NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
AMOUNT
BoQ
URAIAN ITEM PEKERJAAN
KONTRAK AMENDEMEN NO 2 Bobot
Keterangan
(Rp) (Rp) (%)
No.
DIAJUKAN OLEH
HUTAMA - BASUKI, KSO
( Kontraktor )
Lanjar Samadi, ST
Manajer Proyek
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 - -- - --
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, b Ls 1.000 495,000,000.00 495,000,000.00 0.0505 1.000 495,000,000.00 495,000,000.00 0.0505 - -- - --
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 103,713,500.00 103,713,500.00 0.0106 1.000 103,713,500.00 103,713,500.00 0.0106 - -- - --
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 66,000,000.00 66,000,000.00 0.0067 1.000 66,000,000.00 66,000,000.00 0.0067 - -- - --
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 165,038,500.00 165,038,500.00 0.0168 1.000 165,038,500.00 165,038,500.00 0.0168 - -- - --
1.6 Fasilitas Komunikasi Ls 1.000 150,928,800.00 150,928,800.00 0.0154 1.000 150,928,800.00 150,928,800.00 0.0154 - -- - --
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 148,500,000.00 148,500,000.00 0.0152 1.000 148,500,000.00 148,500,000.00 0.0152 - -- - --
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 8,900.00 800,816,482.00 0.0817 137,786.640 8,900.00 1,226,301,096.00 0.1252 47,807.260 425,484,614.00 - --
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 53,900.00 34,175,289,610.00 3.4886 582,344.610 53,900.00 31,388,374,479.00 3.2041 - -- 51,705.290 2,786,915,131.00
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 107,800.00 75,650,264,844.00 7.7224 711,447.200 107,800.00 76,694,008,160.00 7.8290 9,682.220 1,043,743,316.00 - --
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m3 824,179.170 103,000.00 84,890,454,510.00 8.6657 824,179.170 103,000.00 84,890,454,510.00 8.6657 - -- - --
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 136,700.00 77,111,517,201.00 7.8716 564,093.030 136,700.00 77,111,517,201.00 7.8716 - -- - --
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 226,300.00 406,145,307,988.00 41.4595 1,800,543.504 226,300.00 407,462,994,955.20 41.5940 5,822.744 1,317,686,967.20 - --
Page 2
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
Page 3
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
Page 4
HUTAMA – BASU
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 0.2046 1.000 2,004,000,000.00 2,004,000,000.00 0.2046 --
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.000 0.0505 1.000 495,000,000.00 495,000,000.00 0.0505 --
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 0.0106 1.000 103,713,500.00 103,713,500.00 0.0106 --
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 0.0067 1.000 66,000,000.00 66,000,000.00 0.0067 --
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 0.0168 1.000 165,038,500.00 165,038,500.00 0.0168 --
1.6 Fasilitas Komunikasi Ls 1.000 0.0154 1.000 150,928,800.00 150,928,800.00 0.0154 --
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 0.0152 1.000 148,500,000.00 148,500,000.00 0.0152 --
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 0.0817 137,786.640 8,900.00 1,226,301,096.00 0.1252 47,807.260
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 3.4886 582,344.610 53,900.00 31,388,374,479.00 3.2041 --
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 7.7224 711,447.200 107,800.00 76,694,008,160.00 7.8290 9,682.220
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 8.6657 824,179.170 103,000.00 84,890,454,510.00 8.6657 --
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 7.8716 564,093.030 136,700.00 77,111,517,201.00 7.8716 --
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 41.4595 1,800,543.504 226,300.00 407,462,994,955.20 41.5940 5,822.744
Page 5
HUTAMA – BASU
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
2.4 PEKERJAAN BETON
2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.350 2.9496 20,617.350 1,401,500.00 28,895,216,025.00 2.9496 --
2.4.2 Bekisting expose m2 5,815.650 0.1362 5,815.650 229,500.00 1,334,691,675.00 0.1362 --
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 2.7728 19,381.040 1,401,500.00 27,162,527,560.00 2.7728 --
2.4.4 Bekisting non expose m2 971.160 0.0166 971.160 167,000.00 162,183,720.00 0.0166 --
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.080 0.4347 212.080 20,081,000.00 4,258,778,480.00 0.4347 --
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.950 0.5206 253.950 20,081,000.00 5,099,569,950.00 0.5206 --
2.4.7 Caping Beton K.225 m3 5,382.950 0.7701 5,382.950 1,401,500.00 7,544,204,425.00 0.7701 --
Page 6
HUTAMA – BASU
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
REKAPITULASI VOLUME MC - 0
Volume
ORIGINAL CONTRACT MC - 0 %
BoQ URAIAN ITEM PEKERJAAN Satuan
Bertambah
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12)
IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 0.0393 1.00 385,000,000.00 385,000,000.00 0.0393 --
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 0.0100 3.00 32,800,000.00 98,400,000.00 0.0100 --
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 0.0057 3.00 18,751,000.00 56,253,000.00 0.0057 --
4.4 Mesin Pemotong rumput 90 cc buah 3.00 0.0006 3.00 2,100,000.00 6,300,000.00 0.0006 --
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 0.0029 1.00 28,611,500.00 28,611,500.00 0.0029 --
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 0.0014 2.00 6,930,000.00 13,860,000.00 0.0014 --
4.7 Kamera DSLR 24 Megapixel buah 1.00 0.0009 1.00 9,200,000.00 9,200,000.00 0.0009 --
4.8 LCD Portable live in 30.000 hours buah 2.00 0.0024 2.00 11,711,500.00 23,423,000.00 0.0024 --
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 0.0026 3.00 8,533,000.00 25,599,000.00 0.0026 --
4.1 GPS Echosounder Multi Layer Dual Frequency buah 1.00 0.0225 1.00 220,000,000.00 220,000,000.00 0.0225 --
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 0.0153 2.00 75,000,000.00 150,000,000.00 0.0153 --
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 0.0512 1.00 502,000,000.00 502,000,000.00 0.0512 --
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 0.0225 4.00 55,000,000.00 220,000,000.00 0.0225 --
4.14 CCTV Standar 8 camera set 2.00 0.0030 2.00 14,500,000.00 29,000,000.00 0.0030 --
Page 7
HUTAMA – BASUKI KSO
REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang
(13) (14)
--
--
--
--
--
--
--
--
--
51,705.290
--
--
--
--
--
--
--
--
--
--
--
Page 8
HUTAMA – BASUKI KSO
REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang
(13) (14)
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
Page 9
HUTAMA – BASUKI KSO
REKAPITULASI VOLUME MC - 0
Volume
REMARK
Berkurang
(13) (14)
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
Martapura, 2019
DIAJUKAN OLEH :
Kontraktor
Hutama - Basuki, KSO
Lanjar Samadi, ST
Manajer Proyek
Page 10
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 0.2046 1.00 2,004,000,000.00 2,004,000,000.00 0.2108 1.00 #DIV/0! #DIV/0!
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 0.0505 1.00 495,000,000.00 495,000,000.00 0.0521 1.00 #DIV/0! #DIV/0!
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 0.0106 1.00 103,713,500.00 103,713,500.00 0.0109 1.00 #DIV/0! #DIV/0!
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 0.0067 1.00 66,000,000.00 66,000,000.00 0.0069 1.00 #DIV/0! #DIV/0!
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 0.0168 1.00 165,038,500.00 165,038,500.00 0.0174 1.00 #DIV/0! #DIV/0!
1.6 Fasilitas Komunikasi Ls 1.00 0.0154 1.00 150,928,800.00 150,928,800.00 0.0159 1.00 #DIV/0! #DIV/0!
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 0.0152 1.00 148,500,000.00 148,500,000.00 0.0156 1.00 #DIV/0! #DIV/0!
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.38 0.0817 137,786.64 8,900.00 1,226,301,096.00 0.1290 0.00 #DIV/0! #DIV/0!
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.90 3.4886 582,344.61 53,900.00 31,388,374,479.00 3.3015 0.00 #DIV/0! #DIV/0!
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.98 7.7224 711,447.20 107,800.00 76,694,008,160.00 8.0669 0.00 #DIV/0! #DIV/0!
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.17 8.6657 824,179.17 103,000.00 84,890,454,510.00 8.9290 0.00 #DIV/0! #DIV/0!
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 7.8716 564,093.03 136,700.00 77,111,517,201.00 8.1108 0.00 #DIV/0! #DIV/0!
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.76 41.4595 1,800,543.50 226,300.00 407,462,994,955.20 42.8582 0.00 #DIV/0! #DIV/0!
Page 11
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.00 0.0037 21.00 1,720,000.00 36,120,000.00 0.0038 0.05 #DIV/0! #DIV/0!
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.00 0.0648 10.00 63,500,000.00 635,000,000.00 0.0668 0.10 #DIV/0! #DIV/0!
2.5.3 V-notch set 1.00 0.0024 1.00 23,550,000.00 23,550,000.00 0.0025 1.00 #DIV/0! #DIV/0!
2.5.4 Pelat Settlement set 16.00 0.0604 16.00 37,000,000.00 592,000,000.00 0.0623 0.06 #DIV/0! #DIV/0!
2.5.5 Inklinometer set 1.00 0.0130 1.00 127,000,000.00 127,000,000.00 0.0134 1.00 #DIV/0! #DIV/0!
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kelembaban cuaca) unit 1.00 0.0311 1.00 305,000,000.00 305,000,000.00 0.0321 1.00 #DIV/0! #DIV/0!
2.5.7 Total Earth Pressure unit 6.00 0.0040 6.00 6,500,000.00 39,000,000.00 0.0041 0.17 #DIV/0! #DIV/0!
Page 12
HUTAMA – BASUKI KSO
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
PROGRESS TERHADAP MC - 0
PROGRESS TERHADAP
CONTRACT
MC - 0 % PROGRESS TERHADAP MC - 0 % PRESTASI
BoQ URAIAN ITEM PEKERJAAN Satuan KET
No. Volume BOBOT ( % ) Volume Harga satuan Jumlah harga BOBOT ( % ) Volume BOBOT ( % ) FISIK ( % )
(1) (2) (3) (4) (7) (8) (9) (10) (11) (12) (13) (14) (15)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.00 0.0917 1,520.00 591,300.00 898,776,000.00 0.0945 0.00 #DIV/0! #DIV/0!
Pekerjaan LPB, tebal = 300 mm m3 2,280.00 0.1315 2,280.00 565,000.00 1,288,200,000.00 0.1355 0.00 #DIV/0! #DIV/0!
Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 0.0227 180.16 1,232,000.00 221,957,120.00 0.0233 0.01 #DIV/0! #DIV/0!
Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 0.0120 380.00 308,600.00 117,268,000.00 0.0123 0.00 #DIV/0! #DIV/0!
Canstin (60 x 30 x 25 x 20) bh 4,767.00 0.0338 4,767.00 69,500.00 331,306,500.00 0.0348 0.00 #DIV/0! #DIV/0!
Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 0.0130 1.00 127,800,000.00 127,800,000.00 0.0134 1.00 #DIV/0! #DIV/0!
Page 13
ORIGINAL CONTRACT
BoQ IKUT KONTRAK Volume Pekerjaan yang tdk berubah ( disesuaikan dengan kontrak ) VOLUME PEKERJAAN TANAH BENDUNGAN U
URAIAN ITEM PEKERJAAN
Pekerjaan PEKERJAAN LAIN- JETTY DAN INSTRUMEN Besi Tulangan Ulir Clearing & grubbing Galian Pondasi - Galian Tanah diangkut
Satuan Volume Harga satuan Jumlah harga BOBOT ( % ) Pekerjaan Persiapan ALAT PENUNJANG OP Caping Beton K.225 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan
Dewatering LAIN TRASHBOOM BENDUNGAN D32 Caping Grouting ke disposal
No.
(1) (2) (3) (4) (5) (6) (7)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 2,004,000,000.00 2,004,000,000.00 0.2046 1.00
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 495,000,000.00 495,000,000.00 0.0505 1.00
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 103,713,500.00 103,713,500.00 0.0106 1.00
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 66,000,000.00 66,000,000.00 0.0067 1.00
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 165,038,500.00 165,038,500.00 0.0168 1.00
1.6 Fasilitas Komunikasi Ls 1.00 150,928,800.00 150,928,800.00 0.0154 1.00
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 148,500,000.00 148,500,000.00 0.0152 1.00
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.38 8,900.00 800,816,482.00 0.0817 137,786.64
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.90 53,900.00 34,175,289,610.00 3.4886 582,344.61
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.98 107,800.00 75,650,264,844.00 7.7224
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.17 103,000.00 84,890,454,510.00 8.6657
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 136,700.00 77,111,517,201.00 7.8716 564,093.03
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.76 226,300.00 406,145,307,988.00 41.4595 1,800,543.504
1.00 2,004,000,000.00
1.00 495,000,000.00
1.00 103,713,500.00
1.00 66,000,000.00
1.00 165,038,500.00
1.00 150,928,800.00
1.00 148,500,000.00
1.00 955,105,000.00
137,786.64 1,226,301,096.00
582,344.61 31,388,374,479.00
711,447.20 711,447.20 76,694,008,160.00
824,179.17 824,179.17 84,890,454,510.00
564,093.03 77,111,517,201.00
1,800,543.50 407,462,994,955.20
21.00 36,120,000.00
10.00 635,000,000.00
1.00 23,550,000.00
16.00 592,000,000.00
1.00 127,000,000.00
1.00 305,000,000.00
6.00 39,000,000.00
33.35 1,474,070.00
26.20 1,912,600.00
168.25 235,802,375.00
276.00 40,158,000.00
312.06 400,529,010.00
9.00 11,088,000.00
1,485.42 248,065,140.00
90.90 1,825,362,900.00
750.00 1,710,000,000.00
1.00 385,000,000.00
3.00 98,400,000.00
3.00 56,253,000.00
3.00 6,300,000.00
1.00 28,611,500.00
2.00 13,860,000.00
1.00 9,200,000.00
2.00 23,423,000.00
3.00 25,599,000.00
1.00 220,000,000.00
2.00 150,000,000.00
1.00 502,000,000.00
4.00 220,000,000.00
2.00 29,000,000.00
1,520.00 898,776,000.00
2,280.00 1,288,200,000.00
180.16 221,957,120.00
380.00 117,268,000.00
4,767.00 331,306,500.00
1.00 127,800,000.00
BALANCE
MC - 0
Increase Decrease
REMARK
Satuan Volume Harga satuan Jumlah harga BOBOT ( % ) Volume Jumlah ( RP ) Volume Jumlah ( RP )
3,133,180,800.00 0.3198 - -
4,474,392,095.00 0.4567 - -
1,767,646,500.00 0.1804 - -
2,985,307,620.00 0.3047 - -
979,618,743,714.20 100.0000 2,786,914,897.2001 2,786,915,131.0000
QUANTITY
ORIGINAL
CONTRACT
BoQ Works Item Unit REMARK
TOTAL
Quantity
No.
1 PREPARATION WORK
1-01 Mobilization and Demobilization Ls 1.00 1.00
1-02 Temporary Facilities Ls 1.00 1.00
1-03 Operation and Maintenance for Engineer's Site Facilities Ls 1.00 1.00
1-04 Water Control and Dewatering System Ls 1.00 1.00
1-05 Report, Photograph and Video Ls 1.00 1.00
1-06 Temporary Access Roads Ls 1.00 1.00
1-07 Site Testing Laboratory Ls 1.00 1.00
1-08 Topographic Survey Ls 1.00 1.00
1-09 Pre Pilling Test Ls 1.00 1.00
1-10 Security, Safety and Health Control Ls 1.00 1.00
1-11 Relocation of Public Utility Ls 1.00 1.00
1-12 Soil Invetigationed Drilling 20 m depth --
- Mechanical Boring including SPT Nos 5.00 5.00
- Dutch Cone Penetrometer Test Nos 5.00 5.00
3 EARTH WORK
3-01 Excavation of common soil and structure by Machinery, within Transportation < 4.0 km m3 5,076.00 10,356.39
3-02 Excavation of common soil and structure by Man Power, within Transportation < 4.0 km m3 9,267.00 1,261.18
3-03 Excavation Riverbank by Machinery, within Transportation < 4.0 km m3 3,536.00 32,844.26
3-04 Backfill from Borrow Area by Man-power m3 6,111.00 5,298.07
3-05 Grass and Soding m2 29,972.00 --
3-06 Embankment from Borrow area m3 3,965.00 14,756.20
3-07 Embankment from Stock yard, within Transportation m3 10,988.00 --
4 CONCRETE WORK
4-01 Concrete K-350 m3 0 --
4-02 Concrete K-300 m3 0 --
4-03 Concrete K-250 m3 203.00 157.04
Pedestrian Bridge
- Abudment 157.04
4-04 Concrete K-225 m3 8,931.00 7,911.28
(Left) River Bank Protection By CCSP 1,118.00
- Coping Concrete 628.77
- Base Concrete 218.44
- Top Concrete 208.90
- Expansion Joint 20.45
- Frame 20.32
- Adjust Concrete 21.12
(Right) River Bank Protection By CCSP 1,085.43
- Coping Concrete 610.59
- Base Concrete 212.12
- Top Concrete 202.86
- Expansion Joint 20.07
- Frame 19.94
- Adjust Concrete 19.86
(Left) Inspection Road and Parapet Wall 1,225.89
- Parapet Wall 1,225.89
(Right) Inspection Road and Parapet Wall 1,189.35
- Parapet Wall 1,189.35
(Left) Slope protection & Drain 1,243.41
- Coping Concrete 805.80
- Base Concrete 196.32
- Top Concrete 198.82
- Expansion Joint 11.28
- Frame 11.28
- Adjust Concrete 19.92
(Right) Slope protection & Drain 1,181.77
- Coping Concrete 765.35
- Base Concrete 186.96
- Top Concrete 188.84
- Expansion Joint 10.65
- Frame 10.65
- Adjust Concrete 19.32
Cross Drainage 768.90
- (1.0 x 1.0) M 130.92
- (1.0 x 1.5) M 148.22
- (1.5 x 1.5) M 71.27
- 2 (1.5 x 1.5) M 195.83
- 3 (1.5 x 1.5) M 72.08
- 5 (1.5 x 1.5) M 150.58
Water Bus Station 16.48
Access People 82.06
4-05 Concrete K-175 m3 1,303.00 768.19
(Left) Inspection Road and Parapet Wall
- Inspection Road 370.57
(Right) Inspection Road and Parapet Wall
- Inspection Road 359.53
Access People 38.09
4-06 Lean Concrete K-100 m3 427.00 1,506.65
(Left) River Bank Protection By CCSP
- Coping Concrete --
- Base Concrete 57.43
- Top Concrete 44.47
- Expansion Joint 10.53
- Frame 12.56
(Right) River Bank Protection By CCSP
- Coping Concrete --
- Base Concrete 55.77
- Top Concrete 43.18
- Expansion Joint 10.34
- Frame 12.32
(Left) Inspection Road and Parapet Wall
- Parapet Wall 149.73
- Inspection Road 185.29
(Right) Inspection Road and Parapet Wall
- Parapet Wall 145.26
- Inspection Road 179.76
(Left) Slope protection & Drain
- Coping Concrete 156.55
- Base Concrete 50.65
- Top Concrete 50.65
- Expansion Joint 9.40
- Frame 11.28
(Right) Slope protection & Drain
- Coping Concrete 148.70
- Base Concrete 48.11
- Top Concrete 48.11
- Expansion Joint 8.87
- Frame 10.65
Cross Drainage
- (1.0 x 1.0) M 9.07
- (1.0 x 1.5) M 11.74
- (1.5 x 1.5) M 4.97
- 2 (1.5 x 1.5) M 12.38
- 3 (1.5 x 1.5) M 4.54
- 5 (1.5 x 1.5) M 7.42
Access People 6.93
4-09 Reinforcement Steel Bar KG 372,775.00 362,065.41
(Left) River Bank Protection By CCSP
- Coping Concrete 12,487.62
- Base Concrete 8,980.28
- Top Concrete 7,893.41
- Expansion Joint 1,501.90
- Frame 2,124.61
(Right) River Bank Protection By CCSP
- Coping Concrete 12,130.15
- Base Concrete 8,722.74
- Top Concrete 7,666.98
- Expansion Joint 1,474.09
- Frame 2,085.02
(Left) Inspection Road and Parapet Wall
- Parapet Wall 51,998.23
(Right) Inspection Road and Parapet Wall
- Parapet Wall 50,452.78
(Left) Slope protection & Drain
- Coping Concrete 29,395.01
- Base Concrete 8,713.09
- Top Concrete 7,793.55
- Expansion Joint 1,317.18
- Frame 1,860.71
(Right) Slope protection & Drain
- Coping Concrete 27,940.54
- Base Concrete 8,275.39
- Top Concrete 7,401.19
- Expansion Joint 1,244.00
- Frame 1,757.34
Cross Drainage
- (1.0 x 1.0) M 13,900.88
- (1.0 x 1.5) M 16,884.35
- (1.5 x 1.5) M 8,344.40
- 2 (1.5 x 1.5) M 21,798.62
- 3 (1.5 x 1.5) M 7,585.05
- 5 (1.5 x 1.5) M 12,141.76
- Pedestrian Bridge 12,034.00
Water Bus Station 894.21
Access People 5,266.32
4-10 Formwork < 2,5 m m2 43,596.00 35,705.40
(Left) River Bank Protection By CCSP
- Coping Concrete 1,704.69
- Base Concrete 627.47
- Top Concrete 763.07
- Expansion Joint 165.29
- Frame 166.16
(Right) River Bank Protection By CCSP
- Coping Concrete 1,672.53
- Base Concrete 609.22
- Top Concrete 740.77
- Expansion Joint 162.29
- Frame 163.16
(Left) Inspection Road and Parapet Wall
- Parapet Wall 3,996.83
(Right) Inspection Road and Parapet Wall
- Parapet Wall 3,878.15
(Left) Slope protection & Drain
- Coping Concrete 6,484.14
- Base Concrete 640.95
- Top Concrete 1,254.63
- Expansion Joint 56.38
- Frame 84.56
(Right) Slope protection & Drain
- Coping Concrete 6,166.29
- Base Concrete 608.59
- Top Concrete 1,200.28
- Expansion Joint 53.24
- Frame 79.87
Cross Drainage
- (1.0 x 1.0) M 601.57
- (1.0 x 1.5) M 770.51
- (1.5 x 1.5) M 400.29
- 2 (1.5 x 1.5) M 1,025.73
- 3 (1.5 x 1.5) M 335.92
- 5 (1.5 x 1.5) M 537.79
Water Bus Station 120.22
Access People 634.80
4-11 Formwork > 2,5 m m2 149.00 172.82
Pedestrian Bridge 172.82
8 MISCELLANEOUS WORK
8-1 Elastic Joint Filler, t = 10 mm m2 1,622.00 4,582.68
(Left) River Bank Protection By CCSP
- Base & Top Concrete 889.32
- Expansion Joint 109.88
(Right) River Bank Protection By CCSP
- Base & Top Concrete 863.60
- Expansion Joint 107.84
(Left) Inspection Road and Parapet Wall
- Parapet Wall 87.11
- Inspection Road 103.99
(Right) Inspection Road and Parapet Wall
- Parapet Wall 84.88
- Inspection Road 100.88
(Left) Slope protection & Drain
- Side Drain 459.00
- Base & Top Concrete 607.80
- Expansion Joint 79.51
(Right) Slope protection & Drain
- Side Drain 436.50
- Base & Top Concrete 577.29
- Expansion Joint 75.09
8-2 Geo-textile mattress, 2 mm thickness m2 16,675.00 9,403.64
8-3 Water Stop m 3,405.00 2,411.08
(Left) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 133.21
(Right) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 129.75
(Left) Slope protection & Drain
- Side Drain 1,074.06
(Right) Slope protection & Drain
- Side Drain 1,074.06
8-4 Hand Rail and Ladder using steel galvanized pipe, d = 5 cm --
- Galvanized Parapet Steel Ladder nos 110.00 14.00
Access People 14.00
- Galvanized Coping Steel Ladder nos 110.00 14.00
Access People 14.00
8-5 Joint Sealent m2 990.00 364.09
(Left) River Bank Protection By CCSP
- Base & Top Concrete 37.05
- Expansion Joint 65.45
(Right) River Bank Protection By CCSP
- Base & Top Concrete 35.98
- Expansion Joint 64.24
(Left) Inspection Road and Parapet Wall
- Parapet Wall 5.85
- Inspection Road 15.61
(Right) Inspection Road and Parapet Wall
- Parapet Wall 5.70
- Inspection Road 15.14
(Left) Slope protection & Drain
- Side Drain 18.36
- Base & Top Concrete 36.84
- Expansion Joint 5.88
(Right) Slope protection & Drain
- Side Drain 17.46
- Base & Top Concrete 34.99
- Expansion Joint 5.55
8-6 Anchor Bar D = 20 mm nos 1,313.00 251.00
Cross Drainage
- (1.0 x 1.0) M 49.00
- (1.0 x 1.5) M 56.00
- (1.5 x 1.5) M 24.00
- 2 (1.5 x 1.5) M 64.00
- 3 (1.5 x 1.5) M 22.00
- 5 (1.5 x 1.5) M 36.00
8-7 Dowel Bar Ø = 20 mm nos 4,561.00 11,133.00
(Left) River Bank Protection By CCSP
- Expansion Joint 689.00
(Right) River Bank Protection By CCSP
- Expansion Joint 676.00
(Left) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 693.00
(Right) Inspection Road and Parapet Wall
- Expansion Joint Parapet Wall 675.00
(Left) Slope protection & Drain
- Side Drain 3,672.00
- Expansion Joint 636.00
(Right) Slope protection & Drain
- Side Drain 3,492.00
- Expansion Joint 600.00
8-8 Roof and steel frame for Water Bus Station nos 2.00 4.00
Water Bus Station 4.00
8-9 Lamp Post nos 19.00 19.00
(Left) Inspection Road and Parapet Wall 10.00
(Right) Inspection Road and Parapet Wall 9.00
8-10 Slide gate H = 1.20m x B=1.20m set 7.00 14.00
Cross Drainage
- (1.0 x 1.0) M 7.00
- (1.0 x 1.5) M 7.00
8-11 Slide gate H = 1.20m x B=1.70m set 4.00 --
8-12 Slide gate H = 1.70m x B=1.70m set 2.00 19.00
Cross Drainage
- (1.5 x 1.5) M 3.00
- 2 (1.5 x 1.5) M 8.00
- 3 (1.5 x 1.5) M 3.00
- 5 (1.5 x 1.5) M 5.00
URAIAN BOBOT
NO SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET
ITEM PEKERJAAN (%)
1 2 3 4 5 11
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 2,004,000,000.000 2,004,000,000.000 0.20457
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) Ls 1.00 495,000,000.000 495,000,000.000 0.05053
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.00 103,713,500.000 103,713,500.000 0.01059
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.00 66,000,000.000 66,000,000.000 0.00674
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.00 165,038,500.000 165,038,500.000 0.01685
1.6 Fasilitas Komunikasi Ls 1.00 150,928,800.000 150,928,800.000 0.01541
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.00 148,500,000.000 148,500,000.000 0.01516
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 8,900.000 800,816,482.000 0.08175
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 53,900.000 34,175,289,610.000 3.48863
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 107,800.000 75,650,264,844.000 7.72242
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 103,000.000 84,890,454,510.000 8.66566
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 136,700.000 77,111,517,201.000 7.87158
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 226,300.000 406,145,307,988.000 41.45953
4,474,392,095.000 0.45675
IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.000 385,000,000.000 385,000,000.000 0.03930
- Total Station (Digital) 1 buah - -
- Sipat Datar (Water Pass) 2 buah - -
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 32,800,000.000 98,400,000.000 0.01004
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 18,751,000.000 56,253,000.000 0.00574
4.4 Mesin Pemotong rumput 90 cc buah 3.000 2,100,000.000 6,300,000.000 0.00064
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.000 28,611,500.000 28,611,500.000 0.00292
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.000 6,930,000.000 13,860,000.000 0.00141
4.7 Kamera DSLR 24 Megapixel buah 1.000 9,200,000.000 9,200,000.000 0.00094
4.8 LCD Portable live in 30.000 hours buah 2.000 11,711,500.000 23,423,000.000 0.00239
4.9 Printer LaserJet Scan, USB, Fax buah 3.000 8,533,000.000 25,599,000.000 0.00261
4.10 GPS Echosounder Multi Layer Dual Frequency buah 1.000 220,000,000.000 220,000,000.000 0.02246
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.000 75,000,000.000 150,000,000.000 0.01531
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.000 502,000,000.000 502,000,000.000 0.05124
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.000 55,000,000.000 220,000,000.000 0.02246
4.14 CCTV Standar 8 camera set 2.000 14,500,000.000 29,000,000.000 0.00296
- -
Jumlah IV 1,767,646,500.000 0.18044
URAIAN BOBOT
NO SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET
ITEM PEKERJAAN (%)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.000 591,300.000 898,776,000.000 0.09175
Pekerjaan LPB, tebal = 300 mm m3 2,280.000 565,000.000 1,288,200,000.000 0.13150
Beton K 125, untuk lantai kerja untuk trotoar m3 180.160 1,232,000.000 221,957,120.000 0.02266
Aspal hotmix, untuk jalan di puncak bendungan m2 380.000 308,600.000 117,268,000.000 0.01197
Canstin (60 x 30 x 25 x 20) bh 4,767.000 69,500.000 331,306,500.000 0.03382
Pengadaan tiang listrik beserta kelengkapannya Ls 1.000 127,800,000.000 127,800,000.000 0.01305
Jumlah V 2,985,307,620.000 0.30474
J U M L A H ( I + II + III + IV + V ) 979,618,743,948.000 100.00000
JADWAL PELAKSANAAN PEKERJAAN
AMANDEMEN NO. 6
TAHUN 2018 TAHUN 2019
No. URAIAN PEKERJAAN SATUAN
Okt 2018 Nov 2018 Des 2018 Jan 2019 Feb 2019 Mar 2019 Apr 2019 Mei 2019 Jun 2019 Jul 2019 Aug 2019 Sep 2019 Okt 2019 Nov 2019
KUANTITAS BOBOT (%)
17 Okt s.d 30 Okt 31 Okt s.d 27 Nov 28 Nov s.d 01 Jan 02 Jan s.d 29 Jan 30 Jan s.d 26 Feb 27 Feb s.d 02 Apr 03 Apr s.d 30 Apr 01 Mei s.d 28 Mei 29 Mei s.d 02 Jul 03 Jul s.d 30 Jul 31 Jul s.d 27 Aug 28 Aug s.d 01 Sep 02 Sep s.d 29 Okt 30 Okt s.d 26 Nov
1 2 3 4 5 6 7 8 9 10 11 12 13 13 14
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.00 0.2046 0.0013 0.01577
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, bengkel kerja dll) LS 1.00 0.0505 0.0067 0.0067
2 BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING AMANDEMEN NO 2 ( MC-0 )
24 OKTOBER 2019
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya Ls 1.00 0.0975
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 133,837.17 0.1216 0.08270
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 635,188.70 3.4949 0.70878
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 711,447.20 7.8290
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 746,454.06 7.8484
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.03 7.8716
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,823,488.89 42.1241
2,3 PEKERJAAN TIMBUNAN
2.3.1 Timbunan Inti (Zone 1) m3 564,093.02 2.5624
2.3.2 Timbunan Filter Halus / Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.73 1.3822
2.3.3 Timbunan Filter Kasar / Zona 2b (material Kerikil dari luar) m3 86,135.73 1.9388
2.3.4 Timbunan Zone 3A, Rockfill dari Stockpile m3 648,951.54 4.8160
2.3.5 Timbunan Zone 3A, Rockfill m3 1,113,977.10 5.0831
2.3.6 Timbunan Zone 3B, Rockfill (transisi) dari Stockpile m3 634,125.72 4.7060
2.3.7 Timbunan Riprap / Zona 4 (material Batu) m3 115,266.54 1.0825
2,4 PEKERJAAN BETON
2.4.1 Grouting Gallery, (Beton K 225) m3 20,617.35 2.9496
2.4.2 Bekisting expose m2 5,815.65 0.1362
2.4.3 Backfill Concrete , Beton Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.04 2.7728
2.4.4 Bekisting non expose m2 971.16 0.0166
2.4.5 Besi Tulangan Ulir D32 Caping Grouting ton 212.08 0.4347
2.4.6 Besi Tulangan Ulir D32 Grouting Gallery ton 253.95 0.5206
2.4.7 Caping Beton K.225 m3 5,382.95 0.7701
2,5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.00 0.0037
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.00 0.0648
2.5.3 V-notch set 1.00 0.0024
2.5.4 Pelat Settlement set 16.00 0.0604
2.5.5 Inklinometer set 1.00 0.0130
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, temperatur dan kelembaban cuaca) unit 1.00 0.0311
2.5.7 Total Earth Pressure unit 6.00 0.0040
TAHUN 2018 - 2023
TAHUN 2020 TAHUN 2021
Des 2019 Jan 2020 Feb 2020 Mar 2020 Apr 2020 Mei 2020 Jun 2020 Jul 2020 Aug 2020 Sep 2020 Okt 2020 Nov 2020 Des 2020 Jan 2021 Feb 2021 Mar 2021 Apr 2021 Mei 2021 Jun 2021 Jul 2021 Aug 2021 Sep 2021 Okt 2021 Nov 2021 Des 2021,
27 Nov s.d 31 Des 01 Jan s.d 28 Jan 29 Jan s.d 25 Feb 26 Feb s.d 31 Mar 01 Apr s.d 28 Apr 29 Apr s.d 26 Mei 27 Mei s.d 30 Jun 01 Jul s.d 28 Jul 29 Jul s.d 01 Sep 02 Sep s.d 29 Sep 30 Sep s.d 27 Okt 28 Okt s.d 01 Des 02 Des s.d 29 Des 30 Des s.d 26 Jan 27 Jan s.d 23 Feb 24 Feb s.d 30 Mar 31 Mar s.d 27 Apr 28 Apr s.d 01 Jun 02 Jun s.d 29 Jun 30 Jun s.d 27 Jul 28 Jul s.d 31 Aug 01 Sep s.d 28 Sep 29 Sep s.d 26 Okt 27 Okt s.d 30 Nov 01 Des s.d 28 Des
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043
0.00067 0.00010 0.00010 0.00010 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030
0.00328 0.00025 0.00025 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029
AMANDEMEN NO 6 ( MC-1 )
30 JUNI 2020 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049 0.0049
0.01945 0.01945
0.71540 0.00924 0.00404 0.00498 0.11634 0.33646 0.38034 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241 0.15241
0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219 0.5219
Jan 2022 Feb 2022 Mar 2022 Apr 2022 Mei 2022 Jun 2022 Jul 2022 Aug 2022 Sep 2022 Okt 2022 Nov 2022 Des 2022 Jan 2023 Feb 2023 Mar 2023 Apr 2023 Mei 2023 Jun 2023 Jul 2023 Aug 2023 Sep 2023 KETERANGAN
29 Des s.d 01 Feb 02 Feb s.d 01 Mar 02 Mar s.d 29 Mar 30 Mar s.d 26 Apr 27 Apr s.d 31 Mei 01 Jun s.d 28 Jun 29 Jun s.d 26 Jul 27 Jul s.d 30 Aug 31 Aug s.d 27 Sep 28 Sep s.d 01 Nov 02 Nov s.d 29 Nov 30 Nov s.d 27 Des 28 Des s.d 31 Jan 01 Feb s.d 28 Feb 01 Mar s.d 28 Mar 29 Mar s.d 25 Apr 26 Apr s.d 30 Mei 31 Mei s.d 27 Juni 28 Jun s.d 01 Aug 02 Aug s.d 29 Aug 30 Aug s.d 20 Sep
40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
100_
0.03023
0.00463
0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027 0.00027
0.00084
0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043
0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030 0.00030
0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029 0.00029
0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617 0.4617
0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280 0.3280
1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552 1.7552
0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 0.1068 _75
0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576 0.0576
0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808 0.0808
0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007 0.2007
0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118 0.2118
0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961 0.1961
0.3608 0.3608 0.3608
0.2950
0.0136
0.0017 0.0017
0.0435 0.0435
0.0521
0.0770 0.0770
4 ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari : set 1.00 0.0393
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.00 0.0100
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.00 0.0057
4.4 Mesin Pemotong rumput 90 cc buah 3.00 0.0006
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah set 1.00 0.0029
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm buah 2.00 0.0014
4.7 Kamera DSLR 24 Megapixel buah 1.00 0.0009
4.8 LCD Portable live in 30.000 hours buah 2.00 0.0024
4.9 Printer LaserJet Scan, USB, Fax buah 3.00 0.0026
4.10 GPS Echosounder Multi Layer Dual Frequency buah 1.00 0.0225
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm buah 2.00 0.0153
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK) unit 1.00 0.0512
4.13 CCTV (Rotating and Zooming) dan Instalasi set 4.00 0.0225
4.14 CCTV Standar 8 camera set 2.00 0.0030
5 PEKERJAAN LAIN-LAIN
5.1 Pekerjaan LPA, tebal = 200 mm m3 1,520.00 0.0917
5.2 Pekerjaan LPB, tebal = 300 mm m3 2,280.00 0.1315
5.3 Beton K 125, untuk lantai kerja untuk trotoar m3 180.16 0.0227
5.4 Aspal hotmix, untuk jalan di puncak bendungan m2 380.00 0.0120
5.5 Canstin (60 x 30 x 25 x 20) ` bh 4,767.00 0.0338
5.6 Pengadaan tiang listrik beserta kelengkapannya Ls 1.00 0.0130
Rencana % 100.0000 0.0315 0.0315 0.0315 0.0315 0.0315 0.0315 0.0315 0.0010 0.0010 0.0010 0.0010 0.0010 0.0007 0.0002 0.0010
BULAN
Realisasi % 0.0006 0.0068 0.0068 0.0001 0.0005 0.0001 0.0003 0.0003 0.0001 0.0001 0.0001 0.0014 0.0001
KONTRAK AWAL Rencana % - 0.0315 0.0631 0.0946 0.1261 0.1577 0.1892 0.2207 0.2217 0.2227 0.2236 0.2246 0.2256 0.2263 0.2265 0.2275
KOMULATIF Realisasi % - 0.0006 0.0075 0.0143 0.0144 0.0149 0.0150 0.0153 0.0155 0.0156 0.0157 0.0158 0.0173 0.0173
Deviasi % -0.0309 -0.0556 -0.0803 -0.1117 -0.1428 -0.1742 -0.2054 -0.2061 -0.2070 -0.2079 -0.2087 -0.2083 -0.2089
Rencana % 0.0173 0.0313 0.0316
BULAN
Realisasi % 0.0158 0.7915
KOMULATIF Realisasi %
Deviasi %
schedule Amandemen No
( Warnah Hitam )
schedule Kontrak
( Warnah Hitam )
schedule Amandemen No 6
( Warnah Hijau )
schedule Realisasi
( Warnah Merah )
0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0010 0.0059 0.0059 0.3348 1.0188 1.2552 1.6158 4.6471 4.6471 4.6471 4.6471 4.7173 4.7238 4.7238 4.7119
0.2285 0.2294 0.2304 0.2314 0.2324 0.2333 0.2343 0.2353 0.2362 0.2372 0.2382 0.2440 0.2499 0.5846 1.6034 2.8586 4.4744 9.1216 13.7687 18.4158 23.0630 27.7802 32.5040 37.2277 41.9396
0.0321 0.0321 0.0321 0.0321 0.0321 0.0012 0.0012 0.0012 0.0012 0.0012 0.0012 0.0061 0.0061 0.4692 0.9911 1.2058 1.5664 4.6033 4.6033 4.6033 4.6033 4.7179 4.7244 4.7244 4.7126
0.1124 0.1444 0.1765 0.2085 0.2406 0.2418 0.2430 0.2441 0.2453 0.2465 0.2477 0.2537 0.2598 0.7290 1.7201 2.9258 4.4923 9.0956 13.6989 18.3022 22.9056 27.6235 32.3478 37.0722 41.7848
0.0370 0.0370 0.0370 0.0370 0.0419 0.0116 0.1835 0.7000 0.9578 1.3184 4.3774 4.3774 4.3774 4.3774 4.6920 4.6985 4.6985 4.6867
0.6432
2.40230 2.4393 2.4763 2.5133 2.5503 2.5922 2.6038 2.7874 3.4873 4.4451 5.7636 10.1410 14.5184 18.8958 23.2733 27.9653 32.6638 37.3623 42.0490
2.4023 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454
0.6061
0.0001 0.0001
0.0001 0.0001
0.0120 0.0120
0.0020 0.0020
0.0393
0.0100
_25
0.0057
0.0006
0.0029
0.0014
0.0009
0.0024
0.0026
0.0225
0.0153
0.0512
0.0056 0.0056 0.0056 0.0056
0.0007 0.0007 0.0007 0.0007
0.0459 0.0459
0.0658 0.0658
0.0113 0.0113
0.0060 0.0060
0.0169 0.0169
0.0065 0.0065 0_
4.4346 4.0740 3.9518 3.9518 3.4488 3.4487 3.4440 3.4321 3.4321 3.4321 3.4321 3.4446 3.2358 2.9226 3.2836 3.2837 0.5766 0.2584 0.3176 0.2060 0.0491
46.3742 50.4482 54.4001 58.3519 61.8007 65.2495 68.6934 72.1256 75.5577 78.9898 82.4220 85.8666 89.1023 92.0249 95.3085 98.5923 99.1689 99.4273 99.7449 99.9509 100.0000
4.4353 4.0746 3.9525 3.9525 3.4424 3.4424 3.4375 3.4257 3.4257 3.4257 3.4257 3.4382 3.4382 2.9284 3.2893 3.2893 0.5326 0.3009 0.3202 0.2060 0.0323
46.2201 50.2947 54.2472 58.1997 61.6421 65.0844 68.5220 71.9476 75.3733 78.7990 82.2247 85.6629 89.1010 92.0295 95.3187 98.6080 99.1406 99.4415 99.7617 99.9677 100.0000
4.4094 4.0488 3.9266 3.9266 3.4165 3.4165 3.4116 3.3998 3.3998 3.3998 3.3998 3.4123 3.4123 2.9506 3.3115 3.3115 0.5327 0.3010 0.3203 0.2064 0.0370
46.4584 50.5072 54.4338 58.3604 61.7769 65.1934 68.6051 72.0049 75.4047 78.8045 82.2043 85.6166 89.0289 91.9796 95.2910 98.6025 99.1352 99.4362 99.7566 99.9630 100.0000
3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454 3.0454
NAMA PPK : PPK BENDUNGAN I SNVT Pembangunan Bendungan BBWS Sumatera VIII
NAMA PAKET : PEMBANGUNAN BENDUNGAN TIGA DIHAJI PAKET I DI KABUPATEN OKU SELATAN
NOMOR KONTRAK : 01/SP/BEND.I/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL KONTRAK : 16 Oktober 2018
NOMOR SPMK : 01/SPMK/P.BENDUNGAN.S.VIII-Ah/BEND.I/X/2018
TANGGAL SPMK : 17 Oktober 2018
TAHUN ANGGARAN : 2018 - 2023
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
I PEKERJAAN PERSIAPAN
1.1 Mobilisasi dan Demobilisasi Peralatan Konstruksi Ls 1.000 0.2046 1.000 0.2046 0.2032 0.0013 - -
1.2 Mobilisasi dan Demobilisasi fasilitas kontraktor (Kantor Rumah staff, Barak kerja,gudang, ben Ls 1.000 0.0505 1.000 0.0505 0.0371 0.0135 - -
1.3 Penyediaan Air Bersih Selama Konstruksi Ls 1.000 0.0106 1.000 0.0106 0.0106 - - -
1.4 Mobilisasi dan Demobilisasi Peralatan Laboratorium Lapangan Ls 1.000 0.0067 1.000 0.0067 0.0067 - - -
1.5 Penyediaan Suplai listrik dan Penerangan ( Penyambungan Listrik ke PLN ) Ls 1.000 0.0168 1.000 0.0168 0.0168 - - -
1.6 Fasilitas Komunikasi Ls 1.000 0.0154 1.000 0.0154 0.0129 0.0025 - -
1.7 Penyediaan Video dan photo selama kegiatan konstruksi Ls 1.000 0.0152 1.000 0.0152 0.0152 - - -
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m m2 89,979.380 0.0817 137,786.640 0.1252 0.0817 - 0.0434 -
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m m3 634,049.900 3.4886 582,344.610 3.2041 3.4886 - - 0.2845
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m m3 701,764.980 7.7224 711,447.200 7.8290 7.7224 - 0.1065 -
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m m3 824,179.170 8.6657 824,179.170 8.6657 8.6657 - - -
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan m3 564,093.030 7.8716 564,093.030 7.8716 7.8716 - - -
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan m3 1,794,720.760 41.4595 1,800,543.504 41.5940 41.4595 - 0.1345 -
Page 35
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
2.5 INSTRUMEN BENDUNGAN
2.5.1 Patok geser nos 21.000 0.0037 21.000 0.0037 0.0037 - - -
2.5.2 Pengadaan, pemasangan vibrating piezometer titk 10.000 0.0648 10.000 0.0648 0.0648 - - -
2.5.3 V-notch set 1.000 0.0024 1.000 0.0024 0.0024 - - -
2.5.4 Pelat Settlement set 16.000 0.0604 16.000 0.0604 0.0604 - - -
2.5.5 Inklinometer set 1.000 0.0130 1.000 0.0130 0.0130 - - -
2.5.6 Pengadaan dan Pemasangan stasiun klimatologi otomatis (curah hujan, kecepatan angin, unit 1.000 0.0311 1.000 0.0311 0.0311 - - -
2.5.7 Total Earth Pressure unit 6.000 0.0040 6.000 0.0040 0.0040 - - -
Page 36
SISAH RENCANA
KONTRAK AWAL AMANDEMEN NO 2 REALISASI BOBOT % ( AMD NO 2 )
BoQ URAIAN ITEM PEKERJAAN Satuan (KONTRAK)
No. Volume BOBOT ( % ) Volume BOBOT ( % ) BOBOT ( % ) BOBOT ( % ) Bertambah ( + ) Berkurang ( - )
(1) (2) (3) (4) (4) (8) (5) ( 6 = 4-7 ) (7) (8 = 5 - 4) (9 = 4 - 5)
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm m3 1,520.000 0.0917 1,520.000 0.0917 0.0917 - - -
Pekerjaan LPB, tebal = 300 mm m3 2,280.000 0.1315 2,280.000 0.1315 0.1315 - - -
Beton K 125, untuk lantai kerja untuk trotoar m3 180.160 0.0227 180.160 0.0227 0.0227 - - -
Aspal hotmix, untuk jalan di puncak bendungan m2 380.000 0.0120 380.000 0.0120 0.0120 - - -
Canstin (60 x 30 x 25 x 20) bh 4,767.000 0.0338 4,767.000 0.0338 0.0338 - - -
Pengadaan tiang listrik beserta kelengkapannya Ls 1.000 0.0130 1.000 0.0130 0.0130 - - -
Menyetujui dan menyanggupi Hasil evaluasi bobot (%) tersebut diatas sebagai dasar pekerjaan
Pembangunan Bendungan Tiga Dihaji Paket I di Kab. OKU Selatan
Page 37
KETERANGAN
(10)
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
Page 38
KETERANGAN
(10)
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
Page 39
KETERANGAN
(10)
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
Page 40
KETERANGAN
(10)
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
TIDAK BERUBAH
PENYEDIA JASA,
HUTAMA - BASUKI, KSO
Lanjar Samadi, ST
Manajer Proyek
Page 41
LAPO
NAMA KEGIATAN : Pembangunan Bendungan Tiga Dihaji Paket 1 Di Kabupaten OKU Selatan
NOMOR KONTRAK : 01/SP/BEND.1/P.BENDUNGAN.S.VIII-Ah/X/2018
TANGGAL : 16 Oktober 2018
AMANDEMEN NO 1 : 01/SP.AMD.01/BEND.I/P.BENDUNGAN.S.VIII-Ah/VII/2019
TANGGAL : 11 Juli 2019
AMANDEMEN NO 2 : 01/SP/AMD.02/BEND.I/P.BENDUNGAN. S.VIII-Ah/X/2019
TANGGAL : 24 Oktober 2019
AMANDEMEN NO 3 : PR.02.01./76.2/BEND.I/PB-Ah/XI/2019
TANGGAL : 25 November 2019
AMANDEMEN NO 4 : 01/SP/AMD.04/BEND.I/P.BENDUNGAN. S.VIII-Ah/IV/2020
TANGGAL : 20 April 2020
AMANDEMEN NO 5 : 01/SP/AMD.05/BEND.I/P.BENDUNGAN. S.VIII-Ah/V/2020
TANGGAL : 04 Mei 2020
AMANDEMEN NO 6 : 01/SP/AMD.06/BEND.I/P.BENDUNGAN. S.VIII-Ah/VI/2020
TANGGAL : 30 Juni 2020
KONTRAKTOR : Hutama - Basuki, KSO
KONSULTAN SUPERVISI : PT Virama Karya (Persero) KSO PT. Tata Guna Patria, PT. Tritunggal Pratyaksa,
LAPORAN BULAN KE : 22
TANGGAL : 01 Juli 2020 s/d 28 Juli 2020
URAIAN
NO
ITEM PEKERJAAN
1 2
I PEKERJAAN PERSIAPAN
Jumlah I
II BENDUNGAN UTAMA
2.1 PEKERJAAN DEWATERING
2.1.1 Pekerjaan dewatering selama konstruksi untuk galian, timbunan dan lainnya
2.2 PEKERJAAN TANAH BENDUNGAN UTAMA & COFFERDAM UTAMA (MAIN COFFERDAM)
2.2.1 Galian Pondasi Bendungan
2.2.1.1 Clearing & grubbing dibuang ke disposal dengan jarak 1000 - 1500 m
2.2.1.2 Galian Pondasi - Galian Tanah diangkut ke disposal dengan jarak 1000-1500 m
2.2.1.3 Galian Batu di Pondasi dengan mekanis diangkut ke disposal dengan jarak 1000-1500 m
2.2.1.4 Galian Batu di Pondasi dengan mekanis diangkut ke stockpile dengan jarak sampai 700 m
2.2.2 Galian Tanah di Borrow Area di angkut ke Lokasi Penimbunan
2.2.3 Galian Batu Quarry (dengan peledakan), diangkut ke Lokasi Penimbunan
Jumlah II
III JETTY DAN TRASHBOOM
3.1 Galian Tanah diangkut ke disposal dengan jarak sampai 700 m
3.2 Timbunan Tanah didatangkan
3.3 Beton K-225 untuk angker
3.4 Weep Hole Pipa PVC dia. 2", L = 1,5 m (termasuk penyaring)
3.5 Beton Mutu fc' = 14,5 MPa (K-175) Type A
3.6 Beton Mutu fc' = 9.8 MPa (K-125)
3.7 Bekisting non expose
3.8 Besi Tulangan Ulir D32
3.9 Penyaring sampah (Floating trash boom) setiap @ 3m, termasuk jaring dan kabel (sling)
IV ALAT PENUNJANG OP
4.1 Peralatan Survey terdiri dari :
- Total Station (Digital) 1 buah
- Sipat Datar (Water Pass) 2 buah
4.2 Komputer Desktop (Intel i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ),
termasuk UPS, Printer A3, Stabilizer, MS Office, AutoCAD)
4.3 Laptop (Intel Core i7 , HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA
4.4 Mesin Pemotong rumput 90 cc
4.5 Pompa Air 4" 2 buah dan Pompa Air 2" 2 buah
4.6 Chainsaw , rated power 2.2 Kw/8500 rpm
4.7 Kamera DSLR 24 Megapixel
4.8 LCD Portable live in 30.000 hours
4.9 Printer LaserJet Scan, USB, Fax
4.10 GPS Echosounder Multi Layer Dual Frequency
4.11 Mesin Fotocopy A3 B/W copier, color scan black white speed 25/30 ipm
4.12 Speed boat untuk OP (6 penumpang 2 engine 85 PK)
4.13 CCTV (Rotating and Zooming) dan Instalasi
4.14 CCTV Standar 8 camera
Jumlah IV
V. PEKERJAAN LAIN-LAIN
Pekerjaan LPA, tebal = 200 mm
Pekerjaan LPB, tebal = 300 mm
Beton K 125, untuk lantai kerja untuk trotoar
Aspal hotmix, untuk jalan di puncak bendungan
Canstin (60 x 30 x 25 x 20)
Pengadaan tiang listrik beserta kelengkapannya
Jumlah V
J U M L A H ( I + II + III + IV + V )
DISETUJUI OLEH :
Direksi Pekerjaan
BBWS Sumatera VIII
Jumlah I 0.31984
m3 564,093.020 2.56244
Zona 2a (material Pasir dari luar), sejauh 5 km m3 86,135.730 1.38223
Zona 2b (material Kerikil dari luar) m3 86,135.730 1.93881
ckfill dari Stockpile m3 648,951.540 4.81603
m3 1,113,977.100 5.08308
ckfill (transisi) dari Stockpile m3 634,125.720 4.70601
a 4 (material Batu) m3 115,266.540 1.08252
m3 20,617.350 2.94964
m2 5,815.650 0.13625
n Mutu fc' = 19,3 Mpa (K-225) Type A m3 19,381.040 2.77277
m2 971.160 0.01656
Caping Grouting ton 212.080 0.43474
Grouting Gallery ton 253.950 0.52057
m3 5,382.950 0.77012
0.45675
el i7 , HDD : 1 TB, Memory 4 MB, Monitor 19 inch flat slim ), buah 3.000 0.01004
A3, Stabilizer, MS Office, AutoCAD)
HDD : 1 TB, RAM 4 GB, Monitor 12 inch ) VGA NVIDIA buah 3.000 0.00574
buah 3.000 0.00064
an Pompa Air 2" 2 buah set 1.000 0.00292
2.2 Kw/8500 rpm buah 2.000 0.00141
buah 1.000 0.00094
buah 2.000 0.00239
buah 3.000 0.00261
Layer Dual Frequency buah 1.000 0.02246
W copier, color scan black white speed 25/30 ipm buah 2.000 0.01531
penumpang 2 engine 85 PK) unit 1.000 0.05124
oming) dan Instalasi set 4.000 0.02246
set 2.000 0.00296
Jumlah IV 0.18044
m3 1,520.000 0.09175
m3 2,280.000 0.13150
ai kerja untuk trotoar m3 180.160 0.02266
an di puncak bendungan m2 380.000 0.01197
bh 4,767.000 0.03382
beserta kelengkapannya Ls 1.000 0.01305
Jumlah V 0.30474
100.00000
DIPERIKSA OLEH :
PT. Virama Karya, KSO
(Konsultan Supervisi)
AMANDEMEN NO 6 PRESTASI
VOLUME s/d BOBOT s/d VOLUME BOBOT VOLUME s/d BOBOT s/d FISIK KET
Bulan lalu Bulan lalu (%) Bulan ini Bulan ini (%) Bulan ini Bulan ini (%) (%)
6 7 8 9 10 11
- 0.04400 - 0.04400
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- 2.35829 0.64315 3.00144
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- - - - -
- -
- - - - - - -
- -
- -
- - - - - - -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
- - - - -
- -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - -
-
- 2.40230 0.64315 3.04545
DIBUAT OLEH :
Hutama - Basuki, KSO
(Kontraktor)