JADWAL PELAKSANAAN PEKERJAAN ( REVISI 01 )

PEKERJAAN : PEMBANGUNAN FLY OVER JALAN UNTUNG SUROPATI - RA BASYID


KEGIATAN : PEMBANGUNAN FLY OVER
NOMOR KONTRAK : 602.2/08/KTR-T/K.3/III.03/2019
TANGGAL KONTRAK : Monday, March 11, 2019
TAHUN ANGGARAN : 2019 rencana
PROVINSI : LAMPUNG
KABUPATEN / KOTA : BANDAR LAMPUNG

Bulan Ke :
Persentase I II III IV V VI VII VIII
No. Mata Pembayaran Uraian Satuan Bobot mc 00 Keterangan
18 Maret - 18 april 19 19 April - 18 Mei 19 19 Mei - 18 Juni 19 19 Juni - 18 Juli 19 19 Juli - 18 Agustus 19 19 agustus - 18 September 19 19 September - 18 Oktober 19 19 Oktober - 12 November 19
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

DIVISI 1. - MOBILISASI
1.2 Mobilisasi LS 0.186 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 100
1.8 Manajemen dan Keselamatan Lalu Lintas LS 1.012 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026
1.18.(2) Relokasi Tiang Listrik yang ada, Tegangan rendah LS -
1.20.2 Pengeboran, termasuk SPT dan Laporan M' 0.042 0.008 0.008 0.008 0.008 0.008
1.21 Manajemen Mutu LS 0.074 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

DIVISI 2. - DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M3 0.345 0.017 0.017 0.017 0.003 0.003 0.003 0.003 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.002 0.005 0.009 0.018 0.018 0.018 0.018 0.185
2.2 Pasangan Batu dengan Mortar M3 1.596 0.089 0.018 0.018 0.018 0.018 0.004 0.002 0.002 0.002 0.002 0.002 0.002 0.003 0.005 0.006 0.005 0.700 0.700
2.3.4h U-Ditch 40 X 40 X 100 Mm M1 -
2.3.4k U-Ditch 100 X 100 X 100 Mm M1 0.674 0.067 0.067 0.067 0.067 0.067 0.067 0.067 0.067 0.135
2.3.4f Box Culvert Pre 100 X 100 X 100 Mm M1 1.053 0.211 0.211 0.211 0.211 0.211

DIVISI 3. PEKERJAAN TANAH 80


3.1.1 Galian Biasa '(termasuk pembuangan ke luar) M3 1.836 0.092 0.092 0.092 0.023 0.023 0.023 0.023 0.005 0.002 0.001 0.001 0.001 0.001 0.001 0.001 0.002 0.003 0.003 0.005 0.102 0.714 0.023 0.302 0.302
3.1.3 Galian Struktur dengan kedalaman 0 - 2 meter M3 0.047 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
3.1.4 Galian Struktur dengan kedalaman 2 - 4 meter M3 0.104 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013
3.2.1 Timbunan Biasa M3 0.945 0.118 0.473 0.079 0.079 0.158 0.020 0.005 0.001 0.014
3.2.2 Timbunan Pilihan M3 2.043 0.511 0.511 0.511 0.255 0.128 0.051 0.077
3.3 Penyiapan Badan Jalan M2 0.014 0.014
A.2.3.1.10 Pemadatan tanah ( per 20 cm ), …untuk pekerjaan struktur M3 0.269 0.067 0.067 0.06725 0.017 0.004 0.001 0.000 0.04567
A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug M3 0.330 0.083 0.0825 0.083 0.083
A.4.4.1.3 Pemasangan 1 m2 Batu bata M2 0.069 0.017 0.01725 0.017 0.017

DIVISI 4 - PELEBARAN PERKERASAN DAN BAHU JALAN 60


4.2.1 Lapis Pondasi Agregat Kelas A M3 1.620 0.324 0.324 0.324 0.324 0.324
4.2.2 Lapis Pondasi Agregat Kelas B M3 2.255 0.376 0.376 0.376 0.376 0.376 0.376

DIVISI 6. PERKERASAN ASPAL


6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 0.186 0.031 0.031 0.031 0.031 0.062
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 0.045 - 0.015 0.015 0.015
6.3(5a) Laston Lapis Aus (AC-WC) (gradasi halus/kasar) Ton 1.242 0.621 0.621
6.3(6a) Laston Lapis Antara (AC-BC) (gradasi halus/kasar) Ton -
6.3(7a) Laston Lapis Pondasi (AC-Base) (gradasi halus/kasar) Ton 3.383 0.677 0.677 0.338 1.015 0.338 0.203 0.135

DIVISI 7. STRUKTUR 40
7.1 (5) Beton mutu sedang dengan fc’=30 MPa (K-350) M3 16.721 0.880 0.880 0.880 0.880 0.147 0.073 0.037 0.006 0.006 0.006 0.009 0.014 0.021 0.041 0.165 0.660 2.640 0.147 0.587 0.587 1.173 1.291 1.420 1.846 0.923 0.308 0.077 0.340 0.300 0.379
7.1 (9) Beton Siklop fc’=15 MPa (K-175) M3 0.778 0.039 0.039 0.039 0.039 0.039 0.006 0.003 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.003 0.013 0.003 0.003 0.003 0.003 0.536 0.000 0.000 0.000 0.000
7.2 (1)c Unit Pracetak Gelagar Tipe I Bentang 40 meter Buah 19.742 2.820 2.820 2.820 2.820 2.820 2.820 2.820
7.2 (1)d Unit Pracetak Gelagar Tipe I Bentang 45 meter Buah 5.897 1.966 1.966 1.966
7.2.(6) Beton Diafragma K350 (fc’ 30 MPa) termasuk pekerjaan penegangan setelah pengecoran (post-tension)
m3 0.906 0.227 0.227 0.113 0.227 0.057 0.057
7.3 (3) Baja Tulangan BJ 39 Ulir Kg 26.191 0.748 0.187 0.047 0.056 0.056 0.056 0.056 0.056 0.056 0.168 0.589 1.179 0.074 0.221 0.055 0.018 0.037 0.074 0.184 0.921 0.184 0.037 5.000 6.000 7.000 3.131
7.6 (11) Tiang Bor Beton ukuran 1000 mm M1 6.872 0.764 0.764 0.764 0.764 0.764 0.764 0.764 0.764 0.764
7.6 (16) Pengujian Pembebanan Dinamis Cara PDA (Pile Driving Analisys)/PDLT (Pile Dynamic Buah
Load Test) 0.108 0.054 0.054
7.11 (1) Expansion Joint Tipe Asphaltic Plug M1 0.113 0.113
7.12 (4) Perletakan Elastomer jenis 3 (400 x 450 x 45) Buah 0.204 0.102 0.102
7.13. Sandaran (Railing) M1 -
7.14 Papan Nama Jembatan Buah 0.002 0.002 20
7.15 (1) Pembongkaran Pasangan Batu M3 0.445 0.074 0.074 0.074 0.012 0.037 0.148 0.025
7.15 (2) Pembongkaran Beton M3 0.204 0.041 0.082 0.016 0.033 0.033
7.16 Pipa Cucuran Baja M1 -
7.11.(5) Joint Filler untuk Sambungan Konstruksi M1 0.078 0.016 0.016 0.016 0.016 0.016

DIVISI 8 - PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


A.5.1.1.32 Pemasangan 1m pipa PVC tipe AW diameter 3" M1 0.288 0.058 0.115 0.038 0.038 0.038
A.5.1.1.32 Pemasangan 1m pipa PVC tipe AW diameter 2" M1 0.124 0.062 0.041 0.021
0 Pemasangan Lampu Penerangan Jalan Umum Ls 1.746 0.873 0.873
0 pemasangan 1m Pipa PVC tipe AW diameter 6" M1 0.100 0.020 0.040 0.020 0.010 0.010
0 pengecetan hitam putih M2 0.109 0.036 0.036 0.036
0
Kemajuan Pekerjaan Mingguan 100.00 0.06 0.04 0.22 0.27 0.43 1.02 1.07 1.18 1.02 1.01 1.14 1.18 1.16 1.26 1.64 1.99 2.52 2.50 2.11 2.60 2.94 3.89 2.32 1.38 2.32 4.79 4.60 4.74 7.78 6.21 5.22 8.04 6.49 7.47 3.68 0.23 0.32 1.60 1.58
Kemajuan Pekerjaan Mingguan Komulatif (%) - 0.06 0.10 0.32 0.59 1.02 2.04 3.11 4.29 5.31 6.32 7.45 8.63 9.79 11.05 12.69 14.68 17.20 19.70 21.81 24.41 27.34 31.23 33.55 34.93 37.25 42.04 46.64 51.38 59.15 65.36 70.58 78.63 85.11 92.58 96.26 96.49 96.82 98.42 100.00