REKAPITULASI

PEKERJAAN : DED Sistem Penyediaan Air Minum (SPAM) Ibu Kota Kecamatan (IKK)
PAKET : I, II, III
B. PAKET I
a) Ruas I - Pamanjatan
### Err:509
b) Jalan Pematang - Pamanjatan - Arah Intake Manarap
C. PAKET II
a) Desa Cintapuri Darussalam
b) Simpang Madurejo arah Danau Salak (Martapura)
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A : 2018

NO. URAIAN PEKERJAAN HARGA (Rp)


(1) (2) (3)

B. PAKET I
a) Ruas I - Pamanjatan 20,585,764,490.44
b) Jalan Pematang - Pamanjatan - Arah Intake Manarap 4,569,666,769.23
SUB TOTAL = 25,155,431,259.67
C. PAKET II
a) Desa Cintapuri Darussalam Err:509
SUB TOTAL = Err:509
[A] TOTAL KESELURUHAN = Err:509
[B] PPN 10% = Err:509
[C] TOTAL = [A] + [B] = Err:509
[D] PEMBULATAN = [C] = Err:509

Terbilang : Err:509

Banjarmasin, 9 Agustus 2017


Konsultan Perencana
..................................

..................................
Direktur
REKAPITULASI
PEKERJAAN : DED SPAM IKK Desa Kayu Bawang
PAKET : I
LOKASI : Jalan Irigasi, Desa Kayu Bawang, Kecamatan Gambut
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A : 2018

NO. URAIAN PEKERJAAN HARGA (Rp)


(1) (2) (3)

A Jalan Irigasi, Desa Kayu Bawang, Kecamatan Gambut


I PEKERJAAN PERSIAPAN -

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN -

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN -

IV PEKERJAAN JEMBATAN PIPA -

V PEKERJAAN CROSSING JALAN -

VI PEKERJAAN LAIN-LAIN -
SUB TOTAL = -
[A] TOTAL KESELURUHAN = -
[B] PPN 10% = -
[C] TOTAL = [A] + [B] = -
[D] PEMBULATAN = [C] = -

Terbilang : Rupiah.

Banjarmasin, 9 Agustus 2017


Konsultan Perencana
PT. WINAGUNA SARANA TEKNIK

Dedi Sutisna, AMd


Direktur
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : DED SPAM IKK Desa Kayu Bawang
PAKET : I
LOKASI : Jalan Irigasi, Desa Kayu Bawang, Kecamatan Gambut
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A. : 2018

NO. HARGA
NO. URAIAN PEKERJAAN VOLUME
ANALISA SATUAN (Rp)
(1) (2) (3) (4) (5)

A Jalan Irigasi, Desa Kayu Bawang, Kecamatan Gambut


I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan patok di sepanjang jalur pipa 1 - m 1,013.19
2 Mobilisasi dan demobilisasi -- 1.00 Ls 20,000,000.00
3 Pembuatan rambu pengaman lalu lintas -- 3.00 Ls 500,000.00
4 Dokumentasi foto 3 phase -- 1.00 set 500,000.00
5 Pembersihan lokasi pekerjaan -- 1.00 Ls 3,000,000.00
Total I

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN


1 Pengadaan Pipa
1 Pipa HDPE S-8 PN.10 Ø 160 mm -- m 323,082.50
Sub Total
2 Pengadaan Aksesoris
ND. 1
1 Stub Flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00
2 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00
3 Rubber packing Ø 200 mm -- 2.00 bh 46,000.00
4 Giboult joint Ø 160 mm -- 1.00 bh 797,500.00
5 Mur baut 5/8 × 10 cm -- 24.00 bh 9,545.00
Sub Total
ND. 2, 3 dan 4
1 Tee Verlop HDPE Ø 160×110 mm -- 3.00 bh 362,940.00
2 Stub Flange HDPE Ø 110 mm -- 6.00 bh 605,705.00
3 Rubber packing jadi Ø 200 mm -- 6.00 bh 46,000.00
4 Gate Valve Ø 110 mm -- 3.00 bh 1,719,250.00
5 Giboult joint Ø 110 mm -- 3.00 bh 429,000.00
6 Mur baut 5/8 × 10 cm -- 36.00 bh 9,545.00
Sub Total
ND. 5
1 Stub Flange HDPE Ø 160 mm -- 2.00 bh 605,705.00
2 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00
3 Giboult joint Ø 160 mm -- 1.00 bh 797,500.00
4 Tee Verlop HDPE Ø 160×110 mm -- 2.00 bh 362,940.00
5 Rubber packing jadi Ø 200 mm -- 1.00 bh 46,000.00
6 Mur baut 5/8 × 10 cm -- 24.00 bh 9,545.00
Sub Total
Total II

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN


1 Pekerjaan Galian Tanah
1 Galian tanah keras pipa HDPE S-8 PN.10 Ø 160 mm / Ø 6" 3 - m3 99,160.00
Sub Total
2 Pekerjaan Pemasangan Pipa HDPE
1 Pemasangan pipa HDPE S-8 PN.10 Ø 160 mm / Ø 6" 19 - m 121,052.33
NO. HARGA
NO. URAIAN PEKERJAAN VOLUME
ANALISA SATUAN (Rp)
(1) (2) (3) (4) (5)
Sub Total
3 Pekerjaan Pengurugan Kembali Galian Tanah
1 Pengurugan kembali pipa HDPE S-8 PN.10 Ø 160 mm / Ø 6" 4 - m3 77,765.00
Sub Total
Total III

IV PEKERJAAN JEMBATAN PIPA


1 Jembatan pipa Ø 160 mm L = 13 m Jb1 1.00 bh 351,784,664.90
Total IV

V PEKERJAAN CROSSING JALAN


1 Crossing jalan cor beton Ø 160 mm, L = 39,00 m
Pekerjaan membongkar beton 7 2.63 m3 676,655.00
Pemasangan beton kembali 9 2.63 m 3
1,055,651.87
Total V

VI PEKERJAAN LAIN-LAIN
1 Pengetesan pipa HDPE S-8 PN.10 Ø 160 mm / Ø 6" 25 - m 2,653.30
2 Pekerjaan interkoneksi dengan pipa eksisting -- 1.00 Ls 1,200,000.00
Total VI
CANA ANGGARAN BIAYA (RAB)

JUMLAH HARGA
(Rp)
(6)

-
20,000,000.00
1,500,000.00
500,000.00
3,000,000.00

2,590,260.00
2,760,000.00
92,000.00
797,500.00
229,080.00

1,088,820.00
3,634,230.00
276,000.00
5,157,750.00
1,287,000.00
343,620.00

1,211,410.00
2,760,000.00
797,500.00
725,880.00
46,000.00
229,080.00

-
JUMLAH HARGA
(Rp)
(6)

351,784,664.90

1,781,294.29
2,779,003.54

-
1,200,000.00
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb1
JEMBATAN PIPA 160 MM DENGAN BENTANG 13 M

NO. HARGA
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA SATUAN (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 160 mm Bentang: 13.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 74,500.00 989,397.25
2 Urugan tanah kembali 4 4.43 m 3
77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m3 186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,286,207.44

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
413,440.40 11,601,137.62
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m2 413,440.40 504,397.29
4 Pemasangan baja WF 200.100.5,5.8 mm -- 277.33 kg 30,432.75 8,440,016.87
5 Balok penyangga kayu ulin 8/16 -- 0.02 m 3
9,472,100.00 236,423.62
6 Angkur baut Ø 22 mm -- 52.00 bh 91,162.50 4,740,450.00
7 Klem penjepit dari plat -- 13.00 Ls 125,000.00 1,625,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 44,780,006.69

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 160 mm -- 24.70 m 621,000.00 15,338,700.00
2 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
3 All Flange Bend GI 45° Ø 160 mm -- 4.00 bh 637,560.00 2,550,240.00
4 Tee Verlop GI Ø 160 × 110 mm -- 1.00 bh 362,940.00 362,940.00
5 Street box 30 1.00 bh 30,510.26 30,510.26
6 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
7 Flange Steel Ø 160 mm -- 9.00 bh 223,790.00 2,014,110.00
8 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
9 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00 1,909,000.00
10 Rubber packing jadi Ø 200 mm -- 10.00 bh 46,000.00 460,000.00
11 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
12 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00 1,518,000.00
13 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00 82,800.00
Sub Total 27,789,785.26
NO. HARGA
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA SATUAN (Rp)

(1) (2) (3) (4) (5) (6)

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 160 mm -- 24.70 m 50,800.00 1,254,760.00
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk ### 220,077,026.74
3 Pemotongan pipa -- 3.00 ttk ### 41,264,442.51
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 160 × 160 mm -- 2.00 Ls 600,000.00 1,200,000.00
Sub Total 264,021,229.25

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 32 24.12 m2 483,398.66 11,657,436.24
2 Pengaman dari pipa besi Ø 300 mm -- 1.00 Ls 100,000.00 100,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 11,907,436.24
TOTAL 351,784,664.90
REKAPITULASI
PEKERJAAN : DED SPAM IKK Desa Gambut
PAKET : I
LOKASI : a) Ruas I - Pamanjatan
b) Jalan Pematang - Pamanjatan - Arah Intake Manarap
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A : 2018

NO. URAIAN PEKERJAAN HARGA (Rp)


(1) (2) (3)

A Ruas I - Pamanjatan
I PEKERJAAN PERSIAPAN 33,728,631.85

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN 16,857,397,167.50

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN 2,497,204,563.64

IV PEKERJAAN JEMBATAN PIPA 1,057,599,372.95

V PEKERJAAN CROSSING JALAN 91,063,245.71

VI PEKERJAAN LAIN-LAIN 48,771,508.79


SUB TOTAL = 20,585,764,490.44

B Jalan Pematang - Pamanjatan - Arah Intake Manarap


I PEKERJAAN PERSIAPAN 28,272,603.70

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN 3,908,042,515.00

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN 614,315,785.94

0 PEKERJAAN JEMBATAN PIPA -

IV PEKERJAAN LAIN-LAIN 19,035,864.59


SUB TOTAL = 4,569,666,769.23
[A] TOTAL KESELURUHAN = 25,155,431,259.67
[B] PPN 10% = 2,515,543,125.97
[C] TOTAL = [A] + [B] = 27,670,974,385.64
[D] PEMBULATAN = [C] = 27,670,974,000.00
Dua Puluh Tujuh Milyar Enam Ratus Tujuh Puluh Juta Sembilan Ratus Tujuh Puluh
Terbilang :
Empat Ribu Rupiah.
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : DED SPAM IKK Desa Gambut
PAKET : I
LOKASI : a) Ruas I - Pamanjatan
b) Jalan Pematang - Pamanjatan - Arah Intake Manarap
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A. : 2018

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)

A Ruas I - Pamanjatan
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan patok di sepanjang jalur pipa 1 8,615.00 m 1,013.19 8,728,631.85
2 Mobilisasi dan demobilisasi -- 1.00 Ls 20,000,000.00 20,000,000.00
3 Pembuatan rambu pengaman lalu lintas -- 3.00 Ls 500,000.00 1,500,000.00
4 Dokumentasi foto 3 phase -- 1.00 set 500,000.00 500,000.00
5 Pembersihan lokasi pekerjaan -- 1.00 Ls 3,000,000.00 3,000,000.00
Total I 33,728,631.85

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN


1 Pengadaan Pipa
1 Pipa HDPE S-8 PN.10 Ø 400 mm / 16 inch -- 8,615.00 m 1,934,131.50 16,662,542,872.50
Sub Total 16,662,542,872.50
2 Pengadaan Aksesoris
Node #1 - STA 0+000
1 Stub Flange HDPE Ø 400 mm / 16 inch -- 1.00 bh 7,319,520.00 7,319,520.00
2 Rubber packing jadi Ø 400 mm / 16 inch -- 1.00 bh 97,175.00 97,175.00
3 Mur baut 3/4 × 10 cm -- 16.00 bh 12,650.00 202,400.00
Sub Total 7,619,095.00
Node #2 - STA 0+360
1 Stub Flange HDPE Ø 400 mm / 16 inch -- 2.00 bh 7,319,520.00 14,639,040.00
2 Rubber packing jadi Ø 400 mm / 16 inch -- 2.00 bh 97,175.00 194,350.00
3 All flange bend steel 90° × 400 mm / 16 inch -- 1.00 bh 5,052,125.00 5,052,125.00
4 Mur baut 3/4 × 10 cm -- 32.00 bh 12,650.00 404,800.00
Sub Total 20,290,315.00
Node #3 - STA 2+890
1 Stub Flange HDPE Ø 400 mm / 16 inch -- 2.00 bh 7,319,520.00 14,639,040.00
2 Stub Flange HDPE Ø 300 mm / 12 inch -- 3.00 bh 3,745,895.00 11,237,685.00
3 Gate Valve Ø 400 mm / 16 inch -- 1.00 bh 52,900,000.00 52,900,000.00
4 Rubber packing jadi Ø 400 mm / 16 inch -- 2.00 bh 97,175.00 194,350.00
5 Rubber packing jadi Ø 300 mm / 12 inch -- 3.00 bh 74,750.00 224,250.00
6 Tee all flange Ø 400 × 300 mm / 16 × 12 inch -- 1.00 bh 12,500,000.00 12,500,000.00
7 Mur baut 3/4 × 10 cm -- 68.00 bh 12,650.00 860,200.00
Sub Total 92,555,525.00
Node #4 - STA 8+160
1 Stub Flange HDPE Ø 400 mm / 16 inch -- 1.00 bh 7,319,520.00 7,319,520.00
2 Gate Valve Ø 400 mm / 16 inch -- 1.00 bh 52,900,000.00 52,900,000.00
3 Flange adaptor Ø 200 mm / 8 inch -- 2.00 bh 4,266,730.00 8,533,460.00
4 Rubber packing jadi Ø 400 mm / 16 inch -- 1.00 bh 97,175.00 97,175.00
5 Rubber packing jadi Ø 200 mm / 8 inch -- 4.00 bh 46,000.00 184,000.00
6 Tee all flange Ø 200 × 200 mm / 8 × 8 inch -- 1.00 bh 1,712,005.00 1,712,005.00
7 Reducer all flange Ø 400 × 200 mm / 16 × 8 inch -- 1.00 bh 3,036,000.00 3,036,000.00
8 Mur baut 3/4 × 10 cm -- 48.00 bh 12,650.00 607,200.00
Sub Total 74,389,360.00
Total II 16,857,397,167.50
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN


1 Pekerjaan Galian Tanah
1 Galian tanah keras pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 3 8,270.40 m3 99,160.00 820,092,864.00
Sub Total 820,092,864.00
2 Pekerjaan Pemasangan Pipa HDPE
1 Pemasangan pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 22 8,615.00 m 129,791.28 1,118,151,874.95
Sub Total 1,118,151,874.95
3 Pekerjaan Pengurugan Kembali Galian Tanah
1 Pengurugan kembali pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 4 7,187.81 m3 77,765.00 558,959,824.70
Sub Total 558,959,824.70
Total III 2,497,204,563.64

IV PEKERJAAN JEMBATAN PIPA


1 Jembatan pipa Ø 400 mm L=3m Jb1 3.00 bh 133,600,203.77 400,800,611.31
2 Jembatan pipa Ø 400 mm L=4m Jb2 1.00 bh 178,947,725.41 178,947,725.41
3 Jembatan pipa Ø 400 mm L=8m Jb3 1.00 bh 206,070,294.63 206,070,294.63
4 Jembatan pipa Ø 400 mm L = 10 m Jb4 1.00 bh 271,780,741.59 271,780,741.59
Total IV 1,057,599,372.95

V PEKERJAAN CROSSING JALAN


1 Crossing jalan cor beton Ø 400 mm, L = 550,50 m
Pekerjaan membongkar beton 7 64.14 m3 676,655.00 43,400,651.70
Pemasangan beton kembali 9 64.14 m 3
1,055,651.87 67,709,510.83
Sub Total 111,110,162.53
2 Crossing jalan aspal, pipa Ø 400 mm L = 38,00 m
Pembongkaran aspal lama 30 30.40 m2 30,510.26 927,511.90
Pekerjaan pengaspalan hotmix tebal 3 cm 31 30.40 m 2
273,643.33 8,318,757.33
Sub Total 9,246,269.24
Total V 91,063,245.71

VI PEKERJAAN LAIN-LAIN
1 Pengetesan pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 29 8,615.00 m 5,521.94 47,571,508.79
2 Pekerjaan interkoneksi dengan pipa eksisting -- 1.00 Ls 1,200,000.00 1,200,000.00
Total VI 48,771,508.79

B Jalan Pematang - Pamanjatan - Arah Intake Manarap


I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan patok di sepanjang jalur pipa 1 3,230.00 m 1,013.19 3,272,603.70
2 Mobilisasi dan demobilisasi -- 1.00 Ls 20,000,000.00 20,000,000.00
3 Pembuatan rambu pengaman lalu lintas -- 3.00 Ls 500,000.00 1,500,000.00
4 Dokumentasi foto 3 phase -- 1.00 set 500,000.00 500,000.00
5 Pembersihan lokasi pekerjaan -- 1.00 Ls 3,000,000.00 3,000,000.00
Total I 28,272,603.70

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN


1 Pengadaan Pipa
1 Pipa HDPE S-8 PN.10 Ø 300 mm -- 3,230.00 m 1,202,594.50 3,884,380,235.00
Sub Total 3,884,380,235.00
2 Pengadaan Aksesoris
Node #5 - STA 0+400
1 Stub Flange Ø 300 mm -- 2.00 bh 3,745,895.00 7,491,790.00
2 Rubber packing jadi Ø 300 mm -- 2.00 bh 74,750.00 149,500.00
3 All flange bend steel 90° × 300 mm / 12 inch -- 1.00 bh 3,886,250.00 3,886,250.00
4 Mur baut 3/4 × 10 cm -- 24.00 bh 12,650.00 303,600.00
Sub Total 11,831,140.00
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)
Node #6 - STA 3+000
1 Stub Flange Ø 300 mm -- 2.00 bh 3,745,895.00 7,491,790.00
2 Rubber packing jadi Ø 300 mm -- 2.00 bh 74,750.00 149,500.00
3 All flange bend steel 90° × 300 mm / 12 inch -- 1.00 bh 3,886,250.00 3,886,250.00
4 Mur baut 3/4 × 10 cm -- 24.00 bh 12,650.00 303,600.00
Sub Total 11,831,140.00
Total II 3,908,042,515.00

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN


1 Pekerjaan Galian Tanah
1 Galian tanah keras pipa HDPE S-8 PN.10 Ø 300 mm / Ø 12" 3 1,453.50 m3 99,160.00 144,129,060.00
Sub Total 144,129,060.00
2 Pekerjaan Pemasangan Pipa HDPE
1 Pemasangan pipa HDPE S-8 PN.10 Ø 300 mm / Ø 12" 21 3,230.00 m 116,071.28 374,910,233.55
Sub Total 374,910,233.55
3 Pekerjaan Pengurugan Kembali Galian Tanah
1 Pengurugan kembali pipa HDPE S-8 PN.10 Ø 300 mm / Ø 12" 4 1,225.18 m3 77,765.00 95,276,492.39
Sub Total 95,276,492.39
Total III 614,315,785.94

IV PEKERJAAN LAIN-LAIN
1 Pengetesan pipa HDPE S-8 PN.10 Ø 300 mm / Ø 12" 29 3,230.00 m 5,521.94 17,835,864.59
2 Pekerjaan interkoneksi dengan pipa eksisting -- 1.00 Ls 1,200,000.00 1,200,000.00
Total VI 19,035,864.59
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb1
JEMBATAN PIPA 400 MM DENGAN BENTANG 3 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 3.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 3.95 m3 107,482.50 424,236.65
2 Urugan tanah kembali 4 1.32 m3 77,765.00 102,313.60
3 Pasir urug tebal 10 cm 5 0.20 m 3
186,993.00 37,445.35
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 108.00 m 11,376.50 1,228,662.00
Sub Total 1,792,657.60

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.10 m3 1,055,651.87 105,697.14
2 Abutmen Utama
Beton (K-200) 10 0.51 m3 1,032,323.23 524,420.20
Besi 11 80.49 kg 14,220.13 1,144,623.77
Bekisting 12 4.92 m 2
413,440.40 2,034,126.77
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m2 413,440.40 504,397.29
Sub Total 4,797,722.86

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 8.10 m 5,462,500.00 44,246,250.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 1.00 bh 954,500.00 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 8.00 bh 1,341,820.00 10,734,560.00
10 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
11 Rubber packing jadi Ø 400 mm -- 8.00 bh 97,175.00 777,400.00
12 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
13 Street box 32 1.00 bh 483,398.66 483,398.66
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 128.00 bh 12,650.00 1,619,200.00
16 Mur baut 5/8 × 10 cm -- 24.00 bh 10,350.00 248,400.00
Sub Total 111,969,192.07
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 8.10 m 290,455.50 2,352,689.55
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 12,439,743.39

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 10.18 m2 201,487.00 2,050,887.86
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 2,600,887.86
TOTAL 133,600,203.77
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb2 (1 titik, Jb4)
JEMBATAN PIPA 400 MM DENGAN BENTANG 4 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 4.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 3.95 m3 107,482.50 424,236.65
2 Urugan tanah kembali 4 1.32 m3 77,765.00 102,313.60
3 Pasir urug tebal 10 cm 5 0.20 m 3
186,993.00 37,445.35
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 108.00 m 11,376.50 1,228,662.00
Sub Total 1,792,657.60

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.10 m3 1,055,651.87 105,697.14
2 Abutmen Utama
Beton (K-200) 10 0.51 m3 1,032,323.23 524,420.20
Besi 11 80.49 kg 14,220.13 1,144,623.77
Bekisting 12 4.92 m 2
413,440.40 2,034,126.77
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
413,440.40 504,397.29
Sub Total 4,797,722.86

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 15.70 m 5,462,500.00 85,761,250.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00 1,909,000.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00 9,392,740.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00 321,080.00
11 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00 971,750.00
12 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
13 Street box 32 1.00 bh 483,398.66 483,398.66
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00 1,518,000.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00 82,800.00
Sub Total 153,184,962.07
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 15.70 m 290,455.50 4,560,151.35
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 14,647,205.19

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 19.73 m2 201,487.00 3,975,177.70
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 4,525,177.70
TOTAL 178,947,725.41
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb3 (1 titik, Jb6)
JEMBATAN PIPA 400 MM DENGAN BENTANG 8 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 8.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m 3
77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
413,440.40 11,601,137.62
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,044,678.35 214,420.23
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m2 413,440.40 504,397.29
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 473.33 kg 30,432.75 14,404,836.48
5 Balok penyangga kayu ulin 8/16 -- 0.06 m3 9,472,100.00 533,468.67
6 Angkur baut Ø 22 mm -- 32.00 bh 91,162.50 2,917,200.00
7 Klem penjepit dari plat -- 8.00 Ls 125,000.00 1,000,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 48,596,157.25

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 12.10 m 5,462,500.00 66,096,250.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 1.00 bh 954,500.00 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 9.00 bh 1,341,820.00 12,076,380.00
10 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
11 Street box 32 1.00 bh 483,398.66 483,398.66
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)
12 Rubber packing jadi Ø 400 mm -- 2.00 bh 97,175.00 194,350.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 168.00 bh 12,650.00 2,125,200.00
16 Mur baut 5/8 × 10 cm -- 24.00 bh 10,350.00 248,400.00
Sub Total 135,083,962.07

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 12.10 m 290,455.50 3,514,511.55
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 13,601,565.39

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 22.41 m2 201,487.00 4,514,378.38
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 5,064,378.38
TOTAL 206,070,294.63
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb4 (1 titik, Jb2)
JEMBATAN PIPA 400 MM DENGAN BENTANG 10 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)

(1) (2) (3) (4) (5)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 10.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50
2 Urugan tanah kembali 4 4.43 m3 77,765.00
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50
Sub Total

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23
Besi 11 573.13 kg 14,220.13
Bekisting 12 28.06 m 2
382,070.60
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23
Besi 11 19.17 kg 14,220.13
Bekisting 12 1.22 m2 382,070.60
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 591.67 kg 30,432.75
5 Balok penyangga kayu ulin 8/16 -- 0.07 m3 9,472,100.00
6 Angkur baut Ø 22 mm -- 80.00 bh 91,162.50
7 Klem penjepit dari plat -- 10.00 Ls 125,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00
Sub Total

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 21.70 m 5,462,500.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00
11 Street box 32 1.00 bh 483,398.66
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)

(1) (2) (3) (4) (5)


12 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00
Sub Total

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 21.70 m 290,455.50
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83
3 Pemotongan pipa -- 3.00 ttk 350,634.41
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00
Sub Total

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 45.27 m2 201,487.00
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00
Sub Total
TOTAL
CIAN BIAYA PEMBANGUNAN
EMBATAN PIPA Jb4 (1 titik, Jb2)
ATAN PIPA 400 MM DENGAN BENTANG 10 M

JUMLAH HARGA (Rp)

(6)

1,427,421.34
344,252.69
86,811.50
1,865,746.00
3,724,231.54

245,043.19

7,253,103.00
8,149,977.42
10,720,901.04

211,884.34
272,573.35
466,126.13
18,006,045.60
666,835.84
7,293,000.00
1,250,000.00
1,500,000.00
56,035,489.91

118,536,250.00
14,639,040.00
2,590,260.00
16,541,600.00
14,636,358.41
2,760,000.00
1,909,000.00
720,935.00
9,392,740.00
321,080.00
483,398.66
JUMLAH HARGA (Rp)

(6)
971,750.00
51,750.00
805,000.00
1,518,000.00
82,800.00
185,959,962.07

6,302,884.35
5,610,150.60
1,051,903.24
225,000.00
3,200,000.00
16,389,938.19

9,121,119.89
400,000.00
150,000.00
9,671,119.89
271,780,741.59
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb5 (1 titik)
JEMBATAN PIPA 300 MM DENGAN BENTANG 7 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 7.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m3 77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
413,440.40 11,601,137.62
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
413,440.40 504,397.29
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 414.17 kg 30,432.75 12,604,231.92
5 Balok penyangga kayu ulin 8/16 -- 0.05 m 3
9,472,100.00 466,785.09
6 Angkur baut Ø 22 mm -- 28.00 bh 91,162.50 2,552,550.00
7 Klem penjepit dari plat -- 7.00 Ls 125,000.00 875,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 46,236,683.22

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 18.70 m 5,462,500.00 102,148,750.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00 1,909,000.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00 9,392,740.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00 321,080.00
11 Street box 32 1.00 bh 483,398.66 483,398.66
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)


12 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00 971,750.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00 1,518,000.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00 82,800.00
Sub Total 169,572,462.07

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 18.70 m 290,455.50 5,431,517.85
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 15,518,571.69

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 29.80 m2 201,487.00 6,004,133.89
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 6,554,133.89
TOTAL 241,606,082.41
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb7 (1 titik)
JEMBATAN PIPA 400 MM DENGAN BENTANG 12 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)

(1) (2) (3) (4) (5)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 12.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50
2 Urugan tanah kembali 4 4.43 m3 77,765.00
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50
Sub Total

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23
Besi 11 573.13 kg 14,220.13
Bekisting 12 28.06 m 2
413,440.40
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,044,678.35
Besi 11 19.17 kg 13,528.00
Bekisting 12 1.22 m 2
413,440.40
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 710.00 kg 30,432.75
5 Balok penyangga kayu ulin 8/16 -- 0.08 m 3
9,472,100.00
6 Angkur baut Ø 22 mm -- 96.00 bh 91,162.50
7 Klem penjepit dari plat -- 12.00 Ls 125,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00
Sub Total

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 23.70 m 5,462,500.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00
11 Street box 32 1.00 bh 483,398.66
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)

(1) (2) (3) (4) (5)


12 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00
Sub Total

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 23.70 m 290,455.50
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83
3 Pemotongan pipa -- 3.00 ttk 350,634.41
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00
Sub Total

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 51.38 m2 201,487.00
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00
Sub Total
TOTAL
CIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb7 (1 titik)
ATAN PIPA 400 MM DENGAN BENTANG 12 M

JUMLAH HARGA (Rp)

(6)

1,427,421.34
344,252.69
86,811.50
1,865,746.00
3,724,231.54

245,043.19

7,253,103.00
8,149,977.42
11,601,137.62

214,420.23
259,306.51
504,397.29
21,607,254.72
800,203.01
8,751,600.00
1,500,000.00
1,500,000.00
62,386,442.99

129,461,250.00
14,639,040.00
2,590,260.00
16,541,600.00
14,636,358.41
2,760,000.00
1,909,000.00
720,935.00
9,392,740.00
321,080.00
483,398.66
JUMLAH HARGA (Rp)

(6)
971,750.00
51,750.00
805,000.00
1,518,000.00
82,800.00
196,884,962.07

6,883,795.35
5,610,150.60
1,051,903.24
225,000.00
3,200,000.00
16,970,849.19

10,352,865.15
400,000.00
150,000.00
10,902,865.15
290,869,350.93
REKAPITULASI
PEKERJAAN : DED SPAM IKK Desa Sungkai Kecamatan Simpang Empat Kab. Banjar (PDAM)
PAKET : II
LOKASI : a) Desa Cintapuri Darussalam
b) Simpang Madurejo arah Danau Salak (Martapura)
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A : 2018

NO. URAIAN PEKERJAAN HARGA (Rp)


(1) (2) (3)

A Desa Cintapuri Darussalam


I PEKERJAAN PERSIAPAN 51,513,312.00
II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN Err:509
III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN 6,266,401,397.90
IV PEKERJAAN JEMBATAN PIPA 3,231,581,271.61
V PEKERJAAN CROSSING JALAN 20,675,540.11
VI PEKERJAAN LAIN-LAIN 183,136,862.65
SUB TOTAL = Err:509
[A] TOTAL KESELURUHAN = Err:509
[B] PPN 10% = Err:509
[C] TOTAL = [A] + [B] = Err:509
[D] PEMBULATAN = [C] = Err:509

Terbilang : Err:509
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : DED SPAM IKK Desa Sungkai Kecamatan Simpang Empat Kab. Banjar (PDAM)
PAKET : II
LOKASI : a) Desa Cintapuri Darussalam
b) Simpang Madurejo arah Danau Salak (Martapura)
KOTA/KAB. : Banjar
PROVINSI : Kalimantan Selatan
T.A. : 2018

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)
(1) (2) (3) (4) (5)

A Desa Cintapuri Darussalam


I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan patok di sepanjang jalur pipa 1 32,948.00 m 744.00
2 Mobilisasi dan demobilisasi -- 1.00 Ls 20,000,000.00
3 Pembuatan rambu pengaman lalu lintas -- 6.00 Ls 500,000.00
4 Dokumentasi foto 3 phase -- 2.00 set 500,000.00
5 Pembersihan lokasi pekerjaan -- 1.00 Ls 3,000,000.00
Total I

II PEKERJAAN PENGADAAN PIPA DAN AKSESORIS JARINGAN


1 Pengadaan Pipa
1 Pipa HDPE S-8 PN.10 Ø 400 mm -- 32,948.00 m 1,202,594.50
Sub Total
2 Pengadaan Aksesoris
Node 1
1 Stub Flange HDPE Ø 400 mm -- 2.00 bh 3,745,895.00
2 Reducer Ø 400 × 200 mm -- 1.00 bh 3,036,000.00
3 Rubber packing jadi Ø 400 mm -- 2.00 bh Err:509
4 Mur baut 5/8 × 10 cm -- 16.00 bh Err:509
Sub Total
Node 2, 3, 4, 5, 6, 7, 8 dan 9
1 Stub Flange HDPE Ø 400 mm -- 16.00 bh 3,745,895.00
2 Rubber packing jadi Ø 400 mm -- 16.00 bh Err:509
3 Bend HDPE 90° × 400 mm -- 8.00 bh 3,745,895.00
4 Mur baut 5/8 × 10 cm -- 16.00 bh Err:509
Sub Total
Node 10
1 Stub Flange HDPE Ø 400 mm -- 5.00 bh 3,745,895.00
2 Gate Valve Ø 400 mm -- 1.00 bh Err:509
3 Rubber packing jadi Ø 400 mm -- 5.00 bh Err:509
4 Giboult joint Ø 400 mm -- 2.00 bh 45,000.00
5 Mur baut 5/8 × 10 cm -- 80.00 bh Err:509
Sub Total
Total II

III PEKERJAAN PEMASANGAN PIPA DAN AKSESORIS JARINGAN


1 Pekerjaan Galian Tanah
1 Galian tanah keras pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 3 14,826.60 m3 99,160.00
Sub Total
2 Pekerjaan Pemasangan Pipa HDPE
1 Pemasangan pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 21 32,948.00 m 116,071.28
Sub Total
3 Pekerjaan Pengurugan Kembali Galian Tanah
1 Pengurugan kembali pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 4 12,497.64 m3 77,765.00
Sub Total
Total III
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME
ANALISA (Rp)
(1) (2) (3) (4) (5)

IV PEKERJAAN JEMBATAN PIPA


1 Jembatan pipa Ø 400 mm L=3m Jb1 4.00 bh 133,600,203.77
2 Jembatan pipa Ø 400 mm L = 3,6 m Jb7 4.00 bh 137,203,894.69
3 Jembatan pipa Ø 400 mm L = 4m Jb2 2.00 bh 178,947,725.41
4 Jembatan pipa Ø 400 mm L = 18 m Jb8 1.00 bh 308,329,352.80
5 Jembatan pipa Ø 400 mm L = 20 m Jb9 1.00 bh 326,510,185.35
6 Jembatan pipa Ø 400 mm L = 12 m Jb7 1.00 bh 290,869,350.93
7 Jembatan pipa Ø 400 mm L = 10 m Jb4 1.00 bh 271,780,741.59
8 Jembatan pipa Ø 400 mm L = 11 m Jb10 1.00 bh 278,797,793.69
9 Jembatan pipa Ø 400 mm L = 15 m Jb11 1.00 bh 314,182,002.57
Total IV

V PEKERJAAN CROSSING JALAN


1 Crossing jalan cor beton Ø 400 mm, L = 59,00 m
Pekerjaan membongkar beton 7 0.60 m3 676,655.00
Pemasangan beton kembali 9 0.60 m 3
1,055,651.87
Sub Total
2 Crossing jalan aspal, pipa Ø 300 mm L = 534,00 m
Pembongkaran aspal lama 30 64.56 m2 30,510.26
Pekerjaan pengaspalan hotmix tebal 3 cm 31 64.56 m 2
273,643.33
Sub Total
Total V

VI PEKERJAAN LAIN-LAIN
1 Pengetesan pipa HDPE S-8 PN.10 Ø 400 mm / Ø 16" 29 32,948.00 m 5,521.94
2 Pekerjaan interkoneksi dengan pipa eksisting -- 1.00 Ls 1,200,000.00
Total VI
CANA ANGGARAN BIAYA (RAB)

JUMLAH HARGA (Rp)

(6)

24,513,312.00
20,000,000.00
3,000,000.00
1,000,000.00
3,000,000.00
51,513,312.00

39,623,083,586.00
39,623,083,586.00

7,491,790.00
3,036,000.00
Err:509
Err:509
Err:509

59,934,320.00
Err:509
29,967,160.00
Err:509
Err:509

18,729,475.00
Err:509
Err:509
90,000.00
Err:509
Err:509
Err:509

1,470,205,656.00
1,470,205,656.00

3,824,316,524.82
3,824,316,524.82

971,879,217.08
971,879,217.08
6,266,401,397.90
JUMLAH HARGA (Rp)

(6)

534,400,815.09
548,815,578.76
357,895,450.82
308,329,352.80
326,510,185.35
290,869,350.93
271,780,741.59
278,797,793.69
314,182,002.57
3,231,581,271.61

405,993.00
633,391.12
1,039,384.12

1,969,742.39
17,666,413.60
19,636,155.99
20,675,540.11

181,936,862.65
1,200,000.00
183,136,862.65
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb7
JEMBATAN PIPA 400 MM DENGAN BENTANG 3,60 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 3.60 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 3.95 m3 107,482.50 424,236.65
2 Urugan tanah kembali 4 1.32 m 3
77,765.00 102,313.60
3 Pasir urug tebal 10 cm 5 0.20 m 3
186,993.00 37,445.35
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 108.00 m 11,376.50 1,228,662.00
Sub Total 1,792,657.60

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.10 m3 1,055,651.87 105,697.14
2 Abutmen Utama
Beton (K-200) 10 0.51 m3 1,032,323.23 524,420.20
Besi 11 80.49 kg 14,220.13 1,144,623.77
Bekisting 12 4.92 m 2
413,440.40 2,034,126.77
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
413,440.40 504,397.29
Sub Total 4,797,722.86

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 8.70 m 5,462,500.00 47,523,750.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 1.00 bh 954,500.00 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 8.00 bh 1,341,820.00 10,734,560.00
10 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
11 Rubber packing jadi Ø 400 mm -- 8.00 bh 97,175.00 777,400.00
12 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
13 Street box 32 1.00 bh 483,398.66 483,398.66
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 128.00 bh 12,650.00 1,619,200.00
16 Mur baut 5/8 × 10 cm -- 24.00 bh 10,350.00 248,400.00
Sub Total 115,246,692.07
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 8.70 m 290,455.50 2,526,962.85
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 12,614,016.69

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 10.93 m2 201,487.00 2,202,805.47
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 2,752,805.47
TOTAL 137,203,894.69
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb8
JEMBATAN PIPA 400 MM DENGAN BENTANG 18 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 18.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m 3
77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
413,440.40 11,601,137.62
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,017,548.33 208,851.79
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
413,440.40 504,397.29
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 1,065.00 kg 30,432.75 32,410,882.08
5 Balok penyangga kayu ulin 8/16 -- 0.13 m 3
9,472,100.00 1,200,304.51
6 Angkur baut Ø 22 mm -- 144.00 bh 91,162.50 13,127,400.00
7 Klem penjepit dari plat -- 18.00 Ls 125,000.00 2,250,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 78,723,670.25

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 23.70 m 5,462,500.00 129,461,250.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 2,470,200.00 9,880,800.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 1.00 bh 954,500.00 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 11.00 bh 1,341,820.00 14,760,020.00
10 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
11 Rubber packing jadi Ø 400 mm -- 11.00 bh 97,175.00 1,068,925.00
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)
12 Rubber packing jadi Ø 160 mm -- 2.00 bh 40,250.00 80,500.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Street box 32 1.00 bh 483,398.66 483,398.66
15 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
16 Mur baut 3/4 × 10 cm -- 200.00 bh 12,650.00 2,530,000.00
17 Mur baut 5/8 × 10 cm -- 24.00 bh 10,350.00 248,400.00
Sub Total 195,831,677.07

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 23.70 m 290,455.50 6,883,795.35
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 16,970,849.19

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 62.18 m2 201,487.00 12,528,924.75
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 13,078,924.75
TOTAL 308,329,352.80
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb9
JEMBATAN PIPA 400 MM DENGAN BENTANG 20 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 20.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m3 77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m3 186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
413,440.40 11,601,137.62
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,017,548.33 208,851.79
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m2 413,440.40 504,397.29
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 1,183.33 kg 30,432.75 36,012,091.20
5 Balok penyangga kayu ulin 8/16 -- 0.14 m3 9,472,100.00 1,333,671.68
6 Angkur baut Ø 22 mm -- 160.00 bh 91,162.50 14,586,000.00
7 Klem penjepit dari plat -- 20.00 Ls 125,000.00 2,500,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 84,166,846.54

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 25.70 m 5,462,500.00 140,386,250.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 2,470,200.00 9,880,800.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 1.00 bh 954,500.00 954,500.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 11.00 bh 1,341,820.00 14,760,020.00
10 Flange Steel Ø 50 mm -- 2.00 bh 80,270.00 160,540.00
11 Rubber packing jadi Ø 400 mm -- 11.00 bh 97,175.00 1,068,925.00
12 Rubber packing jadi Ø 160 mm -- 2.00 bh 40,250.00 80,500.00
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)
(1) (2) (3) (4) (5) (6)
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Street box 32 1.00 bh 483,398.66 483,398.66
15 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
16 Mur baut 3/4 × 10 cm -- 200.00 bh 12,650.00 2,530,000.00
17 Mur baut 5/8 × 10 cm -- 24.00 bh 10,350.00 248,400.00
Sub Total 206,756,677.07

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 25.70 m 290,455.50 7,464,706.35
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 17,551,760.19

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 68.30 m2 201,487.00 13,760,670.01
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 14,310,670.01
TOTAL 326,510,185.35
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb10
JEMBATAN PIPA 400 MM DENGAN BENTANG 11 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 11.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m 3
77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
382,070.60 10,720,901.04
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
382,070.60 466,126.13
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 650.83 kg 30,432.75 19,806,650.16
5 Balok penyangga kayu ulin 8/16 -- 0.08 m 3
9,472,100.00 733,519.42
6 Angkur baut Ø 22 mm -- 88.00 bh 91,162.50 8,022,300.00
7 Klem penjepit dari plat -- 11.00 Ls 125,000.00 1,375,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 58,757,078.05

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 22.70 m 5,462,500.00 123,998,750.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00 1,909,000.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00 9,392,740.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00 321,080.00
11 Street box 32 1.00 bh 483,398.66 483,398.66
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)


12 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00 971,750.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00 1,518,000.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00 82,800.00
Sub Total 191,422,462.07

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 22.70 m 290,455.50 6,593,339.85
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 16,680,393.69

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 34 48.33 m2 158,583.00 7,663,628.35
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 8,213,628.35
TOTAL 278,797,793.69
RINCIAN BIAYA PEMBANGUNAN
JEMBATAN PIPA Jb10
JEMBATAN PIPA 400 MM DENGAN BENTANG 15 M

NO. HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)

Pembuatan Jembatan Pipa Ø 400 mm Bentang: 15.00 m


I PEKERJAAN GALIAN, TANAH DAN PEMANCANGAN
1 Galian tanah biasa sedalam 1 m 2 13.28 m3 107,482.50 1,427,421.34
2 Urugan tanah kembali 4 4.43 m 3
77,765.00 344,252.69
3 Pasir urug tebal 10 cm 5 0.46 m 3
186,993.00 86,811.50
4 Pemancangan kayu galam Ø 8-10 panjang 4 m 8 164.00 m 11,376.50 1,865,746.00
Sub Total 3,724,231.54

II PEKERJAAN STRUKTUR
1 Lantai kerja tebal 5 cm (K-175) 9 0.23 m3 1,055,651.87 245,043.19
2 Abutmen Utama
Beton (K-200) 10 7.03 m3 1,032,323.23 7,253,103.00
Besi 11 573.13 kg 14,220.13 8,149,977.42
Bekisting 12 28.06 m 2
382,070.60 10,720,901.04
3 Abutmen Penyangga Pipa
Beton (K-200) 10 0.21 m3 1,032,323.23 211,884.34
Besi 11 19.17 kg 14,220.13 272,573.35
Bekisting 12 1.22 m 2
382,070.60 466,126.13
4 Pemasangan baja WF 2× 250.150.6.9 mm -- 887.50 kg 30,432.75 27,009,068.40
5 Balok penyangga kayu ulin 8/16 -- 0.11 m 3
9,472,100.00 1,000,253.76
6 Angkur baut Ø 22 mm -- 120.00 bh 91,162.50 10,939,500.00
7 Klem penjepit dari plat -- 15.00 Ls 125,000.00 1,875,000.00
8 Pagar pengaman baja L Ø 12 mm -- 2.00 Ls 750,000.00 1,500,000.00
Sub Total 69,643,430.63

III PEKERJAAN PENGADAAN PIPA GI DAN AKSESORIS


1 Pipa GI Medium A Ø 400 mm -- 26.70 m 5,462,500.00 145,848,750.00
2 Stub flange HDPE Ø 400 mm -- 2.00 bh 7,319,520.00 14,639,040.00
3 Stub flange HDPE Ø 160 mm -- 2.00 bh 1,295,130.00 2,590,260.00
4 All Flange Bend GI 45° Ø 400 mm -- 4.00 bh 4,135,400.00 16,541,600.00
5 Tee Verlop GI Ø 400 × 160 mm -- 1.00 bh 14,636,358.41 14,636,358.41
6 Gate Valve Ø 160 mm -- 1.00 bh 2,760,000.00 2,760,000.00
7 Gate Valve Ø 50 mm -- 2.00 bh 954,500.00 1,909,000.00
8 Air Valve GI Ø 50 mm -- 1.00 bh 720,935.00 720,935.00
9 Flange Steel Ø 400 mm -- 7.00 bh 1,341,820.00 9,392,740.00
10 Flange Steel Ø 50 mm -- 4.00 bh 80,270.00 321,080.00
11 Street box 30 1.00 bh 30,510.26 30,510.26
NO. HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA (Rp)
ANALISA (Rp)

(1) (2) (3) (4) (5) (6)


12 Rubber packing jadi Ø 400 mm -- 10.00 bh 97,175.00 971,750.00
13 Rubber packing jadi Ø 50 mm -- 2.00 bh 25,875.00 51,750.00
14 Bend HDPE 90° Ø 160 mm -- 1.00 bh 805,000.00 805,000.00
15 Mur baut 3/4 × 10 cm -- 120.00 bh 12,650.00 1,518,000.00
16 Mur baut 5/8 × 10 cm -- 8.00 bh 10,350.00 82,800.00
Sub Total 212,819,573.67

IV PEKERJAAN PEMASANGAN PIPA GI DAN AKSESORIS


1 Pemasangan pipa GI medium A Ø 400 mm 35 26.70 m 290,455.50 7,755,161.85
2 Pengelasan sambungan pipa dan Flange Steel (2x las) -- 8.00 ttk 701,268.83 5,610,150.60
3 Pemotongan pipa -- 3.00 ttk 350,634.41 1,051,903.24
4 Pemasangan box air valve dari besi plat -- 1.00 Ls 225,000.00 225,000.00
5 Koneksi pipa HDPE Ø 400 × 400 mm -- 2.00 Ls 1,600,000.00 3,200,000.00
Sub Total 17,842,215.69

IV PEKERJAAN LAIN-LAIN
1 Pengecetan pipa dan besi yang tampak (3x cat) 32 60.55 m2 158,583.00 9,602,551.05
2 Pengaman dari pipa besi Ø 400 mm -- 1.00 Ls 400,000.00 400,000.00
3 Pembersihan lokasi/izin -- 1.00 Ls 150,000.00 150,000.00
Sub Total 10,152,551.05
TOTAL 314,182,002.57
REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN

No. Uraian Pekerjaan Harga Satuan (Rp)


(1) (2) (3)
1 1 m Pengukuran dan pematokan kembali 1,013.19
2 1 m3 Penggalian tanah biasa sedalam 1 m 107,482.50
3 1 m3 Menggali tanah keras sedalam 1 m 99,160.00
4 1 m3 Pengurugan kembali galian tanah 77,765.00
5 1 m3 Pengurugan dengan pasir urug 186,993.00
6 1 m3 Pembuangan tanah sejauh 30 m 46,576.00
7 1 m3 Pembongkaran beton bertulang 676,655.00
8 1 m Pemancangan kayu galam Ø8-10, panjang 4 m 11,376.50
9 1 m3 Membuat lantai kerja dengan beton mutu f'c = 14,5 MPa, slump (120±20) mm (K-175) 1,055,651.87
10 1 m3 Membuat beton mutu f'c = 16,9 MPa, slump (120±20) mm (K-200) 1,032,323.23
11 1 kg Pembesian dengan besi polos 14,220.13
12 1 m2 Pemasangan bekisting beton 413,440.40
13 1 m2 Pemasangan dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 SP : 3 PP 134,356.50
14 1 m2 Pemasangan plesteran 1 SP : 3 PP tebal 15 mm 86,558.90
15 1 m2 Pemasangan acian 52,811.00
16 1 m Pemasangan pipa tanam Ø 63 mm 57,531.93
17 1 m Pemasangan pipa tanam Ø 90 mm 71,277.04
18 1 m Pemasangan pipa tanam Ø 110 mm 107,699.83
19 1 m Pemasangan pipa tanam Ø 160 mm 121,052.33
20 1 m Pemasangan pipa tanam Ø 200 mm 160,113.74
21 1 m Pemasangan pipa tanam Ø 300 mm 116,071.28
22 1 m Pemasangan pipa tanam Ø 400 mm 129,791.28
23 1 m Pengetesan pipa Ø 63 mm, panjang 400 m 2,210.42
24 1 m Pengetesan pipa Ø 90 mm, panjang 400 m 2,330.61
25 1 m Pengetesan pipa Ø 110 mm, panjang 400 m 2,653.30
26 1 m Pengetesan pipa Ø 160 mm, panjang 400 m 3,313.62
27 1 m Pengetesan pipa Ø 200 mm, panjang 400 m 4,008.17
28 1 m Pengetesan pipa Ø 300 mm, panjang 400 m 5,408.17
29 1 m Pengetesan pipa Ø 400 mm, panjang 400 m 5,521.94
30 1 m2 Pembongkaran aspal lama 30,510.26
31 1 m2 Pekerjaan jalan hotmix tebal 3 cm (per 150 m2) 273,643.33
32 1 buah Pemasangan Street Box Ø 200 mm 483,398.66
33 1 cm Pengelasan dengan las listrik 2,790.26
34 1 m2 Pengecatan baja galvanis manual 3 lapis 201,487.00
35 1 m Pemasangan pipa GI Ø 400 mm 290,455.50
ANALISA HARGA SATUAN PEKERJAAN
SNI Tahun 2016

Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)

1 1 m Pengukuran dan pematokan kembali


6.000 Pekerja OH 137,200.00 823,200.00
0.300 Mandor OH 183,300.00 54,990.00
20.000 Bahan dan alat pematokan buah 5,000.00 100,000.00
1.000 Alat bantu Ls 35,000.00 35,000.00
Harga Satuan / 1 km 878,190.00 135,000.00
Harga Satuan / m 878.19 135.00
2 1 m Penggalian tanah biasa sedalam 1 m
3

0.750 Pekerja OH 137,200.00 102,900.00


0.025 Mandor OH 183,300.00 4,582.50
Harga Satuan 107,482.50
3 1 m3 Menggali tanah keras sedalam 1 m
1.000 Pekerja OH 95,000.00 95,000.00
0.032 Mandor OH 130,000.00 4,160.00
Harga Satuan 99,160.00
4 1 m3 Pengurugan kembali galian tanah
0.500 Pekerja OH 137,200.00 68,600.00
0.050 Mandor OH 183,300.00 9,165.00
Harga Satuan 77,765.00
5 1 m3 Pengurugan dengan pasir urug
0.300 Pekerja OH 137,200.00 41,160.00
0.010 Mandor OH 183,300.00 1,833.00
1.200 Pasir urug m3 120,000.00 144,000.00
Harga Satuan 42,993.00 144,000.00
6 1 m3 Pembuangan tanah sejauh 30 m
0.330 Pekerja OH 137,200.00 45,276.00
0.010 Mandor OH 130,000.00 1,300.00
Harga Satuan 46,576.00
7 1 m3 Pembongkaran beton bertulang
6.667 Pekerja OH 95,000.00 633,365.00
0.333 Mandor OH 130,000.00 43,290.00
Harga Satuan 676,655.00
8 1 m Pemancangan kayu galam Ø8-10, panjang 4 m
0.050 Pekerja OH 95,000.00 4,750.00
0.003 Tukang Kayu OH 120,000.00 360.00
0.001 Kepala Tukang OH 183,300.00 183.30
0.004 Mandor OH 183,300.00 733.20
1.000 Kayu dolken/galam Ø 8-10 cm, panjang 4 m m 3,750.00 3,750.00
0.002 Timbris unit 400,000.00 800.00
0.002 Kereta (gerobak) dorong unit 400,000.00 800.00
Harga Satuan 6,026.50 5,350.00
9 1 m3 Membuat lantai kerja dengan beton mutu f'c = 14,5 MPa, slump (120±20) mm (K-175)
1.650 Pekerja OH 137,200.00 226,380.00
0.275 Tukang Batu OH 120,000.00 33,000.00
0.028 Kepala Tukang OH 130,000.00 3,640.00
0.083 Mandor OH 183,300.00 15,213.90
326.000 Semen Portland (PC) kg 1,500.00 489,000.00
0.543 Pasir beton m 3
162,000.00 87,942.86
0.762 Kerikil m3 206,600.00 157,475.11
215.000 Air bersih liter 200.00 43,000.00
Harga Satuan 278,233.90 777,417.97
Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)
10 1 m3 Membuat beton mutu f'c = 16,9 MPa, slump (120±20) mm (K-200)
1.650 Pekerja OH 95,000.00 156,750.00
0.275 Tukang Batu OH 168,300.00 46,282.50
0.028 Kepala Tukang OH 183,300.00 5,132.40
0.083 Mandor OH 130,000.00 10,790.00
352.000 Semen Portland (PC) kg 1,500.00 528,000.00
0.522 Pasir beton m 3
162,000.00 84,587.14
0.764 Kerikil m3 206,600.00 157,781.19
215.000 Air bersih liter 200.00 43,000.00
Harga Satuan 218,954.90 813,368.33
11 1 kg Pembesian dengan besi polos
0.070 Pekerja OH 137,200.00 9,604.00
0.070 Tukang Besi OH 168,300.00 11,781.00
0.007 Kepala Tukang OH 183,300.00 1,283.10
0.004 Mandor OH 183,300.00 733.20
10.500 Besi beton polos kg 11,000.00 115,500.00
0.150 Kawat beton kg 22,000.00 3,300.00
Harga Satuan / 10 kg 23,401.30 118,800.00
Harga Satuan / kg 2,340.13 11,880.00
12 1 m Pemasangan bekisting beton
2

0.660 Pekerja OH 137,200.00 90,552.00


0.330 Tukang Kayu OH 120,000.00 39,600.00
0.033 Kepala Tukang OH 183,300.00 6,048.90
0.033 Mandor OH 183,300.00 6,048.90
0.030 Kayu papan bekisting m3 2,484,000.00 74,520.00
0.400 Paku rupa-rupa kg 24,100.00 9,640.00
0.200 Minyak bekisting liter 50,853.00 10,170.60
0.020 Balok bekisting m3 3,268,000.00 65,360.00
0.350 Plywood t = 9 mm lembar 190,000.00 66,500.00
3.000 Kayu dolken/galam Ø 8-10 cm, panjang 4 m batang 15,000.00 45,000.00
Harga Satuan 142,249.80 271,190.60
13 1 m2 Pemasangan dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 SP : 3 PP
0.300 Pekerja OH 137,200.00 41,160.00
0.100 Tukang Batu OH 120,000.00 12,000.00
0.010 Kepala Tukang OH 130,000.00 1,300.00
0.015 Mandor OH 183,300.00 2,749.50
70.000 Bata merah buah 700.00 49,000.00
14.370 Semen Portland (PC) kg 1,500.00 21,555.00
0.040 Pasir pasang m3 164,800.00 6,592.00
Harga Satuan 57,209.50 77,147.00
14 1 m2 Pemasangan plesteran 1 SP : 3 PP tebal 15 mm
0.300 Pekerja OH 137,200.00 41,160.00
0.150 Tukang Batu OH 168,300.00 25,245.00
0.015 Kepala Tukang OH 130,000.00 1,950.00
0.015 Mandor OH 183,300.00 2,749.50
7.776 Semen Portland (PC) kg 1,500.00 11,664.00
0.023 Pasir pasang m3 164,800.00 3,790.40
Harga Satuan 71,104.50 15,454.40
15 1 m2 Pemasangan acian
0.200 Pekerja OH 137,200.00 27,440.00
0.100 Tukang Batu OH 168,300.00 16,830.00
0.010 Kepala Tukang OH 183,300.00 1,833.00
0.010 Mandor OH 183,300.00 1,833.00
3.250 Semen Portland (PC) kg 1,500.00 4,875.00
Harga Satuan 47,936.00 4,875.00
Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)
16 1 m Pemasangan pipa tanam Ø 63 mm
0.165 Pekerja OH 137,200.00 22,597.65
0.082 Tukang Pipa OH 168,300.00 13,860.00
0.041 Mandor OH 183,300.00 7,547.65
0.167 Mesin sambung pipa BF/EF jam 52,000.00 8,701.47
0.065 Genset jam 39,000.00 2,549.02
0.016 Scrapper jam 26,000.00 424.84
0.023 Chain Block (Takel) + kaki tiga jam 32,500.00 743.46
0.005 Truck jam 211,875.62 1,107.85
Harga Satuan 44,005.29 13,526.64
17 1 m Pemasangan pipa tanam Ø 90 mm
0.175 Pekerja OH 137,200.00 24,010.00
0.088 Tukang Pipa OH 168,300.00 14,726.25
0.044 Mandor OH 183,300.00 8,019.38
0.301 Mesin sambung pipa BF/EF jam 52,000.00 15,662.65
0.163 Genset jam 39,000.00 6,372.55
0.016 Scrapper jam 26,000.00 424.84
0.026 Chain Block (Takel) + kaki tiga jam 32,500.00 849.67
0.006 Truck jam 211,875.62 1,211.71
Harga Satuan 46,755.63 24,521.42
18 1 m Pemasangan pipa tanam Ø 110 mm
0.233 Pekerja OH 95,000.00 22,166.67
0.117 Tukang Pipa OH 168,300.00 19,635.00
0.058 Mandor OH 183,300.00 10,692.50
0.469 Mesin sambung pipa BF/EF jam 52,000.00 24,364.12
0.310 Genset jam 39,000.00 12,107.84
0.065 Scrapper jam 26,000.00 1,699.35
0.098 Chain Block (Takel) + kaki tiga jam 32,500.00 3,186.27
0.065 Truck jam 211,875.62 13,848.08
Harga Satuan 52,494.17 55,205.67
19 1 m Pemasangan pipa tanam Ø 160 mm
0.311 Pekerja OH 95,000.00 29,555.56
0.156 Tukang Pipa OH 168,300.00 26,180.00
0.078 Mandor OH 130,000.00 10,111.11
0.469 Mesin sambung pipa BF/EF jam 52,000.00 24,364.12
0.310 Genset jam 39,000.00 12,107.84
0.065 Scrapper jam 26,000.00 1,699.35
0.098 Chain Block (Takel) + kaki tiga jam 32,500.00 3,186.27
0.065 Truck jam 211,875.62 13,848.08
Harga Satuan 65,846.67 55,205.67
20 1 m Pemasangan pipa tanam Ø 200 mm
0.400 Pekerja OH 137,200.00 54,880.00
0.200 Tukang Pipa OH 168,300.00 33,660.00
0.100 Mandor OH 183,300.00 18,330.00
0.649 Mesin sambung pipa BF/EF jam 52,000.00 33,761.71
0.441 Genset jam 39,000.00 17,205.88
0.016 Scrapper jam 26,000.00 424.84
0.023 Chain Block (Takel) + kaki tiga jam 32,500.00 743.46
0.005 Truck jam 211,875.62 1,107.85
Harga Satuan 106,870.00 53,243.74
Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)
21 1 m Pemasangan pipa tanam Ø 300 mm
0.300 Pekerja OH 137,200.00 41,160.00
0.080 Tukang Pipa OH 168,300.00 13,464.00
0.004 Mandor OH 183,300.00 733.20
0.200 Supervisor OH 125,000.00 25,000.00
0.150 Mesin sambung pipa BF/EF jam 52,000.00 7,800.00
0.150 Genset jam 39,000.00 5,850.00
0.066 Scrapper jam 26,000.00 1,716.00
0.200 Chain Block (Takel) + kaki tiga jam 32,500.00 6,500.00
0.065 Truck jam 211,875.62 13,848.08
Harga Satuan 80,357.20 35,714.08
22 1 m Pemasangan pipa tanam Ø 400 mm
0.400 Pekerja OH 137,200.00 54,880.00
0.080 Tukang Pipa OH 168,300.00 13,464.00
0.004 Mandor OH 183,300.00 733.20
0.200 Supervisor OH 125,000.00 25,000.00
0.150 Mesin sambung pipa BF/EF jam 52,000.00 7,800.00
0.150 Genset jam 39,000.00 5,850.00
0.066 Scrapper jam 26,000.00 1,716.00
0.200 Chain Block (Takel) + kaki tiga jam 32,500.00 6,500.00
0.065 Truck jam 211,875.62 13,848.08
Harga Satuan 94,077.20 35,714.08
23 1 m Pengetesan pipa Ø 63 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
3.739 Air bersih m3 20,000.00 74,775.96
1.908 Pompa jam 32,500.00 61,997.99
0.392 Genset jam 39,000.00 15,294.12
Harga Satuan / 400 m 732,100.00 152,068.07
Harga Satuan / m 1,830.25 380.17
24 1 m Pengetesan pipa Ø 90 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
5.299 Air bersih m 3
20,000.00 105,975.00
2.309 Pompa jam 32,500.00 75,050.20
0.490 Genset jam 39,000.00 19,117.65
Harga Satuan / 400 m 732,100.00 200,142.85
Harga Satuan / m 1,830.25 500.36
25 1 m Pengetesan pipa Ø 110 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
11.398 Air bersih m3 20,000.00 227,964.00
2.410 Pompa jam 32,500.00 78,313.25
0.588 Genset jam 39,000.00 22,941.18
Harga Satuan / 400 m 732,100.00 329,218.43
Harga Satuan / m 1,830.25 823.05
26 1 m Pengetesan pipa Ø 160 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
24.115 Air bersih m 3
20,000.00 482,304.00
2.711 Pompa jam 32,500.00 88,102.41
0.588 Genset jam 39,000.00 22,941.18
Harga Satuan / 400 m 732,100.00 593,347.59
Harga Satuan / m 1,830.25 1,483.37
27 1 m Pengetesan pipa Ø 200 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)
37.680 Air bersih m3 20,000.00 753,600.00
2.912 Pompa jam 32,500.00 94,628.51
0.588 Genset jam 39,000.00 22,941.18
Harga Satuan / 400 m 732,100.00 871,169.69
Harga Satuan / m 1,830.25 2,177.92
28 1 m Pengetesan pipa Ø 300 mm, panjang 400 m
4.000 Pekerja OH 137,200.00 548,800.00
1.000 Kepala Tukang OH 183,300.00 183,300.00
65.680 Air bersih m3 20,000.00 1,313,600.00
2.912 Pompa jam 32,500.00 94,628.51
0.588 Genset jam 39,000.00 22,941.18
Harga Satuan / 400 m 732,100.00 1,431,169.69
Harga Satuan / m 1,830.25 3,577.92
29 1 m Pengetesan pipa Ø 400 mm, panjang 400 m
4.456 Pekerja OH 137,200.00 611,363.20
1.594 Operator OH 130,000.00 207,220.00
0.697 Mandor OH 183,300.00 127,760.10
50.240 Air bersih m3 20,000.00 1,004,800.00
0.081 Pompa jam 32,500.00 2,632.50
30.000 Solar liter 8,500.00 255,000.00
Harga Satuan / 400 m 946,343.30 1,262,432.50
Harga Satuan / m 2,365.86 3,156.08
30 1 m2 Pembongkaran aspal lama
0.133 Pekerja OH 137,200.00 18,302.48
0.067 Mandor OH 183,300.00 12,207.78
Harga Satuan 30,510.26
31 1 m2 Pekerjaan jalan hotmix tebal 3 cm (per 150 m2)
6.000 Pekerja OH 137,200.00 823,200.00
1.000 Mandor OH 183,300.00 183,300.00
2.000 Operator OH 130,000.00 260,000.00
2.000 Pembantu Mekanik OH 95,000.00 190,000.00
1.000 Supir terampil OH 120,000.00 120,000.00
1.000 Pembantu Supir OH 95,000.00 95,000.00
180.000 Agregat kelas C m3 218,000.00 39,240,000.00
1.000 Alat bantu hotmix Ls 35,000.00 35,000.00
1.000 Vibro jam 100,000.00 100,000.00
Harga Satuan / 150 m2 1,671,500.00 39,375,000.00
Harga Satuan / m 2
11,143.33 262,500.00
32 1 buah Pemasangan Street Box Ø 200 mm
0.048 Galian tanah m3 107,482.50 5,159.16
0.016 Pondasi street box m3 1,055,651.87 16,890.43
0.019 Cor pengunci street box m3 1,055,651.87 19,951.82
0.500 Pipa PVC Ø 150 mm m 232,794.50 116,397.25
0.500 Street box buah 650,000.00 325,000.00
Harga Satuan 483,398.66
33 1 cm Pengelasan dengan las listrik
0.040 Pekerja OH 95,000.00 3,800.00
0.020 Tukang Besi OH 168,300.00 3,366.00
0.002 Kepala Tukang OH 183,300.00 366.60
0.002 Mandor OH 130,000.00 260.00
0.400 Kawat las listrik kg 10,000.00 4,000.00
0.300 Solar liter 8,500.00 2,550.00
0.040 Minyak pelumas liter 33,000.00 1,320.00
0.170 Alat sewa jam 72,000.00 12,240.00
Harga Satuan / 10 cm 7,792.60 20,110.00
Harga Satuan / 1 cm 779.26 2,011.00
Harga Satuan
No. Uraian Satuan Harga Upah (Rp) Harga Bahan (Rp)
(Rp)
(1) (2) (3) (4) (5) (6)
34 1 m2 Pengecatan baja galvanis manual 3 lapis
0.400 Pekerja OH 95,000.00 38,000.00
0.800 Tukang Cat OH 168,300.00 134,640.00
0.080 Kepala Tukang OH 183,300.00 14,664.00
0.020 Mandor OH 130,000.00 2,600.00
0.110 Cat dasar kg 25,000.00 2,750.00
0.170 Cat menie besi kg 27,500.00 4,675.00
0.080 Cat besi kg 48,000.00 3,840.00
0.010 Kuas buah 6,500.00 65.00
0.010 Tiner liter 25,300.00 253.00
Harga Satuan 189,904.00 11,583.00
35 1 m Pemasangan pipa GI Ø 400 mm
1.212 Pekerja OH 137,200.00 166,286.40
0.606 Tukang Pipa OH 168,300.00 101,989.80
0.121 Mandor OH 183,300.00 22,179.30
Harga Satuan 290,455.50
LISA HARGA SATUAN PEKERJAAN
SNI Tahun 2016

Jumlah (Rp)

(7)

823,200.00
54,990.00
100,000.00
35,000.00
1,013,190.00
1,013.19

102,900.00
4,582.50
107,482.50

95,000.00
4,160.00
99,160.00

68,600.00
9,165.00
77,765.00

41,160.00
1,833.00
144,000.00
186,993.00

45,276.00
1,300.00
46,576.00

633,365.00
43,290.00
676,655.00

4,750.00
360.00
183.30
733.20
3,750.00
800.00
800.00
11,376.50

226,380.00
33,000.00
3,640.00
15,213.90
489,000.00
87,942.86
157,475.11
43,000.00
1,055,651.87
Jumlah (Rp)

(7)

156,750.00
46,282.50
5,132.40
10,790.00
528,000.00
84,587.14
157,781.19
43,000.00
1,032,323.23

9,604.00
11,781.00
1,283.10
733.20
115,500.00
3,300.00
142,201.30
14,220.13

90,552.00
39,600.00
6,048.90
6,048.90
74,520.00
9,640.00
10,170.60
65,360.00
66,500.00
45,000.00
413,440.40

41,160.00
12,000.00
1,300.00
2,749.50
49,000.00
21,555.00
6,592.00
134,356.50

41,160.00
25,245.00
1,950.00
2,749.50
11,664.00
3,790.40
86,558.90

27,440.00
16,830.00
1,833.00
1,833.00
4,875.00
52,811.00
Jumlah (Rp)

(7)

22,597.65
13,860.00
7,547.65
8,701.47
2,549.02
424.84
743.46
1,107.85
57,531.93

24,010.00
14,726.25
8,019.38
15,662.65
6,372.55
424.84
849.67
1,211.71
71,277.04

22,166.67
19,635.00
10,692.50
24,364.12
12,107.84
1,699.35
3,186.27
13,848.08
107,699.83

29,555.56
26,180.00
10,111.11
24,364.12
12,107.84
1,699.35
3,186.27
13,848.08
121,052.33

54,880.00
33,660.00
18,330.00
33,761.71
17,205.88
424.84
743.46
1,107.85
160,113.74
Jumlah (Rp)

(7)

41,160.00
13,464.00
733.20
25,000.00
7,800.00
5,850.00
1,716.00
6,500.00
13,848.08
116,071.28

54,880.00
13,464.00
733.20
25,000.00
7,800.00
5,850.00
1,716.00
6,500.00
13,848.08
129,791.28

548,800.00
183,300.00
74,775.96
61,997.99
15,294.12
884,168.07
2,210.42

548,800.00
183,300.00
105,975.00
75,050.20
19,117.65
932,242.85
2,330.61

548,800.00
183,300.00
227,964.00
78,313.25
22,941.18
1,061,318.43
2,653.30

548,800.00
183,300.00
482,304.00
88,102.41
22,941.18
1,325,447.59
3,313.62

548,800.00
183,300.00
Jumlah (Rp)

(7)
753,600.00
94,628.51
22,941.18
1,603,269.69
4,008.17

548,800.00
183,300.00
1,313,600.00
94,628.51
22,941.18
2,163,269.69
5,408.17

611,363.20
207,220.00
127,760.10
1,004,800.00
2,632.50
255,000.00
2,208,775.80
5,521.94

18,302.48
12,207.78
30,510.26

823,200.00
183,300.00
260,000.00
190,000.00
120,000.00
95,000.00
39,240,000.00
35,000.00
100,000.00
41,046,500.00
273,643.33

5,159.16
16,890.43
19,951.82
116,397.25
325,000.00
483,398.66

3,800.00
3,366.00
366.60
260.00
4,000.00
2,550.00
1,320.00
12,240.00
27,902.60
2,790.26
Jumlah (Rp)

(7)

38,000.00
134,640.00
14,664.00
2,600.00
2,750.00
4,675.00
3,840.00
65.00
253.00
201,487.00

166,286.40
101,989.80
22,179.30
290,455.50
DAFTAR HARGA SATUAN UPAH DAN BAHAN

No. Uraian Pekerja Upah (Rp) Satuan


(1) (2) (3) (4)
A UPAH
1 Pekerja 137,200.00 OH
2 Tukang batu 168,300.00 OH
3 Tukang kayu 168,300.00 OH
4 Tukang besi 168,300.00 OH
5 Tukang pipa 168,300.00 OH
6 Tukang Cat 168,300.00 OH
7 Kepala Tukang 183,300.00 OH
8 Operator 130,000.00 OH
9 Pembantu Mekanik 95,000.00 OH
10 Supir Terampil 120,000.00 OH
11 Pembantu Supir 95,000.00 OH
12 Mandor 183,300.00 OH
13 Supervisor 125,000.00 OH

B BAHAN DAN ALAT


1 Pasir urug 120,000.00 m3
2 Bata merah 700.00 buah
3 Semen Portland (PC) 1,500.00 kg
4 Pasir pasang 164,800.00 m3
5 Air bersih 20,000.00 m3
6 Pompa 32,500.00 hari
7 Kayu papan bekisting 2,484,000.00 m3
8 Paku rupa-rupa 24,100.00 kg
9 Minyak bekisting 50,853.00 liter
10 Balok bekisting 3,268,000.00 m3
11 Plywood t = 9 mm 190,000.00 lembar
12 Kayu dolken/galam Ø 8-10 cm, panjang 4 m 15,000.00 batang
13 Pasir beton 162,000.00 m3
14 Kerikil 206,600.00 m3
15 Besi beton polos 11,000.00 kg
16 Kawat beton 22,000.00 kg
17 Bahan dan alat pematokan 5,000.00 buah
18 Alat bantu 35,000.00 Ls
19 Agregat kelas C 218,000.00 m3
20 Balok kayu ulin 9,472,100.00 m3
21 Angkur baut Ø 22 mm 91,162.50 buah
22 Kawat las listrik 10,000.00 kg
23 Solar 8,500.00 liter
24 Minyak pelumas 33,000.00 liter
25 Cat dasar 25,000.00 kg
26 Cat menie besi 27,500.00 kg
27 Cat besi 48,000.00 kg
28 Kuas 6,500.00 buah
29 Tiner 25,300.00 liter

C HARGA PIPA
No. Uraian Pekerja Upah (Rp) Satuan
(1) (2) (3) (4)
1 Pipa HDPE S-8 PN.10 Ø 160 mm 323,082.50 m
2 Pipa HDPE S-8 PN.10 Ø 200 mm 504,319.50 m
3 Pipa HDPE S-8 PN.10 Ø 300 mm 1,202,594.50 m
4 Pipa HDPE S-8 PN.10 Ø 400 mm 1,934,131.50 m
5 Pipa GIP Medium A Ø 160 mm 621,000.00 m
6 Pipa GIP Medium A Ø 300 mm 2,147,441.00 m
7 Pipa GIP Medium A Ø 400 mm 5,462,500.00 m
7 Pipa PVC Ø 150 mm 232,794.50 m

D HARGA AKSESORIS JEMBATAN PIPA


1 Stub Flange HDPE Ø 110 mm 605,705.00 buah
1 Stub flange HDPE Ø 160 mm 1,295,130.00 buah
2 Stub flange HDPE Ø 300 mm 3,745,895.00 buah
3 Stub flange HDPE Ø 400 mm 7,319,520.00 buah
3 All Flange Bend GI 45° Ø 160 mm 637,560.00 buah
4 All Flange Bend GI 45° Ø 300 mm 2,470,200.00 buah
5 All Flange Bend GI 45° Ø 400 mm 4,135,400.00 buah
5 Tee Verlop GI Ø 160 mm × 110 mm 362,940.00 buah
6 Tee Verlop GI Ø 300 mm × 50 mm 725,880.00 buah
7 Tee Verlop GI Ø 400 mm × 160 mm 14,636,358.41 buah
8 Tee Verlop GI Ø 400 mm × 300 mm 12,500,000.00 buah
7 Air valve Ø 50 mm 720,935.00 buah
8 Gate valve resilient Ø 400 mm 52,900,000.00 buah
9 Gate valve Ø 300 mm 10,666,250.00 buah
10 Gate valve Ø 200 mm 4,628,750.00 buah
11 Gate valve Ø 160 mm 2,760,000.00 buah
12 Gate valve Ø 110 mm 1,719,250.00 buah
13 Gate valve Ø 50 mm 954,500.00 buah
14 Flange Steel Ø 160 mm 223,790.00 buah
15 Flange Steel Ø 300 mm 585,005.00 buah
16 Flange Steel Ø 400 mm 1,341,820.00 buah
16 Flange Steel Ø 50 mm 80,270.00 buah
17 Giboult Joint Ø 160 mm 797,500.00 buah
18 Giboult Joint Ø 110 mm 429,000.00 buah
19 Giboult Joint Ø 250 mm 1,155,000.00 buah
20 Giboult Joint Ø 300 mm 1,540,000.00 buah
21 Giboult Joint Ø 400 mm 2,420,000.00 buah
21 Unequal tee HDPE Ø 300×200 mm 1,871,100.00 buah

E HARGA ALAT
1 Vibro 100,000.00 unit/jam
2 Alat bantu hotmix 35,000.00 Ls
3 Mesin sambung pipa BF/EF 52,000.00 jam
4 Genset 39,000.00 jam
5 Scrapper 26,000.00 jam
6 Chain Block (Takel) + kaki tiga 32,500.00 jam
7 Truck 211,875.62 jam

F HARGA AKSESORIS JEMBATAN PIPA


1 Tee HDPE Ø 160 mm (6") 994,175.00 buah
2 Tee HDPE Ø 200 mm (8") 1,712,005.00 buah
No. Uraian Pekerja Upah (Rp) Satuan
(1) (2) (3) (4)
3 Tee HDPE Ø 250 mm (10") 2,705,720.00 buah
4 Equal tee HDPE Ø 400 mm (16") 9,739,810.00 buah
5 Reducer HDPE Ø 250 mm x 200 mm 1,434,510.00 buah
6 Reducer HDPE Ø 250 mm x 160 mm 1,434,510.00 buah
7 Reducer HDPE Ø 200 mm x 160 mm 1,163,800.00 buah
8 Reducer HDPE Ø 160 mm x 110 mm 733,700.00 buah
9 Reducer HDPE Ø 400 mm x 160 mm 3,036,000.00 buah
10 Reducer HDPE Ø 400 mm x 200 mm 3,036,000.00 buah
10 Stub End HDPE Ø 300 mm (12") 3,745,895.00 buah
11 Stub End HDPE Ø 250 mm (10") 2,044,125.00 buah
12 Stub End HDPE Ø 160 mm (6") 1,196,000.00 buah
13 Rubber packing jadi Ø 400 mm 97,175.00 buah
14 Rubber packing jadi Ø 300 mm 74,750.00 buah
13 Rubber packing jadi Ø 250 mm 54,625.00 buah
14 Rubber packing jadi Ø 200 mm 46,000.00 buah
15 Rubber packing jadi Ø 160 mm 40,250.00 buah
16 Rubber packing jadi Ø 50 mm 25,875.00 buah
17 Mur baut ¾ x 5 cm 23,345.00 buah
18 Mur baut 5/8 x 5 cm 9,545.00 buah
19 Mur baut 3/4 × 10 cm 12,650.00 buah
20 Mur baut 5/8 × 10 cm 10,350.00 buah
21 Bend HDPE 90° x 400 mm 5,052,125.00 buah
22 Bend HDPE 90° x 300 mm 3,886,250.00 buah
23 Bend HDPE 90° x 250 mm 2,875,000.00 buah
24 Bend HDPE 90° x 200 mm 925,750.00 buah
25 Bend HDPE 90° x 160 mm 805,000.00 buah
25 Stub Flange PE-100(PN8) + Backing Ring Ø 400 mm 7,319,520.00 buah
26 Stub Flange PE-100(PN8) + Backing Ring Ø 300 mm 3,745,895.00 buah
27 Stub Flange PE-100(PN8) + Backing Ring Ø 200 mm 1,832,985.00 buah
28 Stub Flange PE-100(PN8) + Backing Ring Ø 160 mm 1,295,130.00 buah
29 Street box 650,000.00 buah
30 Flange Adaptor for HDPE DCl-JIS 10 K Ø 200 mm 4,266,730.00 buah