916
8 82.8389 58.726 302 45 20.263 302.7556 3200 3030 3115 16.736 0.259 -14.07458704 9.055033452 656.298 1098.618 148.416
9 82.7692 69.403 313 25 56.263 313.4323 1400 1220 1310 17.715 2.209 -12.86428729 12.17889453 657.508 1101.742 150.366
10 82.7456 59.244 303 16 23.263 303.2731 1700 1550 1625 14.761 1.525 -12.34099795 8.098237784 658.031 1097.661 149.682
11 82.9044 47.979 292 0 31.263 292.0087 1400 1262 1331 13.589 1.632 -12.59913339 5.092601805 657.773 1094.656 149.789
12 83.0025 34.172 278 12 5.263 278.2015 2100 1970 2035 12.807 0.808 -12.67607639 1.826980687 657.696 1091.390 148.965
13 83.8178 22.453 266 28 56.263 266.4823 2300 2174 2237 12.454 0.383 -12.43040917 -0.764131886 657.942 1088.799 148.540
14 83.5361 8.411 252 26 26.263 252.4406 3300 3176 3238 12.243 -0.580 -11.67239019 -3.693592489 658.700 1085.869 147.577
15 87.7439 355.107 239 8 12.263 239.1367 3100 2958 3029 14.178 -1.199 -12.17030544 -7.273182355 658.202 1082.290 146.958
16 87.8708 1.748 245 46 40.263 245.7779 2500 2344 2422 15.578 -0.572 -14.20696368 -6.391465101 656.165 1083.172 147.585
17 87.7269 21.771 265 48 0.263 265.8001 2400 2250 2325 14.976 -0.460 -14.93618593 -1.096825764 655.436 1088.466 147.698
18 87.6517 35.817 279 50 48.263 279.8467 2400 2248 2324 15.174 -0.431 -14.95094084 2.595037994 655.421 1092.158 147.726
19 86.9111 48.376 292 24 20.263 292.4056 2500 2338 2419 16.153 -0.276 -14.9335517 6.156882205 655.439 1095.720 147.881
20 83.1058 74.331 318 21 36.263 318.3601 3700 3450 3575 24.640 0.675 -16.37183538 18.41418013 654.001 1107.977 148.832
21 82.9419 59.461 303 29 25.263 303.4904 3300 3086 3193 21.077 0.688 -17.57768459 11.63015902 652.795 1101.193 148.845
22 85.2006 49.162 293 11 28.263 293.1912 3400 3194 3297 20.456 -0.308 -18.80288144 8.055500966 651.569 1097.618 147.849

18
23 85.0694 33.303 277 19 56.263 277.3323 3400 3192 3296 20.646 -0.244 -20.47751613 2.634962942 649.895 1092.198 147.913
24 85.1014 15.616 259 38 42.263 259.6451 3700 3476 3588 22.237 -0.411 -21.8744963 -3.996936142 648.498 1085.566 147.746
25 87.9753 13.113 257 8 32.263 257.1423 2800 2502 2651 29.763 -0.328 -29.01652135 -6.623130977 641.356 1082.940 147.829
26 88.0569 26.156 270 11 9.263 270.1859 2500 2230 2365 26.969 -0.179 -26.96881798 0.087505491 643.404 1089.650 147.978
27 87.2814 40.905 284 56 3.263 284.9342 2600 2346 2473 25.343 0.001 -24.48683299 6.531114252 645.886 1096.094 148.158
28 87.3683 55.649 299 40 44.263 299.6790 1800 1552 1676 24.748 0.732 -21.5011474 12.25357677 648.871 1101.817 148.890
29 83.9539 68.676 312 42 19.263 312.7054 3500 3234 3367 26.305 0.690 -19.33018546 17.84072451 651.042 1107.404 148.847
30 83.9878 66.572 310 36 6.263 310.6017 1900 1618 1759 27.891 2.449 -21.17600335 18.15114542 649.196 1107.714 150.607
31 84.3406 87.173 331 12 7.263 331.2020 1500 1222 1361 27.530 2.638 -13.26165816 24.1248789 657.111 1113.688 150.795
32 84.4992 43.122 287 9 6.263 287.1517 1200 922 1061 27.545 2.863 -26.31955503 8.122976357 644.053 1097.686 151.020
33 85.2592 28.108 272 8 14.263 272.1373 1400 1110 1255 28.802 2.405 -28.78186963 1.074143779 641.590 1090.637 150.562
34 85.2819 17.660 261 41 22.263 261.6895 1800 1488 1644 30.989 2.185 -30.66351345 -4.479052357 639.709 1085.084 150.342
41 85.4156 74.458 318 29 15.263 318.4876 3300 2570 2935 72.534 4.152 -48.07402339 54.31405696 622.298 1143.877 152.309
42 85.3933 78.288 322 19 3.263 322.3176 3300 2634 2967 66.170 3.636 -40.44892767 52.36798442 629.923 1141.931 151.793
43 85.4569 83.281 327 18 39.263 327.3109 3200 2588 2894 60.816 3.209 -32.84553171 51.18360216 637.527 1140.747 151.366
44 86.3011 88.718 332 44 51.263 332.7476 2000 1440 1720 55.767 3.156 -25.5363236 49.57667724 644.836 1139.140 151.313
45 87.0594 96.326 340 21 21.263 340.3559 1600 1096 1348 50.267 2.505 -16.89870417 47.34175368 653.474 1136.905 150.662
46 87.0844 93.759 337 47 19.263 337.7887 1200 774 987 42.490 2.448 -16.06214386 39.33687265 654.310 1128.900 150.605
47 86.3833 85.649 329 40 44.263 329.6790 1600 1138 1369 46.016 2.811 -23.23101118 39.72162165 647.141 1129.285 150.968
48 86.3528 78.661 322 41 27.263 322.6909 1700 1182 1441 51.590 3.118 -31.26968786 41.03382081 639.103 1130.597 151.276
49 85.4922 73.457 317 29 11.263 317.4865 2800 2220 2510 57.642 3.305 -38.95222819 42.48873803 631.420 1132.052 151.462
50 84.7511 68.145 312 10 27.263 312.1742 3600 2938 3269 65.646 4.033 -48.65065786 44.07388168 621.722 1133.637 152.190
51 84.7958 62.162 306 11 28.263 306.1912 3000 2378 2689 61.688 4.201 -49.78557942 36.42577377 620.587 1125.989 152.358
52 85.2508 65.530 309 33 35.263 309.5598 2500 1952 2226 54.424 3.567 -41.95902055 34.66195654 628.413 1124.225 151.724
53 84.4100 69.888 313 55 1.263 313.9170 3000 2522 2761 47.346 3.144 -34.10578271 32.84024437 636.267 1122.403 151.301
54 84.4419 75.645 319 40 27.263 319.6742 2600 2190 2395 40.615 2.828 -26.28354271 30.96425696 644.089 1120.527 150.985
55 84.6736 86.316 330 20 42.263 330.3451 2100 1762 1931 33.509 2.464 -16.5792914 29.11979624 653.793 1118.683 150.621
56 84.7258 77.403 321 25 57.263 321.4326 1800 1492 1646 30.540 2.444 -19.03955671 23.87827001 651.333 1113.441 150.601
57 84.5336 70.451 314 28 48.263 314.4801 2100 1750 1925 34.682 2.665 -24.74567721 24.30059772 645.627 1113.864 150.822

19
58 84.5981 61.661 305 41 26.263 305.6906 2600 2170 2385 42.619 2.916 -34.61417583 24.86422476 635.758 1114.427 151.073
59 84.6017 56.352 300 22 52.263 300.3812 2500 1992 2246 50.350 3.783 -43.43624986 25.46472583 626.936 1115.028 151.940
60 84.6300 52.864 296 53 36.263 296.8934 2500 1920 2210 57.492 4.465 -51.27422121 26.00547825 619.098 1115.568 152.622

c. Pengukuran Minggu 4
Pada minggu keempat pengukuran, dilakukan kegiatan pengukuran pengawalan (monitoring) penggalian final jogging track sisi
utara karena adanya revisi shop drawing berupa perluasan badan embung sisi utara. Disajikan pada Tabel 2.4
Tabel 2.4 Data Ukur Minggu 4
VA HA Azimuth Bacaan Bak Ukur Jarak ∆H D SIN Az D COS Az Koordinat
SA TA
DD DD D M S DD BA BB BT X Y Z

BM2 512.820 1012.820 160.164

205.38091

TL5 553.227 1097.989 156.767

1.218 1 93.6542 241.0516 86 25 57.26328 86.432573 1700 976 1338 72.106 -4.725 71.966187 4.4866549 625.193 1102.476 152.042

2 93.3472 234.5855 79 57 59.26328 79.966462 1800 1062 1431 73.548 -4.515 72.42356 12.813943 585.244 1025.634 152.253

4 93.6578 240.9161 86 17 49.26328 86.297018 2500 1878 2189 61.947 -4.931 61.817514 4.0007906 574.638 1016.821 151.836

5 93.6236 232.128 77 30 32.26328 77.508962 2200 1602 1901 59.561 -4.455 58.15131 12.882292 570.971 1025.702 152.313

6 94.6633 240.6375 86 1 6.263285 86.018406 2000 1474 1737 52.252 -4.781 52.126209 3.6281924 564.946 1016.448 151.986

7 94.6492 232.113 77 29 38.26328 77.493962 2000 1490 1745 50.665 -4.647 49.462823 10.971113 562.283 1023.791 152.120

8 94.7289 240.5797 85 57 38.26328 85.960629 2300 1828 2064 46.879 -4.724 46.762751 3.3022622 559.583 1016.122 152.043

9 94.7364 232.0958 77 28 36.26328 77.47674 2200 1736 1968 46.084 -4.568 44.987223 9.99259 557.807 1022.813 152.199

10 94.8089 240.4022 85 46 59.26328 85.783129 2500 2080 2290 41.705 -4.581 41.591929 3.0666338 554.412 1015.887 152.187

11 92.8883 231.1527 76 32 1.263285 76.533684 3900 3504 3702 39.499 -4.477 38.413493 9.198382 551.233 1022.018 152.291

12 96.0581 243.3591 88 44 24.26328 88.740073 2100 1730 1915 36.588 -4.580 36.579053 0.8044984 549.399 1013.624 152.187

13 96.1467 232.5736 77 57 16.26328 77.954518 2200 1850 2025 34.599 -4.533 33.836945 7.2203434 546.657 1020.040 152.234

20
14 97.7511 253.4641 98 50 42.26328 98.845073 2200 1920 2060 27.491 -4.584 27.163755 -4.2270552 539.984 1008.593 152.184

15 97.5992 237.6694 83 3 1.263285 83.050351 2700 2462 2581 23.384 -4.483 23.211983 2.8293694 536.032 1015.649 152.285

16 100.7028 261.5111 106 53 31.26328 106.89202 1600 1364 1482 22.786 -4.571 21.802916 -6.6209146 534.623 1006.199 152.197

17 100.8131 243.3327 88 42 49.26328 88.713684 2400 2214 2307 17.945 -4.516 17.940838 0.4028475 530.761 1013.223 152.251

18 104.6397 288.4436 133 49 28.26328 133.82452 1700 1524 1612 16.476 -4.698 11.886663 -11.408668 524.707 1001.411 152.070

19 106.4033 273.0877 118 28 7.263285 118.46868 3000 2886 2943 10.491 -4.813 9.222291 -5.0007709 522.042 1007.819 151.954

20 103.8822 334.4183 179 47 57.26328 179.79924 1900 1716 1808 17.341 -4.876 0.0607608 -17.3407 512.881 995.479 151.892

21 103.6636 348.2377 193 37 7.263285 193.61868 3456 3344 3400 10.575 -4.753 -2.4899879 -10.277711 510.330 1002.542 152.015

22 101.2475 344.4355 189 48 59.26328 189.81646 2298 2102 2200 18.854 -4.732 -3.2145269 -18.578299 509.605 994.242 152.036

23 101.5456 1.19555 206 34 35.26328 206.57646 3464 3336 3400 12.287 -4.692 -5.4972126 -10.988953 507.323 1001.831 152.075

24 93.5306 30.9869 236 22 4.263285 236.36785 4066 3734 3900 33.074 -4.723 -27.537845 -18.318381 485.282 994.502 152.045

25 96.8219 19.1322 224 30 47.26328 224.51313 1788 1412 1600 37.069 -4.817 -25.988396 -26.433866 486.832 986.386 151.951

26 95.8447 20.0247 225 24 20.26328 225.40563 1300 1200 1250 9.896 -1.045 -7.0471065 -6.9480255 505.773 1005.872 155.722

27 95.7275 8.588 213 58 8.263285 213.96896 1537 1463 1500 7.326 -1.017 -4.0935239 -6.0759961 508.726 1006.744 155.751

28 95.7667 252.6667 98 2 51.26328 98.047573 1450 1382 1416 6.731 -0.878 6.6650599 -0.9423571 519.485 1011.878 155.890

29 95.6525 228.9877 74 22 7.263285 74.368684 500 330 415 16.835 -0.863 16.212441 4.5361483 529.032 1017.356 155.904

30 93.9811 228.3772 73 45 29.26328 73.758129 714 486 600 22.690 -0.961 21.784527 6.3462576 534.605 1019.166 155.806

31 93.0917 226.7294 72 6 37.26328 72.110351 700 360 530 33.901 -1.143 32.261979 10.413899 545.082 1023.234 155.624

32 88.4397 226.5913 71 58 20.26328 71.972295 4004 3596 3800 40.770 -1.471 38.768241 12.617293 551.588 1025.437 155.296

33 93.0081 228.1241 73 30 18.26328 73.505073 980 504 742 47.469 -2.018 45.515331 13.477872 558.335 1026.298 154.749

34 93.0083 228.718 74 5 56.26328 74.098962 1252 744 998 50.660 -2.442 48.721643 13.879679 561.542 1026.700 154.325

35 90.0447 229.4722 74 51 11.26328 74.853129 4800 4200 4500 60.000 -3.329 57.915517 15.677645 570.736 1028.498 153.439

21
d. Pengukuran Minggu 5
Pada minggu kelima pengukuran, dilakukan kegiatan pengukuran pengawalan (monitoring) penggalian final area main dam sisi
utara dan jogging track sisi barat. Hasil pengukuran disajikan pada Tabel 2.5
Tabel 2.5 Data Ukur Minggu 5
VA HA Azimuth Bacaan Bak Ukur Jarak ∆H D SIN Az D COS Az Koordinat
SA TA
DD DD D M S DD BA BB BT X Y Z
BM2 512.82 1012.82 160.164
244.0295
CP1 670.372 1089.563 148.134
1.336
1 87.366 89.147 333 10 34.26328 333.176 2026 1770 1898 25.546 0.613 -11.528 22.797 658.845 1112.360 148.747
2 86.554 83.815 327 50 40.26328 327.845 1826 1600 1713 22.518 0.979 -11.985 19.064 658.388 1108.627 149.113
3 85.592 76.211 320 14 26.26328 320.241 1300 1100 1200 19.882 1.669 -12.716 15.284 657.657 1104.847 149.803
4 83.134 68.418 312 26 50.26328 312.447 1400 1212 1306 18.531 2.261 -13.674 12.507 656.698 1102.070 150.395
5 83.104 64.935 308 57 51.26328 308.964 1100 938 1019 15.966 2.248 -12.415 10.040 657.958 1099.603 150.382
6 83.487 52.054 296 5 0.263285 296.083 1500 1358 1429 14.017 1.507 -12.590 6.163 657.783 1095.726 149.641
7 83.597 40.722 284 45 5.263285 284.751 1200 1064 1132 13.431 1.711 -12.988 3.420 657.384 1092.983 149.845
8 83.786 26.458 270 29 14.26328 270.487 2200 2068 2134 13.045 0.623 -13.045 0.111 657.328 1089.674 148.757
9 83.791 14.695 258 43 27.26328 258.724 2300 2172 2236 12.650 0.476 -12.406 -2.474 657.966 1087.089 148.610
10 90.821 351.431 235 27 38.26328 235.461 2200 2058 2129 14.197 -0.996 -11.695 -8.049 658.678 1081.514 147.138
11 94.061 354.936 238 57 56.26328 238.966 2100 1938 2019 16.119 -1.827 -13.811 -8.310 656.561 1081.253 146.307
12 90.173 15.926 259 57 21.26328 259.956 2300 2156 2228 14.400 -0.935 -14.179 -2.511 656.193 1087.052 147.199
13 90.062 26.593 270 37 19.26328 270.622 2200 2050 2125 15.000 -0.805 -14.999 0.163 655.373 1089.726 147.329
14 87.280 38.650 282 40 46.26328 282.680 2700 2550 2625 14.966 -0.578 -14.601 3.285 655.771 1092.848 147.556
15 87.425 47.605 291 38 3.263285 291.634 2700 2536 2618 16.367 -0.546 -15.214 6.034 655.158 1095.597 147.588
16 86.211 58.631 302 39 39.26328 302.661 2400 2224 2312 17.523 0.185 -14.752 9.457 655.620 1099.020 148.319
17 84.329 65.480 309 30 34.26328 309.510 2700 2516 2608 18.220 0.537 -14.057 11.592 656.315 1101.155 148.671
18 84.394 75.578 319 36 26.26328 319.607 2700 2490 2595 20.800 0.783 -13.479 15.841 656.894 1105.404 148.917

22
19 86.991 81.823 325 51 7.263285 325.852 1900 1672 1786 22.737 0.745 -12.763 18.817 657.609 1108.380 148.879
20 85.647 66.810 310 50 21.26328 310.839 1400 1062 1231 33.605 2.663 -25.424 21.976 644.948 1111.539 150.797
21 85.870 58.627 302 39 22.26328 302.656 1000 662 831 33.625 2.933 -28.309 18.144 642.063 1107.707 151.067
22 85.790 54.499 298 31 42.26328 298.528 900 576 738 32.225 2.970 -28.313 15.391 642.060 1104.954 151.104
23 85.755 49.403 293 25 57.26328 293.433 700 360 530 33.814 3.316 -31.025 13.447 639.347 1103.010 151.450
24 85.753 49.861 293 53 25.26328 293.890 800 470 635 32.819 3.138 -30.007 13.291 640.365 1102.854 151.272
25 85.722 45.006 289 2 7.263285 289.035 600 252 426 34.606 3.499 -32.714 11.287 637.658 1100.850 151.633
26 85.698 39.369 283 23 55.26328 283.399 1000 640 820 35.797 3.209 -34.823 8.295 635.549 1097.858 151.343
27 85.601 35.173 279 12 8.263285 279.202 800 412 606 38.572 3.697 -38.075 6.168 632.297 1095.731 151.831
28 85.538 34.892 278 55 16.26328 278.921 900 516 708 38.168 3.607 -37.706 5.919 632.667 1095.482 151.741
29 85.541 31.014 275 2 38.26328 275.044 2200 1800 2000 39.758 2.437 -39.604 3.496 630.768 1093.059 150.571
30 85.496 27.464 271 29 38.26328 271.494 2300 1872 2086 42.536 2.601 -42.522 1.109 627.851 1090.672 150.735
31 85.504 33.771 277 48 3.263285 277.801 1800 1402 1601 39.555 2.845 -39.189 5.369 631.183 1094.932 150.979
32 87.791 26.201 270 13 51.26328 270.231 1900 1468 1684 43.136 1.316 -43.135 0.174 627.237 1089.737 149.450
33 87.812 23.247 267 16 35.26328 267.276 2600 2142 2371 45.733 0.713 -45.682 -2.173 624.691 1087.390 148.847
34 91.885 20.502 264 31 54.26328 264.532 1800 1372 1586 42.754 -1.657 -42.559 -4.074 627.813 1085.489 146.477
35 92.690 18.604 262 37 59.26328 262.633 2500 2064 2282 43.504 -2.990 -43.145 -5.578 627.227 1083.985 145.144
36 92.583 23.606 267 38 8.263285 267.636 1600 1212 1406 38.721 -1.817 -38.688 -1.597 631.684 1087.966 146.317
37 90.457 31.084 275 6 48.26328 275.113 2800 2468 2634 33.198 -1.563 -33.066 2.959 637.307 1092.522 146.571
38 90.366 33.751 277 46 51.26328 277.781 1900 1578 1739 32.199 -0.609 -31.902 4.359 638.470 1093.922 147.525
39 89.178 38.556 282 35 6.263285 282.585 2500 2198 2349 30.194 -0.580 -29.468 6.579 640.904 1096.142 147.554
40 87.404 44.998 289 1 37.26328 289.027 3400 3120 3260 27.943 -0.657 -26.416 9.110 643.956 1098.673 147.477
41 87.286 51.669 295 41 55.26328 295.699 2800 2520 2660 27.937 0.000 -25.174 12.115 645.198 1101.678 148.134
42 87.274 55.452 299 28 54.26328 299.482 2200 1918 2059 28.136 0.617 -24.493 13.847 645.879 1103.410 148.751
43 87.199 62.243 306 16 22.26328 306.273 2300 2010 2155 28.931 0.596 -23.324 17.116 647.048 1106.679 148.730
44 84.943 66.754 310 46 59.26328 310.783 3300 3000 3150 29.767 0.820 -22.539 19.444 647.833 1109.007 148.954
45 84.947 70.435 314 27 51.26328 314.464 3200 2924 3062 27.386 0.696 -19.545 19.183 650.827 1108.746 148.830
46 84.506 65.954 309 59 0.263285 309.983 3300 3040 3170 25.762 0.644 -19.739 16.554 650.633 1106.117 148.778
47 84.556 56.061 300 5 26.26328 300.091 3116 2874 2995 23.982 0.627 -20.750 12.024 649.622 1101.587 148.761

23
48 87.445 47.544 291 34 26.26328 291.574 3200 2970 3085 22.954 -0.725 -21.346 8.440 649.026 1098.003 147.409
49 87.449 46.165 290 11 41.26328 290.195 3400 3146 3273 25.350 -0.808 -23.791 8.751 646.581 1098.314 147.326
50 87.401 55.972 300 0 6.263285 300.002 2100 1836 1968 26.346 0.564 -22.816 13.174 647.557 1102.737 148.698
51 87.273 59.441 303 28 12.26328 303.470 1900 1680 1790 21.950 0.592 -18.310 12.106 652.062 1101.669 148.726
52 87.118 46.902 290 55 54.26328 290.932 3200 2998 3099 20.149 -0.749 -18.819 7.198 651.553 1096.761 147.385
53 87.151 34.931 278 57 37.26328 278.960 3300 3070 3185 22.943 -0.707 -22.663 3.573 647.709 1093.136 147.427
54 87.293 37.135 281 9 53.26328 281.165 3400 3136 3268 26.341 -0.687 -25.843 5.100 644.530 1094.663 147.447
55 87.311 35.478 279 30 28.26328 279.508 3100 2914 3007 18.559 -0.799 -18.304 3.066 652.068 1092.629 147.335
56 87.318 20.628 264 39 28.26328 264.658 3100 2910 3005 18.958 -0.781 -18.876 -1.765 651.496 1087.798 147.353
57 87.383 27.635 271 39 51.26328 271.664 3200 2960 3080 23.950 -0.649 -23.940 0.696 646.432 1090.259 147.485
58 87.378 31.058 275 5 14.26328 275.087 3400 3110 3255 28.939 -0.593 -28.825 2.566 641.547 1092.129 147.541
59 91.840 27.774 271 48 11.26328 271.803 2300 2002 2151 29.769 -1.771 -29.755 0.937 640.618 1090.500 146.363
60 91.889 20.578 264 36 26.26328 264.607 3100 2850 2975 24.973 -2.463 -24.862 -2.347 645.510 1087.216 145.671
61 90.448 15.247 259 16 36.26328 259.277 3700 3498 3599 20.199 -2.421 -19.846 -3.758 650.526 1085.805 145.713
62 90.298 351.328 235 21 25.26328 235.357 4000 3796 3898 20.399 -2.668 -16.783 -11.596 653.590 1077.967 145.466
63 90.283 3.088 247 7 4.263285 247.118 3900 3686 3793 21.399 -2.563 -19.715 -8.321 650.657 1081.242 145.571
64 90.290 10.882 254 54 42.26328 254.912 3700 3446 3573 25.399 -2.366 -24.524 -6.612 645.849 1082.951 145.768
65 90.237 17.818 261 50 49.26328 261.847 3600 3284 3442 31.599 -2.237 -31.280 -4.481 639.092 1085.082 145.897
66 90.258 16.649 260 40 44.26328 260.679 3500 3122 3311 37.799 -2.145 -37.300 -6.122 633.072 1083.441 145.989
67 90.320 14.700 258 43 47.26328 258.730 4500 4110 4305 38.999 -3.187 -38.247 -7.622 632.126 1081.941 144.947
68 90.468 6.327 250 21 22.26328 250.356 5000 4680 4840 31.998 -3.765 -30.136 -10.757 640.237 1078.806 144.369
69 93.312 5.577 249 36 24.26328 249.607 2000 1700 1850 29.900 -2.244 -28.026 -10.419 642.347 1079.144 145.890
70 93.851 350.977 235 0 22.26328 235.006 3000 2608 2804 39.023 -4.095 -31.968 -22.379 638.404 1067.184 144.039
71 93.780 345.133 229 9 44.26328 229.162 2600 2180 2390 41.817 -3.817 -31.638 -27.345 638.735 1062.218 144.317
72 93.897 343.164 227 11 35.26328 227.193 2800 2396 2598 40.213 -4.001 -29.502 -27.326 640.870 1062.237 144.133
73 94.018 349.513 233 32 32.26328 233.542 2800 2420 2610 37.813 -3.930 -30.413 -22.470 639.959 1067.093 144.204
74 95.794 347.016 231 2 45.26328 231.046 3500 3100 3300 39.592 -5.981 -30.789 -24.892 639.583 1064.671 142.153
CP1 670.372 1089.563 148.134
64.030

24
BM2 512.820 1012.820 160.164
1.363
AS1 99.304 279.469 343 29 56.26328 343.498962 1900 1510 1705 37.981 -6.565 -10.788 36.416 502.032 1049.236 153.599
AS2 102.382 321.061 25 5 26.26328 25.09062869 2600 2120 2360 45.793 -11.050 19.419 41.472 532.239 1054.292 149.114
AS3 98.593 348.129 52 9 30.26328 52.15840647 3100 2320 2710 76.259 -12.870 60.222 46.783 573.042 1059.603 147.294
AS4 97.250 2.836 66 51 55.26328 66.86535091 1900 650 1275 123.009 -15.560 113.117 48.330 625.937 1061.150 144.604
1 98.259 267.200 331 13 46.26328 331.2295176 2500 2130 2315 36.237 -6.212 -17.441 31.763 495.379 1044.583 153.952
2 98.243 270.296 334 19 32.26328 334.3256287 1900 1460 1680 43.096 -6.560 -18.671 38.841 494.149 1051.661 153.604
3 98.214 272.594 336 37 24.26328 336.6234065 1000 480 740 50.939 -6.730 -20.211 46.757 492.609 1059.577 153.434
4 97.028 274.924 338 57 11.26328 338.9531287 2200 1612 1906 57.920 -7.683 -20.801 54.056 492.019 1066.876 152.481
5 96.061 278.622 342 39 6.263285 342.6517398 2700 2050 2375 64.275 -7.836 -19.166 61.352 493.654 1074.172 152.328
6 96.033 292.977 357 0 24.26328 357.0067398 2500 1840 2170 65.271 -7.706 -3.408 65.182 509.412 1078.002 152.458
7 94.979 293.176 357 12 18.26328 357.2050731 2200 1530 1865 66.495 -6.295 -3.242 66.416 509.578 1079.236 153.869
8 94.711 286.439 350 28 5.263285 350.4681287 2000 1308 1654 68.733 -5.956 -11.382 67.784 501.438 1080.604 154.208
9 95.144 286.771 350 48 3.263285 350.8009065 3400 2724 3062 67.057 -7.735 -10.720 66.194 502.100 1079.014 152.429
10 94.387 280.088 344 7 1.263285 344.1170176 1800 1110 1455 68.596 -5.355 -18.773 65.977 494.047 1078.797 154.809
11 92.383 272.919 336 56 54.26328 336.9484065 2000 1320 1660 67.882 -3.122 -26.580 62.462 486.240 1075.282 157.042
12 91.139 267.198 331 13 38.26328 331.2272954 2300 1678 1989 62.175 -1.863 -29.927 54.499 482.893 1067.319 158.301
13 91.144 265.356 329 23 7.263285 329.3853509 2500 1932 2216 56.777 -1.987 -28.915 48.863 483.905 1061.683 158.177
14 91.658 265.240 329 16 11.26328 329.2697954 2300 1736 2018 56.353 -2.286 -28.796 48.440 484.024 1061.260 157.878
15 91.688 265.269 329 17 55.26328 329.2986842 3400 2882 3141 51.755 -3.303 -26.424 44.501 486.396 1057.321 156.861
16 92.075 264.131 328 9 36.26328 328.1600731 3900 3460 3680 43.942 -3.909 -23.182 37.330 489.638 1050.150 156.255
17 95.151 262.304 326 20 2.263285 326.333962 2200 1806 2003 39.082 -4.163 -21.665 32.528 491.155 1045.348 156.001

25
III.1.2 Hasil Plotting Situasi Tampak Atas
a. Hasil Plotting Data Ukur Minggu 1
Hasil progres pengukuran pada minggu pertama adalah galian dari STA 0+00
sampai STA 0+75 dengan kondisi elevasi akhir sesuai shop drawing sebesar
+152,00 m pada bagian jogging track. Disajikan pada Gambar 2.1.

Gambar 2.1. Plot Data Ukur Minggu 1

b. Hasil Plotting Data Ukur Minggu 2


Hasil progres pengukuran pada minggu kedua adalah timbunan dari STA 0+25
sampai STA 0+50 dan galian pada STA 0+50 sampai STA 0+100 dengan kondisi
elevasi akhir rerata + 150,65 m. Kurang ±1,5 meter dari shop drawing sebesar
+152,00 m pada bagian jogging track seperti pada Gambar 2.2.

Gambar 2.2. Plot Data Ukur Minggu 2

26
d. Hasil Plotting Data Ukur Minggu 3
Hasil progres pengukuran pada minggu ketiga adalah timbunan dari area vasum
dengan kondisi elevasi rerata +150,94 m, kurang ±1 meter dari elevasi rencana
+152,00 m, ditambah dengan galian pada main dam untuk dijadikan timbunan
pada jogging track sisi selatan. Penggalian tanah pada main dam bertujuan untuk
mempermudah mobilisasi material tanah sebagai bahan timbunan sisi selatan
proyek. Untuk main dam yang digali akan ditimbun menggunakan tanah yang
didatangkan dari luar dengan mempertimbangan kemudahan mobilisasi dum
truk dan rencana kerja alat berat. Adapun elevasi rencana dari main dam adalah
sebesar +152,00 m seperti pada Gambar 2.3.

Gambar 2.3. Plot Data Ukur Minggu 3


e. Hasil Plotting Data Ukur Minggu 4
Pada minggu keempat pelaksanaan Kerja Praktik terdapat revisi shop drawing
berupa perubahan luasan embung pada sisi utara, sehingga terdapat perubahan
rencana kerja dengan penggalian kembali jogging track sisi utara. Hasil progres
pengukuran pada minggu keempat adalah galian jogging track sisi utara dengan
elevasi tanah sesuai desain plan sebesar +152,00 m, tetapi mengalami
pergeseran ± 3 meter dari rencana awal seperti pada Gambar 2.4.

27
Gambar 2.4. Plot Data Ukur Minggu 4
f. Hasil Plotting Data Ukur Minggu 5
Hasil progres pengukuran pada minggu kelima adalah galian tanah jogging track
sisi barat dan galian maindam untuk dijadikan material timbunan pada jogging
track sisi selatan seperti pada Gambar 2.5.

Gambar 2.5. Plot Data Ukur Minggu 5

28
III.1.3 Hasil Penggambaran Penampang Melintang
a. Progress Minggu 1
Disajikan Tabel 2.6 berupa gambar penampang melintang progres mingggu 1
Tabel 2.6. Gambar Penampang Melintang Data Ukur Minggu 1

Gambar 2.6 Progres Galian M1 pada Gambar 2.7 Progres Galian M1 pada
STA 0+00 STA 0+25

Gambar 2.8 Progres Galian M1 pada Gambar 2.9 Progres Galian M1 pada
STA 0+50 STA 0+75

Pada minggu 1 dilakukan pengukuran lapangan berdasarkan progres pengerjaan


galian jogging track sebelah utara. Didapatkan hasil ukuran progres pengerjaan
berada di atas empat garis STA yakni, STA 0+00 gambar 2.6, STA 0+25 gambar
2.7, STA 0+50 gambar 2.8, STA 0+75 gambar 2.9. Warna merah mengindikasikan
rencana pengerjaan galian, sedangkan warna biru mengindikasikan pengerjaan
timbunan.
b. Progress Minggu 2
Disajikan Tabel 2.7 berupa gambar penampang melintang progres mingggu 2
Tabel 2.7. Gambar Penampang Melintang Data Ukur Minggu 2

Gambar 2.10 Progres Galian M2 pada Gambar 2.11 Progres Galian M2 pada
STA 0+25 STA 0+50

29
Gambar 2.12 Progres Galian M2 pada Gambar 2.13 Progres Galian M2 pada
STA 0+75 STA 1+00

Pada minggu 2 dilakukan pengukuran lapangan berdasarkan progres pengerjaan


galian dan timbunan jogging track sebelah selatan. Didapatkan hasil ukuran progres
pengerjaan timbunan berada sepanjang STA 0+25 gambar 2.10 hingga STA 0+50
gambar 2.11. Progres pengerjaan galian berada sepanjang STA 0+75 gambar 2.12
hingga STA 0+100 gambar 2.13.
c. Progress Minggu 3
Disajikan Tabel 2.8 berupa gambar penampang melintang progres mingggu 3
Tabel 2.8. Gambar Penampang Melintang Data Ukur Minggu 3

Gambar 2.14 Progres Galian M3 pada Gambar 2.15 Progres Galian M3 pada
STA 0+00 STA 0+010

Gambar 2.16 Progres Galian M3 pada


STA 0+15

Pada minggu 3 dilakukan pengukuran lapangan berdasarkan progres pengerjaan


galian main dam sebelah sisi utara. Didapatkan hasil ukuran progres pengerjaan
penggalian main dam melalui skema perhitungan STA berinterval 10 m

30
menggunakan topografi yang dibuat khusus untuk main dam sepanjang STA 0+00
gambar 2.14, STA 0+10 gambar 2.15, hingga STA 0+15 gambar 2.16.
d. Progress Minggu 4
Disajikan Tabel 2.9 berupa gambar penampang melintang progres mingggu 4
Tabel 2.9. Gambar Penampang Melintang Data Ukur Minggu 4

Gambar 2.17 Progres Galian M4 pada STA Gambar 2.18 Progres Galian M4 pada
0+00 STA 0+25

Gambar 2.19 Progres Galian M4 pada STA Gambar 2.20 Progres Galian M4 pada
0+50 STA 0+75

Gambar 2.21 Progres Galian M4 pada STA


1+00

Pada minggu 4 dilakukan pengukuran lapangan berdasarkan progres pengerjaan


galian jogging track sebelah utara untuk kedua kalinya. Didapatkan hasil ukuran
progres pengerjaan galian berada di atas lima garis STA yakni, STA 0+00 gambar
2.17, STA 0+25 gambar 2.18, STA 0+50 gambar 2.19, STA 0+75 gambar 2.20, STA
0+100 gambar 2.21.

31
e. Progress Minggu 5
Disajikan Tabel 2.10 berupa gambar penampang melintang progres mingggu 5
Tabel 2.10. Gambar Penampang Melintang Data Ukur Minggu 5

Gambar 2.22 Progres Galian M4 pada SA Gambar 2.23 Progres Galian M4 pada
0+00 SA 0+015

Pada minggu kelima, dilakukan


penggalian main dam lanjutan melalui
skema perhitungan STA yang sam dengan
interval 10 m.
Gambar 2.24 Progres Galian M4 pada SA
0+030

Pada minggu 5 dilakukan pengukuran lapangan berdasarkan progres pengerjaan


galian main dam lanjutan. Didapatkan hasil ukuran progres pengerjaan penggalian
main dam melalui skema perhitungan STA berinterval 15 m menggunakan topografi
yang dibuat khusus untuk main dam sepanjang STA 0+00 gambar 2.22, STA 0+15
gambar 2.23, hingga STA 0+30 gambar 2.24.

32
III.1.4 Hitungan Volume Cut And Fill
a. Perhitungan volume pada minggu pertama disajikan pada rangkaian table berikut ;
Tabel 2.11. Perhitungan Luas Penampang M1 STA 0+00
Sketch Drawing Calculation : Luas Penampang Patok STA 0+00 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi utara
Patok STA 0+00 Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1282.340 34.561 - 0.00
2 1282.340 34.468 44199.695 44318.953 m2
3 1289.259 34.468 44199.695 44438.179 m2
4 1289.521 34.496 44474.278 44447.210 m2
5 1289.525 34.794 44867.594 44483.454 m2
6 1282.340 34.561 44567.274 44617.738 m2
Amount 222308.536 222305.534 m2
1280.000 1282.000 1284.000 1286.000 1288.000 1290.000
Area = (a-b)/2 1.501 m2

Tabel 2.12. Perhitungan Luas Penampang M1 STA 0+25


Sketch Drawing Calculation : Luas Penampang Patok STA 0+25 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi utara
Patok STA 0+25 m Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1467.588 34.503 - 0.000
2 1471.850 34.468 50584.823 50783.241 m2
3 1473.850 36.665 53965.380 50800.662 m2
4 1473.850 37.068 54632.672 54038.710 m2
5 1471.689 36.853 54315.794 54552.568 m2
6 1468.031 35.262 51894.698 54101.346 m2
7 1467.588 35.197 51670.287 51750.088 m2
8 1467.588 34.503 50636.189 51654.695 m2
1466.000 1468.000 1470.000 1472.000 1474.000 1476.000 Amount 367699.843 367681.310 m2
Area = (a-b)/2 9.266 m2

33
Tabel 2.13. Perhitungan Luas Penampang M1 STA 0+50
Sketch Drawing Calculation : Luas Penampang Patok STA 0+50 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi utara
Patok STA 0+50 m Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1635.378 34.788 - 0.00
2 1640.56 34.811 56929.144 57071.801 m2
3 1645.376 37.531 61571.857 57277.184 m2
4 1644.697 37.355 61463.020 61727.123 m2
5 1635.623 36.935 60746.884 61098.697 m2
6 1635.372 36.801 60192.562 60402.465 m2
7 1635.378 34.788 56891.321 60183.546 m2
Amount 357794.79 357760.82 m2
1634 1636 1638 1640 1642 1644 1646
Area = (a-b)/2 16.985 m2

Tabel 2.14. Perhitungan Luas Penampang M1 STA 0+75


Sketch Drawing Calculation : Luas Penampang Patok STA 0+75 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi utara
Patok STA 0+75 m Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1802.321 36.487 - 0.00
2 1806.284 36.468 65727.04 65905.88 m2
3 1806.281 39.533 71407.83 65871.46 m2
4 1806.006 39.305 70995.87 71396.84 m2
5 1802.795 38.610 69729.89 70858.86 m2
6 1802.321 38.543 69485.13 69587.61 m2
7 1802.321 36.487 65761.29 69466.86 m2
Amount 413107.05 413087.50 m2
1802.000 1803.000 1804.000 1805.000 1806.000 1807.000
Area = (a-b)/2 9.772 m2

34
Tabel 2.15. Rekapitulasi Perhitungan Volume Minggu 1
REKAP PERHITUNGAN VOLUME`
VOLUME (m3)
JARAK ANTAR PATOK LEBAR PENAMPANG LEBAR RATA-RATA KETERANGAN
NO. PATOK {Jarak X Lebar Rata”}
m m2 m2
STA 0+00 1.501
25 5.383 134.575 Galian
STA 0+25 9.266
25 13.085 327.125 Galian
STA 0+50 16.895
25 21.756 543.900 Galian
STA 0+75 9.722
JUMLAH 1005.6 Galian

b. Perhitungan volume pada minggu kedua disajikan pada rangkaian table berikut :
Tabel 2.16. Perhitungan Luas Penampang M2 STA 0+25
Sketch Drawing Calculation : Luas Penampang Patok STA 0+25 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi selatan
Patok STA 0+25 m
Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1381.71 32.62 - 0.00
2 1381.71 33.00 45600.50912 45074.04575 m2
3 1383.84 34.47 47624.67688 45671.00353 m2
4 1392.78 34.47 47698.33499 48006.47891 m2
5 1393.26 34.25 47701.45922 48022.71334 m2
6 1393.26 30.01 41804.61628 47717.62474 m2
7 1391.93 30.37 42310.39821 41764.97967 m2
8 1388.72 30.98 43120.72339 42172.64896 m2
9 1387.44 31.45 43671.07784 42981.47278 m2
1380.00 1385.00 1390.00 1395.00 10 1386.35 31.51 43711.2657 43596.54845 m2
11 1384.89 32.28 44756.9234 43631.08547 m2
12 1381.71 32.62 45178.01207 44607.06107 m2

35
Amount 493178.00 493245.66 m2
Area = (a-b)/2 33.827 m2

Tabel 2.17. Perhitungan Luas Penampang M2 STA 0+50


Sketch Drawing Calculation : Luas Penampang Patok STA 0+50 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi selatan
Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
Patok STA 0+50 m
1 1571.974 30.341 0.000 0.000
2 1571.974 31.913 50166.406 47695.263 m2
3 1567.676 33.968 53396.813 50029.244 m2
4 1566.632 34.468 54034.656 53215.356 m2
5 1556.256 34.466 53995.539 53641.032 m2
6 1557.428 34.301 53381.137 53678.313 m2
7 1560.059 34.232 53313.875 53511.584 m2
8 1562.917 32.915 51349.342 53501.775 m2
9 1567.676 32.493 50783.862 51600.056 m2
1555.000 1560.000 1565.000 1570.000 1575.000 10 1571.974 30.341 47564.858 51078.151 m2
Amount 467986.49 467950.77 m2
Area = (a-b)/2 17.860 m2

Tabel 2.18. Perhitungan Luas Penampang M2 STA 0+75


Sketch Drawing Calculation : Luas Penampang Patok STA 0+75 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi selatan
Distance Elevation a b
Patok STA 0+75 m Point
(x) (y) = xi * (yi+1) = (xi+1) * yi
Sat.
1 1725.294 39.825 0.000 0.000 m2
2 1725.294 40.938 70630.086 68709.834 m2
3 1725.834 40.881 70531.744 70652.192 m2
4 1728.750 40.378 69685.725 70673.029 m2
5 1730.609 39.433 68169.799 69878.530 m2
6 1733.381 39.029 67543.939 68352.413 m2
1722.000 1728.000 1734.000 1740.000 1746.000 1752.000
7 1736.868 38.189 66196.087 67788.221 m2
8 1739.419 37.738 65545.925 66426.672 m2

36
9 1743.886 36.201 62968.707 65810.770 m2
10 1747.357 34.594 60327.992 63256.071 m2
11 1748.295 34.366 60049.671 60480.517 m2
12 1748.295 33.193 58031.156 60081.906 m2
13 1746.907 34.458 60242.749 57985.084 m2
14 1745.439 34.639 60511.112 60144.337 m2
15 1743.906 35.490 61945.630 60407.160 m2
16 1737.638 36.872 64301.302 61668.773 m2
17 1736.617 37.520 65196.178 64032.542 m2
18 1732.624 38.681 67174.082 65008.052 m2
19 1725.294 39.825 69001.751 66736.097 m2
Amount 1168053.63 1168092.20 m2
Area = (a-b)/2 19.288 m2

Tabel 2.19. Perhitungan Luas Penampang M2 STA 1+00


Sketch Drawing Calculation : Luas Penampang Patok STA 1+00 m
Excavation by Machinery Section Pekerjaan : Jogging track sisi selatan
Distance Elevation a b
Patok STA 1+00 m Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1944.208 32.473 0 0 m2
2 1944.208 33.873 65856.16 63134.27 m2
3 1943.728 33.967 66038.91 65839.90 m2
4 1940.881 35.062 68150.99 65925.90 m2
5 1934.805 36.596 71028.48 67838.13 m2
6 1932.495 37.091 71763.85 70721.59 m2
7 1933.691 36.597 70723.52 71722.53 m2
8 1940.258 35.098 67868.69 71007.62 m2
1930 1932 1934 1936 1938 1940 1942 1944 1946
9 1944.208 32.473 63006.00 68237.81 m2
Amount 544436.60 544427.76 m2
Area = (a-b)/2 4.419 m2

37
Tabel 2.20. Rekapitulasi Perhitungan Volume Minggu 2
REKAP PERHITUNGAN VOLUME`
VOLUME (m3)
JARAK ANTAR PATOK LEBAR PENAMPANG LEBAR RATA-RATA KETERANGAN
NO. PATOK {Jarak X Lebar Rata”}
m m2 m2
STA 0+25 33.827
25 25.843 646.075 Timbunan
STA 0+50 17.860
25 18.574 464.350 Galian & Timbunan
STA 0+75 19.288
25 11.853 296.325 Galian
STA 1+00 4.419
878.25 Timbunan
JUMLAH
528.50 Galian

c. Perhitungan volume pada minggu ketiga disajikan pada rangkaian table berikut :
Tabel 2.21. Perhitungan Luas Penampang M3 STA 0+00
Sketch Drawing Calculation : Luas Penampang Patok SA 0+00 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Patok SA 0+00 m Point
Distance Elevation a b
Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1925.947 29.4950 0.0000 0 m2
2 1926.134 29.5890 56986.8458 56811.32233 m2
3 1926.669 30.0440 57868.7699 57008.20904 m2
4 1930.776 31.2340 60177.5795 58008.23414 m2
5 1944.118 32.4720 62696.1583 60722.58161 m2
6 1946.189 32.7620 63693.1939 63196.64921 m2

1920 1925 1930 1935 1940 1945 1950 1955 7 1946.743 32.6790 63599.5103 63779.19417 m2
8 1950.286 31.8920 62085.5278 63733.39619 m2
9 1950.704 31.7760 61972.2879 62211.85197 m2
10 1950.703 31.6890 61815.8591 61985.53853 m2

38
11 1947.517 32.2470 62904.3196 61714.86621 m2
12 1940.437 32.1000 62515.2957 62573.27194 m2
13 1934.166 31.4330 60993.7562 62086.7286 m2
14 1931.575 31.0080 59974.6193 60715.19698 m2
15 1925.947 29.4950 56971.8046 59719.76458 m2
Amount 854255.53 854266.81 m2
Area = (a-b)/2 5.634 m2

Tabel 2.22. Perhitungan Luas Penampang M3 STA 0+10


Sketch Drawing Calculation : Luas Penampang Patok SA 0+10 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Distance Elevation a B
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 2026.55 30.5080 0.0000 0 m2
Patok SA 0+10 m 2 2026.551 30.2140 61230.1817 61826.01791 m2
3 2033.182 30.3810 61568.6459 61430.56095 m2
4 2038.603 30.3170 61639.9787 61934.79774 m2
5 2042.178 31.3130 63834.7757 61912.71043 m2
6 2048.962 31.3000 63920.1714 64159.14711 m2
7 2048.962 32.1560 65886.4221 64132.5106 m2
8 2047.745 32.5220 66636.3422 65847.28822 m2
9 2046.217 32.5680 66690.9592 66547.06927 m2
10 2043.061 33.0570 67641.7954 66538.41065 m2
2025 2030 2035 2040 2045 2050 2055 11 2031.122 31.6530 64669.0098 67142.79995 m2
12 2029.236 31.4270 63832.0711 64231.40711 m2
13 2026.735 30.5450 61983.0136 63694.20085 m2
14 2026.55 30.5080 61831.6314 61900.96975 m2
Amount 831365.00 831297.89 m2
Area = (a-b)/2 33.555 m2

39
Tabel 2.23. Perhitungan Luas Penampang M3 STA 0+15
Sketch Drawing Calculation : Luas Penampang Patok STA 0+15 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Distance Elevation a B
Point Sat.
Patok SA 0+15 m (x) (y) = xi * (yi+1) = (xi+1) * yi
1 2128.611 30.9490 0.0000 0 m2
2 2133.155 30.4460 64807.6905 66019.0141 m2
3 2139.598 30.6260 65330.0050 65142.20071 m2
4 2145.321 31.3580 67093.5141 65702.60095 m2
5 2150.908 31.3150 67180.7271 67448.17306 m2
6 2150.905 32.7850 70517.5188 67355.59008 m2
7 2150.807 32.8170 70586.2494 70514.2075 m2
8 2146.542 33.0010 70978.7818 70443.06881 m2
9 2144.041 33.3970 71688.0632 70755.49704 m2
10 2135.76 32.5630 69816.4071 71327.97672 m2
2125 2130 2135 2140 2145 2150 2155
11 2131.958 32.1710 68709.5350 69422.94835 m2
12 2128.611 30.9490 65981.9681 68479.54448 m2
Amount 752690.46 752610.82 m2
Area = (a-b)/2 39.819 m2

Tabel 2.24. Rekapitulasi Perhitungan Volume Minggu 3


REKAP PERHITUNGAN VOLUME`
VOLUME (m3)
JARAK ANTAR PATOK LEBAR PENAMPANG LEBAR RATA-RATA KETERANGAN
NO. PATOK {Jarak X Lebar Rata”}
m m2 m2
SA 0+00 5.634
10 19.594 195.94 Galian
SA 0+10 33.555
5 36.687 183.435 Galian
SA 0+15 39.819
JUMLAH 379.375 Galian

40
d. Perhitungan volume pada minggu keempat disajikan pada rangkaian table berikut :
Tabel 2.25. Perhitungan Luas Penampang M4 STA 0+00
Sketch Drawing Calculation : Luas Penampang Patok STA 0+00 m
Excavation by Machinery Section Pekerjaan : penggalian jogging track utara
Patok STA 0+00 m Point
Distance Elevation a b
Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1281.180 34.468 0.000 0.000 m2
2 1281.180 34.523 44230.177 44159.712 m2
3 1289.386 34.789 44570.971 44513.473 m2
4 1289.385 34.721 44768.771 44856.415 m2
5 1281.180 34.468 44442.522 44483.851 m2
Amount 178012.44 178013.45 m2
1280.000 1282.000 1284.000 1286.000 1288.000 1290.000
Area = (a-b)/2 0.509 m2

Tabel 2.26. Perhitungan Luas Penampang M4 STA 0+25


Sketch Drawing Calculation : Luas Penampang Patok STA 0+25 m
Excavation by Machinery Section Pekerjaan : penggalian jogging track utara
Patok STA 0+25 m Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1463.54 34.608 0 0 m2
2 1463.54 34.468 50445.30 50650.19 m2
3 1470.138 34.667 50736.54 50672.72 m2
4 1473.623 37.045 54461.26 51086.09 m2
5 1471.689 36.853 54307.43 54518.72 m2
6 1468.031 35.262 51894.70 54101.35 m2
7 1463.54 34.608 50805.62 51607.35 m2
1462 1464 1466 1468 1470 1472 1474 1476
Amount 312650.84 312636.41 m2
Area = (a-b)/2 7.215 m2

41
Tabel 2.27. Perhitungan Luas Penampang M4 STA 0+50
Sketch Drawing Calculation : Luas Penampang Patok STA 0+50 m
Excavation by Machinery Section Pekerjaan : penggalian jogging track utara
Distance Elevation a b
Patok STA 0+50 m Point
(x) (y) = xi * (yi+1) = (xi+1) * yi
Sat.
1 1635.43 34.468 0 0 m2
2 1635.43 36.832 60236.15776 56370.00124 m2
3 1635.623 36.935 60404.60705 60243.26634 m2
4 1644.697 37.355 61098.69717 60746.8837 m2
5 1645.652 37.603 61845.54129 61473.33046 m2
6 1647.728 37.691 62026.26953 61959.51598 m2
7 1644.731 34.667 57121.78658 61991.55612 m2

1634 1636 1638 1640 1642 1644 1646 1648 1650 8 1635.43 34.468 56690.58811 56695.45181 m2
Amount 419423.65 419480.01 m2
Area = (a-b)/2 28.179 m2

Tabel 2.28. Perhitungan Luas Penampang M4 STA 0+75


Sketch Drawing Calculation : Luas Penampang Patok STA 0+75 m
Excavation by Machinery Section Pekerjaan : penggalian jogging track utara
Distance Elevation a b
Patok STA 0+75 m Point
(x) (y) = xi * (yi+1) = (xi+1) * yi
Sat.
1 1797.8240 36.468 0 0 m2
2 1797.8230 37.155 66798.1507 65563.00916 m2
3 1797.8850 37.165 66816.0918 66800.41718 m2
4 1799.2130 38.105 68508.4079 66867.75115 m2
5 1802.7950 38.61 69467.6139 68695.50348 m2
6 1806.0060 39.305 70858.8575 69729.89166 m2
7 1806.8960 40.043 72317.8983 71020.04728 m2
8 1809.0930 40.11 72474.5986 72441.511 m2
9 1809.6840 40.19 72707.4477 72586.42524 m2
10 1805.6570 36.483 66022.7014 72569.35483 m2
1796.0000 1800.0000 1804.0000 1808.0000 1812.0000
11 1797.8240 36.468 65848.6995 65590.01299 m2
Amount 691820.47 691863.92 m2
Area = (a-b)/2 21.726 m2

42
Tabel 2.29. Perhitungan Luas Penampang M4 STA 1+00
Sketch Drawing Calculation : Luas Penampang Patok STA 1+00 m
Excavation by Machinery Section Pekerjaan : pemggalian jogging track utara
Patok STA 1+00 m Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1984.254 34.468 0 0 m2
2 1984.43 34.563 68581.771 68399.33324 m2
3 1986.926 34.899 69254.62257 68674.12334 m2
4 1986.926 34.483 68515.16926 69341.73047 m2
5 1984.254 34.468 68485.36537 68423.03068 m2
1984 1984.5 1985 1985.5 1986 1986.5 1987 1987.5
Amount 274836.93 274838.22 m2
Area = (a-b)/2 0.645 m2

Tabel 2.30. Rekapitulasi Perhitungan Volume Minggu 4


REKAP PERHITUNGAN VOLUME`
VOLUME (m3)
JARAK ANTAR PATOK LEBAR PENAMPANG LEBAR RATA-RATA KETERANGAN
NO. PATOK {Jarak X Lebar Rata”}
m m2 m2
STA 0+00 0.509
25 3.862 48.275 Galian
STA 0+25 7.215
25 17.697 442.425 (-327.125) =115.300* Galian
STA 0+50 28.179
25 24.952 623.800 (-543.900) = 79.9* Galian
STA 0+75 21.726
25 11.185 279.637 Galian
STA 1+00 0.645
JUMLAH 523.112 Galian
*Dikurangi volume progress minggu pertama untuk mendapatkan volume progres minggu keempat pada volume STA 0+25 - 0+50 dan STA
0+50 - 0+75 karena pada lokasi yang sama.

43
e. Perhitungan volume pada minggu kelima disajikan pada rangkaian table berikut :
Tabel 2.31. Perhitungan Luas Penampang M5 STA 0+00
Sketch Drawing Calculation : Luas Penampang Patok SA 0+00 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 1929.344 32.8300 0.0000 0 m2
2 1929.344 31.3150 60417.4074 63340.36352 m2
Patok SA 0+00 3 1931.69 31.9180 61580.8018 60490.87235 m2
4 1932.626 33.2030 64137.9031 61685.55667 m2
5 1935.012 33.0390 63852.0304 64248.20344 m2
6 1936.886 33.4470 64720.3464 63992.77655 m2
7 1939.812 33.8110 65488.0525 64880.89196 m2
8 1949.66 33.5350 65051.5954 65919.95426 m2
9 1949.664 33.5930 65494.9284 65381.98224 m2
10 1938.622 34.2590 66793.5390 65124.12885 m2
11 1938.494 34.2790 66454.0235 66410.86595 m2
1925 1930 1935 1940 1945 1950 1955 12 1938.143 34.2520 66397.2965 66437.6039 m2
13 1937.527 34.2020 66288.3669 66364.1748 m2
14 1931.478 33.2110 64347.2092 66060.41056 m2
15 1929.707 32.9350 63613.2279 64087.49918 m2
16 1929.344 32.8300 63352.2808 63542.94464 m2
Amount 967989.01 967968.23 m2
Area = (a-b)/2 10.394 m2

44
Tabel 2.32. Perhitungan Luas Penampang M5 STA 0+15
Sketch Drawing Calculation : Luas Penampang Patok SA 0+15 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 2026.815 29.266 0.000 0.000 m2
2 2026.832 26.837 54393.634 59317.265 m2
3 2033.107 28.365 57491.090 54562.493 m2
4 2038.525 28.831 58616.508 57822.762 m2
5 2040.155 30.009 61174.097 58819.709 m2
6 2042.689 29.915 61031.237 61299.054 m2
Patok SA 0+15 7 2046.340 29.794 60859.876 61216.261 m2
8 2050.762 31.166 63776.232 61100.403 m2
9 2054.142 31.246 64078.109 64019.390 m2
10 2056.771 31.298 64290.536 64265.867 m2
11 2056.769 32.551 66949.953 64372.756 m2
12 2055.536 32.930 67729.403 66909.752 m2
13 2050.538 33.105 68048.519 67524.216 m2
14 2048.306 33.454 68598.698 67809.170 m2
2025.000 2030.000 2035.000 2040.000 2045.000 2050.000 2055.000 2060.000 15 2040.276 32.560 66692.843 68255.393 m2
16 2036.468 32.128 65549.987 66307.398 m2
17 2031.198 30.153 61405.620 65258.329 m2
18 2029.543 29.867 60665.791 61196.810 m2
19 2029.137 29.627 60129.270 60604.235 m2
20 2027.389 29.348 59551.113 60065.454 m2
21 2026.815 29.266 59333.566 59482.967 m2
Amount 1250366.08 1250209.68 m2
Area = (a-b)/2 78.202 m2

45
Tabel 2.33. Perhitungan Luas Penampang M5 STA 0+30
Sketch Drawing Calculation : Luas Penampang Patok SA 0+30 m
Excavation by Machinery Section Pekerjaan : penggalian maindam sisi utara
Distance Elevation a b
Point Sat.
(x) (y) = xi * (yi+1) = (xi+1) * yi
1 2128.65 28.7750 0.0000 0 m2
2 2134.449 29.6670 63150.6596 61418.76998 m2
3 2137.071 31.2250 66648.1700 63400.48536 m2
4 2140.38 31.3910 67084.7958 66833.3655 m2
5 2143.123 31.5640 67558.9543 67274.77409 m2
Patok SA 0+30 6 2152.802 31.3850 67261.9154 67951.04233 m2
7 2155.577 31.3490 67488.1899 67652.78415 m2
8 2155.577 31.8850 68730.5726 67575.18337 m2
9 2153.839 32.3500 69732.9160 68675.15652 m2
10 2153.733 32.3510 69678.8455 69673.26255 m2
11 2150.463 32.8390 70726.4380 69569.62851 m2
12 2142.303 31.6440 68049.2512 70351.08822 m2
13 2135.412 31.1350 66700.6039 67572.97733 m2
14 2131.276 30.0160 64096.5266 66357.27826 m2
15 2131.241 30.0090 63957.4615 63971.32986 m2
2125 2130 2135 2140 2145 2150 2155 2160 16 2130.968 29.8190 63551.4754 63948.21871 m2
17 2130.938 29.7840 63468.7509 63542.44022 m2
18 2130.042 29.2300 62287.3177 63441.17093 m2
19 2128.65 28.9880 61745.6575 62220.4395 m2
20 2128.65 28.7750 61251.9038 61705.3062 m2
21 2128.65 28.7750 61251.9038 61251.90375 m2
Amount 1314422.31 1314386.61 m2
Area = (a-b)/2 17.849 m2

46
Tabel 2.34. Rekapitulasi Perhitungan Volume Minggu 5
REKAP PERHITUNGAN VOLUME`
VOLUME (m3)
JARAK ANTAR PATOK LEBAR PENAMPANG LEBAR RATA-RATA KETERANGAN
NO. PATOK {Jarak X Lebar Rata”}
m m2 m2
SA 0+00 10.934
15 44.568 668.52 (-379.375) = 289.145 Galian
SA 0+15 78.202
15 48.205 720.382 Galian
SA 0+30 17.849
JUMLAH 1388.902 Galian
*Dikurangi progress minggu ketiga untuk mendapatkan volume progres minggu kelima pada SA 0+00 - 0+15 karena pada lokasi yang sama.

47
III.2 Analisis Pengukuran dan Perhitungan Volume Progres
Pada perhitungan volume di atas didapatkan hasil yang disajikan pada tabel 2.35.
Tabel 2.35. Hasil Volume 5 Minggu
Minggu Volume Timbunan Volume Galian
1 - 1005.6 m³
2 878.25 m³ 528.50 m³
3 - 379.375 m³
4 - 523.112 m³
5 - 1388.902 m³
Jumlah Total 878. 25 m³ 3825.489 m³

Volume total yang didapatkan adalah sebesar 3825.489 m³ untuk galian dan 878.25
m³ untuk timbunan pada progress perhitungan volume tanah sampai minggu ke 5.
Pada perhitungan volume tanah hakikatnya memang tidak dapat dihitung secara pasti
berapa besar volume galian atau timbunan tanah yang didapatkan. Hal ini disebabkan
belum ada alat ukur pasti yang benar-benar akurat untuk menghitung besar volume
tanah, tetapi ada beberapa metode yang dapat digunakan untuk perhitungan volume
tanah. Pada kegiatan kontruksi, perhitungan volume banyak menggunakan
penampang rata-rata karena lebih mudah dan sesuai jika menggunakan aplikasi
AutoCAD, berbeda dengan bidang lain yang menggunakan perhitungan surface
seperti pertambangan Pada kegiatan praktik ini menggunakan metode penampang
rata-rata, yang dirasa penulis memiliki banyak kekurangan, antara lain :

1. Pada pengukuran ini jarak antar STA terlampau jauh, yakni sebesar 25 m. Hal ini
akan menyebabkan adanya volume hilang atau tidak terhitung karena jarak
pengambilan topografi yang jauh, sehingga topografi diantara kedua STA tidak
akan terhitung sempurna. Dalam artian, apabila topografi di antara STA relief nya
lebih tinggi (gundukan) dari kedua STA, maka akan terjadi volume hilang atau
kurang dari besar semestinya pada perhitungan volume. Sebaliknya apabila
topografi di antara kedua STA relief nya lebih rendah (cekungan) maka akan
terjadi kelebihan volume pada perhitungan volume. Padahal relief pada lokasi
proyek adalah perbukitan dengan banyak gundukan dan lereng menjorok.
2. Apabila perhitungan volume berada diantara dua penampang STA yang berbeda
(sisi pertama timbunan dan sisi yang lain galian), maka akan terjadi keambiguan
atau ketidakjelasan besar volume galian dan timbunan pada perhitungan volume
antar STA karena tidak adanya kejelasan pasti letak perbatasan timbunan dan
galian. Sehingga pada metode ini, besar volume galian dan timbunan dianggap

48
sama atau besar volume dibagi dua sama besarnya seperti pada perhitungan
volume minggu kedua diantara STA 0+25 dan 0+50.
3. Pada perhitungan volume dua penampang STA dengan jangkauan (terbesar
dikurangi terkecil) luas penampang sangat besar, maka akan terjadi lonjakan atau
pengurangan volume yang besar dari volume yang didapatkan, seperti pada
minggu ke 4 antara STA 0+75 dan 1+00.

Semua hasil analisis di atas akan berpengaruh terhadap kerugian atau keuntungan
proyek jika melihat pada Rencana Anggaran yang sudah disusun bilamana perbedaan
dengan besar volume sebenarnya terlampau besar. Selain fakta tersebut pada hasil
perhitungan volume per pekan, sering terjadi perbedaan hasil akhir volume yang
didapatkan antara kontraktor proyek dengan konsultan pengawas. Hal ini disebabkan
oleh beberapa factor sebagai berikut :
a. Pembuatan beberapa titik BM yang dilakukan oleh kontraktor berada di dalam area
pembangunan proyek. Sehingga ketika dilakukan penggalian tanah di beberapa
area titik tersebut hilang dan menyisakan dua buah titik BM. Hal ini tidak sesuai
dengan standar pengukuran yang ada, dan menjadi masalah dan mempersulit di
kemudian hari.
b. Sisa BM acuan yang digunakan kontraktor berada pada area tanah yang labil
sehingga rawan terjadi pergeseran dan distorsi ketika melakukan pengukuran,.
Akibatnya ketika praktikan melakukan uji coba pergeseran titik BM, pada salah
satu titik BM mengalami pergeseran sejauh 3 cm. Dari sisa titik BM tersebut,
praktikan mengikat dan membentuk sebuah poligon untuk membuat poligon
tertutup sehingga dapat dilakukan pengurangan kesalahan distorsi dan ada
perbedaan hasil pengukuran cukup besar.
c. Alat yang digunakan oleh konsultan pengawas memiliki ketelitian lebih kecil dari
kontraktor yakni berupa Teodolit, sehingga sulit untuk memastikan besar
perhitungan volume yang mendekati nilai sesungguhnya .
d. Penggunaan alat survey yang tidak dipahami oleh surveyor kontraktor membuat
akuisisi data dilakukan secara manual dengan menuliskan nilai koordinat pada
sebuah catatan, sehingga dimungkinkan terjadinya human error walaupun
menggunakan alat Total Station. Hal ini terjadi akibat kesalahan dalam melakukan
penyewaan alat yang tidak dikuasai sepenuhnya oleh surveyor, sehingga tidak
dapat melakukan save otomatis data dan pembuatan file job.

49
BAB IV
PENUTUP

IV.1. Kesimpulan
Dari hasil kegiatan kerja praktik ini dapat disimpulkan bahwa pengaplikasian
pengetahuan yang telah diperoleh selama kegiatan perkuliahan di kampus cukup
berbeda dengan pengaplikasian yang dilakukan ketika kegiatan kerja praktik di CV
Karya Gemilang. Hal ini disebabkan karena teori dan praktikum yang diperoleh di
perkuliahan hanya pada konteks pengukuran dasarnya saja. Ada banyak pengetahun
dan problem yang akan muncul ketika terjun langsung di dunia pekerjaan
sesungguhnya. Dengan adanya kerja praktik ini akan memberikan gambaran dan
tantangan kepada praktikan untuk siap dalam menyelesaikan permasalahan yang akan
muncul di pekerjaan lapangan sesungguhnya, sehingga dapat mencarikan solusi yang
terbaik. Hal tersebut juga dapat dijadikan tolak ukur kemampuan praktikan dalam
memahami ilmu di lingkup pekerjaan geodesi dan geomatika.

IV.2. Saran
Selama penulis melakukan kegiatan kerja praktik sampai dengan penyusunan laporan
ini, ada beberapa saran yang didasarkan pada kesulitan penulis dalam pelaksanaan
kegiatan tersebut. Adapun saran-saran yang dapat penulis berikan dalam penyusunan
laporan Kerja Praktek ini sebagai berikut :

1. Dalam melakukan pengukuran lapangan sebagai seorang quantity survey, penulis


menyarankan untuk menggunakan alat ukur yang memiliki ketelitian sebanding
atau lebih tinggi agar data yang dihasilkan lebih akurat dan presisi. Selain itu lebih
cepat dalam proses pengambilan data dan akurat ketika melakukan pengawalan
kegiatan pengukuran
2. Dalam pembuatan titik-titik BM acuan perlu memperhatikan pemilihan lokasi dan
keamanan titik, sehingga tidak terjadi hal-hal yang tidak diinginkan seperti titik
hilang yang akan merugikan ketika proyek sudah berjalan. Untuk itu tetap perlu
dilakukan checking guna memastikan koordinat yang dipakai sudah tepat serta hasil
pengukuran presisi dan akurat, karena keamanan titik BM akan sangat berpengaruh
terhadap kevalidan data hasil pengukuran.

50
DAFTAR PUSTAKA

Adi, S. (2019). ANALISIS DAN KARAKTERISASI BADAN AIR SUNGAI,. Badan


Pengkajian dan Penerapan Teknologi.
Basuki, S. (2011). ILMU UKUR TANAH. Yogyakarta: Gadjah Mada University Press.
Gultom, R. I., Rassarandi, F. D., & Siagian, G. P. (2020). PERHITUNGAN VOLUME
GALIAN DAN TIMBUNAN DENGAN METODE. Seminar Nasional Terapan Riset
Inovatif (SENTRINOV).
Hidayat. (2014). K-LEVEL: APLIKASI HITUNG KERANGKA KONTROL VERTIKAL
BERDASARKAN METODE KUADRAT TERKECIL. Geomatika.
Susetyo, D. B., Yuniar, H. T., & Saputra, L. R. (2013). STANDARISASI APLIKASI
SURVEY PEMETAAN. Forum Ilmiah Tahunan Ikatan Surveyor Indonesia, 3.

51
LAMPIRAN