l = (D/2) + 1 = (120 / 2) + 1 = 61
l.i 7*1 7
TC = = = = 0.32563 min
s.n 0,18 * 119,427 21.4968153
l = L gambar + 1 = 21 mm
l = L gambar + 1 = 21 mm
l.i 7*1 7
TC = = = = 0.32563 min
s.n 0,18 * 119,427 21.4968153
l= H + (0,3 * d) + 1 = 20 + (0,3*10) + 1 = 24
~ Allowance DT + ST
= x 100%
60 . D
20 + 25
= x 100%
60 x 8
45
= x 100%
480
= 0.09375 x 100%
= 9.375 %
~ STT = MT / Effisiensi
= 3,72671/0,90625
= 4.11223172413793 min / unit
~ DS = 1 / STT
= 1 / 4,112231724
= 0.243177 unit / min
STANDART TIME CALCULATION
Part Name : A4 - 007 Machine : Mesin Bubut
Part Number : Die Material : S45C
Made by : Muhammad Iqbal
Date : 22 November 2022
Diketahui : MT = 14.5652 min / unit
DT = 20 min / hari
Demand = 25 unit / hari
ST = 5 x Demand
= 125 min / hari
D = 8 Jam / hari
~ Allowance DT + ST
= x 100%
60 . D
20 + 125
= x 100%
60 x 8
145
= x 100%
480
= 0.302083333333333 x 100%
= 30.2 %
~ STT = MT / Effisiensi
= 14,5652 / 0,69792
= 20.8695402985075 min / unit
~ DS = 1 / STT
= 1 / 20,8695403
= 0.047917 unit / min
STANDART TIME CALCULATION
Part Name : A4 - 007 Machine : Mesin Bor
Part Number : Die Material : S45C
Made by : Muhammad Iqbal
Date : 22 November 2022
Diketahui : MT = 4.98022 min / unit
DT = 20 min / hari
Demand = 25 unit / hari
ST = 5 x Demand
= 125 min / hari
D = 8 Jam / hari
~ Allowance DT + ST
= x 100%
60 . D
20 + 125
= x 100%
60 x 8
145
= x 100%
480
= 0.302083333333333 x 100%
= 30.2 %
~ STT = MT / Effisiensi
= 4,98022 / 0,69792
= 7.1358376119403 min / unit
~ DS = 1 / STT
= 1 / 7,135837612
= 0.140138 unit / min