ELECTRICAL,JOB PLANNING

BULAN OKTOBER 2019


NO JOB DESCRIPTION week 1 2 3 4
Pemindahan jalur power
1 genset 03 ke 02

Pemasangan hexos fan pos


27,kamar mandi mess
paping,kamar mandi mess
2 cokro
Pendataan ac inventaris
3 ws,dan mess
Pemasangan lampu merkuri
4 500 watt area tyre
5 perapian panel area ws

ket.
week. 1.oke
2.waiting

Di ketahui
Di siapkan
NOTE
PT.MANDIRI HERINDO ADIPERKASA
SITE-KIDECO,electrik rebuilding
tanggal 01,09,2018

NO JOB DESCRIPTION MATERIAL LOKASI ESTIMASI PEKERJAAN KETERANGAN


PEKERJAAN
pemasangan lampu di ruang saklar lampu 1pcs,fitting lampu
1 fuel 1pcs,lampu 43w 1pcs ruang fuel 3hour pemasangan selesai

penambahan 1 titik lampu


2 material lengkap ruang tool welder 3hour pemasangan selesai
ruang tool welder

penambahan lampu jalan lampu sorot philips 500w 1pcs,kabel


3 pos 27 4hour pemasangan selesai
pos27 nym 2,5mm 10 meter

pemasangan lampu rotari kekuragan lampu rotari 1pcs dan


4 pos masuk security 4hour proses RO,
pos security lampu sorot 500A 1pcs

pemasangan lp baru area kekurangan lampu sorot 500w hpit all area jalan workshop
5 6hour proses RO,144/hr/18
jalan,depan office 10pcs dan kantor

pemasangan box panel baru kekurangan rel mcb,pilot lamp,acb


6 area tyre 1day pemasangan selesai
di area tyre 50A 1pcs
lampu sorot philips 500w hpit
7 penambahan lampu area 10pcs,lampu ml 500w merkuri area workshop 1week proses RO,144/hr/18
workshop
10pcs
acb 250a 2pcs,busbar
peremajaan box panel all
8 3mm,amperemeter,voltmeter,isolat all area mha 23 1week proses RO,143/hr/18
area
or,
penggantian bola lampu
9 lampu ml 500w philips 1pcs ruang oli 3hour proses RO,144/hr/18
yang mati di ruang oli
pemasangan lampu sorot
lampu sorot halolite 500w philips
10 lambang MHA didepan 2pcs office 4hour
office
Disiapkan oleh, Diperiksa oleh, Mengetahui oleh,

Ade Chandra.S M. Irfan Gangga Gautama AdiBrata D. K


Electrik Rebuilding Section Head PM Section Head HRGA Project Manager
PT.MANDIRI HERINDO ADIPERKASA
SITE-KIDECO,electrical building
oktober 2018

NO JOB DESCRIPTION MATERIAL LOKASI ESTIMASI PEKERJAAN KETERANGAN


PEKERJAAN
Pemasangan lampu gudang
1 safety lampu philips 32 watt gudang safety 3hour done

Pemasangan lampu sorot


2 lampu sorot philips 400w hpit scrap 4hour done
area scrap

Pemasangan lampu area


3 lampu ml 500w philips 1pcs ruang oli 3hour done
gudang oli

4 cleaning ac area office - office 5hour done

5 perbaikan lampu area fuel lampu essential 80w ruang fuel 1hour done

repair lampu sorot eks


6 - area workshop 2weeks done
workshop

7 Pasang instalasi listrik dan lampu ml 500w philips 2pcs tyre 1day done
lampu area tyre

lampu sorot philips 500w hpit


penambahan lampu area
8 10pcs,lampu ml 500w merkuri area workshop 2weeks done
workshop 10pcs

pemasangan lampu sorot


lampu sorot halolite 500w philips
9 lambang MHA didepan office 4hour done
2pcs
office

10

Disiapkan oleh, Diperiksa oleh, Mengetahui oleh,

Ade Chandra.S Gangga Gautama AdiBrata D. K


Electrical building Section Head HRGA Project Manager
PT.MANDIRI HERINDO ADIPERKASA
SITE-KIDECO,electrik rebuilding
tanggal 14-10-19

NO JOB DESCRIPTION MATERIAL LOKASI START FINISH


PEKERJAAN
1 Pemindahan jalur power genset 03 ke 02 - R. Genset 10/8/2019 10/8/2019
Pemasangan exhaust fan pos 27,kamar mandi mess Pos 27, Mess Cokro,
2 paping,kamar mandi mess cokro Exhaust fan baru Mess Paping 10/12/2019

3 Pendataan ac inventaris ws,dan mess - WS & Mess 10/10/2019


4 Pemasangan lampu merkuri 500 watt area tyre Lampu mercury, fitting Tyre 10/7/2019 10/7/2019

5 perapian panel area ws (1 Panel) - WS 10/6/2019 10/6/2019

PENCAPAIAN

Disiapkan oleh, Diperiksa oleh,

Ade Chandra.S M. Irfan Gangga Gautama


Electrik Rebuilding Pengawas Langsung Section Head HRGA
OPEN High
CLOSED Meduim
ON PROGRESS Low
DUE PROGRESS % STATUS PRIORITY KETERANGAN ACCURACY
DATE
10/9/2019 100 CLOSED High 0
10/19/2019 33 ON PROGRESS Meduim Mess Paping, Mess Cokro
-43750
10/17/2019 33 ON PROGRESS Low Mess Paping, Mess Cokro -43748
10/8/2019 100 CLOSED High 0

Pekerjaan dilakukan saat off


10/12/2019 100 ON PROGRESS High
hauling
0
73.3

Mengetahui oleh,

Kriel Kala Lembang


Project Manager