ANALISA HARGA SATUAN PEKERJAAN
PROYEK :
LOKASI :

HARGA
NO. KODE URAIAN KOEF. SATUAN JUMLAH
SATUAN
Unit PEKERJAAN PEMASANGAN PROFILE BAJA PER 1 Kg

UPAH Pekerja / knek 0.0060 org/hr 55,000.00 330.00


Tukang Las / Besi 0.0400 org/hr 65,000.00 2,600.00
Kepala Tukang 0.0050 org/hr 80,000.00 400.00
Mandor 0.0050 org/hr 100,000.00 500.00

Jumlah Harga Upah 3,830.00

BAHAN
Baja Profile Wf 1.050 kg 8,600.00 9,030.00
Alat Las 1.050 kg 3,000.00 3,150.00
Cat Meni 0.0050 m2 25,000.00 125.00
Erexion / Alat Bantu 10.0000 ls 100.00 1,000.00

Jumlah Harga Bahan 13,305.00

ALAT

Jumlah Harga Alat -


Jumlah 17,135.00
Keuntungan + Overhead 10% 1,713.50
Jumlah Total 18,848.50
Dibulatkan 18,840.00