Anda di halaman 1dari 54

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII

NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018

NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018

TANGGAL SPMK : 17 Oktober 2018

TAHUN ANGGARAN : 2018 - 2023

REKAPITULASI KUANTITAS DAN HARGA

AMOUNT
BoQ
URAIAN ITEM PEKERJAAN
KONTRAK AMENDEMEN NO 2 Bobot
Keterangan
(Rp) (Rp) (%)
No.

(1) (2) (3) (4) (5) (6)

I PEKERJAAN PERSIAPAN 3,133,180,800.00 3,133,180,800.00 0.320%

II BENDUNGAN UTAMA 967,258,216,933.00 967,258,216,699.20 98.738%


III JETTY DAN TRASHBOOM 4,474,392,095.00 4,474,392,095.00 0.457%

IV ALAT PENUNJANG OP 1,767,646,500.00 1,767,646,500.00 0.180%

V. PEKERJAAN LAIN-LAIN 2,985,307,620.00 2,985,307,620.00 0.305%

TOTAL 979,618,743,948.00 979,618,743,714.20 100.000%


VAT 10 % Not Borne 97,961,874,394.80 97,961,874,371.42

GRAND TOTAL 1,077,580,618,342.80 1,077,580,618,085.62

DIAJUKAN OLEH
HUTAMA - BASUKI, KSO
( Kontraktor )

Lanjar Samadi, ST
Manajer Proyek
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

BILL OF QUANTITY ( BOQ ) MC - 0


BALANCE
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan Bertambah Berkurang REMARK
No. Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Jumlah ( RP ) Volume Jumlah ( RP )
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 - -- - --
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, b Ls 1.000 495,000,000.00 495,000,000.00 0.0505 1.000 495,000,000.00 495,000,000.00 0.0505 - -- - --
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 103,713,500.00 103,713,500.00 0.0106 1.000 103,713,500.00 103,713,500.00 0.0106 - -- - --
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 66,000,000.00 66,000,000.00 0.0067 1.000 66,000,000.00 66,000,000.00 0.0067 - -- - --
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 165,038,500.00 165,038,500.00 0.0168 1.000 165,038,500.00 165,038,500.00 0.0168 - -- - --
1.6 Fasilitas Komunikasi Ls 1.000 150,928,800.00 150,928,800.00 0.0154 1.000 150,928,800.00 150,928,800.00 0.0154 - -- - --
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 148,500,000.00 148,500,000.00 0.0152 1.000 148,500,000.00 148,500,000.00 0.0152 - -- - --

Jumlah I 3,133,180,800.00 0.3198 3,133,180,800.00 0.3198 - -


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.000 955,105,000.00 955,105,000.00 0.0975 1.000 955,105,000.00 955,105,000.00 0.0975 - -- - --

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 8,900.00 800,816,482.00 0.0817 137,786.640 8,900.00 1,226,301,096.00 0.1252 47,807.260 425,484,614.00 - --
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 53,900.00 34,175,289,610.00 3.4886 582,344.610 53,900.00 31,388,374,479.00 3.2041 - -- 51,705.290 2,786,915,131.00
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 107,800.00 75,650,264,844.00 7.7224 711,447.200 107,800.00 76,694,008,160.00 7.8290 9,682.220 1,043,743,316.00 - --
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m3 824,179.170 103,000.00 84,890,454,510.00 8.6657 824,179.170 103,000.00 84,890,454,510.00 8.6657 - -- - --
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 136,700.00 77,111,517,201.00 7.8716 564,093.030 136,700.00 77,111,517,201.00 7.8716 - -- - --
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 226,300.00 406,145,307,988.00 41.4595 1,800,543.504 226,300.00 407,462,994,955.20 41.5940 5,822.744 1,317,686,967.20 - --

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.020 44,500.00 25,102,139,390.00 2.5624 564,093.020 44,500.00 25,102,139,390.00 2.5624 - -- - --
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 157,200.00 13,540,536,756.00 1.3822 86,135.730 157,200.00 13,540,536,756.00 1.3822 - -- - --
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.730 220,500.00 18,992,928,465.00 1.9388 86,135.730 220,500.00 18,992,928,465.00 1.9388 - -- - --
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.540 72,700.00 47,178,776,958.00 4.8160 648,951.540 72,700.00 47,178,776,958.00 4.8160 - -- - --
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.100 44,700.00 49,794,776,370.00 5.0831 1,113,977.100 44,700.00 49,794,776,370.00 5.0831 - -- - --
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.720 72,700.00 46,100,939,844.00 4.7060 634,125.720 72,700.00 46,100,939,844.00 4.7060 - -- - --
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.540 92,000.00 10,604,521,680.00 1.0825 115,266.540 92,000.00 10,604,521,680.00 1.0825 - -- - --

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.350 1,401,500.00 28,895,216,025.00 2.9496 20,617.350 1,401,500.00 28,895,216,025.00 2.9496 - -- - --
2.4.2 Bekisting expose m2 5,815.650 229,500.00 1,334,691,675.00 0.1362 5,815.650 229,500.00 1,334,691,675.00 0.1362 - -- - --
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 1,401,500.00 27,162,527,560.00 2.7728 19,381.040 1,401,500.00 27,162,527,560.00 2.7728 - -- - --
2.4.4 Bekisting non expose m2 971.160 167,000.00 162,183,720.00 0.0166 971.160 167,000.00 162,183,720.00 0.0166 - -- - --
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.080 20,081,000.00 4,258,778,480.00 0.4347 212.080 20,081,000.00 4,258,778,480.00 0.4347 - -- - --
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.950 20,081,000.00 5,099,569,950.00 0.5206 253.950 20,081,000.00 5,099,569,950.00 0.5206 - -- - --
2.4.7 Caping Beton K.225 m3 5,382.950 1,401,500.00 7,544,204,425.00 0.7701 5,382.950 1,401,500.00 7,544,204,425.00 0.7701 - -- - --

Page 2
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

BILL OF QUANTITY ( BOQ ) MC - 0


BALANCE
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan Bertambah Berkurang REMARK
No. Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Jumlah ( RP ) Volume Jumlah ( RP )
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.000 1,720,000.00 36,120,000.00 0.0037 21.000 1,720,000.00 36,120,000.00 0.0037 - -- - --
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.000 63,500,000.00 635,000,000.00 0.0648 10.000 63,500,000.00 635,000,000.00 0.0648 - -- - --
2.5.3 V-notch set 1.000 23,550,000.00 23,550,000.00 0.0024 1.000 23,550,000.00 23,550,000.00 0.0024 - -- - --
2.5.4 Pelat Settlement set 16.000 37,000,000.00 592,000,000.00 0.0604 16.000 37,000,000.00 592,000,000.00 0.0604 - -- - --
2.5.5 Inklinometer set 1.000 127,000,000.00 127,000,000.00 0.0130 1.000 127,000,000.00 127,000,000.00 0.0130 - -- - --
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin unit 1.000 305,000,000.00 305,000,000.00 0.0311 1.000 305,000,000.00 305,000,000.00 0.0311 - -- - --
2.5.7 Total Earth Pressure unit 6.000 6,500,000.00 39,000,000.00 0.0040 6.000 6,500,000.00 39,000,000.00 0.0040 - -- - --

Jumlah II 967,258,216,933.00 98.7382 967,258,216,699.20 98.7382 2,786,914,897.20 2,786,915,131.00


III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.350 44,200.00 1,474,070.00 0.0002 33.350 44,200.00 1,474,070.00 0.0002 - -- - --
3.2 Timbunan Tanah didatangkan m3 26.200 73,000.00 1,912,600.00 0.0002 26.200 73,000.00 1,912,600.00 0.0002 - -- - --
3.3 Beton K-225 untuk angker m3 168.250 1,401,500.00 235,802,375.00 0.0241 168.250 1,401,500.00 235,802,375.00 0.0241 - -- - --
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.000 145,500.00 40,158,000.00 0.0041 276.000 145,500.00 40,158,000.00 0.0041 - -- - --
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.060 1,283,500.00 400,529,010.00 0.0409 312.060 1,283,500.00 400,529,010.00 0.0409 - -- - --
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.000 1,232,000.00 11,088,000.00 0.0011 9.000 1,232,000.00 11,088,000.00 0.0011 - -- - --
3.7 Bekisting non expose m2 1,485.420 167,000.00 248,065,140.00 0.0253 1,485.420 167,000.00 248,065,140.00 0.0253 - -- - --
3.8 Besi Tulangan Ulir D32 ton 90.900 20,081,000.00 1,825,362,900.00 0.1863 90.900 20,081,000.00 1,825,362,900.00 0.1863 - -- - --
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.000 2,280,000.00 1,710,000,000.00 0.1746 750.000 2,280,000.00 1,710,000,000.00 0.1746 - -- - --

Jumlah III 4,474,392,095.00 0.4567 4,474,392,095.00 0.4567 - -


IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.000 385,000,000.00 385,000,000.00 0.0393 1.000 385,000,000.00 385,000,000.00 0.0393 - -- - --
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 32,800,000.00 98,400,000.00 0.0100 3.000 32,800,000.00 98,400,000.00 0.0100 - -- - --
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 18,751,000.00 56,253,000.00 0.0057 3.000 18,751,000.00 56,253,000.00 0.0057 - -- - --
4.4 Mesin Pemotong rumput 90 cc buah 3.000 2,100,000.00 6,300,000.00 0.0006 3.000 2,100,000.00 6,300,000.00 0.0006 - -- - --
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.000 28,611,500.00 28,611,500.00 0.0029 1.000 28,611,500.00 28,611,500.00 0.0029 - -- - --
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.000 6,930,000.00 13,860,000.00 0.0014 2.000 6,930,000.00 13,860,000.00 0.0014 - -- - --
4.7 Kamera DSLR 24 Megapixel buah 1.000 9,200,000.00 9,200,000.00 0.0009 1.000 9,200,000.00 9,200,000.00 0.0009 - -- - --
4.8 LCD Portable live in 30.000 hours buah 2.000 11,711,500.00 23,423,000.00 0.0024 2.000 11,711,500.00 23,423,000.00 0.0024 - -- - --
4.9 Printer LaserJet Scan, USB, Fax buah 3.000 8,533,000.00 25,599,000.00 0.0026 3.000 8,533,000.00 25,599,000.00 0.0026 - -- - --
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.000 220,000,000.00 220,000,000.00 0.0225 1.000 220,000,000.00 220,000,000.00 0.0225 - -- - --
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.000 75,000,000.00 150,000,000.00 0.0153 2.000 75,000,000.00 150,000,000.00 0.0153 - -- - --
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.000 502,000,000.00 502,000,000.00 0.0512 1.000 502,000,000.00 502,000,000.00 0.0512 - -- - --
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.000 55,000,000.00 220,000,000.00 0.0225 4.000 55,000,000.00 220,000,000.00 0.0225 - -- - --
4.14 CCTV Standar 8 camera set 2.000 14,500,000.00 29,000,000.00 0.0030 2.000 14,500,000.00 29,000,000.00 0.0030 - -- - --

Jumlah IV 1,767,646,500.00 0.1804 1,767,646,500.00 0.1804 - -

Page 3
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

BILL OF QUANTITY ( BOQ ) MC - 0


BALANCE
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan Bertambah Berkurang REMARK
No. Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Jumlah ( RP ) Volume Jumlah ( RP )
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.000 591,300.00 898,776,000.00 0.0917 1,520.000 591,300.00 898,776,000.00 0.0917 - -- - --
Pekerjaan LPB, tebal = 300 mm m3 2,280.000 565,000.00 1,288,200,000.00 0.1315 2,280.000 565,000.00 1,288,200,000.00 0.1315 - -- - --
Beton K 125, untuk lantai kerja untuk trotoar m3 180.160 1,232,000.00 221,957,120.00 0.0227 180.160 1,232,000.00 221,957,120.00 0.0227 - -- - --
Aspal hotmix, untuk jalan di puncak bendungan m2 380.000 308,600.00 117,268,000.00 0.0120 380.000 308,600.00 117,268,000.00 0.0120 - -- - --
Canstin (60 x 30 x 25 x 20) bh 4,767.000 69,500.00 331,306,500.00 0.0338 4,767.000 69,500.00 331,306,500.00 0.0338 - -- - --
Pengadaan tiang listrik beserta kelengkapannya Ls 1.000 127,800,000.00 127,800,000.00 0.0130 1.000 127,800,000.00 127,800,000.00 0.0130 - -- - --

Jumlah V 2,985,307,620.00 0.3047 2,985,307,620.00 0.3047 - -


J U M L A H ( I + II + III + IV + V ) 979,618,743,948.00 100.0000 979,618,743,714.20 100.0000 2,786,914,897.20 2,786,915,131.00

Palembang , Oktober 2019


Menyetujui dan menyanggupi Hasil evaluasi tersebut diatas sebagai dasar perhitungan biaya pelaksanaan : Panitia Peneliti Pelaksanaan Kontrak
Pembangunan Bendungan Tiga Dihaji Paket I di Kab. OKU Selatan Nama/Jabatan

Kontraktor 1. Dave Harold Irhajadi Muchaimin, ST.M.Eng 1 ……………………………………


HUTAMA - BASUKI, KSO Ketua
2. Devi Popilia,ST.MT 2 ……………………………………
Sekretaris/Anggota
3. Akson Nurhanafi, ST, M.Eng 3 ……………………………………
Anggota
4. Piterson Maru' Ao, ST 4 ……………………………………
Lanjar Samadi, ST Anggota
Manajer Proyek 5. Saidah, SH 5 ……………………………………
Anggota

Page 4
HUTAMA – BASU

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 0.2046 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 --
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.000 0.0505 1.000 495,000,000.00 495,000,000.00 0.0505 --
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 0.0106 1.000 103,713,500.00 103,713,500.00 0.0106 --
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 0.0067 1.000 66,000,000.00 66,000,000.00 0.0067 --
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 0.0168 1.000 165,038,500.00 165,038,500.00 0.0168 --
1.6 Fasilitas Komunikasi Ls 1.000 0.0154 1.000 150,928,800.00 150,928,800.00 0.0154 --
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 0.0152 1.000 148,500,000.00 148,500,000.00 0.0152 --

Jumlah I 0.3198 3,133,180,800.00 0.3198


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.000 0.0975 1.000 955,105,000.00 955,105,000.00 0.0975 --

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 0.0817 137,786.640 8,900.00 1,226,301,096.00 0.1252 47,807.260
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 3.4886 582,344.610 53,900.00 31,388,374,479.00 3.2041 --
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 7.7224 711,447.200 107,800.00 76,694,008,160.00 7.8290 9,682.220
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 8.6657 824,179.170 103,000.00 84,890,454,510.00 8.6657 --
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 7.8716 564,093.030 136,700.00 77,111,517,201.00 7.8716 --
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 41.4595 1,800,543.504 226,300.00 407,462,994,955.20 41.5940 5,822.744

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.020 2.5624 564,093.020 44,500.00 25,102,139,390.00 2.5624 --
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 1.3822 86,135.730 157,200.00 13,540,536,756.00 1.3822 --
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.730 1.9388 86,135.730 220,500.00 18,992,928,465.00 1.9388 --
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.540 4.8160 648,951.540 72,700.00 47,178,776,958.00 4.8160 --
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.100 5.0831 1,113,977.100 44,700.00 49,794,776,370.00 5.0831 --
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.720 4.7060 634,125.720 72,700.00 46,100,939,844.00 4.7060 --
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.540 1.0825 115,266.540 92,000.00 10,604,521,680.00 1.0825 --

Page 5
HUTAMA – BASU

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
2.4 PEKERJAAN BETON
2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.350 2.9496 20,617.350 1,401,500.00 28,895,216,025.00 2.9496 --
2.4.2 Bekisting expose m2 5,815.650 0.1362 5,815.650 229,500.00 1,334,691,675.00 0.1362 --
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 2.7728 19,381.040 1,401,500.00 27,162,527,560.00 2.7728 --
2.4.4 Bekisting non expose m2 971.160 0.0166 971.160 167,000.00 162,183,720.00 0.0166 --
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.080 0.4347 212.080 20,081,000.00 4,258,778,480.00 0.4347 --
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.950 0.5206 253.950 20,081,000.00 5,099,569,950.00 0.5206 --
2.4.7 Caping Beton K.225 m3 5,382.950 0.7701 5,382.950 1,401,500.00 7,544,204,425.00 0.7701 --

2.5 INSTRUMEN BENDUNGAN


2.5.1 Patok geser nos 21.000 0.0037 21.000 1,720,000.00 36,120,000.00 0.0037 --
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.000 0.0648 10.000 63,500,000.00 635,000,000.00 0.0648 --
2.5.3 V-notch set 1.000 0.0024 1.000 23,550,000.00 23,550,000.00 0.0024 --
2.5.4 Pelat Settlement set 16.000 0.0604 16.000 37,000,000.00 592,000,000.00 0.0604 --
2.5.5 Inklinometer set 1.000 0.0130 1.000 127,000,000.00 127,000,000.00 0.0130 --
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kel unit 1.000 0.0311 1.000 305,000,000.00 305,000,000.00 0.0311 --
2.5.7 Total Earth Pressure unit 6.000 0.0040 6.000 6,500,000.00 39,000,000.00 0.0040 --

Jumlah II 98.7382 967,258,216,699.20 98.7382


III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.350 0.0002 33.350 44,200.00 1,474,070.00 0.0002 --
3.2 Timbunan Tanah didatangkan m3 26.200 0.0002 26.200 73,000.00 1,912,600.00 0.0002 --
3.3 Beton K-225 untuk angker m3 168.250 0.0241 168.250 1,401,500.00 235,802,375.00 0.0241 --
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.000 0.0041 276.000 145,500.00 40,158,000.00 0.0041 --
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.060 0.0409 312.060 1,283,500.00 400,529,010.00 0.0409 --
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.000 0.0011 9.000 1,232,000.00 11,088,000.00 0.0011 --
3.7 Bekisting non expose m2 1,485.420 0.0253 1,485.420 167,000.00 248,065,140.00 0.0253 --
3.8 Besi Tulangan Ulir D32 ton 90.900 0.1863 90.900 20,081,000.00 1,825,362,900.00 0.1863 --
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.000 0.1746 750.000 2,280,000.00 1,710,000,000.00 0.1746 --

Jumlah III 0.4567 4,474,392,095.00 0.4567

Page 6
HUTAMA – BASU

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 0.0393 1.00 385,000,000.00 385,000,000.00 0.0393 --
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 0.0100 3.00 32,800,000.00 98,400,000.00 0.0100 --
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 0.0057 3.00 18,751,000.00 56,253,000.00 0.0057 --
4.4 Mesin Pemotong rumput 90 cc buah 3.00 0.0006 3.00 2,100,000.00 6,300,000.00 0.0006 --
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 0.0029 1.00 28,611,500.00 28,611,500.00 0.0029 --
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 0.0014 2.00 6,930,000.00 13,860,000.00 0.0014 --
4.7 Kamera DSLR 24 Megapixel buah 1.00 0.0009 1.00 9,200,000.00 9,200,000.00 0.0009 --
4.8 LCD Portable live in 30.000 hours buah 2.00 0.0024 2.00 11,711,500.00 23,423,000.00 0.0024 --
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 0.0026 3.00 8,533,000.00 25,599,000.00 0.0026 --
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.00 0.0225 1.00 220,000,000.00 220,000,000.00 0.0225 --
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 0.0153 2.00 75,000,000.00 150,000,000.00 0.0153 --
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 0.0512 1.00 502,000,000.00 502,000,000.00 0.0512 --
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 0.0225 4.00 55,000,000.00 220,000,000.00 0.0225 --
4.14 CCTV Standar 8 camera set 2.00 0.0030 2.00 14,500,000.00 29,000,000.00 0.0030 --

Jumlah IV 0.1804 1,767,646,500.00 0.1804


V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.00 0.0917 1,520.00 591,300.00 898,776,000.00 0.0917 --
Pekerjaan LPB, tebal = 300 mm m3 2,280.00 0.1315 2,280.00 565,000.00 1,288,200,000.00 0.1315 --
Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 0.0227 180.16 1,232,000.00 221,957,120.00 0.0227 --
Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 0.0120 380.00 308,600.00 117,268,000.00 0.0120 --
Canstin (60 x 30 x 25 x 20) bh 4,767.00 0.0338 4,767.00 69,500.00 331,306,500.00 0.0338 --
Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 0.0130 1.00 127,800,000.00 127,800,000.00 0.0130 --

Jumlah V 0.3047 2,985,307,620.00 0.3047


J U M L A H ( I + II + III + IV + V ) 100.0000 979,618,743,714.20 100.0000
Martapura, 2019
DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :
Direksi Pekerjaan Konsultan Supervisi Kontraktor
PPK Bendungan I BBWS Sumatera VIII PT. Virama Karya ( Persero ), KSO Hutama - Basuki, KSO

PITERSON MARU' AO, ST Ir. Zaki BR, MM Lanjar Samadi, ST


NIP. 19750521 200911 1001 Team Leader Manajer Proyek

Page 7
HUTAMA – BASUKI KSO

REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang

(13) (14)

--
--
--
--
--
--
--

--

--
51,705.290
--
--
--
--

--
--
--
--
--
--
--

Page 8
HUTAMA – BASUKI KSO

REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang

(13) (14)

--
--
--
--
--
--
--

--
--
--
--
--
--
--

--
--
--
--
--
--
--
--
--

Page 9
HUTAMA – BASUKI KSO

REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang

(13) (14)

--

--

--
--
--
--
--
--
--
--
--
--
--
--

--
--
--
--
--
--

Martapura, 2019
DIAJUKAN OLEH :
Kontraktor
Hutama - Basuki, KSO

Lanjar Samadi, ST
Manajer Proyek

Page 10
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 0.2046 1.00 2,004,000,000.00 2,004,000,000.00 0.2108 1.00 #DIV/0! #DIV/0!
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 0.0505 1.00 495,000,000.00 495,000,000.00 0.0521 1.00 #DIV/0! #DIV/0!
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 0.0106 1.00 103,713,500.00 103,713,500.00 0.0109 1.00 #DIV/0! #DIV/0!
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 0.0067 1.00 66,000,000.00 66,000,000.00 0.0069 1.00 #DIV/0! #DIV/0!
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 0.0168 1.00 165,038,500.00 165,038,500.00 0.0174 1.00 #DIV/0! #DIV/0!
1.6 Fasilitas Komunikasi Ls 1.00 0.0154 1.00 150,928,800.00 150,928,800.00 0.0159 1.00 #DIV/0! #DIV/0!
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 0.0152 1.00 148,500,000.00 148,500,000.00 0.0156 1.00 #DIV/0! #DIV/0!

Jumlah I 0.3198 3,133,180,800.00 0.3296 #DIV/0!


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 0.0975 1.00 955,105,000.00 955,105,000.00 0.1005 1.00 #DIV/0! #DIV/0!

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.38 0.0817 137,786.64 8,900.00 1,226,301,096.00 0.1290 0.00 #DIV/0! #DIV/0!
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.90 3.4886 582,344.61 53,900.00 31,388,374,479.00 3.3015 0.00 #DIV/0! #DIV/0!
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.98 7.7224 711,447.20 107,800.00 76,694,008,160.00 8.0669 0.00 #DIV/0! #DIV/0!
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.17 8.6657 824,179.17 103,000.00 84,890,454,510.00 8.9290 0.00 #DIV/0! #DIV/0!
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 7.8716 564,093.03 136,700.00 77,111,517,201.00 8.1108 0.00 #DIV/0! #DIV/0!
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.76 41.4595 1,800,543.50 226,300.00 407,462,994,955.20 42.8582 0.00 #DIV/0! #DIV/0!

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.02 2.5624 564,093.02 44,500.00 25,102,139,390.00 2.6403 0.00 #DIV/0! #DIV/0!
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.73 1.3822 86,135.73 157,200.00 13,540,536,756.00 1.4242 0.00 #DIV/0! #DIV/0!
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.73 1.9388 86,135.73 220,500.00 18,992,928,465.00 1.9977 0.00 #DIV/0! #DIV/0!
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.54 4.8160 648,951.54 72,700.00 47,178,776,958.00 4.9624 0.00 #DIV/0! #DIV/0!
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.10 5.0831 1,113,977.10 44,700.00 49,794,776,370.00 5.2376 0.00 #DIV/0! #DIV/0!
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.72 4.7060 634,125.72 72,700.00 46,100,939,844.00 4.8490 0.00 #DIV/0! #DIV/0!
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.54 1.0825 115,266.54 92,000.00 10,604,521,680.00 1.1154 0.00 #DIV/0! #DIV/0!

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.35 2.9496 20,617.35 1,401,500.00 #DIV/0! #DIV/0! #DIV/0!
2.4.2 Bekisting expose m2 5,815.65 0.1362 5,815.65 229,500.00 1,334,691,675.00 0.1404 0.00 #DIV/0! #DIV/0!
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.04 2.7728 19,381.04 1,401,500.00 27,162,527,560.00 2.8570 0.00 #DIV/0! #DIV/0!
2.4.4 Bekisting non expose m2 971.16 0.0166 971.16 167,000.00 162,183,720.00 0.0171 0.00 #DIV/0! #DIV/0!
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.08 0.4347 212.08 20,081,000.00 4,258,778,480.00 0.4480 0.00 #DIV/0! #DIV/0!
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.95 0.5206 253.95 20,081,000.00 5,099,569,950.00 0.5364 0.00 #DIV/0! #DIV/0!
2.4.7 Caping Beton K.225 m3 5,382.95 0.7701 5,382.95 1,401,500.00 7,544,204,425.00 0.7935 0.00 #DIV/0! #DIV/0!

Page 11
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.00 0.0037 21.00 1,720,000.00 36,120,000.00 0.0038 0.05 #DIV/0! #DIV/0!
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.00 0.0648 10.00 63,500,000.00 635,000,000.00 0.0668 0.10 #DIV/0! #DIV/0!
2.5.3 V-notch set 1.00 0.0024 1.00 23,550,000.00 23,550,000.00 0.0025 1.00 #DIV/0! #DIV/0!
2.5.4 Pelat Settlement set 16.00 0.0604 16.00 37,000,000.00 592,000,000.00 0.0623 0.06 #DIV/0! #DIV/0!
2.5.5 Inklinometer set 1.00 0.0130 1.00 127,000,000.00 127,000,000.00 0.0134 1.00 #DIV/0! #DIV/0!
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kelembaban cuaca) unit 1.00 0.0311 1.00 305,000,000.00 305,000,000.00 0.0321 1.00 #DIV/0! #DIV/0!
2.5.7 Total Earth Pressure unit 6.00 0.0040 6.00 6,500,000.00 39,000,000.00 0.0041 0.17 #DIV/0! #DIV/0!

Jumlah II 98.7382 938,363,000,674.20 98.6999 #DIV/0!


III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.35 0.0002 33.35 44,200.00 1,474,070.00 0.0002 0.03 #DIV/0! #DIV/0!
3.2 Timbunan Tanah didatangkan m3 26.20 0.0002 26.20 73,000.00 1,912,600.00 0.0002 0.04 #DIV/0! #DIV/0!
3.3 Beton K-225 untuk angker m3 168.25 0.0241 168.25 1,401,500.00 235,802,375.00 0.0248 0.01 #DIV/0! #DIV/0!
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.00 0.0041 276.00 145,500.00 40,158,000.00 0.0042 0.00 #DIV/0! #DIV/0!
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.06 0.0409 312.06 1,283,500.00 400,529,010.00 0.0421 0.00 #DIV/0! #DIV/0!
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.00 0.0011 9.00 1,232,000.00 11,088,000.00 0.0012 0.11 #DIV/0! #DIV/0!
3.7 Bekisting non expose m2 1,485.42 0.0253 1,485.42 167,000.00 248,065,140.00 0.0261 0.00 #DIV/0! #DIV/0!
3.8 Besi Tulangan Ulir D32 ton 90.90 0.1863 90.90 20,081,000.00 1,825,362,900.00 0.1920 0.01 #DIV/0! #DIV/0!
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.00 0.1746 750.00 2,280,000.00 1,710,000,000.00 0.1799 0.00 #DIV/0! #DIV/0!

Jumlah III 0.4567 4,474,392,095.00 0.4706 #DIV/0!


IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 0.0393 1.00 385,000,000.00 385,000,000.00 0.0405 1.00 #DIV/0! #DIV/0!
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 0.0100 3.00 32,800,000.00 98,400,000.00 0.0104 0.33 #DIV/0! #DIV/0!
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 0.0057 3.00 18,751,000.00 56,253,000.00 0.0059 0.33 #DIV/0! #DIV/0!
4.4 Mesin Pemotong rumput 90 cc buah 3.00 0.0006 3.00 2,100,000.00 6,300,000.00 0.0007 0.33 #DIV/0! #DIV/0!
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 0.0029 1.00 28,611,500.00 28,611,500.00 0.0030 1.00 #DIV/0! #DIV/0!
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 0.0014 2.00 6,930,000.00 13,860,000.00 0.0015 0.50 #DIV/0! #DIV/0!
4.7 Kamera DSLR 24 Megapixel buah 1.00 0.0009 1.00 9,200,000.00 9,200,000.00 0.0010 1.00 #DIV/0! #DIV/0!
4.8 LCD Portable live in 30.000 hours buah 2.00 0.0024 2.00 11,711,500.00 23,423,000.00 0.0025 0.50 #DIV/0! #DIV/0!
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 0.0026 3.00 8,533,000.00 25,599,000.00 0.0027 0.33 #DIV/0! #DIV/0!
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.00 0.0225 1.00 220,000,000.00 220,000,000.00 0.0231 1.00 #DIV/0! #DIV/0!
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 0.0153 2.00 75,000,000.00 150,000,000.00 0.0158 0.50 #DIV/0! #DIV/0!
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 0.0512 1.00 502,000,000.00 502,000,000.00 0.0528 1.00 #DIV/0! #DIV/0!
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 0.0225 4.00 55,000,000.00 220,000,000.00 0.0231 0.25 #DIV/0! #DIV/0!
4.14 CCTV Standar 8 camera set 2.00 0.0030 2.00 14,500,000.00 29,000,000.00 0.0031 0.50 #DIV/0! #DIV/0!

Jumlah IV 0.1804 1,767,646,500.00 0.1859 #DIV/0!

Page 12
HUTAMA – BASUKI KSO

NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.00 0.0917 1,520.00 591,300.00 898,776,000.00 0.0945 0.00 #DIV/0! #DIV/0!
Pekerjaan LPB, tebal = 300 mm m3 2,280.00 0.1315 2,280.00 565,000.00 1,288,200,000.00 0.1355 0.00 #DIV/0! #DIV/0!
Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 0.0227 180.16 1,232,000.00 221,957,120.00 0.0233 0.01 #DIV/0! #DIV/0!
Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 0.0120 380.00 308,600.00 117,268,000.00 0.0123 0.00 #DIV/0! #DIV/0!
Canstin (60 x 30 x 25 x 20) bh 4,767.00 0.0338 4,767.00 69,500.00 331,306,500.00 0.0348 0.00 #DIV/0! #DIV/0!
Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 0.0130 1.00 127,800,000.00 127,800,000.00 0.0134 1.00 #DIV/0! #DIV/0!

Jumlah V 0.3047 2,985,307,620.00 0.3140 #DIV/0!


J U M L A H ( I + II + III + IV + V ) 100.0000 950,723,527,689.20 100.0000 #DIV/0!

DISETUJUI OLEH : DIPERIKSA OLEH : DIAJUKAN OLEH :


PPK Bendungan 1 PT. Virama Karya, KSO Hutama - Basuki, KSO
BBWS Sumatera VIII ( Konsultan Supervisi ) ( Kontraktor )

Amaraldo Azmi, ST.,MPSDA Ir. Zaki BR, MM Lanjar Samadi, ST

NIP. 19820423 200502 1 001 Team Leader Manajer Proyek

Page 13
ORIGINAL CONTRACT
BoQ IKUT KONTRAK Volume Pekerjaan yang tdk berubah ( disesuaikan dengan kontrak ) VOLUME PEKERJAAN TANAH BENDUNGAN U
URAIAN ITEM PEKERJAAN
Pekerjaan PEKERJAAN LAIN- JETTY DAN INSTRUMEN Besi Tulangan Ulir Clearing & grubbing Galian Pondasi - Galian Tanah diangkut
Satuan Volume Harga satuan Jumlah harga BOBOT ( % ) Pekerjaan Persiapan ALAT PENUNJANG OP Caping Beton K.225 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan
Dewatering LAIN TRASHBOOM BENDUNGAN D32 Caping Grouting ke disposal
No.
(1) (2) (3) (4) (5) (6) (7)
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 2,004,000,000.00 2,004,000,000.00 0.2046 1.00
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 495,000,000.00 495,000,000.00 0.0505 1.00
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 103,713,500.00 103,713,500.00 0.0106 1.00
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 66,000,000.00 66,000,000.00 0.0067 1.00
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 165,038,500.00 165,038,500.00 0.0168 1.00
1.6 Fasilitas Komunikasi Ls 1.00 150,928,800.00 150,928,800.00 0.0154 1.00
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 148,500,000.00 148,500,000.00 0.0152 1.00

Jumlah I 3,133,180,800.00 0.3198


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 955,105,000.00 955,105,000.00 0.0975 1.00

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.38 8,900.00 800,816,482.00 0.0817 137,786.64
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.90 53,900.00 34,175,289,610.00 3.4886 582,344.61
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.98 107,800.00 75,650,264,844.00 7.7224
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.17 103,000.00 84,890,454,510.00 8.6657
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 136,700.00 77,111,517,201.00 7.8716 564,093.03
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.76 226,300.00 406,145,307,988.00 41.4595 1,800,543.504

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.02 44,500.00 25,102,139,390.00 2.5624
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.73 157,200.00 13,540,536,756.00 1.3822
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.73 220,500.00 18,992,928,465.00 1.9388
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.54 72,700.00 47,178,776,958.00 4.8160
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.10 44,700.00 49,794,776,370.00 5.0831
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.72 72,700.00 46,100,939,844.00 4.7060
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.54 92,000.00 10,604,521,680.00 1.0825

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.35 1,401,500.00 28,895,216,025.00 2.9496
2.4.2 Bekisting expose m2 5,815.65 229,500.00 1,334,691,675.00 0.1362
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.04 1,401,500.00 27,162,527,560.00 2.7728
2.4.4 Bekisting non expose m2 971.16 167,000.00 162,183,720.00 0.0166
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.08 20,081,000.00 4,258,778,480.00 0.4347 212.08
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.95 20,081,000.00 5,099,569,950.00 0.5206
2.4.7 Caping Beton K.225 m3 5,382.95 1,401,500.00 7,544,204,425.00 0.7701 5,382.95

2.5 INSTRUMEN BENDUNGAN


2.5.1 Patok geser nos 21.00 1,720,000.00 36,120,000.00 0.0037 21.00
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.00 63,500,000.00 635,000,000.00 0.0648 10.00
2.5.3 V-notch set 1.00 23,550,000.00 23,550,000.00 0.0024 1.00
2.5.4 Pelat Settlement set 16.00 37,000,000.00 592,000,000.00 0.0604 16.00
2.5.5 Inklinometer set 1.00 127,000,000.00 127,000,000.00 0.0130 1.00
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kel unit 1.00 305,000,000.00 305,000,000.00 0.0311 1.00
2.5.7 Total Earth Pressure unit 6.00 6,500,000.00 39,000,000.00 0.0040 6.00

Jumlah II 967,258,216,933.00 98.7382


III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.35 44,200.00 1,474,070.00 0.0002 33.35
3.2 Timbunan Tanah didatangkan m3 26.20 73,000.00 1,912,600.00 0.0002 26.20
3.3 Beton K-225 untuk angker m3 168.25 1,401,500.00 235,802,375.00 0.0241 168.25
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.00 145,500.00 40,158,000.00 0.0041 276.00
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.06 1,283,500.00 400,529,010.00 0.0409 312.06
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.00 1,232,000.00 11,088,000.00 0.0011 9.00
3.7 Bekisting non expose m2 1,485.42 167,000.00 248,065,140.00 0.0253 1,485.42
3.8 Besi Tulangan Ulir D32 ton 90.90 20,081,000.00 1,825,362,900.00 0.1863 90.90
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.00 2,280,000.00 1,710,000,000.00 0.1746 750.00

Jumlah III 4,474,392,095.00 0.4567


IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 385,000,000.00 385,000,000.00 0.0393 1.00
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 32,800,000.00 98,400,000.00 0.0100 3.00
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 18,751,000.00 56,253,000.00 0.0057 3.00
4.4 Mesin Pemotong rumput 90 cc buah 3.00 2,100,000.00 6,300,000.00 0.0006 3.00
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 28,611,500.00 28,611,500.00 0.0029 1.00
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 6,930,000.00 13,860,000.00 0.0014 2.00
4.7 Kamera DSLR 24 Megapixel buah 1.00 9,200,000.00 9,200,000.00 0.0009 1.00
4.8 LCD Portable live in 30.000 hours buah 2.00 11,711,500.00 23,423,000.00 0.0024 2.00
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 8,533,000.00 25,599,000.00 0.0026 3.00
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.00 220,000,000.00 220,000,000.00 0.0225 1.00
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 75,000,000.00 150,000,000.00 0.0153 2.00
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 502,000,000.00 502,000,000.00 0.0512 1.00
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 55,000,000.00 220,000,000.00 0.0225 4.00
4.14 CCTV Standar 8 camera set 2.00 14,500,000.00 29,000,000.00 0.0030 2.00

Jumlah IV 1,767,646,500.00 0.1804


V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.00 591,300.00 898,776,000.00 0.0917 1,520.00
Pekerjaan LPB, tebal = 300 mm m3 2,280.00 565,000.00 1,288,200,000.00 0.1315 2,280.00
Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 1,232,000.00 221,957,120.00 0.0227 180.16
Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 308,600.00 117,268,000.00 0.0120 380.00
Canstin (60 x 30 x 25 x 20) bh 4,767.00 69,500.00 331,306,500.00 0.0338 4,767.00
Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 127,800,000.00 127,800,000.00 0.0130 1.00

Jumlah V 2,985,307,620.00 0.3047


J U M L A H ( I + II + III + IV + V ) 979,618,743,948.00 100.0000
Volume Pekerjaan MC-0 %
VOLUME PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM) IKUT KONTRAK VOLUME PEKERJAAN TIMBUNAN IKUT KONTRAK PEKERJAAN BETON JUMLAH
Galian Batu di Pondasi dengan mekanis Galian Batu di Pondasi dengan Timbunan Filter Halus / Zona 2a Timbunan Filter Kasar / Zona 2b Timbunan Zone 3A, Rockfill Timbunan Zone 3B, Rockfill Timbunan Riprap / Zona 4 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Besi Tulangan Ulir D32 Grouting TOTAL VOLUME
Timbunan Inti (Zone 1) Timbunan Zone 3A, Rockfill Grouting Gallery, (Beton K 225) Bekisting expose Bekisting non expose ( RP )
diangkut ke disposal mekanis diangkut ke stockpile (material Pasir dari luar), (material Kerikil dari luar) dari Stockpile (transisi) dari Stockpile (material Batu) Type A Gallery

1.00 2,004,000,000.00
1.00 495,000,000.00
1.00 103,713,500.00
1.00 66,000,000.00
1.00 165,038,500.00
1.00 150,928,800.00
1.00 148,500,000.00

1.00 955,105,000.00

137,786.64 1,226,301,096.00
582,344.61 31,388,374,479.00
711,447.20 711,447.20 76,694,008,160.00
824,179.17 824,179.17 84,890,454,510.00
564,093.03 77,111,517,201.00
1,800,543.50 407,462,994,955.20

564,093.02 564,093.02 25,102,139,390.00


86,135.73 86,135.73 13,540,536,756.00
86,135.73 86,135.73 18,992,928,465.00
648,951.54 648,951.54 47,178,776,958.00
1,113,977.10 1,113,977.10 49,794,776,370.00
634,125.72 634,125.72 46,100,939,844.00
115,266.54 115,266.54 10,604,521,680.00

20,617.35 20,617.35 28,895,216,025.00


5,815.65 5,815.65 1,334,691,675.00
19,381.04 19,381.04 27,162,527,560.00
971.16 971.16 162,183,720.00
212.08 4,258,778,480.00
253.950 253.95 5,099,569,950.00
5,382.95 7,544,204,425.00

21.00 36,120,000.00
10.00 635,000,000.00
1.00 23,550,000.00
16.00 592,000,000.00
1.00 127,000,000.00
1.00 305,000,000.00
6.00 39,000,000.00

33.35 1,474,070.00
26.20 1,912,600.00
168.25 235,802,375.00
276.00 40,158,000.00
312.06 400,529,010.00
9.00 11,088,000.00
1,485.42 248,065,140.00
90.90 1,825,362,900.00
750.00 1,710,000,000.00

1.00 385,000,000.00

3.00 98,400,000.00

3.00 56,253,000.00
3.00 6,300,000.00
1.00 28,611,500.00
2.00 13,860,000.00
1.00 9,200,000.00
2.00 23,423,000.00
3.00 25,599,000.00
1.00 220,000,000.00
2.00 150,000,000.00
1.00 502,000,000.00
4.00 220,000,000.00
2.00 29,000,000.00

1,520.00 898,776,000.00
2,280.00 1,288,200,000.00
180.16 221,957,120.00
380.00 117,268,000.00
4,767.00 331,306,500.00
1.00 127,800,000.00
BALANCE
MC - 0
Increase Decrease
REMARK
Satuan Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Jumlah ( RP ) Volume Jumlah ( RP )

Ls 1.00 2,004,000,000.00 2,004,000,000.00 0.2046 -- -- -- --


Ls 1.00 495,000,000.00 495,000,000.00 0.0505 -- -- -- --
Ls 1.00 103,713,500.00 103,713,500.00 0.0106 -- -- -- --
Ls 1.00 66,000,000.00 66,000,000.00 0.0067 -- -- -- --
Ls 1.00 165,038,500.00 165,038,500.00 0.0168 -- -- -- --
Ls 1.00 150,928,800.00 150,928,800.00 0.0154 -- -- -- --
Ls 1.00 148,500,000.00 148,500,000.00 0.0152 -- -- -- --

3,133,180,800.00 0.3198 - -

Ls 1.00 955,105,000.00 955,105,000.00 0.0975 -- -- -- --

m2 137,786.64 8,900.00 1,226,301,096.00 0.1252 47,807.26 425,484,614.00 -- --


m3 582,344.61 53,900.00 31,388,374,479.00 3.2041 -- -- 51,705.29 2,786,915,131.00
m3 711,447.20 107,800.00 76,694,008,160.00 7.8290 9,682.22 1,043,743,316.00 -- --
m3 824,179.17 103,000.00 84,890,454,510.00 8.6657 -- -- -- --
m3 564,093.03 136,700.00 77,111,517,201.00 7.8716 -- -- -- --
m3 1,800,543.50 226,300.00 407,462,994,955.20 41.5940 5,822.74 1,317,686,967.20 -- --

m3 564,093.02 44,500.00 25,102,139,390.00 2.5624 -- -- -- --


m3 86,135.73 157,200.00 13,540,536,756.00 1.3822 -- -- -- --
m3 86,135.73 220,500.00 18,992,928,465.00 1.9388 -- -- -- --
m3 648,951.54 72,700.00 47,178,776,958.00 4.8160 -- -- -- --
m3 1,113,977.10 44,700.00 49,794,776,370.00 5.0831 -- -- -- --
m3 634,125.72 72,700.00 46,100,939,844.00 4.7060 -- -- -- --
m3 115,266.54 92,000.00 10,604,521,680.00 1.0825 -- -- -- --

m3 20,617.35 1,401,500.00 28,895,216,025.00 2.9496 -- -- -- --


m2 5,815.65 229,500.00 1,334,691,675.00 0.1362 -- -- -- --
m3 19,381.04 1,401,500.00 27,162,527,560.00 2.7728 -- -- -- --
m2 971.16 167,000.00 162,183,720.00 0.0166 -- -- -- --
ton 212.08 20,081,000.00 4,258,778,480.00 0.4347 -- -- -- --
ton 253.95 20,081,000.00 5,099,569,950.00 0.5206 -- -- -- --
m3 5,382.95 1,401,500.00 7,544,204,425.00 0.7701 -- -- -- --

nos 21.00 1,720,000.00 36,120,000.00 0.0037 -- -- -- --


titk 10.00 63,500,000.00 635,000,000.00 0.0648 -- -- -- --
set 1.00 23,550,000.00 23,550,000.00 0.0024 -- -- -- --
set 16.00 37,000,000.00 592,000,000.00 0.0604 -- -- -- --
set 1.00 127,000,000.00 127,000,000.00 0.0130 -- -- -- --
unit 1.00 305,000,000.00 305,000,000.00 0.0311 -- -- -- --
unit 6.00 6,500,000.00 39,000,000.00 0.0040 -- -- -- --

967,258,216,699.20 98.7382 2,786,914,897 2,786,915,131

m3 33.35 44,200.00 1,474,070.00 0.0002 -- -- -- --


m3 26.20 73,000.00 1,912,600.00 0.0002 -- -- -- --
m3 168.25 1,401,500.00 235,802,375.00 0.0241 -- -- -- --
nos 276.00 145,500.00 40,158,000.00 0.0041 -- -- -- --
m3 312.06 1,283,500.00 400,529,010.00 0.0409 -- -- -- --
m3 9.00 1,232,000.00 11,088,000.00 0.0011 -- -- -- --
m2 1,485.42 167,000.00 248,065,140.00 0.0253 -- -- -- --
ton 90.90 20,081,000.00 1,825,362,900.00 0.1863 -- -- -- --
m 750.00 2,280,000.00 1,710,000,000.00 0.1746 -- -- -- --

4,474,392,095.00 0.4567 - -

set 1.00 385,000,000.00 385,000,000.00 0.0393 -- -- -- --

buah 3.00 32,800,000.00 98,400,000.00 0.0100 -- -- -- --

buah 3.00 18,751,000.00 56,253,000.00 0.0057 -- -- -- --


buah 3.00 2,100,000.00 6,300,000.00 0.0006 -- -- -- --
set 1.00 28,611,500.00 28,611,500.00 0.0029 -- -- -- --
buah 2.00 6,930,000.00 13,860,000.00 0.0014 -- -- -- --
buah 1.00 9,200,000.00 9,200,000.00 0.0009 -- -- -- --
buah 2.00 11,711,500.00 23,423,000.00 0.0024 -- -- -- --
buah 3.00 8,533,000.00 25,599,000.00 0.0026 -- -- -- --
buah 1.00 220,000,000.00 220,000,000.00 0.0225 -- -- -- --
buah 2.00 75,000,000.00 150,000,000.00 0.0153 -- -- -- --
unit 1.00 502,000,000.00 502,000,000.00 0.0512 -- -- -- --
set 4.00 55,000,000.00 220,000,000.00 0.0225 -- -- -- --
set 2.00 14,500,000.00 29,000,000.00 0.0030 -- -- -- --

1,767,646,500.00 0.1804 - -

m3 1,520.00 591,300.00 898,776,000.00 0.0917 -- -- -- --


m3 2,280.00 565,000.00 1,288,200,000.00 0.1315 -- -- -- --
m3 180.16 1,232,000.00 221,957,120.00 0.0227 -- -- -- --
m2 380.00 308,600.00 117,268,000.00 0.0120 -- -- -- --
bh 4,767.00 69,500.00 331,306,500.00 0.0338 -- -- -- --
Ls 1.00 127,800,000.00 127,800,000.00 0.0130 -- -- -- --

2,985,307,620.00 0.3047 - -
979,618,743,714.20 100.0000 2,786,914,897.2001 2,786,915,131.0000
QUANTITY
ORIGINAL
CONTRACT
BoQ Works Item Unit REMARK
TOTAL
Quantity
No.

1 PREPARATION WORK
1-01 Mobilization and Demobilization Ls 1.00 1.00
1-02 Temporary Facilities Ls 1.00 1.00
1-03 Operation and Maintenance for Engineer's Site Facilities Ls 1.00 1.00
1-04 Water Control and Dewatering System Ls 1.00 1.00
1-05 Report, Photograph and Video Ls 1.00 1.00
1-06 Temporary Access Roads Ls 1.00 1.00
1-07 Site Testing Laboratory Ls 1.00 1.00
1-08 Topographic Survey Ls 1.00 1.00
1-09 Pre Pilling Test Ls 1.00 1.00
1-10 Security, Safety and Health Control Ls 1.00 1.00
1-11 Relocation of Public Utility Ls 1.00 1.00
1-12 Soil Invetigationed Drilling 20 m depth --
- Mechanical Boring including SPT Nos 5.00 5.00
- Dutch Cone Penetrometer Test Nos 5.00 5.00

2 STRIPPING, LAND CLEARING AND DEMOLISHING WORK


2-01 Land Clearing and Grubbing m2 12,920.00 26,538.78
2-02 Stripping of Top Soil m2 2,606.00 11,120.06
2-03 Demolishing existing wet masonry structure and Gabion Structure m3 1,933.00 5,649.40
2-04 Demolishing of Reinforcement Concrete m3 0 21,753.00

3 EARTH WORK
3-01 Excavation of common soil and structure by Machinery, within Transportation < 4.0 km m3 5,076.00 10,356.39
3-02 Excavation of common soil and structure by Man Power, within Transportation < 4.0 km m3 9,267.00 1,261.18
3-03 Excavation Riverbank by Machinery, within Transportation < 4.0 km m3 3,536.00 32,844.26
3-04 Backfill from Borrow Area by Man-power m3 6,111.00 5,298.07
3-05 Grass and Soding m2 29,972.00 --
3-06 Embankment from Borrow area m3 3,965.00 14,756.20
3-07 Embankment from Stock yard, within Transportation m3 10,988.00 --

4 CONCRETE WORK
4-01 Concrete K-350 m3 0 --
4-02 Concrete K-300 m3 0 --
4-03 Concrete K-250 m3 203.00 157.04
Pedestrian Bridge
- Abudment 157.04
4-04 Concrete K-225 m3 8,931.00 7,911.28
(Left) River Bank Protection By CCSP 1,118.00
- Coping Concrete 628.77
- Base Concrete 218.44
- Top Concrete 208.90
- Expansion Joint 20.45
- Frame 20.32
- Adjust Concrete 21.12
(Right) River Bank Protection By CCSP 1,085.43
- Coping Concrete 610.59
- Base Concrete 212.12
- Top Concrete 202.86
- Expansion Joint 20.07
- Frame 19.94
- Adjust Concrete 19.86
(Left) Inspection Road and Parapet Wall 1,225.89
- Parapet Wall 1,225.89
(Right) Inspection Road and Parapet Wall 1,189.35
- Parapet Wall 1,189.35
(Left) Slope protection & Drain 1,243.41
- Coping Concrete 805.80
- Base Concrete 196.32
- Top Concrete 198.82
- Expansion Joint 11.28
- Frame 11.28
- Adjust Concrete 19.92
(Right) Slope protection & Drain 1,181.77
- Coping Concrete 765.35
- Base Concrete 186.96
- Top Concrete 188.84
- Expansion Joint 10.65
- Frame 10.65
- Adjust Concrete 19.32
Cross Drainage 768.90
- (1.0 x 1.0) M 130.92
- (1.0 x 1.5) M 148.22
- (1.5 x 1.5) M 71.27
- 2 (1.5 x 1.5) M 195.83
- 3 (1.5 x 1.5) M 72.08
- 5 (1.5 x 1.5) M 150.58
Water Bus Station 16.48
Access People 82.06
4-05 Concrete K-175 m3 1,303.00 768.19
(Left) Inspection Road and Parapet Wall
- Inspection Road 370.57
(Right) Inspection Road and Parapet Wall
- Inspection Road 359.53
Access People 38.09
4-06 Lean Concrete K-100 m3 427.00 1,506.65
(Left) River Bank Protection By CCSP
- Coping Concrete --
- Base Concrete 57.43
- Top Concrete 44.47
- Expansion Joint 10.53
- Frame 12.56
(Right) River Bank Protection By CCSP
- Coping Concrete --
- Base Concrete 55.77
- Top Concrete 43.18
- Expansion Joint 10.34
- Frame 12.32
(Left) Inspection Road and Parapet Wall
- Parapet Wall 149.73
- Inspection Road 185.29
(Right) Inspection Road and Parapet Wall
- Parapet Wall 145.26
- Inspection Road 179.76
(Left) Slope protection & Drain
- Coping Concrete 156.55
- Base Concrete 50.65
- Top Concrete 50.65
- Expansion Joint 9.40
- Frame 11.28
(Right) Slope protection & Drain
- Coping Concrete 148.70
- Base Concrete 48.11
- Top Concrete 48.11
- Expansion Joint 8.87
- Frame 10.65
Cross Drainage
- (1.0 x 1.0) M 9.07
- (1.0 x 1.5) M 11.74
- (1.5 x 1.5) M 4.97
- 2 (1.5 x 1.5) M 12.38
- 3 (1.5 x 1.5) M 4.54
- 5 (1.5 x 1.5) M 7.42
Access People 6.93
4-09 Reinforcement Steel Bar KG 372,775.00 362,065.41
(Left) River Bank Protection By CCSP
- Coping Concrete 12,487.62
- Base Concrete 8,980.28
- Top Concrete 7,893.41
- Expansion Joint 1,501.90
- Frame 2,124.61
(Right) River Bank Protection By CCSP
- Coping Concrete 12,130.15
- Base Concrete 8,722.74
- Top Concrete 7,666.98
- Expansion Joint 1,474.09
- Frame 2,085.02
(Left) Inspection Road and Parapet Wall
- Parapet Wall 51,998.23
(Right) Inspection Road and Parapet Wall
- Parapet Wall 50,452.78
(Left) Slope protection & Drain
- Coping Concrete 29,395.01
- Base Concrete 8,713.09
- Top Concrete 7,793.55
- Expansion Joint 1,317.18
- Frame 1,860.71
(Right) Slope protection & Drain
- Coping Concrete 27,940.54
- Base Concrete 8,275.39
- Top Concrete 7,401.19
- Expansion Joint 1,244.00
- Frame 1,757.34
Cross Drainage
- (1.0 x 1.0) M 13,900.88
- (1.0 x 1.5) M 16,884.35
- (1.5 x 1.5) M 8,344.40
- 2 (1.5 x 1.5) M 21,798.62
- 3 (1.5 x 1.5) M 7,585.05
- 5 (1.5 x 1.5) M 12,141.76
- Pedestrian Bridge 12,034.00
Water Bus Station 894.21
Access People 5,266.32
4-10 Formwork < 2,5 m m2 43,596.00 35,705.40
(Left) River Bank Protection By CCSP
- Coping Concrete 1,704.69
- Base Concrete 627.47
- Top Concrete 763.07
- Expansion Joint 165.29
- Frame 166.16
(Right) River Bank Protection By CCSP
- Coping Concrete 1,672.53
- Base Concrete 609.22
- Top Concrete 740.77
- Expansion Joint 162.29
- Frame 163.16
(Left) Inspection Road and Parapet Wall
- Parapet Wall 3,996.83
(Right) Inspection Road and Parapet Wall
- Parapet Wall 3,878.15
(Left) Slope protection & Drain
- Coping Concrete 6,484.14
- Base Concrete 640.95
- Top Concrete 1,254.63
- Expansion Joint 56.38
- Frame 84.56
(Right) Slope protection & Drain
- Coping Concrete 6,166.29
- Base Concrete 608.59
- Top Concrete 1,200.28
- Expansion Joint 53.24
- Frame 79.87
Cross Drainage
- (1.0 x 1.0) M 601.57
- (1.0 x 1.5) M 770.51
- (1.5 x 1.5) M 400.29
- 2 (1.5 x 1.5) M 1,025.73
- 3 (1.5 x 1.5) M 335.92
- 5 (1.5 x 1.5) M 537.79
Water Bus Station 120.22
Access People 634.80
4-11 Formwork > 2,5 m m2 149.00 172.82
Pedestrian Bridge 172.82

5 LOWER RIVER BANK AND PROTECTION WORKS


5-1 Procurement of CCSP Sheet Pile W-350-B -1000, 10 m length pcs 180.00 180.00
5-2 Procurement of CCSP Sheet Pile W-350-B -1000, 10 m length with Water Jet pcs 1,678.00 1,678.00
5-3 Driving Corrugated Concrete Sheet Pile W-350-B-1000, 10m length from the land m 800.00 800.00
5-4 Driving Corrugated Concrete Sheet Pile W-350-B-1000, 10m length from the land (Water Jet) m 8,396.00 8,396.00
5-5 Driving Corrugated Concrete Sheet Pile W-350-B-1000, 10m length by poonton m 800.00 800.00
5-6 Driving Corrugated Concrete Sheet Pile W-350-B-1000, 10m length by poonton (Water Jet) m 8,396.00 8,396.00

6 UPPER RIVER BANK PROTECTION WORK


6-1 Wet Masonry 1 pc : 4 sand m3 90.00 160.55
Water Bus Station 5.54
Access People 155.01
6-2 Plastering Mortar, thick 1.5 cm (1 pc : 3 Ps) m2 0 362.50
Access People 362.50
6-3 Pointing (1 PC : 2 Sand ) m2 0 --
6-4 Weep Hole PVC Pipe 5 cm Nos 0 --
6-5 Gravel and Sand Bedding m3 4,367.00 6,480.50
(Left) River Bank Protection By CCSP
- Frame 3,875.50
(Right) River Bank Protection By CCSP
- Frame 2,226.02
(Left) Slope protection & Drain
- Frame 194.66
(Right) Slope protection & Drain
- Frame 184.32
6-6 Concrete Block, 100 x 100 x 50 cm m2 0 --
6-7 Concrete Block, 40 x 40 x 30 cm pcs 23,545.00 21,498.75
(Left) River Bank Protection By CCSP
- Front View 10,969.25
(Right) River Bank Protection By CCSP
- Front View 10,529.50
6-8 Concrete Block, 40 x 40 x 20 cm pcs 1,512.00 16,959.80
(Left) Slope protection & Drain
- Front View 8,666.18
(Right) Slope protection & Drain
- Front View 8,293.62
7 PEDESTRIAN BRIDGE
7-1 Soil Investigation and Drilling (2 hole @ 20m) --
- Mechanical Boring including SPT Nos 2.00 2.00
- Dutch Cone Penetrometer Test Nos 2.00 2.00
7-2 Soil Test ( 4 sample ) Ls 1.00 1.00
7-3 Pile Dynamic Test ( 2 place ) Ls 1.00 1.00
7-4 Steel Mesh and Supporting Reber for Bearing Pad kg 86.00 86.00
7-5 Rubble Stone for Abutment ( accessories ) m2 14.00 14.00
7-6 Bearing Pad ( Fix Type ) nos 2.00 2.00
7-7 Bearing Pad ( Moveable Type ) nos 2.00 2.00
7-8 Non Shrinkage Mortar m3 0.11 0.11
7-9 Cast-in-Place Concrete Pilling (Bore Pile) for D = 0.8m m' 136.00 136.00
7-10 Cast-in-Place Prestressed Concrete for T-shaped Girder (PC-T Girder) Ls 1.00 1.00
7-11 Asphalt Treatment Base t = 5 cm m2 97.00 97.40
7-12 PVC Pipe Dia 2" for Planter Box nos 6.00 6.00
7-13 Deck Drain Dia 18 cm and PVC Pipe Dia 6" L = 500 mm pcs 4.00 4.00
7-14 Galvanized Pipe dia. 3" for Railling Post m 279.00 279.00
7-15 Planting of Ornament Trees (Planter Pot) nos 24.00 24.00
7-16 Expansion Joint for Bridge m 16.00 16.00

8 MISCELLANEOUS WORK
8-1 Elastic Joint Filler, t = 10 mm m2 1,622.00 4,582.68
(Left) River Bank Protection By CCSP
- Base & Top Concrete 889.32
- Expansion Joint 109.88
(Right) River Bank Protection By CCSP
- Base & Top Concrete 863.60
- Expansion Joint 107.84
(Left) Inspection Road and Parapet Wall
- Parapet Wall 87.11
- Inspection Road 103.99
(Right) Inspection Road and Parapet Wall
- Parapet Wall 84.88
- Inspection Road 100.88
(Left) Slope protection & Drain
- Side Drain 459.00
- Base & Top Concrete 607.80
- Expansion Joint 79.51
(Right) Slope protection & Drain
- Side Drain 436.50
- Base & Top Concrete 577.29
- Expansion Joint 75.09
8-2 Geo-textile mattress, 2 mm thickness m2 16,675.00 9,403.64
8-3 Water Stop m 3,405.00 2,411.08
(Left) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 133.21
(Right) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 129.75
(Left) Slope protection & Drain
- Side Drain 1,074.06
(Right) Slope protection & Drain
- Side Drain 1,074.06
8-4 Hand Rail and Ladder using steel galvanized pipe, d = 5 cm --
- Galvanized Parapet Steel Ladder nos 110.00 14.00
Access People 14.00
- Galvanized Coping Steel Ladder nos 110.00 14.00
Access People 14.00
8-5 Joint Sealent m2 990.00 364.09
(Left) River Bank Protection By CCSP
- Base & Top Concrete 37.05
- Expansion Joint 65.45
(Right) River Bank Protection By CCSP
- Base & Top Concrete 35.98
- Expansion Joint 64.24
(Left) Inspection Road and Parapet Wall
- Parapet Wall 5.85
- Inspection Road 15.61
(Right) Inspection Road and Parapet Wall
- Parapet Wall 5.70
- Inspection Road 15.14
(Left) Slope protection & Drain
- Side Drain 18.36
- Base & Top Concrete 36.84
- Expansion Joint 5.88
(Right) Slope protection & Drain
- Side Drain 17.46
- Base & Top Concrete 34.99
- Expansion Joint 5.55
8-6 Anchor Bar D = 20 mm nos 1,313.00 251.00
Cross Drainage
- (1.0 x 1.0) M 49.00
- (1.0 x 1.5) M 56.00
- (1.5 x 1.5) M 24.00
- 2 (1.5 x 1.5) M 64.00
- 3 (1.5 x 1.5) M 22.00
- 5 (1.5 x 1.5) M 36.00
8-7 Dowel Bar Ø = 20 mm nos 4,561.00 11,133.00
(Left) River Bank Protection By CCSP
- Expansion Joint 689.00
(Right) River Bank Protection By CCSP
- Expansion Joint 676.00
(Left) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 693.00
(Right) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 675.00
(Left) Slope protection & Drain
- Side Drain 3,672.00
- Expansion Joint 636.00
(Right) Slope protection & Drain
- Side Drain 3,492.00
- Expansion Joint 600.00
8-8 Roof and steel frame for Water Bus Station nos 2.00 4.00
Water Bus Station 4.00
8-9 Lamp Post nos 19.00 19.00
(Left) Inspection Road and Parapet Wall 10.00
(Right) Inspection Road and Parapet Wall 9.00
8-10 Slide gate H = 1.20m x B=1.20m set 7.00 14.00
Cross Drainage
- (1.0 x 1.0) M 7.00
- (1.0 x 1.5) M 7.00
8-11 Slide gate H = 1.20m x B=1.70m set 4.00 --
8-12 Slide gate H = 1.70m x B=1.70m set 2.00 19.00
Cross Drainage
- (1.5 x 1.5) M 3.00
- 2 (1.5 x 1.5) M 8.00
- 3 (1.5 x 1.5) M 3.00
- 5 (1.5 x 1.5) M 5.00
URAIAN BOBOT
NO SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET
ITEM PEKERJAAN (%)
1 2 3 4 5 11
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 2,004,000,000.000 2,004,000,000.000 0.20457
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 495,000,000.000 495,000,000.000 0.05053
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 103,713,500.000 103,713,500.000 0.01059
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 66,000,000.000 66,000,000.000 0.00674
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 165,038,500.000 165,038,500.000 0.01685
1.6 Fasilitas Komunikasi Ls 1.00 150,928,800.000 150,928,800.000 0.01541
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 148,500,000.000 148,500,000.000 0.01516

Jumlah I 3,133,180,800.000 0.31984


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 955,105,000.00 955,105,000.000 0.09750

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 8,900.000 800,816,482.000 0.08175
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 53,900.000 34,175,289,610.000 3.48863
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 107,800.000 75,650,264,844.000 7.72242
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 103,000.000 84,890,454,510.000 8.66566
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 136,700.000 77,111,517,201.000 7.87158
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 226,300.000 406,145,307,988.000 41.45953

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.020 44,500.000 25,102,139,390.000 2.56244
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 157,200.000 13,540,536,756.000 1.38223
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.730 220,500.000 18,992,928,465.000 1.93881
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.540 72,700.000 47,178,776,958.000 4.81603
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.100 44,700.000 49,794,776,370.000 5.08308
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.720 72,700.000 46,100,939,844.000 4.70601
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.540 92,000.000 10,604,521,680.000 1.08252

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.350 1,401,500.000 28,895,216,025.000 2.94964
2.4.2 Bekisting expose m2 5,815.65 229,500.000 1,334,691,675.000 0.13625
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 1,401,500.00 27,162,527,560.000 2.77277
2.4.4 Bekisting non expose m2 971.160 167,000.00 162,183,720.000 0.01656
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.080 20,081,000.00 4,258,778,480.000 0.43474
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.950 20,081,000.00 5,099,569,950.000 0.52057
2.4.7 Caping Beton K.225 m3 5,382.950 1,401,500.00 7,544,204,425.000 0.77012
URAIAN BOBOT
NO SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET
ITEM PEKERJAAN (%)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.000 1,720,000.00 36,120,000.000 0.00369
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.000 63,500,000.00 635,000,000.000 0.06482
2.5.3 V-notch set 1.000 23,550,000.00 23,550,000.000 0.00240
2.5.4 Pelat Settlement set 16.000 37,000,000.00 592,000,000.000 0.06043
2.5.5 Inklinometer set 1.000 127,000,000.00 127,000,000.000 0.01296
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kelembaban unit 1.000 305,000,000.00 305,000,000.000 0.03113
2.5.7 Total Earth Pressure unit 6.000 6,500,000.000 39,000,000.000 0.00398
-
Jumlah II 967,258,216,933.000 98.73823
III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.350 44,200.000 1,474,070.000 0.00015
3.2 Timbunan Tanah didatangkan m3 26.200 73,000.000 1,912,600.000 0.00020
3.3 Beton K-225 untuk angker m3 168.250 1,401,500.000 235,802,375.000 0.02407
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.000 145,500.000 40,158,000.000 0.00410
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.060 1,283,500.000 400,529,010.000 0.04089
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.000 1,232,000.000 11,088,000.000 0.00113
3.7 Bekisting non expose m2 1,485.420 167,000.000 248,065,140.000 0.02532
3.8 Besi Tulangan Ulir D32 ton 90.900 20,081,000.000 1,825,362,900.000 0.18633
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.000 2,280,000.000 1,710,000,000.000 0.17456

4,474,392,095.000 0.45675
IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.000 385,000,000.000 385,000,000.000 0.03930
- Total Station (Digital) 1 buah - -
- Sipat Datar (Water Pass) 2 buah - -
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 32,800,000.000 98,400,000.000 0.01004
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 18,751,000.000 56,253,000.000 0.00574
4.4 Mesin Pemotong rumput 90 cc buah 3.000 2,100,000.000 6,300,000.000 0.00064
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.000 28,611,500.000 28,611,500.000 0.00292
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.000 6,930,000.000 13,860,000.000 0.00141
4.7 Kamera DSLR 24 Megapixel buah 1.000 9,200,000.000 9,200,000.000 0.00094
4.8 LCD Portable live in 30.000 hours buah 2.000 11,711,500.000 23,423,000.000 0.00239
4.9 Printer LaserJet Scan, USB, Fax buah 3.000 8,533,000.000 25,599,000.000 0.00261
4.10 GPS Echosounder Multi Layer Dual Frequency buah 1.000 220,000,000.000 220,000,000.000 0.02246
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.000 75,000,000.000 150,000,000.000 0.01531
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.000 502,000,000.000 502,000,000.000 0.05124
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.000 55,000,000.000 220,000,000.000 0.02246
4.14 CCTV Standar 8 camera set 2.000 14,500,000.000 29,000,000.000 0.00296
- -
Jumlah IV 1,767,646,500.000 0.18044
URAIAN BOBOT
NO SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET
ITEM PEKERJAAN (%)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.000 591,300.000 898,776,000.000 0.09175
Pekerjaan LPB, tebal = 300 mm m3 2,280.000 565,000.000 1,288,200,000.000 0.13150
Beton K 125, untuk lantai kerja untuk trotoar m3 180.160 1,232,000.000 221,957,120.000 0.02266
Aspal hotmix, untuk jalan di puncak bendungan m2 380.000 308,600.000 117,268,000.000 0.01197
Canstin (60 x 30 x 25 x 20) bh 4,767.000 69,500.000 331,306,500.000 0.03382
Pengadaan tiang listrik beserta kelengkapannya Ls 1.000 127,800,000.000 127,800,000.000 0.01305
Jumlah V 2,985,307,620.000 0.30474
J U M L A H ( I + II + III + IV + V ) 979,618,743,948.000 100.00000
JADWAL PELAKSANAAN PEKERJAAN

Pekerjaan : Pembangunan Bendungan Tiga Dihaji Paket I di Kabupaten OKU Selatan


Balai : Besar Wilayah Sungai Sumatera VIII
Satker : Pembangunan Bendungan BBWS Sumatera VIII
Tahun Anggaran : 2018 - 2023
Nomor Kontrak : 01/SP/BEND.1/P.BENDUNGAN.S.VIII-Ah/X/2018
Tanggal : 16 Oktober 2018
AMANDEMEN NO 1 : 01/SP/AMD.01/BEND.I/P.BENDUNGAN. S.VIII-Ah/VII/2019
Tanggal : 11 JULI 2019
AMANDEMEN NO 2 : 01/SP/AMD.02/BEND.I/P.BENDUNGAN. S.VIII-Ah/X/2019
Tanggal : 24 Oktober 2019
AMANDEMEN NO 3 : PR.02.01./76.2/BEND.I/PB-Ah/XI/2019
Tanggal : 24 NOVEMBER 2019
AMANDEMEN NO 4 : 01/SP/AMD.04/BEND.I/P.BENDUNGAN. S.VIII-Ah/IV/2020
Tanggal : 20 APRIL 2020
AMANDEMEN NO 5 : 01/SP/AMD.05/BEND.I/P.BENDUNGAN. S.VIII-Ah/V/2020
Tanggal : 04 MEI 2020
AMANDEMEN NO 6 : 01/SP/AMD.06/BEND.I/P.BENDUNGAN. S.VIII-Ah/VI/2020
Tanggal : 30 JUNI 2020
NAMA PENYEDIA JASA : HUTAMA - BASUKI KSO
KONSULTAN SUPERVISI : PT. VIRAMA KARYA, KSO

AMANDEMEN NO. 6
TAHUN 2018 TAHUN 2019
No. URAIAN PEKERJAAN SATUAN
Okt 2018 Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Jun 2019 Jul 2019 Aug 2019 Sep 2019 Okt 2019 Nov 2019
KUANTITAS BOBOT (%)
17 Okt s.d 30 Okt 31 Okt s.d 27 Nov 28 Nov s.d 01 Jan 02 Jan s.d 29 Jan 30 Jan s.d 26 Feb 27 Feb s.d 02 Apr 03 Apr s.d 30 Apr 01 Mei s.d 28 Mei 29 Mei s.d 02 Jul 03 Jul s.d 30 Jul 31 Jul s.d 27 Aug 28 Aug s.d 01 Sep 02 Sep s.d 29 Okt 30 Okt s.d 26 Nov
1 2 3 4 5 6 7 8 9 10 11 12 13 13 14

I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 0.2046 0.0013 0.01577
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) LS 1.00 0.0505 0.0067 0.0067

1.3 Penyediaan Air Bersih Selama Konstruksi LS 1.00 0.0106


1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan LS 1.00 0.0067
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) LS 1.00 0.0168
1.6 Fasilitas Komunikasi LS 1.00 0.0154 0.0006 0.0001 0.0001 0.0001 0.0005 0.0001 0.0003 0.0003 0.0001 0.0001 0.0001 0.0001 0.0001 0.00003 0.00003
1.7 Penyediaan Video dan photo selama kegiatan konstruksi LS 1.00 0.0152

2 BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING AMANDEMEN NO 2 ( MC-0 )
24 OKTOBER 2019
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 0.0975
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 133,837.17 0.1216 0.08270
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 635,188.70 3.4949 0.70878
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 711,447.20 7.8290
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 746,454.06 7.8484
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 7.8716
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,823,488.89 42.1241
2,3 PEKERJAAN TIMBUNAN
2.3.1 Timbunan Inti (Zone 1) m3 564,093.02 2.5624
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.73 1.3822
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.73 1.9388
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.54 4.8160
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.10 5.0831
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.72 4.7060
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.54 1.0825
2,4 PEKERJAAN BETON
2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.35 2.9496
2.4.2 Bekisting expose m2 5,815.65 0.1362
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.04 2.7728
2.4.4 Bekisting non expose m2 971.16 0.0166
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.08 0.4347
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.95 0.5206
2.4.7 Caping Beton K.225 m3 5,382.95 0.7701
2,5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.00 0.0037
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.00 0.0648
2.5.3 V-notch set 1.00 0.0024
2.5.4 Pelat Settlement set 16.00 0.0604
2.5.5 Inklinometer set 1.00 0.0130
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kelembaban cuaca) unit 1.00 0.0311
2.5.7 Total Earth Pressure unit 6.00 0.0040
TAHUN 2018 - 2023
TAHUN 2020 TAHUN 2021

Des 2019 Jan 2020 Feb 2020 Mar 2020 Apr 2020 Mei 2020 Jun 2020 Jul 2020 Aug 2020 Sep 2020 Okt 2020 Nov 2020 Des 2020 Jan 2021 Feb 2021 Mar 2021 Apr 2021 Mei 2021 Jun 2021 Jul 2021 Aug 2021 Sep 2021 Okt 2021 Nov 2021 Des 2021,
27 Nov s.d 31 Des 01 Jan s.d 28 Jan 29 Jan s.d 25 Feb 26 Feb s.d 31 Mar 01 Apr s.d 28 Apr 29 Apr s.d 26 Mei 27 Mei s.d 30 Jun 01 Jul s.d 28 Jul 29 Jul s.d 01 Sep 02 Sep s.d 29 Sep 30 Sep s.d 27 Okt 28 Okt s.d 01 Des 02 Des s.d 29 Des 30 Des s.d 26 Jan 27 Jan s.d 23 Feb 24 Feb s.d 30 Mar 31 Mar s.d 27 Apr 28 Apr s.d 01 Jun 02 Jun s.d 29 Jun 30 Jun s.d 27 Jul 28 Jul s.d 31 Aug 01 Sep s.d 28 Sep 29 Sep s.d 26 Okt 27 Okt s.d 30 Nov 01 Des s.d 28 Des
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

0.00607 0.03023 0.03023 0.03023 0.03023 0.03023


0.00463 0.00463 0.00463 0.00463 0.00463 0.00463 0.00463
0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027

0.00084 0.00084 0.00084 0.00084 0.00084 0.00084 0.00084

0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043

0.00067 0.00010 0.00010 0.00010 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030
0.00328 0.00025 0.00025 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029

AMANDEMEN NO 6 ( MC-1 )
30 JUNI 2020 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049

0.01945 0.01945

0.71540 0.00924 0.00404 0.00498 0.11634 0.33646 0.38034 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241
0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219

0.4617 0.4617 0.4617 0.4617


0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280
1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552

0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068


0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576
0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808
0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007
0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118
0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961

0.2950 0.2950 0.2950 0.2950 0.2950 0.2950 0.2950 0.2950 0.2950


0.0136 0.0136 0.0136 0.0136 0.0136 0.0136 0.0136 0.0136 0.0136
0.2773 0.2773 0.2773 0.2773 0.2773 0.2773 0.2773 0.2773 0.2773 0.2773
0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017 0.0017
0.0435 0.0435 0.0435 0.0435 0.0435 0.0435 0.0435 0.0435
0.0521 0.0521 0.0521 0.0521 0.0521 0.0521 0.0521 0.0521 0.0521
0.0770 0.0770 0.0770 0.0770 0.0770 0.0770 0.0770 0.0770

0.0003 0.0003 0.0003


0.0065 0.0065

0.0050 0.0050 0.0050


TAHUN 2022 TAHUN 2023

Jan 2022 Feb 2022 Mar 2022 Apr 2022 Mei 2022 Jun 2022 Jul 2022 Aug 2022 Sep 2022 Okt 2022 Nov 2022 Des 2022 Jan 2023 Feb 2023 Mar 2023 Apr 2023 Mei 2023 Jun 2023 Jul 2023 Aug 2023 Sep 2023 KETERANGAN
29 Des s.d 01 Feb 02 Feb s.d 01 Mar 02 Mar s.d 29 Mar 30 Mar s.d 26 Apr 27 Apr s.d 31 Mei 01 Jun s.d 28 Jun 29 Jun s.d 26 Jul 27 Jul s.d 30 Aug 31 Aug s.d 27 Sep 28 Sep s.d 01 Nov 02 Nov s.d 29 Nov 30 Nov s.d 27 Des 28 Des s.d 31 Jan 01 Feb s.d 28 Feb 01 Mar s.d 28 Mar 29 Mar s.d 25 Apr 26 Apr s.d 30 Mei 31 Mei s.d 27 Juni 28 Jun s.d 01 Aug 02 Aug s.d 29 Aug 30 Aug s.d 20 Sep
40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

100_
0.03023
0.00463
0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027
0.00084
0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043
0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030
0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029

0.0049 0.0049 0.0049 0.0049 0.0049 0.0049

0.5219 0.5219 0.5219 0.5219

0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617
0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280
1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552

0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 _75
0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576
0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808
0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007
0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118
0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961
0.3608 0.3608 0.3608

0.2950
0.0136

0.0017 0.0017
0.0435 0.0435
0.0521
0.0770 0.0770

0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003 0.0003


0.0065 0.0065 0.0065 0.0065 0.0065 0.0065 0.0065 0.0065
0.0024
0.0050 0.0050 0.0050 0.0050 0.0050 0.0050 0.0050 0.0050 0.0050 50_
0.0130
0.0311
0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
3 JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.35 0.0002
3.2 Timbunan Tanah didatangkan m3 26.20 0.0002
3.3 Beton K-225 untuk angker m3 168.25 0.0241
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.00 0.0041
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.06 0.0409
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.00 0.0011
3.7 Bekisting non expose m2 1,485.42 0.0253
3.8 Besi Tulangan Ulir D32 ton 90.90 0.1863
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.00 0.1746

4 ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 0.0393
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 0.0100
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 0.0057
4.4 Mesin Pemotong rumput 90 cc buah 3.00 0.0006
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 0.0029
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 0.0014
4.7 Kamera DSLR 24 Megapixel buah 1.00 0.0009
4.8 LCD Portable live in 30.000 hours buah 2.00 0.0024
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 0.0026
4.10 GPS Echosounder Multi Layer Dual Frequency buah 1.00 0.0225
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 0.0153
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 0.0512
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 0.0225
4.14 CCTV Standar 8 camera set 2.00 0.0030

5 PEKERJAAN LAIN-LAIN
5.1 Pekerjaan LPA, tebal = 200 mm m3 1,520.00 0.0917
5.2 Pekerjaan LPB, tebal = 300 mm m3 2,280.00 0.1315
5.3 Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 0.0227
5.4 Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 0.0120
5.5 Canstin (60 x 30 x 25 x 20) ` bh 4,767.00 0.0338
5.6 Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 0.0130

Rencana % 100.0000 0.0315 0.0315 0.0315 0.0315 0.0315 0.0315 0.0315 0.0010 0.0010 0.0010 0.0010 0.0010 0.0007 0.0002 0.0010
BULAN
Realisasi % 0.0006 0.0068 0.0068 0.0001 0.0005 0.0001 0.0003 0.0003 0.0001 0.0001 0.0001 0.0014 0.0001

KONTRAK AWAL Rencana % - 0.0315 0.0631 0.0946 0.1261 0.1577 0.1892 0.2207 0.2217 0.2227 0.2236 0.2246 0.2256 0.2263 0.2265 0.2275

KOMULATIF Realisasi % - 0.0006 0.0075 0.0143 0.0144 0.0149 0.0150 0.0153 0.0155 0.0156 0.0157 0.0158 0.0173 0.0173
Deviasi % -0.0309 -0.0556 -0.0803 -0.1117 -0.1428 -0.1742 -0.2054 -0.2061 -0.2070 -0.2079 -0.2087 -0.2083 -0.2089
Rencana % 0.0173 0.0313 0.0316
BULAN
Realisasi % 0.0158 0.7915

AMANDEMEN NO 2 Rencana % - 0.0173 0.0487 0.0803

KOMULATIF Realisasi % 0.0173 0.03314 0.82465


Deviasi % -0.01551 0.74436
Rencana % 0.0173478203730226
BULAN
Realisasi %
AMANDEMEN NO 6 Rencana % -

KOMULATIF Realisasi %
Deviasi %
schedule Amandemen No
( Warnah Hitam )

schedule Kontrak
( Warnah Hitam )

schedule Amandemen No 6
( Warnah Hijau )

schedule Realisasi
( Warnah Merah )

0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0059 0.0059 0.3348 1.0188 1.2552 1.6158 4.6471 4.6471 4.6471 4.6471 4.7173 4.7238 4.7238 4.7119

0.2285 0.2294 0.2304 0.2314 0.2324 0.2333 0.2343 0.2353 0.2362 0.2372 0.2382 0.2440 0.2499 0.5846 1.6034 2.8586 4.4744 9.1216 13.7687 18.4158 23.0630 27.7802 32.5040 37.2277 41.9396

0.0321 0.0321 0.0321 0.0321 0.0321 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0061 0.0061 0.4692 0.9911 1.2058 1.5664 4.6033 4.6033 4.6033 4.6033 4.7179 4.7244 4.7244 4.7126

0.7194 0.0093 0.0044 0.0114 0.1163 0.3365 0.3803

0.1124 0.1444 0.1765 0.2085 0.2406 0.2418 0.2430 0.2441 0.2453 0.2465 0.2477 0.2537 0.2598 0.7290 1.7201 2.9258 4.4923 9.0956 13.6989 18.3022 22.9056 27.6235 32.3478 37.0722 41.7848

1.54400 1.5533 1.5577 1.5692 1.6855 2.0220 2.4023

1.43165 1.40893 1.38127 1.36062 1.44490 1.78017 2.15934

0.0370 0.0370 0.0370 0.0370 0.0419 0.0116 0.1835 0.7000 0.9578 1.3184 4.3774 4.3774 4.3774 4.3774 4.6920 4.6985 4.6985 4.6867

0.6432

2.40230 2.4393 2.4763 2.5133 2.5503 2.5922 2.6038 2.7874 3.4873 4.4451 5.7636 10.1410 14.5184 18.8958 23.2733 27.9653 32.6638 37.3623 42.0490

2.4023 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454

0.6061
0.0001 0.0001
0.0001 0.0001
0.0120 0.0120
0.0020 0.0020

schedule Amandemen No 2 0.0204 0.0204


( Warnah Hitam )
0.0006 0.0006
0.0127 0.0127
0.0932 0.0932
0.0873 0.0873

0.0393

0.0100
_25
0.0057
0.0006
0.0029
0.0014
0.0009
0.0024
0.0026
0.0225
0.0153
0.0512
0.0056 0.0056 0.0056 0.0056
0.0007 0.0007 0.0007 0.0007

0.0459 0.0459
0.0658 0.0658
0.0113 0.0113
0.0060 0.0060
0.0169 0.0169
0.0065 0.0065 0_

4.4346 4.0740 3.9518 3.9518 3.4488 3.4487 3.4440 3.4321 3.4321 3.4321 3.4321 3.4446 3.2358 2.9226 3.2836 3.2837 0.5766 0.2584 0.3176 0.2060 0.0491

46.3742 50.4482 54.4001 58.3519 61.8007 65.2495 68.6934 72.1256 75.5577 78.9898 82.4220 85.8666 89.1023 92.0249 95.3085 98.5923 99.1689 99.4273 99.7449 99.9509 100.0000

4.4353 4.0746 3.9525 3.9525 3.4424 3.4424 3.4375 3.4257 3.4257 3.4257 3.4257 3.4382 3.4382 2.9284 3.2893 3.2893 0.5326 0.3009 0.3202 0.2060 0.0323

46.2201 50.2947 54.2472 58.1997 61.6421 65.0844 68.5220 71.9476 75.3733 78.7990 82.2247 85.6629 89.1010 92.0295 95.3187 98.6080 99.1406 99.4415 99.7617 99.9677 100.0000

4.4094 4.0488 3.9266 3.9266 3.4165 3.4165 3.4116 3.3998 3.3998 3.3998 3.3998 3.4123 3.4123 2.9506 3.3115 3.3115 0.5327 0.3010 0.3203 0.2064 0.0370

46.4584 50.5072 54.4338 58.3604 61.7769 65.1934 68.6051 72.0049 75.4047 78.8045 82.2043 85.6166 89.0289 91.9796 95.2910 98.6025 99.1352 99.4362 99.7566 99.9630 100.0000

3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023

SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 0.2046 1.000 0.2046 0.2032 0.0013 - -
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, ben Ls 1.000 0.0505 1.000 0.0505 0.0371 0.0135 - -
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 0.0106 1.000 0.0106 0.0106 - - -
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 0.0067 1.000 0.0067 0.0067 - - -
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 0.0168 1.000 0.0168 0.0168 - - -
1.6 Fasilitas Komunikasi Ls 1.000 0.0154 1.000 0.0154 0.0129 0.0025 - -
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 0.0152 1.000 0.0152 0.0152 - - -

Jumlah I 0.3198 0.3198 0.3025 0.0173 - -


II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.000 0.0975 1.000 0.0975 0.0975 - - -

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 0.0817 137,786.640 0.1252 0.0817 - 0.0434 -

2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 3.4886 582,344.610 3.2041 3.4886 - - 0.2845

2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 7.7224 711,447.200 7.8290 7.7224 - 0.1065 -

2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 8.6657 824,179.170 8.6657 8.6657 - - -
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 7.8716 564,093.030 7.8716 7.8716 - - -
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 41.4595 1,800,543.504 41.5940 41.4595 - 0.1345 -

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1) m3 564,093.020 2.5624 564,093.020 2.5624 2.5624 - - -
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 1.3822 86,135.730 1.3822 1.3822 - - -
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.730 1.9388 86,135.730 1.9388 1.9388 - - -
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.540 4.8160 648,951.540 4.8160 4.8160 - - -
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.100 5.0831 1,113,977.100 5.0831 5.0831 - - -
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.720 4.7060 634,125.720 4.7060 4.7060 - - -
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.540 1.0825 115,266.540 1.0825 1.0825 - - -

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.350 2.9496 20,617.350 2.9496 2.9496 - - -
2.4.2 Bekisting expose m2 5,815.650 0.1362 5,815.650 0.1362 0.1362 - - -
Page 34
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 2.7728 19,381.040 2.7728 2.7728 - - -
2.4.4 Bekisting non expose m2 971.160 0.0166 971.160 0.0166 0.0166 - - -
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.080 0.4347 212.080 0.4347 0.4347 - - -
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.950 0.5206 253.950 0.5206 0.5206 - - -
2.4.7 Caping Beton K.225 m3 5,382.950 0.7701 5,382.950 0.7701 0.7701 - - -

Page 35
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.000 0.0037 21.000 0.0037 0.0037 - - -
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.000 0.0648 10.000 0.0648 0.0648 - - -
2.5.3 V-notch set 1.000 0.0024 1.000 0.0024 0.0024 - - -
2.5.4 Pelat Settlement set 16.000 0.0604 16.000 0.0604 0.0604 - - -
2.5.5 Inklinometer set 1.000 0.0130 1.000 0.0130 0.0130 - - -
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, unit 1.000 0.0311 1.000 0.0311 0.0311 - - -
2.5.7 Total Earth Pressure unit 6.000 0.0040 6.000 0.0040 0.0040 - - -

Jumlah II 98.7382 98.7382 98.7382 - 0.2845 0.2845


III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m m3 33.350 0.0002 33.350 0.0002 0.0002 - - -
3.2 Timbunan Tanah didatangkan m3 26.200 0.0002 26.200 0.0002 0.0002 - - -
3.3 Beton K-225 untuk angker m3 168.250 0.0241 168.250 0.0241 0.0241 - - -
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring) nos 276.000 0.0041 276.000 0.0041 0.0041 - - -
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A m3 312.060 0.0409 312.060 0.0409 0.0409 - - -
3.6 Beton Mutu fc' = 9.8 MPa (K-125) m3 9.000 0.0011 9.000 0.0011 0.0011 - - -
3.7 Bekisting non expose m2 1,485.420 0.0253 1,485.420 0.0253 0.0253 - - -
3.8 Besi Tulangan Ulir D32 ton 90.900 0.1863 90.900 0.1863 0.1863 - - -
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.000 0.1746 750.000 0.1746 0.1746 - - -

Jumlah III 0.4567 0.4567 0.4567 -


IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.000 0.0393 1.000 0.0393 0.0393 - - -
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 0.0100 3.000 0.0100 0.0100 - - -
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 0.0057 3.000 0.0057 0.0057 - - -
4.4 Mesin Pemotong rumput 90 cc buah 3.000 0.0006 3.000 0.0006 0.0006 - - -
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.000 0.0029 1.000 0.0029 0.0029 - - -
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.000 0.0014 2.000 0.0014 0.0014 - - -
4.7 Kamera DSLR 24 Megapixel buah 1.000 0.0009 1.000 0.0009 0.0009 - - -
4.8 LCD Portable live in 30.000 hours buah 2.000 0.0024 2.000 0.0024 0.0024 - - -
4.9 Printer LaserJet Scan, USB, Fax buah 3.000 0.0026 3.000 0.0026 0.0026 - - -
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.000 0.0225 1.000 0.0225 0.0225 - - -
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.000 0.0153 2.000 0.0153 0.0153 - - -
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.000 0.0512 1.000 0.0512 0.0512 - - -
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.000 0.0225 4.000 0.0225 0.0225 - - -
4.14 CCTV Standar 8 camera set 2.000 0.0030 2.000 0.0030 0.0030 - - -

Jumlah IV 0.1804 0.1804 0.1804 -

Page 36
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.000 0.0917 1,520.000 0.0917 0.0917 - - -
Pekerjaan LPB, tebal = 300 mm m3 2,280.000 0.1315 2,280.000 0.1315 0.1315 - - -
Beton K 125, untuk lantai kerja untuk trotoar m3 180.160 0.0227 180.160 0.0227 0.0227 - - -
Aspal hotmix, untuk jalan di puncak bendungan m2 380.000 0.0120 380.000 0.0120 0.0120 - - -
Canstin (60 x 30 x 25 x 20) bh 4,767.000 0.0338 4,767.000 0.0338 0.0338 - - -
Pengadaan tiang listrik beserta kelengkapannya Ls 1.000 0.0130 1.000 0.0130 0.0130 - - -

Jumlah V 0.3047 0.3047 0.3047 - - -


J U M L A H ( I + II + III + IV + V ) 100.0000 100.0000 99.9827 0.0173 0.2845 0.2845

Menyetujui dan menyanggupi Hasil evaluasi bobot (%) tersebut diatas sebagai dasar pekerjaan
Pembangunan Bendungan Tiga Dihaji Paket I di Kab. OKU Selatan

PENYEDIA JASA, KONSULTAN SUPERVISI


HUTAMA - BASUKI, KSO PT. Virama Karya ( Persero ), KSO

Lanjar Samadi, ST Ir. Zaki BR, MM


Manajer Proyek Team Leader

Page 37
KETERANGAN

(10)

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

TIDAK BERUBAH

ADA PERUBAHAN DIKARENAKAN BOBOT AMANDEMEN NO 2, BERTAMBAH


ADA PERUBAHAN DIKARENAKAN BOBOT AMANDEMEN NO 2, BERKURANG
ADA PERUBAHAN DIKARENAKAN BOBOT AMANDEMEN NO 2, BERTAMBAH
TIDAK BERUBAH
TIDAK BERUBAH
ADA PERUBAHAN DIKARENAKAN BOBOT AMANDEMEN NO 2, BERTAMBAH

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

TIDAK BERUBAH
TIDAK BERUBAH

Page 38
KETERANGAN

(10)
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

Page 39
KETERANGAN

(10)

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

TIDAK BERUBAH

TIDAK BERUBAH

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

Page 40
KETERANGAN

(10)

TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH

PENYEDIA JASA,
HUTAMA - BASUKI, KSO

Lanjar Samadi, ST
Manajer Proyek

Page 41
LAPO
NAMA KEGIATAN : Pembangunan Bendungan Tiga Dihaji Paket 1 Di Kabupaten OKU Selatan
NOMOR KONTRAK : 01/SP/BEND.1/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL : 16 Oktober 2018
AMANDEMEN NO 1 : 01/SP.AMD.01/BEND.I/P.BENDUNGAN.S.VIII-Ah/VII/2019
TANGGAL : 11 Juli 2019
AMANDEMEN NO 2 : 01/SP/AMD.02/BEND.I/P.BENDUNGAN. S.VIII-Ah/X/2019
TANGGAL : 24 Oktober 2019
AMANDEMEN NO 3 : PR.02.01./76.2/BEND.I/PB-Ah/XI/2019
TANGGAL : 25 November 2019
AMANDEMEN NO 4 : 01/SP/AMD.04/BEND.I/P.BENDUNGAN. S.VIII-Ah/IV/2020
TANGGAL : 20 April 2020
AMANDEMEN NO 5 : 01/SP/AMD.05/BEND.I/P.BENDUNGAN. S.VIII-Ah/V/2020
TANGGAL : 04 Mei 2020
AMANDEMEN NO 6 : 01/SP/AMD.06/BEND.I/P.BENDUNGAN. S.VIII-Ah/VI/2020
TANGGAL : 30 Juni 2020
KONTRAKTOR : Hutama - Basuki, KSO
KONSULTAN SUPERVISI : PT Virama Karya (Persero) KSO PT. Tata Guna Patria, PT. Tritunggal Pratyaksa,

LAPORAN BULAN KE : 22
TANGGAL : 01 Juli 2020 s/d 28 Juli 2020

URAIAN
NO
ITEM PEKERJAAN
1 2
I PEKERJAAN PERSIAPAN

1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi


1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll
1.3 Penyediaan Air Bersih Selama Konstruksi
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN )
1.6 Fasilitas Komunikasi
1.7 Penyediaan Video dan photo selama kegiatan konstruksi

Jumlah I
II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya

2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan

2.3 PEKERJAAN TIMBUNAN


2.3.1 Timbunan Inti (Zone 1)
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar)
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile
2.3.5 Timbunan Zone 3A, Rockfill
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile
2.3.7 Timbunan Riprap / Zona 4 (material Batu)

2.4 PEKERJAAN BETON


2.4.1 Grouting Gallery, (Beton K 225)
2.4.2 Bekisting expose
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A
2.4.4 Bekisting non expose
2.4.5 Besi Tulangan Ulir D32 Caping Grouting
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery
2.4.7 Caping Beton K.225

2.5 INSTRUMEN BENDUNGAN


2.5.1 Patok geser
2.5.2 Pengadaan, pemasangan vibrating piezometer
2.5.3 V-notch
2.5.4 Pelat Settlement
2.5.5 Inklinometer
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan
2.5.7 Total Earth Pressure

Jumlah II
III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m
3.2 Timbunan Tanah didatangkan
3.3 Beton K-225 untuk angker
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring)
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A
3.6 Beton Mutu fc' = 9.8 MPa (K-125)
3.7 Bekisting non expose
3.8 Besi Tulangan Ulir D32
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling)

IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari :
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ),
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA
4.4 Mesin Pemotong rumput 90 cc
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm
4.7 Kamera DSLR 24 Megapixel
4.8 LCD Portable live in 30.000 hours
4.9 Printer LaserJet Scan, USB, Fax
4.10 GPS Echosounder Multi Layer Dual Frequency
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK)
4.13 CCTV (Rotating and Zooming) dan Instalasi
4.14 CCTV Standar 8 camera

Jumlah IV
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm
Pekerjaan LPB, tebal = 300 mm
Beton K 125, untuk lantai kerja untuk trotoar
Aspal hotmix, untuk jalan di puncak bendungan
Canstin (60 x 30 x 25 x 20)
Pengadaan tiang listrik beserta kelengkapannya
Jumlah V

J U M L A H ( I + II + III + IV + V )

DISETUJUI OLEH :
Direksi Pekerjaan
BBWS Sumatera VIII

PITERSON MARU' AO, ST


NIP. 19750521 200911 1001
LAPORAN BULANAN
Pembangunan Bendungan Tiga Dihaji Paket 1 Di Kabupaten OKU Selatan
01/SP/BEND.1/P.BENDUNGAN.S.VIII-Ah/X/2018
16 Oktober 2018
01/SP.AMD.01/BEND.I/P.BENDUNGAN.S.VIII-Ah/VII/2019
11 Juli 2019
01/SP/AMD.02/BEND.I/P.BENDUNGAN. S.VIII-Ah/X/2019
24 Oktober 2019
PR.02.01./76.2/BEND.I/PB-Ah/XI/2019
25 November 2019
01/SP/AMD.04/BEND.I/P.BENDUNGAN. S.VIII-Ah/IV/2020
20 April 2020
01/SP/AMD.05/BEND.I/P.BENDUNGAN. S.VIII-Ah/V/2020
04 Mei 2020
01/SP/AMD.06/BEND.I/P.BENDUNGAN. S.VIII-Ah/VI/2020
30 Juni 2020
Hutama - Basuki, KSO
PT Virama Karya (Persero) KSO PT. Tata Guna Patria, PT. Tritunggal Pratyaksa, PT Bina Karya (Persero), PT. Kwarsa Hexagon

01 Juli 2020 s/d 28 Juli 2020


AMANDEMEN NO 06
URAIAN
SAT.
VOLUME BOBOT ( % )
ITEM PEKERJAAN
2 3 4 5

sasi Peralatan Konstruksi Ls 1.00 0.20457


sasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll Ls 1.00 0.05053
elama Konstruksi Ls 1.00 0.01059
sasi Peralatan Laboratorium Lapangan Ls 1.00 0.00674
dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 0.01685
Ls 1.00 0.01541
hoto selama kegiatan konstruksi Ls 1.00 0.01516

Jumlah I 0.31984

elama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 0.09750

ENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)

uang ke disposal dengan jarak 1000 - 1500 m m2 133,837.174 0.12159


Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 635,188.701 3.49490
dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 711,447.200 7.82896
dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 746,454.056 7.84844
ow Area di angkut ke Lokasi Penimbunan m3 564,093.030 7.87158
engan peledakan), diangkut ke Lokasi Penimbunan m3 1,823,488.888 42.12410

m3 564,093.020 2.56244
Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 1.38223
Zona 2b (material Kerikil dari luar) m3 86,135.730 1.93881
ckfill dari Stockpile m3 648,951.540 4.81603
m3 1,113,977.100 5.08308
ckfill (transisi) dari Stockpile m3 634,125.720 4.70601
a 4 (material Batu) m3 115,266.540 1.08252

m3 20,617.350 2.94964
m2 5,815.650 0.13625
n Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 2.77277
m2 971.160 0.01656
Caping Grouting ton 212.080 0.43474
Grouting Gallery ton 253.950 0.52057
m3 5,382.950 0.77012

nos 21.000 0.00369


vibrating piezometer titk 10.000 0.06482
set 1.000 0.00240
set 16.000 0.06043
set 1.000 0.01296
gan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan unit 1.000 0.03113
unit 6.000 0.00398
-
Jumlah II 98.73823

ke disposal dengan jarak sampai 700 m m3 33.350 0.00015


m3 26.200 0.00020
m3 168.250 0.02407
a. 2", L = 1,5 m (termasuk penyaring) nos 276.000 0.00410
MPa (K-175) Type A m3 312.060 0.04089
m3 9.000 0.00113
m2 1,485.420 0.02532
ton 90.900 0.18633
ting trash boom) setiap @ 3m, termasuk jaring dan kabel (sling) m 750.000 0.17456

0.45675

set 1.000 0.03930

el i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 0.01004
A3, Stabilizer, MS Office, AutoCAD)
HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 0.00574
buah 3.000 0.00064
an Pompa Air 2" 2 buah set 1.000 0.00292
2.2 Kw/8500 rpm buah 2.000 0.00141
buah 1.000 0.00094
buah 2.000 0.00239
buah 3.000 0.00261
Layer Dual Frequency buah 1.000 0.02246
W copier, color scan black white speed 25/30 ipm buah 2.000 0.01531
penumpang 2 engine 85 PK) unit 1.000 0.05124
oming) dan Instalasi set 4.000 0.02246
set 2.000 0.00296

Jumlah IV 0.18044

m3 1,520.000 0.09175
m3 2,280.000 0.13150
ai kerja untuk trotoar m3 180.160 0.02266
an di puncak bendungan m2 380.000 0.01197
bh 4,767.000 0.03382
beserta kelengkapannya Ls 1.000 0.01305
Jumlah V 0.30474

100.00000

DIPERIKSA OLEH :
PT. Virama Karya, KSO
(Konsultan Supervisi)

Iwan Setiawan Wempie, ST Setia Widiantoro, ST., MM


Engineer Quantity Manajemen Konstruksi
NAN

sero), PT. Kwarsa Hexagon

AMANDEMEN NO 6 PRESTASI
VOLUME s/d BOBOT s/d VOLUME BOBOT VOLUME s/d BOBOT s/d FISIK KET
Bulan lalu Bulan lalu (%) Bulan ini Bulan ini (%) Bulan ini Bulan ini (%) (%)
6 7 8 9 10 11

0.11327 0.02317 - - 0.1133 0.02317 11.3273


0.26667 0.01347 - - 0.2667 0.01347 26.6667
- - - - - - -
- - - - - - -
- - - - - - -
0.23158 0.00357 - - 0.2316 0.00357 23.1583
0.25000 0.00379 - - 0.2500 0.00379 25.0000

- 0.04400 - 0.04400

- - - - - - -

91,030.17 0.08270 - - 91,030.17 0.08270 68.0156


413,582.70 2.27559 92,671.1500 0.50989 506,253.85 2.78548 79.7013
- - 12,110.0000 0.13326 12,110.00 0.13326 1.7022
- - - - - - -
- - - - - - -
- - - - - - -

- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -

- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- 2.35829 0.64315 3.00144
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- - - - -
- -
- - - - - - -
- -
- -
- - - - - - -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- - - - -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - -
-
- 2.40230 0.64315 3.04545

DIBUAT OLEH :
Hutama - Basuki, KSO
(Kontraktor)

Setia Widiantoro, ST., MM Alfian Noor Ridho, ST


Site Engineering Manager
Manajemen Konstruksi