Audit Information
ID Number Standards applied Certificate No.
ISO 50001:2011
Company Name EAC scope
PT. AMERTA INDAH OTSUKA – SITE SUKABUMI & KEJAYAAN 03
Single site, Multi site Location(s):
Head Office :Wisma Pondok Indah, Room 701 Jl. Sultan Iskandar Muda Kav. V-TA Lt. VII Pondok Indah Jakarta,
12310
Factory 1 : Jl. Raya Siliwangi km. 28 Ds. Kutajaya Kec. Cicurug Kab. Sukabumi
Factory 2 : Jl. Raya Pasuruan – Malang Km. 11, Desa Pacarkeling, Kecamatan Kejayan, Kab. Pasuruan
67172 - Indonesia
Precise Description of the Scope of Certification as agreed with the Organisation:
Production of Isotonic Water and Powder Sachet including its support facilities at Sukabumi & Kejayan Factory
Energy sources : Government Electrical, Natural Gas, HSD /solar (3 energy sources)
Date of Audit Audit Representative
23-25.05.2018 Mr. Mugiyono
Lead Auditor Registration No Auditor(s) Registration No.
Setiawan Tarigan 15 16 036,
15 08 033
Number of employee 700 Kejayaan Plant : 267 Sukabumi Plant: 433
Company information:
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 1 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 2 of 9
PT. TÜV NORD Indonesia
ENERGY PROFILE
Listrik PLN.
Kapasitas terpasang:
- Sukabumi = 5,4 MW dengan dua gardu, dipakai untuk Utility (+/- 50%) dan untuk Produksi (+/- 40%) dan
Office + Building (+/-10%).
- Kejayan = 5,5 MW dengan satu gardu. Skema SEUs-nya sama dengan AIO Sukabumi.
Solar.
Solar dipakai untuk keperluan forklift dan back-up Boiler, Genset dan Gas Turbin. Namun demikian, penggunaan
solar tidak signifikan.
Pengembangan diarahkan ke segenap aspek untuk mempertahankan serta meningkatkan mutu dan keamanan
produk dan berkonsentrasi untuk menuju dan melaksanakan nihil kecelakaan, kelestarian lingkungan hidup serta
effisiensi energi.
Profile perusahaan dapat dilihat dalam website : www.aio.co.id
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 2 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 3 of 9
PT. TÜV NORD Indonesia
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 3 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 4 of 9
PT. TÜV NORD Indonesia
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 4 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 5 of 9
PT. TÜV NORD Indonesia
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 5 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 6 of 9
PT. TÜV NORD Indonesia
10. Review of the opportunities to improve energy performance, objectives, targets and action plans
During implementation of Energy Management System, starting from June 03, 2016, The company has conducted :
- Maping of energy use.
- Calculate the energy consumption for all energy use.
- Evalute the significant energy use dan determine the baseline and performance indicator
- Determine the objective and program to improve the energy efficiency
- Monitoring program and achievement of the result
Best Line is refer to En Consumption Otsuka word wide = 1.6 GJ/Kilo Liter Product.
Register of Opportunity Program (ROOP) FY 2018:
a) Rotary UPS (optimize Power PLN), Estimated Saving cost (IDR) : 7.793.351.630
b) Close loop System HVAC OC-1, Estimated Saving cost (IDR) : 266.812.440
c) Installation secondary receiver tank to stabilize pressure compressor 40 BAR, Estimated Saving cost (IDR) :
60.921.181
d) Install cable nuetral PP Prod OC-1, Estimated Saving cost (IDR) : 86.432.246
e) Close loop System HVAC OC-2, Estimated Saving cost (IDR) : 67.569.384
f) Replacement of assist air packing area with blower water removal system, Estimated Saving cost (IDR) :
93.454.426
11. Date of certification audit was finally agreed with the company: June 2018
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 6 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 7 of 9
PT. TÜV NORD Indonesia
Detailed results
The evaluation of the audit results basically follows the scheme shown below:
Area / Follow-up
No. NC A Standard:clause Set date
Process action *
--
Follow-
Area / Standard:
No. NC B up action Set date
Process clause
*
--
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 7 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 8 of 9
PT. TÜV NORD Indonesia
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 8 from 9
Form Title : FEn-TNI-011
Certification Audit Report Revision No. : 00
Effective Date : 30.01.2015
stage 1 Page : 9 of 9
PT. TÜV NORD Indonesia
FEn-TNI-011 rev.00 Cert Audit Report Stage 1-PT. Amerta Indah Otsuka Page 9 from 9