Anda di halaman 1dari 35

REKAPITULASI

RENCANA ANGGARAN BIAYA


KAMPUS KAUTSAR INSTITUTE

SUB TOTAL TOTAL


NO URAIAN PEKERJAAN
(RP.) (RP.)
A. CUT AND FILL 6,859,168,355.37
B. MASJID 1,793,161,206.22
C. PENDOPO 1,391,931,060.11
D. ASRAMA 2,429,932,103.07
E. RUMAH PIMPINAN 759,709,163.45
F. RUMAH USTADZ 3,464,555,647.56
G. DAPUR 543,106,356.50
H. PAUD 343,363,474.71
I. LAPANGAN OLAHRAGA PUTRA 648,040,511.54
J. LAPANGAN OLAHRAGA PUTRI 525,495,448.02
K. TAMBAK, KEBUN DAN PENGELOLAAN LIMBAH 1,529,466,675.21
L. AREA GAZEBO 774,121,372.33
M. KAMAR MANDI ASRAMA & KANAN KIRI MASJID 1,266,443,660.31
N. BANGUNAN GENSET & RUMAH POMPA 65,845,682.51
O. PEKERJAAN PAGAR SAMPING DAN BELAKANG 634,246,578.73
P. PEK. PAGAR DEPAN, GERBANG & PAPAN NAMA 930,604,312.50
Q. PEK. JALAN ,SALURAN & TAMAN 930,604,312.50
R. PEK. ELEKTRIKAL NON STANDARD 395,302,565.30
S. PEK. MEKANIKAL NON STANDARD 2,378,612,480.41
T. PEKERJAAN POS JAGA 51,642,289.52

TOTAL PEKERJAAN STANDARD 22,328,495,034.41


TOTAL PEKERJAAN BANGUNAN PENDUKUNG 5,386,858,221.47
JUMLAH TOTAL 27,715,353,255.88
JASA KONTRAKTOR(10%) 27,715,353,000.00
Terbilang :

# Dua Puluh Tujuh Milyar Tujuh Ratus Lima Belas Juta Tiga Ratus Lima Puluh Tiga Ribu Rupiah #

Kebumen, 8 September 2020


Dibuat Oleh
Konsultan Perencana

……………………..
RINCIAN
RENCANA ANGGARAN BIAYA

CUT AND FILL


TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN LAHAN
1 Pek. Timbunan Pilhan Dengan Alat 20,000.00 m3 194,321.10 3,886,421,938.21
2 Pek, Striping Dengan Alat 25,000.00 m2 42,381.10 1,059,527,422.76
3 Pek. Pemadatan Tanah 25,000.00 m2 69,081.10 1,727,027,422.76
4 Pek. Pembuatan Kantor Direksikeet 30.00 m2 317,325.98 9,519,779.31
5 Pek. Pengadaan Air & Listrik kerja 1.00 Ls 3,402,402.86 3,402,402.86
6 Pek. Pembuatan kantor sementara 30.00 m2 1,608,979.65 48,269,389.46
7 Biaya Perijinan ( IMB ) 25,000.00 m2 5,000.00 125,000,000.00

TOTAL PERSIAPAN 6,859,168,355.37

MASJID
II. PEKERJAAN STANDARD
A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 80.00 m1 52,739.42 4,219,153.96
2 Pek. Galian Tanah Pondasi Plat Setempat 11.17 m3 24,400.00 272,596.80
3 Pek. Galian Tanah Sloof 25/40 26.16 m3 24,400.00 638,304.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 122.53 m3 24,400.00 2,989,683.20
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 3.00 m3 127,600.00 382,800.00
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 2.00 m3 127,600.00 255,200.00
7 Pek. Urugan Tanah Kembali bks Galian 75.17 m3 11,710.00 880,288.13
8 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 1.84 m3 155,740.00 286,561.60
9 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 159.86 m3 11,710.00 1,871,960.60
JUMLAH - I 11,796,548.29
II. PEKERJAAN PONDASI, POER & SLOOF 63
1 Pek. Aanstamping Batukali 28.44 m3 600,240.00 17,073,226.56
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 35.00 m3 893,748.00 31,281,180.00
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 54.70 m2 109,795.28 6,005,801.82
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.7X0.7X0,0)m 1.27 m3 4,790,681.10 6,103,327.72
5 Beton Sloof SL1 25/40 24.34 m3 4,078,216.72 99,247,482.10
6 Beton Sloof SL2 15/25 6.35 m3 3,526,340.47 22,385,209.30

JUMLAH - II 182,096,227.50

III. PEKERJAAN BETON LANTAI BAWAH


1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 17.55 m3 4,538,000.00 79,641,900.00
2 Pek. Beton Balok B2 25/50 cm, Elevasi +4,95,Beton K-225,tulangan 177,78 kg/m3 192.30 m3 5,666,546.70 1,089,676,929.86
3 Pek.Beton Plat Dak t=12 cm , Elevasi +4,20,Beton K-225 32.16 m3 4,078,216.72 131,155,449.72
4 Pek Beton Balok Lintle Openingan Lengkung, Beton K.175 136.50 m' 110,543.90 15,089,242.35

JUMLAH - III 1,315,563,521.93


TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
SUB TOTAL STRUKTURE 1,509,456,297.71
B. PEKERJAAN ATAP
1 Kolom Pedistal kubah 20.50 m2 250,000.00 5,125,000.00
2 Ring Balk Praktis kubah 20.50 m2 25,000.00 512,500.00
3 Pasangan dinding 1/2 bata 1 : 5 20.50 m2 110,930.00 2,274,065.00
4 Penutup Atap Kubah 20.50 m2 123,750.00 2,536,875.00
5 Pek. Profil Keliling Plat Dak 350.00 m1 15,000.00 5,250,000.00

SUB TOTAL ATAP 15,698,440.00

C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
I.a LANTAI BAWAH
1 Pasangan dinding 1/2 bata 1 : 5 79.80 m2 189,390.50 15,113,361.90
2 Pekerjaan plester dan acian dinding 1 : 5 309.80 m2 37,542.80 11,630,759.44
3 Pekerjaan plester dan acian Profil Tali air dinding 546.00 m1 6,500.00 3,549,000.00
4 Pekerjaan plester dan acian Ban-banan dinding 350.00 m1 15,000.00 5,250,000.00
5 Pekerjaan Pasang dinding Batu alam Andesit 79.80 m2 350,000.00 27,930,000.00
6 Pekerjaan Profil Umpak Pilar Batu Alam 64.00 bh 500,000.00 32,000,000.00
7 Pekerjaan Border dinding keramik 10X20 6.00 m' 25,000.00 150,000.00

SUB JUMLAH 95,623,121.34


JUMLAH - I 95,623,121.34
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES


II.a LANTAI BAWAH
1 Pasang Kusen+Pintu Type Toko Unit 5,218,800.00 -
2 Pasang Kusen+Pintu Type PD2 Unit 5,218,800.00 -
3 Pasang Kusen+Pintu Type P1 Unit 5,218,800.00 -
4 Pasang Kusen+Pintu Type P2 Unit 3,645,300.00 -
5 Pasang Kusen+Pintu Type PVC Unit 463,200.00 -
6 Pasang Kusen+jendela Type J1 Unit 2,837,100.00 -
7 Pasang Kusen+jendela Type J2 Unit 2,837,100.00 -
8 Pasang Kusen+jendela Type J3 Unit 2,837,100.00 -
9 Pasang Kusen+jendela Type J4 Unit 2,837,100.00 -

SUB JUMLAH -
II.b LANTAI ATAS
1 Pasang Kusen+Pintu Type PD2 Unit 2,837,100.00 -
2 Pasang Kusen+Pintu Type P1 Unit 2,837,100.00 -
3 Pasang Kusen+Pintu Type PVC Unit 463,200.00 -
4 Pasang Kusen+jendela Type J1 Unit 2,837,100.00 -
5 Pasang Kusen+Pintu Type PVC Unit 2,837,100.00 -
Pasang Kusen+jendela Type J4 Unit 2,837,100.00 -

SUB JUMLAH -
JUMLAH - II -

III. PEKERJAAN PLAFOND


III.a LANTAI BAWAH
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 m2 250,000.00 -
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 67.00 m2 245,000.00 16,415,000.00
3 Pekerjaan profil gipsum 70.00 m' 13,000.00 910,000.00
4 Pekerjaan profil kayu m' 13,500.00 -
SUB JUMLAH 17,325,000.00
III.b LANTAI ATAS
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 m2 250,000.00 -
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) m2 245,000.00 -
3 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Overstek atap) m2 245,000.00 -
4 Pekerjaan profil gipsum m' 13,000.00 -
5 Pekerjaan profil kayu m' 13,500.00 -
SUB JUMLAH -
JUMLAH - III 17,325,000.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

IV. PEKERJAAN LANTAI


IV.a LANTAI BAWAH
1 Urugan pasir bawah lantai t=10 cm 33.40 m3 127,600.00 4,261,840.00
2 Lantai kerja t = 5 cm 16.70 m2 109,795.28 1,833,581.18
3 Pekerjaan lantai Keramik 334.00 m2 217,530.80 72,655,287.20
4 Pekerjaan Plin lantai keramik 10X40 70.00 m' 32,968.68 2,307,807.60

SUB JUMLAH 81,058,515.98


IV.b LANTAI ATAS
1 Urugan pasir bawah lantai t=10 cm m3 127,600.00 -
2 Pekerjaan lantai keramik 40X40 m2 217,530.80 -
3 Pekerjaan Plin lantai keramik 10X40 m2 217,530.80 -
4 Pekerjaan lantai keramik KM 20X20 m2 217,530.80 -

SUB JUMLAH -
JUMLAH - IV 81,058,515.98

V. PEKERJAAN FINISHING & PENGECATAN


V.a LANTAI BAWAH
1 Pekerjaan Finishing Opening 170.00 m1 7,500.00 1,275,000.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 547.80 m2 21,924.13 12,010,035.68
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 309.80 m2 17,539.30 5,433,675.14
4 Pekerjaan pengecatan plafond 45.00 m2 17,539.30 789,268.50
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood m2 76,447.60 -
SUB JUMLAH SUB JUMLAH 19,507,979.32
V.b LANTAI ATAS
1 Pekerjaan Finishing Opening Kusen pada dinding bata m1 7,500.00 -
2 Pekerjaan pengecatan dinding Exterior Watershiel m2 21,924.13 -
3 Pekerjaan pengecatan dinding bata & partisi (Interior) m2 17,539.30 -
4 Pekerjaan pengecatan plafond m2 17,539.30 -
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood m2 76,447.60 -
6 Pekerjaan pengecatan lisplang kayu m2 33,246.25 -
SUB JUMLAH -
JUMLAH - V -
SUB TOTAL ARSITEKTURE 213,514,616.63
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
F. PEKERJAAN ELEKTRIKAL
I. ELEKTRIKAL LANTAI DASAR
1. PEMASANGAN PANEL
a PP-D/LP-D
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 1P 6A 3.00 bh 70,000.00 210,000.00
- MCB 1P 16A 3.00 bh 70,000.00 210,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm - bh 2,750,000.00 -
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCB 3P 80 A 1.00 bh 825,000.00 825,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 3P 32A 4.00 bh 325,000.00 1,300,000.00
SUB JUMLAH 10,288,000.00
2 PASANG KABEL TRAY
kabel tray elektrikal (300 x 50) mm 30.00 m 222,000.00 6,660,000.00
kabel ladder elektrikal (300 x 100) mm 85.00 m 218,000.00 18,530,000.00
SUB JUMLAH 25,190,000.00
3 PASANG GROUNDING SYSTEM
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00
SUB JUMLAH 2,950,000.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 24.00 titik 196,260.22 4,710,245.28
Down Light 14 W 24.00 titik 196,260.22 4,710,245.28
Down Light 18 W 6.00 titik 196,260.22 1,177,561.32
stop kontak 8.00 titik 56,000.00 448,000.00
Saklar ganda 4.00 titik 24,100.00 96,400.00
Saklar tunggal 4.00 titik 24,100.00 96,400.00

SUB JUMLAH 11,238,851.88


JUMLAH - I 49,666,851.88
III. PENANGKAL PETIR
Cable BC 50 mm2 15.00 m 65,000.00 975,000.00
Road Protection 2.00 bh 200,000.00 400,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00
JUMLAH - III 4,825,000.00
SUB TOTAL PEK. ELEKTRIKAL MASJID 54,491,851.88
TOTAL 1,793,161,206.22
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

PENDOPO
I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi Site 990.00 m2 6,050.00 5,989,500.00

TOTAL PERSIAPAN 5,989,500.00


II. PEKERJAAN STANDARD
A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 85.00 m1 52,739.42 4,482,851.08
2 Pek. Galian Tanah Pondasi Plat Setempat 36.29 m3 24,400.00 885,427.20
3 Pek. Galian Tanah Sloof 25/40 37.80 m3 24,400.00 922,320.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 102.06 m3 24,400.00 2,490,264.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 9.45 m3 127,600.00 1,205,820.00
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 11.34 m3 127,600.00 1,446,984.00
7 Pek. Urugan Tanah Kembali bks Galian 176.15 m3 11,710.00 2,062,693.08
8 Pek. Urugan Tanah Peninggian Bangunan t=60 cm(Tanah dari luar) 417.85 m3 155,740.00 65,076,270.48

JUMLAH - I 78,572,629.84
II. PEKERJAAN PONDASI, POER & SLOOF 63
3
1 Pek. Aanstamping Batukali 50.00 m 600,240.00 30,012,000.00
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 199.31 m3 893,748.00 178,128,445.14
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 186.44 m2 109,795.28 20,469,683.03
4 Pekerjaan Beton Pondasi Plat Type P-1 (1.2X1.2X0,7)m 36.29 m3 4,790,681.10 173,844,235.76
5 Beton Sloof SL1 25/40 37.80 m3 4,078,216.72 154,156,592.02
6 Beton Sloof SL2 15/25 0.90 m3 3,526,340.47 3,173,706.42

JUMLAH - II 559,784,662.36
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Pedistal K2-30/30,Beton K-225,tulangan 184,19 kg/m3 2.50 m3 4,538,000.00 11,345,000.00

JUMLAH - III 11,345,000.00


IV. PEKERJAAN KAYU STRUKTUR BAWAH
1 Pek. Kayu Pilar Soko Guru S-1 (0.35x0.35x7)x4 m 3.43 m3 5,805,645.17 19,913,362.94
2 Pek. Kayu Pilar Soko Guru S-2 (0.3x0.3x4.5)x12 m 4.86 m3 5,805,645.17 28,215,435.53
3 Pek. Kayu Pilar Soko Guru S-3 (0.3x0.3x3.3)x20 m 5.94 m' 5,805,645.17 34,485,532.32
4 Pek. Kayu Balok Tumpang sari T1 Kayu Kelas II (0.25*045*13.2)*2 m 2.97 m3 3,415,435.17 10,143,842.46
5 Pek. Kayu Balok Tumpang sari T2 Kayu Kelas II (0.25*045*9.8)*2 m 2.21 m3 3,415,435.17 7,531,034.55
6 Pek. Kayu Balok Tumpang sari T3 Kayu Kelas II (0.25*05*13) m 4.88 m3 3,415,435.17 16,650,246.46
7 Pek. Kayu Balok Tumpang sari T4 Kayu Kelas II (0.25*025*9.5) m 3.56 m3 3,415,435.17 12,167,487.80
8 Pek. Kayu Balok Tumpang sari T5 Kayu Kelas II (0.25*025*3)*10 m 7.00 m3 3,415,435.17 23,908,046.20
9 Pek. Kayu Balok Tumpang sari T6 Kayu Kelas II (0.25*025*5)*10 m 6.00 m3 3,415,435.17 20,492,611.03
10 Pek. Kayu Balok Tumpang sari T7 Kayu Kelas II (0.37*0.37*10.8)*6 m 8.87 m3 3,415,435.17 30,298,735.25
11 Pek. Kayu Balok Blandar B1 Kayu Kelas II (0.2*0.37*23.9)*6 m 10.61 m3 4,206,395.17 44,636,583.00
12 Pek. Kayu Balok Blandar B2 Kayu Kelas II (0.2*0.37*20.5)*6 m 9.10 m3 4,206,395.17 38,286,608.85
13 Pek. Kayu Balok Blandar B3 Kayu Kelas II (0.21*0.25*23.9)*6 m 7.53 m3 4,206,395.17 31,667,846.04
14 Pek. Kayu Balok Blandar B4 Kayu Kelas II (0.21*0.25*20.5)*6 m 6.46 m3 4,206,395.17 27,162,796.82
15 Pek. Kayu Balok Blandar B5 Kayu Kelas II (0.25*0.25*23.9) m 1.49 m3 4,206,395.17 6,283,302.79
16 Pek. Kayu Balok Blandar B6 Kayu Kelas II (0.25*0.25*20.5) m 1.28 m3 4,206,395.17 5,389,443.81
17 Pek. Kayu Balok Blandar B7 Kayu Kelas II (0.2*0.37*31)*3 m 6.88 m3 4,206,395.17 28,948,411.57
18 Pek. Kayu Balok Blandar B8 Kayu Kelas II (0.2*0.37*26.7)*3 m 5.93 m3 4,206,395.17 24,932,986.74
19 Pek. Kayu Balok Blandar B9 Kayu Kelas II (0.07*0.175*33.3) m 0.41 m3 4,206,395.17 1,715,893.75
20 Pek. Kayu Balok Blandar B10 Kayu Kelas II (0.07*0.175*30) m 0.37 m3 4,206,395.17 1,545,850.23
21 Pek. Kayu Balok Konsol Kayu Kelas II (0.175*0.175*2.8)*20 m 1.72 m3 334,879.27 574,317.94

JUMLAH - IV 414,950,376.05
SUB TOTAL STRUKTURE 655,691,792.21
B. PEKERJAAN ATAP
1 Pek. kayu Jurai Kayu Kelas II (0.08 x 0.12) m 0.96 m3 3,415,435.17 3,278,817.76
2 Pek. kayu Nok Kayu Kelas II (0.08 x 0.12) m 0.10 m3 3,415,435.17 327,881.78
3 Pek. Kayu usuk dan Reng 1,325.00 m2 78,213.93 103,633,454.02
4 Pek. Papan bawah reng 1,325.00 m2 50,497.26 66,908,869.50
5 Pek. Pasang Genteng 1,325.00 m2 102,580.00 135,918,500.00
6 Pek. Pasang Genteng wuwung 110.00 m1 97,556.80 10,731,248.00
7 Pek. Lisplang kayu kelas II uk. (3 x 30) cm 281.00 m1 72,390.10 20,341,618.10

SUB TOTAL ATAP 341,140,389.16


C. PEKERJAAN LANTAI
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
1 Urugan pasir bawah lantai t=10 cm 99.90 m3 127,600.00 12,747,240.00
2 Lantai kerja t = 5 cm 49.95 m2 109,795.28 5,484,274.24
3 Pekerjaan lantai tegel motif 999.00 m2 217,530.80 217,313,269.20

SUB TOTAL LANTAI 235,544,783.44


D. PEKERJAAN FINISHING & PENGECATAN
1 Pek. Dempul dan Gosok kayu 1,515.50 m2 6,929.00 10,500,899.50
2 Pek. Mengeter Rangka kayu 1,560.00 m2 9,202.13 14,355,315.00
3 Pek. Politur kayu 1,515.50 m2 76,447.60 115,856,337.80

SUB TOTAL FINISHING 140,712,552.30


E. PEMASANGAN INSTALASI PENERANGAN/LAMPU
I. INSTALASI & LAMPU
1 Installasi
RM TL 2x36 W 34.00 titik 196,260.22 6,672,847.48
Down Light 14 W titik 196,260.22 -
Down Light 18 W titik 196,260.22 -
Baret Lamp 20 W titik 196,260.22 -
stop kontak 6.00 titik 225,699.25 1,354,195.52

SUB JUMLAH 8,027,043.00


II. PENANGKAL PETIR
Cable BC 50 mm2 15.00 m 65,000.00 975,000.00
Road Protection 2.00 bh 200,000.00 400,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00
SUB JUMLAH 4,825,000.00
SUB TOTAL PEK. ELEKTRIKAL 12,852,043.00
TOTAL 1,391,931,060.11

ASRAMA
HARGA SATUAN HARGA
NO URAIAN PEKERJAAN VOLUME SAT
(RP.) (RP.)
1 2 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pembuatan Gudang 10.00 m2 834,840.70 8,348,406.96
2 Pek. Pengadaan Air & Listrik kerja 1.00 Ls 2,500,000.00 2,500,000.00

TOTAL PERSIAPAN 10,848,406.96


II. PEKERJAAN STANDARD
A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 20.00 m1 52,739.42 1,054,788.49
2 Pek. Galian Tanah Pondasi Plat Setempat 12.54 m3 24,400.00 306,073.60
3 Pek. Galian Tanah Sloof 25/40 15.36 m3 24,400.00 374,784.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 62.72 m3 24,400.00 1,530,368.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 3.84 m3 127,600.00 489,984.00
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 8.96 m3 127,600.00 1,143,296.00
7 Pek. Urugan Tanah Kembali bks Galian 40.00 m3 11,710.00 468,400.00
8 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 159.38 m3 155,740.00 24,821,218.24
9 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 90.62 m3 11,710.00 1,061,207.04
JUMLAH - I 31,250,119.37
II. PEKERJAAN PONDASI, POER & SLOOF 63
1 Pek. Aanstamping Batukali 17.92 m3 600,240.00 10,756,300.80
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 70.00 m3 975,975.60 68,318,292.00
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 1.57 m2 109,795.28 172,159.00
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.7X0.7X0,0)m 1.27 m3 4,790,681.10 6,103,327.72
5 Beton Sloof SL1 25/40 12.80 m3 3,526,340.47 45,137,158.02
6 Beton Sloof SL2 15/25 3.00 m3 3,526,340.47 10,579,021.41

JUMLAH - II 141,066,258.95
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 28.80 m3 4,538,000.00 130,694,400.00
2 Pek. Beton Balok B2 25/50 cm, Elevasi +4,95,Beton K-225,tulangan 177,78 kg/m3 16.00 m3 5,666,546.70 90,664,747.15
3 Pek.Beton Plat Dak t=12 cm , Elevasi +4,20,Beton K-225 52.00 m3 5,666,546.70 294,660,428.25
4 Pek Beton Balok Lintle Openingan, Beton K.175 53.00 m' 110,543.90 5,858,826.70
5 Pek Beton Meja Wasstafel t=10 cm, Beton K.175 7.00 m3 110,543.90 773,807.30
0.67 m3
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
JUMLAH - III 522,652,209.41
IV. PEKERJAAN BETON LANTAI ATAS
1 Pekerjaan kolom Beton K2-30/30,Beton K-225 29.00 m3 4,538,000.00 131,602,000.00
2 Pek Kolom Praktis KP 15/15, Beton K.175 125.00 m' 93,553.18 11,694,147.50
3 Pek. Beton Balok B1 - 30/60 cm, Elevasi +8,56 22.50 m3 5,666,546.70 127,497,300.69
4 Pek. Beton Balok B3 - 20/40 cm, Elevasi +8,56 6.00 m3 5,666,546.70 33,999,280.18
5 Pek. Beton Balok BL - 10/40 cm, Elevasi +9,56 1.60 m3 4,078,216.72 6,525,146.75
6 Pek. Beton Plat Dak Atap t=10 cm,Elv. + 9,56 m3 5,620,695.20 -
7 Pek. Beton Balok RB1 - 15/30 cm, Elevasi +10,56 5.80 m3 4,078,216.72 23,653,656.98
8 Pek Beton Luifel Jendela t= 10 cm, Beton K.175 55.00 m' 110,543.90 6,079,914.50

JUMLAH - IV - 341,051,446.60
SUB TOTAL STRUKTURE 1,036,020,034.32
B. PEKERJAAN ATAP
1 Pek. Rangka Atap baja ringan 671.00 m2 250,000.00 167,750,000.00
2 Pek. Alumunium voil 671.00 m2 25,000.00 16,775,000.00
3 Pek. Pasang Penutup Atap 671.00 m2 102,580.00 68,831,180.00
4 Pek. Bubungan Atap 67.00 m2 97,556.80 6,536,305.60
5 Pek. Talang 30.00 100,252.29
6 Pek. Lisplang 148.00 72,390.10

SUB TOTAL ATAP 259,892,485.60


C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
I.a LANTAI BAWAH
1 Pasangan dinding 1/2 bata 1 : 2 30.00 414,642.00 12,439,260.00
2 Pekerjaan plester dan acian dinding 1 : 2 60.00 43,368.30 2,602,098.00
3 Pasangan dinding 1/2 bata 1 : 5 340.00 m2 384,779.80 130,825,132.00
4 Pekerjaan plester dan acian dinding 1 : 5 680.00 m2 37,542.80 25,529,104.00
5 Pekerjaan plester dan acian Profil Tali air dinding 175.00 m1 6,500.00 1,137,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 223.00 m1 15,000.00 3,345,000.00
7 Pekerjaan Profil Umpak Pilar Batu Alam 10.00 bh 500,000.00 5,000,000.00
8 Pekerjaan Border dinding keramik 10X20 135.00 m' 25,000.00 3,375,000.00

SUB JUMLAH 184,253,094.00


II.b LANTAI ATAS
1 Pasangan dinding 1/2 bata 1 : 2 40.00 m2 414,642.00 16,585,680.00
2 Pekerjaan plester dan acian dinding 1 : 2 80.00 m2 43,368.30 3,469,464.00
3 Pasangan dinding 1/2 bata 1 : 5 390.00 m2 384,779.80 150,064,122.00
4 Pekerjaan plester dan acian dinding 1 : 5 780.00 m2 37,542.80 29,283,384.00
5 Pekerjaan plester dan acian Profil Tali air dinding 165.00 m1 6,500.00 1,072,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 60.00 m1 15,000.00 900,000.00
7 Pekerjaan dinding keramik 20X25 h= 2m 19.00 m2 500,000.00 9,500,000.00
8 Pekerjaan Border dinding keramik 10X20 137.00 m' 25,000.00 3,425,000.00
SUB JUMLAH 214,300,150.00
JUMLAH - I 398,553,244.00
II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES
II.a LANTAI BAWAH
1 Pasang Kusen+Pintu Type P1 1.00 Unit 4,206,395.17 4,206,395.17
2 Pasang Kusen+Pintu Type P2 6.00 Unit 5,996,595.17 35,979,571.03
3 Pasang Kusen+Pintu Type PVC 6.00 Unit 450,000.00 2,700,000.00
4 Pasang Kusen+jendela Type J1 3.00 Unit 3,392,245.17 10,176,735.51
5 Pasang Kusen+jendela Type J2 9.00 Unit 3,415,435.17 30,738,916.54
6 Pasang Kusen+jendela Type J3 12.00 Unit 4,206,395.17 50,476,742.05
7 Pasang Kusen+jendela Type J4 5.00 Unit 2,986,004.47 14,930,022.36

SUB JUMLAH 149,208,382.66


II.b LANTAI ATAS
1 Pasang Kusen+Pintu Type P1 1.00 Unit 4,206,395.17 4,206,395.17
2 Pasang Kusen+Pintu Type P2 6.00 Unit 5,996,595.17 35,979,571.03
3 Pasang Kusen+Pintu Type PVC 6.00 Unit 450,000.00 2,700,000.00
4 Pasang Kusen+jendela Type J1 3.00 Unit 3,392,245.17 10,176,735.51
5 Pasang Kusen+jendela Type J2 9.00 Unit 3,415,435.17 30,738,916.54
6 Pasang Kusen+jendela Type J3 12.00 Unit 4,206,395.17 50,476,742.05
7 Pasang Kusen+jendela Type J4 5.00 Unit 2,986,004.47 14,930,022.36

SUB JUMLAH 149,208,382.66


JUMLAH - II 298,416,765.32
III. PEKERJAAN PLAFOND
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
III.a LANTAI BAWAH
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 55.00 m2 100,926.00 5,550,930.00
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 12.00 m2 32,397.14 388,765.68
3 Pekerjaan profil gipsum 225.00 m' 20,100.00 4,522,500.00

SUB JUMLAH 10,462,195.68


III.b LANTAI ATAS
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 80.00 m2 100,926.00 8,074,080.00
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 12.00 m2 45,468.50 545,622.00
3 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Overstek atap) 30.00 m2 45,468.50 1,364,055.00
4 Pekerjaan profil gipsum 155.00 m' 20,100.00 3,115,500.00

SUB JUMLAH 13,099,257.00


JUMLAH - III 23,561,452.68
IV. PEKERJAAN LANTAI
IV.a LANTAI BAWAH
1 Urugan pasir bawah lantai t=10 cm 33.40 m3 109,795.28 3,667,162.35
2 Lantai kerja t = 5 cm 16.70 m2 217,530.80 3,632,764.36
3 Pekerjaan lantai Keramik 334.00 m2 217,530.80 72,655,287.20
4 Pekerjaan Plin lantai keramik 10X40 70.00 m' 169,583.20 11,870,824.00

SUB JUMLAH 91,826,037.91


IV.b LANTAI ATAS
1 Urugan pasir bawah lantai t=10 cm 5.20 m3 109,795.28 570,935.46
2 Pekerjaan lantai keramik 40X40 52.00 m2 217,530.80 11,311,601.60
3 Pekerjaan Plin lantai keramik 10X40 175.00 m2 217,530.80 38,067,890.00
4 Pekerjaan lantai keramik KM 20X20 12.00 m2 169,583.20 2,034,998.40

SUB JUMLAH 51,985,425.46


JUMLAH - IV 143,811,463.37
V. PEKERJAAN FINISHING & PENGECATAN
V.a LANTAI BAWAH
1 Pekerjaan Finishing Opening 225.00 m1 9,490.00 2,135,250.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 340.00 m2 25,000.00 8,500,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 330.00 m2 17,539.30 5,787,969.00
4 Pekerjaan pengecatan plafond 135.00 m2 17,539.30 2,367,805.50
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 120.00 m2 76,447.60 9,173,712.00
SUB JUMLAH 33,246.25 27,964,736.50
V.b LANTAI ATAS
1 Pekerjaan Finishing Opening Kusen pada dinding bata 120.00 m1 9,490.00 1,138,800.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 380.00 m2 25,000.00 9,500,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 370.00 m2 17,539.30 6,489,541.00
4 Pekerjaan pengecatan plafond 52.00 m2 17,539.30 912,043.60
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 90.00 m2 76,447.60 6,880,284.00
6 Pekerjaan pengecatan lisplang kayu 296.00 m2 33,246.25 9,840,890.00
SUB JUMLAH 34,761,558.60
JUMLAH - V 62,726,295.10
SUB TOTAL ARSITEKTURE 927,069,220.47
E. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
1. LANTAI - 1
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 136.00 m 20,592.00 2,800,512.00
- PPR dia 3/4 inc 75.00 m 82,323.00 6,174,225.00
- PPR dia 1 inc 15.00 m 29,502.00 442,530.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 2.00 unit 100,000.00 200,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00
SUB JUMLAH 9,777,267.00
2. LANTAI - 2
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 175.00 m 20,592.00 3,603,600.00
- PPR dia 3/4 inc 90.00 m 82,323.00 7,409,070.00
- PPR dia 1 inc 50.00 m 29,502.00 1,475,100.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00
SUB JUMLAH 12,747,770.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
JUMLAH - I 22,525,037.00
II. PEKERJAAN INSTALASI AIR KOTOR
1. LANTAI - 1
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 10.00 m 44,730.00 447,300.00
- PVC dia 3 inc 55.00 m 126,806.00 6,974,330.00
- PVC dia 4 inc 75.00 m 185,450.00 13,908,750.00

SUB JUMLAH 21,330,380.00


2. LANTAI - 2
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 125.00 m 44,730.00 5,591,250.00
- PVC dia 3 inc 100.00 m 126,806.00 12,680,600.00
- PVC dia 4 inc 98.00 m 185,450.00 18,174,100.00
SUB JUMLAH 36,445,950.00
JUMLAH - II 57,776,330.00
III. PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 7.00 bh 60,300.00 422,100.00
2 Kran air 1/2" 10.00 bh 51,609.93 516,099.25
3 Closet Duduk "TOTO" 6.00 bh 2,479,969.00 14,879,814.00
4 Washtafel Bulat + Accecories "TOTO" 2.00 bh 770,523.00 1,541,046.00

SUB JUMLAH 17,359,059.25


b. LANTAI ATAS
1 Floor drained "TOTO" 7.00 bh 60,300.00 422,100.00
2 Kran air 1/2" 7.00 bh 51,609.93 361,269.48
3 Closet Duduk "TOTO" 6.00 unit 2,479,969.00 14,879,814.00
4 Washtafel Bulat + Accecories "TOTO" 2.00 bh 770,523.00 1,541,046.00
5 Bak. Kitchen zing lengkap meja beton+keramik 2.00 bh 3,500,000.00 7,000,000.00
6
7
SUB JUMLAH 24,204,229.48
JUMLAH - III 41,563,288.73
SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 121,864,655.73
F. PEKERJAAN ELEKTRIKAL
I. ELEKTRIKAL LANTAI DASAR
1. PEMASANGAN PANEL
a PP-D/LP-D
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 1P 6A 3.00 bh 70,000.00 210,000.00
- MCB 1P 16A 3.00 bh 70,000.00 210,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm - bh 2,750,000.00 -
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCB 3P 80 A 1.00 bh 825,000.00 825,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 3P 32A 4.00 bh 325,000.00 1,300,000.00
SUB JUMLAH 10,288,000.00
2 PASANG KABEL TRAY
kabel tray elektrikal (300 x 50) mm 30.00 m 222,000.00 6,660,000.00
kabel ladder elektrikal (300 x 100) mm 85.00 m 218,000.00 18,530,000.00
SUB JUMLAH 25,190,000.00
3 PASANG GROUNDING SYSTEM
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00
SUB JUMLAH 2,950,000.00
4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 24.00 titik 150,000.00 3,600,000.00
Down Light 14 W 24.00 titik 250,000.00 6,000,000.00
Down Light 18 W 6.00 titik 230,000.00 1,380,000.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
stop kontak 20.00 titik 56,000.00 1,120,000.00
Saklar ganda 7.00 titik 24,100.00 168,700.00
Saklar tunggal 6.00 titik 24,100.00 144,600.00

SUB JUMLAH 12,413,300.00


JUMLAH - I 50,841,300.00
II. ELEKTRIKAL LANTAI ATAS
1 PEMASANGAN PANEL
PP-ATAS/LP-ATAS
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCCB 3P 32 A bh 325,000.00 -
- Pilot Lamp Tlmq+MCB 1P 2A 2.00 set 80,500.00 161,000.00
Output 2.00
- MCB 1P 6A 3.00 bh 70,000.00 210,000.00
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
SUB JUMLAH 5,496,000.00
2 PASANG KABEL TRAY
kabel tray elektrikal (300 x 50) mm 9.00 m 222,000.00 1,998,000.00
kabel ladder elektrikal (300 x 100) mm 10.00 m 218,000.00 2,180,000.00
SUB JUMLAH 4,178,000.00
3 PEMASANGAN INSTALASI PENERANGAN/LAMPU LT.ATAS
Installasi
RM TL 2x36 W 12.00 titik 150,000.00 1,800,000.00
Down Light 14 W 12.00 titik 250,000.00 3,000,000.00
Down Light 18 W 10.00 titik 230,000.00 2,300,000.00
Baret Lamp 20 W 20.00 titik 45,000.00 900,000.00
stop kontak 8.00 titik 56,000.00 448,000.00
Saklar ganda 6.00 bh 30,000.00 180,000.00
Saklar tunggal 8.00 bh 18,000.00 144,000.00
SUB JUMLAH 8,772,000.00
4 PENANGKAL PETIR
Cable BC 50 mm2 20.00 m 65,000.00 1,300,000.00
Road Protection 1.00 bh 200,000.00 200,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00

SUB JUMLAH 4,950,000.00


JUMLAH - II 23,396,000.00
SUB TOTAL PEK. ELEKTRIKAL ASRAMA 74,237,300.00
TOTAL 2,429,932,103.07

RUMAH PIMPINAN
HARGA SATUAN HARGA
NO URAIAN PEKERJAAN VOLUME SAT
(RP.) (RP.)
1 2 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 617.40 m2 1,000.00 617,400.00
2 Pek. Pembersihan Lokasi Site 622.30 m2 6,050.00 3,764,915.00
3 Pek. Pembuatan Kantor Gudang 20.00 m2 200,983.20 4,019,664.00
4 Pek. Pengadaan Air & Listrik kerja 0.10 Ls 2,500,000.00 250,000.00

TOTAL PERSIAPAN 8,651,979.00


II. PEKERJAAN STANDARD
A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 24.00 m1 52,739.42 1,265,746.19
2 Pek. Galian Tanah Pondasi Plat Setempat 1.88 m3 24,400.00 45,750.00
3 Pek. Galian Tanah Sloof 15/20 3.42 m3 24,400.00 83,448.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 34.05 m3 24,400.00 830,820.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 50.59 m3 127,600.00 6,455,443.50
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 5.70 m3 127,600.00 727,320.00
7 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 140.06 m3 155,740.00 21,812,165.70
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 39.35 m3 11,710.00 460,729.95

JUMLAH - I 31,681,423.34
II. PEKERJAAN PONDASI, POER & SLOOF 63
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
1 Pek. Aanstamping Batukali 11.40 m3 600,240.00 6,842,736.00
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 23.84 m3 893,748.00 21,302,483.58
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 1.17 m2 109,795.28 128,185.99
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 1.31 m3 4,790,681.10 6,287,768.94
5 Beton Sloof SL2 15/25 50.30 m3 4,078,216.72 205,134,301.02
6 Pek. Beton sloof 15 x 15 carport 1.38 m3 4,078,216.72 5,627,939.07
7 Pek. Beton rabat Carport 21.00 m3 900,078.60 18,901,650.60

JUMLAH - II 264,225,065.20
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 2.36 m3 6,329,700.04 14,953,916.34
2 Pek. Beton Balok B2 25/50 cm, Elevasi +4,95,Beton K-225,tulangan 177,78 kg/m3 2.57 m3 5,666,546.70 14,534,692.28
3 Pek Beton Balok Lintle Openingan, Beton K.175 16.00 m' 110,543.90 1,768,702.40
4 Pek Beton Meja Dapur t=10 cm, Beton K.175 0.20 m3 110,543.90 22,108.78

JUMLAH - III 31,279,419.80


SUB TOTAL STRUKTURE 327,185,908.34
B. PEKERJAAN ATAP
1 Pek. Rangka Atap baja ringan 237.00 m2 250,000.00 59,250,000.00
2 Pek. Alumunium voil 207.00 m2 25,000.00 5,175,000.00
3 Pek. Pasang Penutup Atap 207.00 m2 102,580.00 21,234,060.00
4 Pek. Bubungan Atap 12.00 m' 102,829.93 1,233,959.10
5 Pek. Lisplang 59.40 m' 72,390.10 4,299,971.94
6 Pek. Penutup Atap Carport 60.00 m2 91,615.00 5,496,900.00

SUB TOTAL ATAP 96,689,891.04


C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
I.a LANTAI BAWAH
1 Pasangan dinding 1/2 bata 1 : 2 9.00 414,642.00 3,731,778.00
2 Pekerjaan plester dan acian dinding 1 : 2 18.00 43,368.30 780,629.40
2
3 Pasangan dinding 1/2 bata 1 : 5 365.70 m 384,779.80 140,713,972.86
4 Pekerjaan plester dan acian dinding 1 : 5 731.40 m2 37,542.80 27,458,803.92
5 Pekerjaan plester dan acian Profil Tali air dinding 175.00 m1 6,500.00 1,137,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 62.00 m1 15,000.00 930,000.00
7 Pekerjaan Border dinding keramik 10X20 15.00 m' 25,000.00 375,000.00

JUMLAH - I 175,127,684.18
II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES
II.a LANTAI BAWAH
1 Pasang Kusen+Pintu Type P1 1.00 Unit 4,206,395.17 4,206,395.17
2 Pasang Kusen+Pintu Type P2 3.00 Unit 5,996,595.17 17,989,785.51
3 Pasang Kusen+Pintu Type PVC 2.00 Unit 450,000.00 900,000.00
4 Pasang Kusen+jendela Type J1 4.00 Unit 3,392,245.17 13,568,980.68
5 Pasang Kusen+jendela Type J2 2.00 Unit 3,415,435.17 6,830,870.34

JUMLAH - II 43,496,031.71
III. PEKERJAAN PLAFOND
III.a LANTAI BAWAH
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 169.00 m2 100,926.00 17,056,494.00
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 9.00 m2 45,468.50 409,216.50
3 Pekerjaan profil gipsum 15.00 m' 20,100.00 301,500.00
4 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Overstek atap) 53.46 m2 45,468.50 2,430,746.01

JUMLAH - III 20,197,956.51


IV. PEKERJAAN LANTAI
IV.a LANTAI BAWAH
1 Urugan pasir bawah lantai t=10 cm 1.60 m3 109,795.28 175,672.45
2 Lantai kerja t = 5 cm 8.00 m2 217,530.80 1,740,246.40
3 Pekerjaan lantai Keramik 160.00 m2 217,530.80 34,804,928.00
4 Pekerjaan Plin lantai keramik 10X40 85.00 m' 169,583.20 14,414,572.00

JUMLAH - IV 51,135,418.85
V. PEKERJAAN FINISHING & PENGECATAN
V.a LANTAI BAWAH
1 Pekerjaan Finishing Opening 46.00 m1 9,490.00 436,540.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 246.00 m2 25,000.00 6,150,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 210.00 m2 17,539.30 3,683,253.00
4 Pekerjaan pengecatan plafond 160.00 m2 17,539.30 2,806,288.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 37.00 m2 76,447.60 2,828,561.20
SUB JUMLAH 33,246.25 15,904,642.20
SUB TOTAL ARSITEKTURE 305,861,733.45
E. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
1. LANTAI - 1
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 16.00 m 20,592.00 329,472.00
- PPR dia 3/4 inc 14.00 m 82,323.00 1,152,522.00
- PPR dia 1 inc 8.00 m 29,502.00 236,016.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00
JUMLAH - I 1,978,010.00
II. PEKERJAAN INSTALASI AIR KOTOR
1. LANTAI - 1
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 6.00 m 44,730.00 268,380.00
- PVC dia 3 inc 20.00 m 126,806.00 2,536,120.00
- PVC dia 4 inc 12.00 m 185,450.00 2,225,400.00

JUMLAH - II 5,029,900.00
III. PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 2.00 bh 60,300.00 120,600.00
2 Kran air 1/2" 5.00 bh 51,609.93 258,049.63
3 Closet Duduk "TOTO" 1.00 bh 2,479,969.00 2,479,969.00
4 Washtafel Bulat + Accecories "TOTO" 1.00 bh 770,523.00 770,523.00

JUMLAH - III 3,629,141.63


SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 10,637,051.63
F. PEKERJAAN ELEKTRIKAL
I. ELEKTRIKAL LANTAI DASAR
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 1P 6A 3.00 bh 70,000.00 210,000.00
- MCB 1P 16A 3.00 bh 70,000.00 210,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm - bh 2,750,000.00 -
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00
Input
- MCB 3P 80 A 1.00 bh 825,000.00 825,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 3P 32A 4.00 bh 325,000.00 1,300,000.00
SUB JUMLAH 5,588,000.00
4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 24.00 titik 150,000.00 3,600,000.00
Down Light 14 W 24.00 titik 250,000.00 6,000,000.00
Down Light 18 W 6.00 titik 230,000.00 1,380,000.00
stop kontak 20.00 titik 56,000.00 1,120,000.00
Saklar ganda 7.00 titik 24,100.00 168,700.00
Saklar tunggal 6.00 titik 24,100.00 144,600.00

SUB JUMLAH 12,413,300.00


4 PENANGKAL PETIR
Cable BC 50 mm2 20.00 m 65,000.00 1,300,000.00
Road Protection 1.00 bh 200,000.00 200,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00

SUB JUMLAH 4,950,000.00


SUB TOTAL PEK.ELEKTRIKAL 10,682,600.00
TOTAL 759,709,163.45
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

RUMAH USTADZ
SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 56.00 m2 1,000.00 56,000.00
2 Pek. Pembersihan Lokasi Site 56.00 m2 6,050.00 338,800.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 8,651,979.00


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 10.00 m1 52,739.42 527,394.25
2 Pek. Galian Tanah Pondasi Plat Setempat 1.88 m3 24,400.00 45,750.00
3 Pek. Galian Tanah Sloof 15/20 2.88 m3 24,400.00 70,272.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 17.28 m3 24,400.00 421,632.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 0.38 m3 127,600.00 47,850.00
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 2.88 m3 127,600.00 367,488.00
7 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 0.37 m3 155,740.00 56,845.10
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 22.04 m3 11,710.00 258,029.85

JUMLAH - I 31,681,423.34
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 5.76 m3 600,240.00 3,457,382.40
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 12.96 m3 893,748.00 11,582,974.08
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 0.38 m2 109,795.28 41,173.23
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 0.75 m3 4,790,681.10 3,593,010.83
5 Beton Sloof SL2 15/25 1.44 m3 4,078,216.72 5,872,632.08

JUMLAH - II 24,547,172.61
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 0.86 m3 6,329,700.04 5,468,860.83
2 Pek. Beton Balok B2 25/50 cm, Elevasi +4,95,Beton K-225,tulangan 177,78 kg/m3 1.08 m3 5,666,546.70 6,119,870.43
3 Pek Beton Balok Lintle Openingan, Beton K.175 12.00 m' 110,543.90 1,326,526.80
4 Pek Beton Meja Dapur t=10 cm, Beton K.175 2.00 m3 110,543.90 221,087.80

JUMLAH - III 13,136,345.87


SUB TOTAL STRUKTURE 69,364,941.82
B. PEKERJAAN ATAP
1 Pek. Rangka Atap baja ringan 96.00 m2 250,000.00 59,250,000.00
2 Pek. Alumunium voil 96.00 m2 25,000.00 5,175,000.00
3 Pek. Pasang Penutup Atap 96.00 m2 102,580.00 21,234,060.00
4 Pek. Bubungan Atap 13.00 m' 102,829.93 1,233,959.10
5 Pek. Lisplang 44.00 m' 72,390.10 4,299,971.94

SUB TOTAL ATAP 91,192,991.04


C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
1 Pasangan dinding 1/2 bata 1 : 2 10.60 0 414,642.00 4,395,205.20
2 Pekerjaan plester dan acian dinding 1 : 2 4.50 0 43,368.30 195,157.35
3 Pasangan dinding 1/2 bata 1 : 5 148.00 m2 384,779.80 56,947,410.40
4 Pekerjaan plester dan acian dinding 1 : 5 296.00 m2 37,542.80 11,112,668.80
5 Pekerjaan plester dan acian Profil Tali air dinding 105.00 m1 6,500.00 682,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 45.00 m1 15,000.00 675,000.00
7 Pekerjaan Border dinding keramik 10X20 48.00 m' 25,000.00 1,200,000.00

JUMLAH - I 75,207,941.75
II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES
1 Pasang Kusen+Pintu Type P1 1.00 Unit 4,206,395.17 4,206,395.17
2 Pasang Kusen+Pintu Type P2 3.00 Unit 5,996,595.17 17,989,785.51
3 Pasang Kusen+Pintu Type PVC 1.00 Unit 450,000.00 450,000.00
4 Pasang Kusen+jendela Type J1 4.00 Unit 3,392,245.17 13,568,980.68
5 Pasang Kusen+jendela Type J2 1.00 Unit 3,415,435.17 3,415,435.17

JUMLAH - II 39,630,596.54
III. PEKERJAAN PLAFOND
1 Pek. Plafond Gypsum 9mm+Rangka Hollow 40x40 56.00 m2 100,926.00 5,651,856.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
2 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 2.25 m2 45,468.50 102,304.13
3 Pekerjaan profil gipsum 48.00 m' 20,100.00 964,800.00
4 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Overstek atap) 25.20 m2 45,468.50 1,145,806.20

JUMLAH - III 20,197,956.51


IV. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 56.00 m3 109,795.28 6,148,535.68
2 Lantai kerja t = 5 cm 2.80 m2 217,530.80 609,086.24
3 Pekerjaan lantai Keramik 56.00 m2 217,530.80 12,181,724.80
4 Pekerjaan Plin lantai keramik 10X40 48.00 m' 169,583.20 8,139,993.60

JUMLAH - IV 51,135,418.85
V. PEKERJAAN FINISHING & PENGECATAN
1 Pekerjaan Finishing Opening 38.00 m1 9,490.00 360,620.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 105.00 m2 25,000.00 2,625,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 148.00 m2 17,539.30 2,595,816.40
4 Pekerjaan pengecatan plafond 56.00 m2 17,539.30 982,200.80
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 24.00 m2 76,447.60 1,834,742.40
JUMLAH V 33,246.25 8,398,379.60
SUB TOTAL ARSITEKTURE 305,861,733.45
E. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 9.00 m 20,592.00 185,328.00
- PPR dia 3/4 inc 6.00 m 82,323.00 493,938.00
- PPR dia 1 inc 4.00 m 29,502.00 118,008.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00
JUMLAH - I 1,057,274.00
II. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 4.00 m 44,730.00 178,920.00
- PVC dia 3 inc 10.00 m 126,806.00 1,268,060.00
- PVC dia 4 inc 8.00 m 185,450.00 1,483,600.00

JUMLAH - II 2,930,580.00
III. PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 2.00 bh 60,300.00 120,600.00
2 Kran air 1/2" 3.00 bh 51,609.93 154,829.78
3 Closet Duduk "TOTO" 1.00 bh 2,479,969.00 2,479,969.00
4 Washtafel Bulat + Accecories "TOTO" 1.00 bh 770,523.00 770,523.00

JUMLAH - III 3,525,921.78


SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 7,513,775.78
F. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 6A 2.00 bh 70,000.00 140,000.00
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 6.00 titik 150,000.00 900,000.00
Down Light 14 W 4.00 titik 250,000.00 1,000,000.00
stop kontak 6.00 titik 56,000.00 336,000.00
Saklar ganda 3.00 titik 24,100.00 72,300.00
Saklar tunggal 3.00 titik 24,100.00 72,300.00

SUB JUMLAH 2,380,600.00


4 PENANGKAL PETIR -
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
Cable BC 50 mm2 10.00 m 65,000.00 650,000.00
Road Protection 1.00 bh 200,000.00 200,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00

SUB JUMLAH 4,300,000.00


SUB TOTAL PEK.ELEKTRIKAL 12,351,100.00
TOTAL (x 7 UNIT) 3,464,555,647.56

DAPUR
VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 247.50 m2 1,000.00 56,000.00
2 Pek. Pembersihan Lokasi Site 123.75 m2 6,050.00 338,800.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 8,651,979.00


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 16.00 m1 52,739.42 843,830.79
2 Pek. Galian Tanah Pondasi Plat Setempat 3.46 m3 24,400.00 84,326.40
3 Pek. Galian Tanah Sloof 15/20 5.67 m3 24,400.00 138,348.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 45.36 m3 24,400.00 1,106,784.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 0.91 m3 127,600.00 116,447.76
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 4.54 m3 127,600.00 578,793.60
7 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 44.31 m3 155,740.00 6,901,462.36
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 54.49 m3 11,710.00 638,031.06

JUMLAH - I 10,408,023.97
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 15.12 m3 600,240.00 9,075,628.80
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 34.02 m3 893,748.00 30,405,306.96
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 0.17 m2 109,795.28 18,994.58
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 1.44 m3 4,790,681.10 6,898,580.78
5 Beton Sloof SL2 15/25 4.73 m3 4,078,216.72 19,269,574.00

JUMLAH - II 65,668,085.13
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 2.56 m3 6,329,700.04 16,204,032.10
2 Pek. Beton Balok B2 20/25 cm, Elevasi +4,95,Beton K-225,tulangan 177,78 kg/m3 6.30 m3 5,666,546.70 35,699,244.19
3 Pek Beton Balok Lintle Openingan, Beton K.175 12.00 m' 110,543.90 1,326,526.80
4 Pek Beton Meja Dapur t=10 cm, Beton K.175 0.58 m3 110,543.90 63,673.29

JUMLAH - III 53,293,476.38


SUB TOTAL STRUKTURE 129,369,585.48
B. PEKERJAAN ATAP
1 Pek. Rangka Atap baja ringan 409.00 m2 250,000.00 102,250,000.00
2 Pek. Alumunium voil 409.00 m2 25,000.00 10,225,000.00
3 Pek. Pasang Penutup Atap 409.00 m2 102,580.00 41,955,220.00
4 Pek. Bubungan Atap 169.00 m' 102,829.93 17,378,257.33
5 Pek. Lisplang 99.00 m' 72,390.10 7,166,619.90

SUB TOTAL ATAP 178,975,097.23


C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
1 Pasangan dinding 1/2 bata 1 : 2 6.00 0 414,642.00 2,487,852.00
2 Pekerjaan plester dan acian dinding 1 : 2 6.00 0 43,368.30 260,209.80
3 Pasangan dinding 1/2 bata 1 : 5 174.00 m2 384,779.80 66,951,685.20
4 Pekerjaan plester dan acian dinding 1 : 5 348.00 m2 37,542.80 13,064,894.40
5 Pekerjaan plester dan acian Profil Tali air dinding 65.00 m1 6,500.00 422,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 43.00 m1 15,000.00 645,000.00
7 Pekerjaan Border dinding keramik 10X20 63.00 m' 25,000.00 1,575,000.00

JUMLAH - I 85,407,141.40
II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES
1 Pasang Kusen+Pintu Type P1 2.00 Unit 4,206,395.17 8,412,790.34
4 Pasang Kusen+jendela Type J1 4.00 Unit 3,392,245.17 13,568,980.68
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
5 Pasang Kusen+boven angin2 2.00 Unit 3,415,435.17 6,830,870.34

JUMLAH - II 28,812,641.37
III. PEKERJAAN PLAFOND
1 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 + (Overstek atap) 277.50 m2 45,468.50 12,617,508.75

JUMLAH - III 12,617,508.75


IV. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 24.75 m3 109,795.28 2,717,433.18
2 Lantai kerja t = 5 cm 12.38 m2 217,530.80 2,691,943.65
3 Pekerjaan lantai Keramik 247.50 m2 217,530.80 53,838,873.00
4 Pekerjaan Plin lantai keramik 10X40 52.60 m' 169,583.20 8,920,076.32

JUMLAH - IV 68,168,326.15
V. PEKERJAAN FINISHING & PENGECATAN
1 Pekerjaan Finishing Opening 28.00 m1 9,490.00 265,720.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 174.00 m2 25,000.00 4,350,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 150.00 m2 17,539.30 2,630,895.00
4 Pekerjaan pengecatan plafond 277.50 m2 17,539.30 4,867,155.75
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 21.00 m2 76,447.60 1,605,399.60

JUMLAH V 33,246.25 13,719,170.35


SUB TOTAL ARSITEKTURE 208,724,788.02
E. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 9.00 m 20,592.00 185,328.00
- PPR dia 3/4 inc 10.00 m 82,323.00 493,938.00
- PPR dia 1 inc 5.00 m 29,502.00 118,008.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00
JUMLAH - I 1,057,274.00
II. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 4.00 m 44,730.00 178,920.00
- PVC dia 3 inc 18.00 m 126,806.00 1,268,060.00
- PVC dia 4 inc 12.00 m 185,450.00 1,483,600.00

JUMLAH - II 2,930,580.00
III. PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 2.00 bh 60,300.00 120,600.00
2 Kran air 1/2" 3.00 bh 51,609.93 154,829.78
3 Washtafel Bulat + Accecories "TOTO" 1.00 bh 770,523.00 770,523.00

JUMLAH - III 1,045,952.78


SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 5,033,806.78
F. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 6A 2.00 bh 70,000.00 140,000.00
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 8.00 titik 150,000.00 1,200,000.00
stop kontak 4.00 titik 56,000.00 224,000.00
Saklar ganda 2.00 titik 24,100.00 48,200.00
Saklar tunggal 2.00 titik 24,100.00 48,200.00

SUB JUMLAH 2,380,600.00


TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
4 PENANGKAL PETIR -
Cable BC 50 mm2 10.00 m 65,000.00 650,000.00
Road Protection 1.00 bh 200,000.00 200,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00

SUB JUMLAH 4,300,000.00


SUB TOTAL PEK.ELEKTRIKAL 12,351,100.00
TOTAL 543,106,356.50

PAUD
VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 730.00 m2 1,000.00 730,000.00
2 Pek. Pembersihan Lokasi Site 365.00 m2 6,050.00 2,208,250.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 3,773,090.70


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 12.00 m1 52,739.42 632,873.09
2 Pek. Galian Tanah Pondasi Plat Setempat 0.86 m3 24,400.00 21,081.60
3 Pek. Galian Tanah Sloof 15/20 2.79 m3 24,400.00 68,076.00
4 Pek. Galian Tanah Pondasi Batu kali menerus 33.48 m3 24,400.00 816,912.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 2.15 m3 127,600.00 274,084.80
6 Pek. Urugan Pasir Bawah Pondasi batu kali t=10cm 9.30 m3 127,600.00 1,186,680.00
7 Pek. Urugan Tanah Peninggian Bangunan t=40 cm(Tanah dari luar) 24.80 m3 155,740.00 3,862,352.00
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 3.00 m3 11,710.00 35,130.00

JUMLAH - I 6,897,189.49
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 11.16 m3 600,240.00 6,698,678.40
2 Pek. Pondasi Batu kali camp. 1Pc:4Psr 50.22 m3 893,748.00 44,884,024.56
3 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 1.07 m2 109,795.28 117,920.13
4 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 0.50 m3 4,790,681.10 2,395,340.55
5 Beton Sloof SL2 15/25 3.49 m3 4,078,216.72 14,222,780.81

JUMLAH - II 68,318,744.45
III. PEKERJAAN BETON LANTAI BAWAH
1 Pekerjaan kolom Beton K2-30/30,Beton K-225,tulangan 184,19 kg/m3 4.32 m3 6,329,700.04 27,344,304.17
2 Pek. Beton Balok B2 20/25 cm, Elevasi +4.00,Beton K-225,tulangan 177,78 kg/m3 4.65 m3 5,666,546.70 26,349,442.14
3 Pek Beton Balok Lintle Openingan, Beton K.175 20.00 m' 110,543.90 2,210,878.00

JUMLAH - III 55,904,624.31


SUB TOTAL STRUKTURE 131,120,558.26
B. PEKERJAAN ATAP
1 Pek. Plat Lantai Atap Elevasi +4.00, Beton K225 7.92 m2 6,172,571.45 48,886,765.85

SUB TOTAL ATAP 48,886,765.85


C. PEKERJAAN ARSITEKTUR
I. PEKERJAAN DINDING & PLESTERAN
1 Pasangan dinding 1/2 bata 1 : 2 10.80 0 414,642.00 4,478,133.60
2 Pekerjaan plester dan acian dinding 1 : 2 10.80 0 43,368.30 468,377.64
3 Pasangan dinding 1/2 bata 1 : 5 104.00 m2 384,779.80 40,017,099.20
4 Pekerjaan plester dan acian dinding 1 : 5 208.00 m2 37,542.80 7,808,902.40
5 Pekerjaan plester dan acian Profil Tali air dinding 25.00 m' 6,500.00 162,500.00
6 Pekerjaan plester dan acian Ban-banan dinding 93.00 m' 15,000.00 1,395,000.00
7 Pekerjaan Border dinding keramik 10X20 30.00 m' 25,000.00 750,000.00
8 Pekerjaan Profilan Dak atap 33.00 m' 78,771.50 2,599,459.50

JUMLAH - I 57,679,472.34
II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES
1 Pasang Kusen+Pintu Type P1 4.00 Unit 4,206,395.17 16,825,580.68
5 Pasang Kusen+Pintu PVC 1.00 Unit 463,200.00 16,825,580.68
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
JUMLAH - II 33,651,161.37
III. PEKERJAAN PLAFOND
1 Pek.Plesteran beton 1 PC : 2 Ps, tebal 15 mm 66.00 m2 50,827.90 3,354,641.40
2 Pek. Plesteran waterproof batacote, 3 lapis 66.00 m2 221,189.40 14,598,500.40
3 Pek. Kompon Gypsum (nonSNI) 66.00 m2 30,852.80 2,036,284.80
4 Pek. List gypsum board, tebal 9 mm 30.00 m' 20,100.00 603,000.00

JUMLAH - III 20,592,426.60


IV. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 6.20 m3 109,795.28 680,730.74
2 Lantai kerja t = 5 cm 3.10 m2 217,530.80 674,345.48
3 Pekerjaan lantai Keramik 62.00 m2 217,530.80 13,486,909.60
4 Pekerjaan Plin lantai keramik 10X40 30.00 m' 169,583.20 5,087,496.00

JUMLAH - IV 19,929,481.82
V. PEKERJAAN FINISHING & PENGECATAN
1 Pekerjaan Finishing Opening 20.00 m1 9,490.00 189,800.00
2 Pekerjaan pengecatan dinding Exterior Watershiel 103.00 m2 25,000.00 2,575,000.00
3 Pekerjaan pengecatan dinding bata & partisi (Interior) 125.00 m2 17,539.30 2,192,412.50
4 Pekerjaan pengecatan langit2 66.00 m2 17,539.30 1,157,593.80
5 Pekerjaan pengecatan politur Daun pintu Lapis Teakwood 26.40 m2 76,447.60 2,018,216.64

JUMLAH V 33,246.25 8,133,022.94


SUB TOTAL ARSITEKTURE 139,985,565.06
E. PEKERJAAN MEKANIKAL & SANITARY
I PEKERJAAN INSTALASI AIR BERSIH
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 7.00 m 20,592.00 144,144.00
- PPR dia 3/4 inc 12.00 m 82,323.00 987,876.00
- PPR dia 1 inc 5.00 m 29,502.00 147,510.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00

JUMLAH - I 1,539,530.00
II. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 5.00 m 44,730.00 223,650.00
- PVC dia 3 inc 12.00 m 126,806.00 1,521,672.00
- PVC dia 4 inc 16.00 m 185,450.00 2,967,200.00

JUMLAH - II 4,712,522.00
III. PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 2.00 bh 60,300.00 120,600.00
2 Kran air 1/2" 2.00 bh 51,609.93 103,219.85
3 Washtafel Bulat + Accecories "TOTO" 1.00 bh 770,523.00 770,523.00

JUMLAH - III 994,342.85


SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 7,246,394.85
F. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 6A 2.00 bh 70,000.00 140,000.00
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
- MCB 3P 6A 1.00 bh 285,000.00 285,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 8.00 titik 150,000.00 1,200,000.00
stop kontak 4.00 titik 56,000.00 224,000.00
Saklar ganda 2.00 titik 24,100.00 48,200.00
Saklar tunggal 2.00 titik 24,100.00 48,200.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

SUB JUMLAH 2,380,600.00


4 PENANGKAL PETIR -
Cable BC 50 mm2 10.00 m 65,000.00 650,000.00
Road Protection 1.00 bh 200,000.00 200,000.00
Installasi & accessories 2.00 titik 250,000.00 500,000.00
Grounding system max. 2 Ohm + Box Control 1.00 titik 2,950,000.00 2,950,000.00

SUB JUMLAH 4,300,000.00


SUB TOTAL PEK.ELEKTRIKAL 12,351,100.00
TOTAL 343,363,474.71

LAPANGAN OLAHRAGA PUTRA


VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 1,155.00 m2 1,000.00 1,155,000.00
2 Pek. Pembersihan Lokasi Site 500.00 m2 6,050.00 3,025,000.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 5,014,840.70


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 36.00 m1 52,739.42 1,898,619.28
2 Pek. Galian Tanah Pondasi Plat Setempat 2.10 m3 24,400.00 51,240.00
3 Pek. Galian Tanah Sloof 15/20 11.64 m3 24,400.00 283,894.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 6.52 m3 127,600.00 831,633.00
7 Pek. Urugan Tanah Peninggian Bangunan t=20 cm(Tanah dari luar) 217.27 m3 155,740.00 33,836,851.10
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 13.74 m3 11,710.00 160,836.85

JUMLAH - I 37,063,074.23
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 93.08 m3 600,240.00 55,870,339.20
2 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 5.35 m2 109,795.28 587,843.93
3 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 1.40 m3 4,790,681.10 6,706,953.54
4 Beton Sloof SL2 15/25 6.98 m3 4,078,216.72 28,470,030.92
5 Pek. Beton Pedistal Tiang Pagar lapangan, net, dan tiang basket 0.45 m3 4,790,681.10 2,155,806.50

JUMLAH - II 93,790,974.09
SUB TOTAL STRUKTURE 130,854,048.32
IV. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 55.10 m3 109,795.28 6,049,719.93
2 Lantai kerja t = 5 cm 27.55 m2 217,530.80 5,992,973.54
3 Pek. Beton bertulang untuk Lantai 1 : 2 : 3 untuk lantai, dengan pembesian 75 kg 66.12 m2 5,620,695.20 371,640,366.31
4 Pek. Plesteran beton 1 PC : 3 Ps, tebal 15 mm 722.00 m' 50,827.90 36,697,743.80

JUMLAH - IV 420,380,803.58
V. PEKERJAAN FINISHING & PENGECATAN
1 Pek. Cat Lantai 722.00 m2 29,883.08 21,575,583.76

JUMLAH V 21,575,583.76
VI. PEKERJAAN BESI DAN ALUMUNIUM
1 Pek. Tiang ring basket+ ring 2.00 ls 5,805,645.17 11,611,290.34
2 Pek. Pagar Keliling Futsal 140.00 m2 297,962.50 41,714,750.00

JUMLAH VI 53,326,040.34
SUB TOTAL ARSITEKTURE 495,282,427.68
I. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 6.00 m 44,730.00 268,380.00
- PVC dia 3 inc 6.00 m 126,806.00 760,836.00

JUMLAH - I 1,029,216.00
II. PEKERJAAN SANITARY
1 Floor drained "TOTO" 4.00 bh 60,300.00 241,200.00

JUMLAH - II 241,200.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 7,246,394.85
F. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 26.00 titik 150,000.00 3,900,000.00
Saklar 3.00 titik 24,100.00 72,300.00

SUB JUMLAH 3,972,300.00


SUB TOTAL PEK.ELEKTRIKAL 9,642,800.00
TOTAL 648,040,511.54

LAPANGAN OLAHRAGA PUTRI


VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 110.88 m2 1,000.00 1,155,000.00
2 Pek. Pembersihan Lokasi Site 110.88 m2 6,050.00 3,025,000.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 5,014,840.70


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 10.00 m1 52,739.42 527,394.25
2 Pek. Galian Tanah Pondasi Plat Setempat 0.45 m3 24,400.00 10,980.00
3 Pek. Galian Tanah Sloof 15/20 1.77 m3 24,400.00 43,188.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 1.21 m3 127,600.00 153,758.00
7 Pek. Urugan Tanah Peninggian Bangunan t=20 cm(Tanah dari luar) 31.08 m3 155,740.00 4,840,399.20
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 2.22 m3 11,710.00 25,996.20

JUMLAH - I 5,601,715.65
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 2.36 m3 600,240.00 1,416,566.40
2 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 0.60 m2 109,795.28 66,151.66
3 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 0.30 m3 4,790,681.10 1,437,204.33
4 Beton Sloof SL2 15/25 2.21 m3 4,078,216.72 9,023,054.49
5 Pek. Beton Pedistal Tiang lampu lapangan, net 0.22 m3 4,790,681.10 1,034,787.12

JUMLAH - II 12,977,764.00
SUB TOTAL STRUKTURE 18,579,479.64
IV. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 110.88 m3 109,795.28 12,174,100.65
2 Lantai kerja t = 5 cm 5.54 m2 217,530.80 1,205,990.76
3 Pek. Beton bertulang untuk Lantai 1 : 2 : 3 untuk lantai, dengan pembesian 75 kg 13.31 m2 5,620,695.20 74,786,721.99
4 Pek. Plesteran beton 1 PC : 3 Ps, tebal 15 mm 110.88 m' 50,827.90 5,635,797.55

JUMLAH - IV 93,802,610.94
V. PEKERJAAN FINISHING & PENGECATAN
1 Pek. Cat Lantai 110.88 m2 29,883.08 3,313,435.91

JUMLAH V 21,575,583.76
VI. PEKERJAAN BESI DAN ALUMUNIUM
1 Pek. Tiang 6.00 ls 1,047,875.00 6,287,250.00

JUMLAH VI 53,326,040.34
SUB TOTAL ARSITEKTURE 495,282,427.68
I. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
- PVC dia 2 inc 4.00 m 44,730.00 178,920.00
- PVC dia 3 inc 4.00 m 126,806.00 507,224.00

JUMLAH - I 686,144.00
F. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 6.00 titik 150,000.00 900,000.00
Saklar 2.00 titik 24,100.00 48,200.00

SUB JUMLAH 948,200.00


SUB TOTAL PEK.ELEKTRIKAL 6,618,700.00
TOTAL 525,495,448.02

TAMBAK, KEBUN DAN PENGELOLAAN LIMBAH


VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 1,100.00 m2 1,000.00 1,100,000.00
2 Pek. Pembersihan Lokasi Site 1,100.00 m2 6,050.00 6,655,000.00
3 Pek. Pembuatan Gudang 1.00 m2 834,840.70 834,840.70

TOTAL PERSIAPAN 8,589,840.70


A. PEKERJAAN STRUKTUR
I. PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 10.00 m1 52,739.42 527,394.25
2 Pek. Galian Tanah Pondasi Plat Setempat 1.60 m3 24,400.00 39,040.00
3 Pek. Galian Tanah Sloof 15/20 25.85 m3 24,400.00 630,740.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 11.14 m3 127,600.00 1,421,464.00
7 Pek. Urugan Tanah Peninggian Bangunan t=20 cm(Tanah dari luar) 1,072.55 m3 155,740.00 167,038,937.00
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 27.45 m3 11,710.00 321,439.50

JUMLAH - I 169,979,014.75
II. PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 103.40 m3 600,240.00 62,064,816.00
2 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 5.57 m2 109,795.28 611,559.71
3 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 1.60 m3 4,790,681.10 7,665,089.76
4 Beton Sloof SL2 15/25 25.85 m3 4,078,216.72 105,421,902.21
5 Pek. Beton Pedistal Tiang 0.95 m3 4,790,681.10 4,527,193.64

JUMLAH - II 180,290,561.32
SUB TOTAL STRUKTURE 350,269,576.07
III. PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 110.00 m3 109,795.28 12,077,480.80
2 Lantai kerja t = 5 cm 55.00 m2 217,530.80 11,964,194.00
3 Pek. Beton bertulang untuk Lantai 1 : 2 : 3 untuk lantai, dengan pembesian 75 kg 132.00 m2 5,620,695.20 741,931,765.77
4 Pek. Plesteran beton 1 PC : 3 Ps, tebal 15 mm 1,100.00 m' 50,827.90 55,910,690.00
5 Pek. Bak kontrol 6.00 ls 109,795.28 658,771.68

SUB TOTAL PEK. LANTAI 822,542,902.25


IV. PEKERJAAN BESI DAN ALUMUNIUM
1 Pek. Rangka baja ringan 320.00 m2 325,600.00 104,192,000.00

JUMLAH VI 104,192,000.00
V. PEKERJAAN ATAP
1 Pek. Penutup Atap 320.00 m3 91,615.00 29,316,800.00
2 Pek.. Kerpusan 55.00 m2 35,123.84 1,931,811.20
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

JUMLAH V 31,248,611.20
SUB TOTAL ARSITEKTURE 957,983,513.45
VI. PEKERJAAN INSTALASI AIR BERSIH
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 40.00 m 20,592.00 823,680.00
- PPR dia 3/4 inc 90.00 m 82,323.00 7,409,070.00
- PPR dia 1 inc 20.00 m 29,502.00 590,040.00
b. Valve (Class 125 psi) -
- Gate valve dia 3/4 inc 1.00 unit 100,000.00 100,000.00
- Gate valve dia 1 inc 1.00 unit 160,000.00 160,000.00

JUMLAH - VI 9,082,790.00
VII. PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 50.00 m 44,730.00 2,236,500.00
- PVC dia 3 inc 115.00 m 126,806.00 14,582,690.00

JUMLAH - VII 686,144.00


SUB TOTAL INSTALASI AIR 9,768,934.00
VIII. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 1.00 bh 325,000.00 325,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 1.00 set 80,500.00 80,500.00
Output
- MCB 1P 16A 2.00 bh 70,000.00 140,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 5,670,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 8.00 titik 150,000.00 1,200,000.00
Saklar 2.00 titik 24,100.00 48,200.00

SUB JUMLAH 1,248,200.00


SUB TOTAL PEK.ELEKTRIKAL 6,618,700.00
IX. PEKERJAAN KOLAM
1 1 m² Pasang Dinding Bata merah tebal 1 bata, 1 PC : 2 Ps 135.00 m2 414,642.00 55,976,670.00
2 1 m² Plesteran 1 PC : 2 Ps, tebal 15 mm 270.00 m2 43,368.30 11,709,441.00
3 Terpal 165.00 m2 550,000.00 90,750,000.00
4 Besi Waremesh m8 36.00 lbr 650,000.00 23,400,000.00
5 Terpal Bulat Diameter 3m 18.00 ls 800,000.00 14,400,000.00
6
SUB JUMLAH 196,236,111.00
TOTAL 1,529,466,675.21

AREA GAZEBO
VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran kembali lokasi site 618.00 m2 1,000.00 618,000.00
2 Pek. Pembersihan Lokasi Site 618.00 m2 6,050.00 3,738,900.00

TOTAL PERSIAPAN 4,356,900.00


II. PEKERJAAN STRUKTUR
A PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 216.00 m1 52,739.42 527,394.25
2 Pek. Galian Tanah Pondasi Plat Setempat 2.40 m3 24,400.00 39,040.00
3 Pek. Galian Tanah Sloof 15/15 7.38 m3 24,400.00 630,740.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 5.92 m3 127,600.00 1,421,464.00
7 Pek. Urugan Tanah Peninggian Bangunan t=55 cm(Tanah dari luar) 402.72 m3 155,740.00 167,038,937.00
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 9.78 m3 11,710.00 321,439.50

JUMLAH - A 169,979,014.75
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
B PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 9.84 m3 600,240.00 5,906,361.60
2 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 2.96 m2 109,795.28 324,994.03
3 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 2.40 m3 4,790,681.10 11,497,634.64
4 Beton Sloof SL2 15/25 5.54 m3 4,078,216.72 22,572,929.55

JUMLAH - B 40,301,919.81
SUB TOTAL STRUKTURE 210,280,934.56
III. PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING
1 Pek. Pasang bata 1pc : 6ps 444.00 m2 384,779.80 170,842,231.20
2 Pek. Plesteran 1pc : 5 ps tebal 15mm 444.00 m3 37,542.80 16,669,003.20

JUMLAH - A 187,511,234.40
B PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 73.80 m3 109,795.28 8,102,891.66
2 Lantai kerja t = 5 cm 36.90 m3 217,530.80 8,026,886.52
3 Pek. Pasangan batu alam 444.00 m2 561,186.50 249,166,806.00

JUMLAH - B 265,296,584.18
C PEKERJAAN KAYU
1 Pek. Tiang gazebo 1.44 m3 4,206,395.17 6,057,209.05
2 Pek.Balok gazebo 3.60 m4 4,206,395.17 15,143,022.62
3 Pek.lantai kayu gazebo 74.40 m2 204,108.50 15,185,672.40

JUMLAH C 36,385,904.06
D PEKERJAAN ATAP
1 Pek. Pek. Rangka atap Kayu 186.00 m2 78,213.93 14,547,790.53
2 Pek.Penutup atap 186.00 m2 102,580.00 19,079,880.00
3 Pek.Lisplang 54.00 m2 72,390.10 3,909,065.40
4 Pek.Kerpusan 144.00 m 97,556.80 14,048,179.20
5 Pek. Mahkota atap 60.00 unit 50,000.00 3,000,000.00

JUMLAH D 54,584,915.13
SUB TOTAL ARSITEKTURE 543,778,637.77
VIII. PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 3.00 bh 325,000.00 975,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 80,500.00 241,500.00
Output
- MCB 1P 16A 3.00 bh 70,000.00 210,000.00
b SDP
- Panel box (800x600x250) mm 1.00 bh 2,750,000.00 2,750,000.00
- Busbar+Wiring Material 1.00 lot 1,950,000.00 1,950,000.00

SUB JUMLAH 6,126,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 2x36 W 60.00 titik 150,000.00 9,000,000.00
Saklar 24.00 titik 24,100.00 578,400.00

SUB JUMLAH 9,578,400.00


SUB TOTAL PEK.ELEKTRIKAL 15,704,900.00
TOTAL 774,121,372.33

KAMAR MANDI ASRAMA & KANAN KIRI MASJID


VOLUME SAT HARGA SATUAN TOTAL JUMLAH HARGA
NO URAIAN PEKERJAAN
(RP.) (RP.)
1 3 4 5 6=5X3
I. PEKERJAAN PERSIAPAN
2 Pek. Pembersihan Lokasi Site 657.00 m2 6,050.00 3,974,850.00

TOTAL PERSIAPAN 3,974,850.00


II. PEKERJAAN STRUKTUR
A PEKERJAAN GALIAN & URUGAN
1 Pek. Pasang Papan Bouplank 190.00 m1 52,739.42 10,020,490.66
2 Pek. Galian Tanah Pondasi Plat Setempat 12.75 m3 24,400.00 311,100.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
3 Pek. Galian Tanah Sloof 15/15 14.55 m3 24,400.00 355,020.00
5 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 11.53 m3 127,600.00 1,470,590.00
7 Pek. Urugan Tanah Peninggian Bangunan t=30 cm(Tanah dari luar) 38.40 m3 155,740.00 5,980,416.00
8 Pek. Urugan Tanah Peninggian Bangunan (Tanah bks galian) 27.30 m3 11,710.00 319,683.00

JUMLAH - A 18,457,299.66
B PEKERJAAN PONDASI, POER & SLOOF
1 Pek. Aanstamping Batukali 14.55 m3 600,240.00 8,733,492.00
2 Pek. Lantai Kerja dibawah Pondasi plat & Sloof t=5 cm 5.76 m2 109,795.28 632,695.30
3 Pekerjaan Beton Pondasi Plat Type P-1 (0.5X0.5X0,25)m 8.50 m3 4,790,681.10 40,720,789.35
4 Beton Sloof SL2 15/15 14.55 m3 4,078,216.72 59,338,053.28

JUMLAH - B 109,425,029.93
SUB TOTAL STRUKTURE 127,882,329.59
C PEKERJAAN ATAP
1 Pek. Pek. Rangka atap baja ringan 615.00 m2 325,600.00 200,244,000.00
2 Pek.Penutup atap 615.00 m2 123,750.00 76,106,250.00
3 Pek.Lisplang 2 x20 cm 260.00 m2 72,390.10 18,821,426.00
4 Pek. Kayu tiang selasar 20 x 10 cm 1.49 m3 3,392,245.17 5,037,484.08
5 Pek. Tiang besi galvanis D 2 in selasar 117.50 m 165,000.00 19,387,500.00

SUB TOTAL ATAP 319,596,660.08


III. PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING
1 Pek. Pasang bata 1pc : 6ps 900.00 m2 187,730.10 168,957,090.00
2 Pek. Plesteran 1pc : 5 ps tebal 15mm 900.00 m3 37,542.80 33,788,520.00
3 Pek. Keramik dinding 25 x 40 cm 1,296.00 m2 213,958.20 277,289,827.20
4 Pek. Dinding Roster 184.00 m2 196,296.50 36,118,556.00

JUMLAH - A 516,153,993.20
B PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t=10 cm 36.50 m3 109,795.28 4,007,527.72
2 Lantai kerja t = 5 cm 18.25 m3 217,530.80 3,969,937.10
3 Pek. Keramik 25x25 365.00 m2 169,583.20 61,897,868.00

JUMLAH - B 69,875,332.82
C PEKERJAAN PINTU JENDELA
1 Pek. Pasang pintu pvc 56.00 m3 463,200.00 25,939,200.00
2 Pek.pasang boven 56.00 m4 295,700.00 16,559,200.00

JUMLAH C 42,498,400.00
D PEKERJAAN PLAFOND
1 Pek. Rangka plafond besi hollow 365.00 m3 171,848.74 62,724,789.72
2 Pek.Plafon GRC 365.00 m4 32,397.14 11,824,956.10

JUMLAH D 74,549,745.82
SUB TOTAL ARSITEKTURE 703,077,471.84
IV PEKERJAAN MEKANIKAL & SANITARY
1 PEKERJAAN INSTALASI AIR BERSIH
a. PIPA AIR BERSIH (PPR PN 16)
- PPR dia 1/2 inc 75.00 m 20,592.00 1,544,400.00
- PPR dia 3/4 inc 175.00 m 82,323.00 14,406,525.00
- PPR dia 1 inc 30.00 m 29,502.00 885,060.00
b. Valve (Class 125 psi)
- Gate valve dia 3/4 inc 5.00 unit 100,000.00 500,000.00
- Gate valve dia 1 inc 5.00 unit 160,000.00 800,000.00
JUMLAH - I 18,135,985.00
2 PEKERJAAN INSTALASI AIR KOTOR
c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)
- PVC dia 2 inc 90.00 m 44,730.00 4,025,700.00
- PVC dia 3 inc 90.00 m 126,806.00 11,412,540.00
- PVC dia 4 inc 90.00 m 185,450.00 16,690,500.00

JUMLAH - II 32,128,740.00
3 PEKERJAAN SANITARY
a. LANTAI BAWAH
1 Floor drained "TOTO" 56.00 bh 60,300.00 3,376,800.00
2 Kran air 1/2" 56.00 bh 51,609.93 2,890,155.80
3 Washtafel Bulat + Accecories "TOTO" 16.00 bh 770,523.00 12,328,368.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
JUMLAH - III 18,595,323.80
SUB TOTAL PEK.MEKANIKAL STANDARD & SANITARY 68,860,048.80
V PEKERJAAN ELEKTRIKAL
1. PEMASANGAN PANEL
a Input
- MCCB 3P 32 A 5.00 bh 325,000.00 1,625,000.00
- Pilot Lamp Tlmq+MCB 1P 2A 5.00 set 80,500.00 402,500.00
Output
- MCB 1P 16A 5.00 bh 70,000.00 350,000.00
b SDP
- Panel box (800x600x250) mm 5.00 bh 2,750,000.00 13,750,000.00
- Busbar+Wiring Material 5.00 lot 1,950,000.00 9,750,000.00

SUB JUMLAH 25,877,500.00


4 PEMASANGAN INSTALASI PENERANGAN/LAMPU
1 Installasi
RM TL 20 W 110.00 titik 150,000.00 16,500,000.00
Saklar 28.00 titik 24,100.00 674,800.00

SUB JUMLAH 17,174,800.00


SUB TOTAL PEK.ELEKTRIKAL 43,052,300.00
TOTAL 1,266,443,660.31
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3

A. BANGUNAN GENSET & RUMAH POMPA


I. PEKERJAAN PERSIAPAN
1 Pek. Pengukuran dan Pek.Bouwplank 14.00 m1 52,739.42 738,351.94
Sub Jumlah I 738,351.94
II. PEKERJAAN TANAH
1 Pek.Galian Tanah Pondasi Menerus 16.35 m3 24,400.00 398,940.00
2 Pek.Urugan Tanah ( Tanah dari Luar ) 24.80 m3 30,250.00 750,200.00
3 Pek.Pasir Urug Bawah Pondasi t = 5 cm 3.27 m3 36,850.00 120,499.50
Sub Jumlah II 1,269,639.50
III. PEKERJAAN PASANGAN
1 Pek. Pas. Aanstamping 6.54 m3 600,240.00 3,925,569.60
2 Pek. Pas. Pondasi Batu Kali 1 : 4 14.72 m3 893,748.00 13,151,501.82
3 Pas. Pondasi Rollag Bata 1.35 m3 252,300.00 340,605.00
4 Pas. Pondasi Dudukan Genset 2.63 m3 3,377,810.00 8,866,751.25
5 Pas. Pasir Urug 6.18 m3 36,850.00 227,548.75
6 Pas. Lantai Kerja t = 3 cm 1.85 m3 223,640.00 414,293.10
7 Pas. Beton Rabat 1 : 3 : 5 6.18 m3 447,280.00 2,761,954.00
8 Pek. Slab Beton t= 10cm 6.18 m3 1,948,630.00 12,032,790.25
9 Pek. Sloof 15/20; 4D16 1.64 m3 3,342,580.00 5,465,118.30
10 Pas. Bata merah 1/2 Batu 1Pc : 5Ps 51.00 m2 53,380.00 2,722,380.00
11 Pek. Kolom 15/15 0.81 m3 4,326,860.00 3,504,756.60
12 Pek. Balok 15/20 0.42 m3 3,677,160.00 1,544,407.20
13 Pas. Plesteran dan Acian 1Pc : 5Ps 102.00 m2 28,250.00 2,881,500.00

Sub Jumlah III 57,839,175.87


IV. PEKERJAAN BESI
1 Pintu Plat besi 1/8" rangka besi siku50x50x5, kusen UNP 6,5 2.00 m2 631,875.00 1,263,750.00
2 Pek.pas. Kunci gembok 1.00 bh 20,000.00 20,000.00
Sub Jumlah IV 1,283,750.00
V. PEKERJAAN LAIN-LAIN
1 Pengecatan Tembok termasuk beton expose 0.42 m2 13,060.00 5,485.20
2 Pas. Titik Lampu 6.00 Ttk 195,000.00 1,170,000.00
3 Pas. Titik Kontak 4.00 Ttk 224,250.00 897,000.00
4 Pas. Armatur 1 x 25 Watt 4.00 bh 75,000.00 300,000.00
5 Pas. Lampu Pilot 4.00 bh 80,000.00 320,000.00
6 Pas. Saklar Ganda 2.00 bh 20,000.00 40,000.00
7 Pas. Exhaus Fan 3.00 Unit 250,000.00 750,000.00
8 BC 50 qmm 17.00 m1 25,000.00 425,000.00
9 Earthing Rood 16 x 2.500 mm 17.00 m1 25,000.00 425,000.00
10 Klem aerthing rood 35.00 bh 5,000.00 175,000.00
11 Pipa PVC 3" AW1 6.00 m1 17,880.00 107,280.00
12 Pembersihan Kembali Areal Kerja 1.00 Ls 100,000.00 100,000.00
Sub Jumlah V 4,714,765.20
Jumlah ( I + II + III + IV + V ) 65,845,682.51
B. PEKERJAAN PAGAR SAMPING DAN BELAKANG M1
I. PEKERJAAN GALIAN & URUGAN
1 Pekerjaan Pasang papan Bouwplank m' 52,739.42 -
2 Pek. Galian Tanah 189.00 m³ 24,400.00 4,611,600.00
3 Pek. Urugan Pasir 27.00 m³ 127,600.00 3,445,200.00
4 Pek. Buangan Tanah Eks Galian 175.00 m³ 31,460.00 5,505,500.00
SUB JUMLAH 13,562,300.00
II. PEKERJAAN PONDASI & BETON
1 Pek. Aanstamping Batu Kali 54.00 m³ 600,240.00 32,412,960.00
2 Pek. Pasangan Batu Kali 1 : 4 (Sekaligus Dinding Saluran Jalan) 141.75 m³ 893,748.00 126,688,779.00
3 Pekerjaan Beton Sloof 15/20 13.50 m³ 4,078,216.72 55,055,925.72
4 Pekerjaan beton Kolom Praktis 15/15 300.00 m' 93,553.18 28,065,954.00
5 Pekerjaan Beton Balok Lintle 15/20 450.00 m' 110,543.90 49,744,755.00
SUB JUMLAH 291,968,373.72
III. PEKERJAAN DINDING & FINISHING
1 Pek. Pasangan Bata 1 : 5 900.00 m² 189,390.50 170,451,450.00
2 Pek. Plester dan Acian 1 : 5 (Dinding & Kolom) 900.00 m² 37,542.80 33,788,520.00
3 Pek. Plester dan Acian Kamprotan (bagian belakang) 900.00 m² 21,500.00 19,350,000.00
4 Pek.Pasang besi siku L.50x50x5 (dudukan Kawat duri) 562.50 Kg 18,985.40 10,679,287.50
5 Pek. Pasang Kawat duri 5 baris kawat 2,250.00 m' 4,100.00 9,225,000.00
6 Pek. Pengecatan Dinding 900.00 m² 17,539.30 15,785,370.00
7 Pek. Pengecatan besi siku 108.00 m² 33,246.25 3,590,595.00
SUB JUMLAH 262,870,222.50
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
SUB TOTAL - B 568,400,896.22
TOTAL 634,246,578.73

C. PEK. PAGAR DEPAN, GERBANG & PAPAN NAMA M1


I. PEKERJAAN GALIAN & URUGAN
1 Pekerjaan Pasang Bouwplank 45.00 m' 52,739.42 2,373,274.10
2 Pek. Galian Tanah 60.78 m³ 24,400.00 1,483,032.00
3 Pek. Urugan Pasir 8.58 m³ 127,600.00 1,094,808.00
4 Pek. Urugan Tanah Kembali 30.00 m³ 11,710.00 351,300.00
5 Pek. Buangan Tanah Eks Galian 30.00 m³ 31,460.00 943,800.00
SUB JUMLAH 6,246,214.10
II. PEKERJAAN PONDASI & BETON
1 Pek. Aanstamping Batu Kali 17.16 m³ 600,240.00 10,300,118.40
2 Pek. Pasangan Batu Kali 1 : 4 (Sekaligus Dinding Saluran Jalan) 45.05 m³ 893,748.00 40,258,878.66
3 Pek. Sloof Beton 15/20 4.29 m³ 4,078,216.72 17,495,549.73
4 Pek. Kolom Praktis 15/15 96.00 m' 93,553.18 8,981,105.28
5 Pek. Balok 15/20 143.00 m' 110,543.90 15,807,777.70
6 Pek. Pondasi plat 0.6 x 0.6 x 1 m 0.72 m³ 4,790,681.10 3,449,290.39
7 Pek. Kolom 0.3 x 0.3 x 4.6 m 0.83 m³ 6,968,706.51 5,770,088.99
8 Pek. Balok 25/40 0.90 m³ 5,666,546.70 5,099,892.03

SUB JUMLAH 92,843,429.77


III. PEKERJAAN DINDING & FINISHING
1 Pek. Pasangan Bata (Dinding Pagar+Bungkus Kolom 15/15) 286.00 m² 70,000.00 20,020,000.00
2 Pek. Plester dan Acian (Dinding & Kolom) 572.00 m² 24,700.00 14,128,400.00
3 Pek. Plester dan Acian Profilan Kolom 650.00 m' 6,500.00 4,225,000.00
4 Pek. Pengecatan Dinding 572.00 m² 28,600.00 16,359,200.00
5 Pek.Pasang Dinding batu alam 76.80 m2 238,100.00 18,286,080.00
6 Pek. Pintu Gerbang (Besi Hollow 40x40&20x40) lengkap 1.00 Unit 5,000,000.00 5,000,000.00

SUB JUMLAH 78,018,680.00


SUB TOTAL - C 177,108,323.87
D. PEK. JALAN ,SALURAN & TAMAN
I. PEKERJAAN SALURAN & JEMBATAN
1 Pekerjaan Drainase Gravel U20cm+Pas Bata (Keliling Bangunan) 1,700.00 m' 160,500.00 272,850,000.00
2 Pekerjaan Drainase Gravel U20cm+Pas Bata (Saluran Kiri/Kanan/Belakang) 450.00 m' 160,500.00 72,225,000.00
3 Pekerjaan Drainase Tertutup Buist beton dia.30cm 15.00 m' 134,800.00 2,022,000.00
4 Pekerjaan Grill Tutup Saluran 60.00 m' 350,000.00 21,000,000.00
SUB JUMLAH 368,097,000.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
II. PEKERJAAN JALAN & PEDESTRIAN
1 Pekerjaan Pembenrukan Badan Jalan 5,664.30 m3 21,000.00 118,950,300.00
2 Pekerjaan Lapisan Pondasi Bawah (LPB) t= 20 cm 1,888.10 m2 48,900.00 92,328,090.00
3 Pekerjaan Lapisan Pondasi Atas (LPA) t= 10 cm 944.05 m2 21,900.00 20,674,695.00
4 Pekerjaan Lapisan Penetrasi (Lapen) t=5 cm 472.03 m2 27,300.00 12,886,282.50
5 Pekerjaan Lapisan Hotmix (AS-WC) t=5 cm 472.03 m2 101,800.00 48,052,145.00
6 Pekerjaan Pedestrian Paving Block 6 cm Natural 800.00 m2 85,400.00 68,320,000.00
7 Pekerjaan Kansteen 116.00 m' 58,800.00 6,820,800.00

SUB JUMLAH 368,032,312.50


III. PEKERJAAN TIANG BENDERA & TAMAN
1 Pasang Tiang Bendera lengkap pondasi & Accessories 2.00 Ls 2,500,000.00 5,000,000.00
2 Pekerjaan Taman
- Urugan Tanah Subur 20 cm 1,400.00 m3 75,000.00 105,000,000.00
- Tanaman Rumput Gajah 3,000.00 m2 25,000.00 75,000,000.00
- Tanaman Pohon Soka 120.00 Tnmn 2,500.00 300,000.00
- Tanaman Pohon Palm Botol 20.00 Tnmn 65,000.00 1,300,000.00
- Tanaman Ketapang Mini 100.00 Tnmn 35,000.00 3,500,000.00
- Tanaman Bougenvil 80.00 Tnmn 50,000.00 4,000,000.00
- Tanaman Pohon Bambu kecil 25.00 Tnmn 15,000.00 375,000.00
SUB JUMLAH 194,475,000.00
SUB TOTAL - D 930,604,312.50
E. PEK. ELEKTRIKAL NON STANDARD
I. PENYAMBUNGAN DAYA PLN
1 Beaya penyambungan (BP) dan Uang jaminan 1.00 Ls 65,430,465.30 65,430,465.30
langganan (UJL) untuk 42 kVA, beserta semua beaya
yang diperlukan untuk perijinan penyambungan daya
JUMLAH - I 65,430,465.30
II. PEKERJAAN PANEL AC
1 Panel PP-AC1
• Panel box (H) 600 x (W) 500 x (D) 400 mm 1.00 Bh 550,000.00 550,000.00
• MCCB in 3P, 100AF/63AT, 25kA 3.00 Bh 649,500.00 1,948,500.00
• MCB out 3P, 20A, 10 kA 3.00 Bh 300,000.00 900,000.00
• Pilot light 220 VAC c/w neon bulb & fuse 6.00 Bh 35,000.00 210,000.00
• Bare copper, 100A 1.00 set 550,000.00 550,000.00
• Instalasi 3.00 Ls 800,000.00 2,400,000.00
• Peralatan dan material bantu 3.00 Ls 800,000.00 2,400,000.00
Sub Jumlah 8,958,500.00
2 Panel PP-AC2
• Panel box (H) 600 x (W) 500 x (D) 400 mm 1.00 Bh 550,000.00 550,000.00
• MCCB in 3P, 100AF/63AT, 25kA 3.00 Bh 649,500.00 1,948,500.00
• MCB out 3P, 20A, 10 kA 3.00 Bh 300,000.00 900,000.00
• Pilot light 220 VAC c/w neon bulb & fuse 6.00 Bh 35,000.00 210,000.00
• Bare copper, 100A 1.00 set 550,000.00 550,000.00
• Instalasi 3.00 Ls 800,000.00 2,400,000.00
• Peralatan dan material bantu 3.00 Ls 800,000.00 2,400,000.00
Sub Jumlah 8,958,500.00
3 Panel PP-AB
• Panel box (H) 600 x (W) 500 x (D) 400 mm 1.00 Bh 550,000.00 550,000.00
• MCB in 3P, 25A, 10kA 3.00 Bh 622,000.00 1,866,000.00
• MCB out 3P, 10A, 10 kA 3.00 Bh 300,000.00 900,000.00
• MCB out 1P, 6A/10A, 6 kA 6.00 Bh 74,000.00 444,000.00
• Direct On Line (DOL) starter 1.00 Bh 520,500.00 520,500.00
• Pilot light 220 VAC c/w neon bulb & fuse 3.00 Bh 35,000.00 105,000.00
• Bare copper, 100A 3.00 set 550,000.00 1,650,000.00
• Instalasi 3.00 Ls 800,000.00 2,400,000.00
• Peralatan dan material bantu 3.00 Ls 800,000.00 2,400,000.00
Sub Jumlah 10,835,500.00
JUMLAH - II 28,752,500.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
III. KABEL DAYA UTAMA
Pengadaan dan pemasangan Kabel daya listrik, galian, pelindung sesuai gambar, urugan kembali.
beserta terminasi dan kelengkapan lainnya.
Dari kWh meter PLN ke MDP
- NYY 4 x 50 mm² 35.00 M¹ 160,000.00 5,600,000.00
Dari MDP ke :
- LP-OL, NYY 4 x 4 mm² 80.00 M¹ 14,800.00 1,184,000.00
- LP-A, NYY 4 x 6 mm² + NYA 6 mm2 30.00 M¹ 26,900.00 807,000.00
- LP-B, NYY 4 x 6 mm² + NYA 6 mm2 30.00 M¹ 26,900.00 807,000.00
- PP-AB, NYY 4 x 4 mm² 30.00 M¹ 14,800.00 444,000.00
- PP-AC1, NYY 4 x 10 mm² + NYA 6 mm2 20.00 M¹ 37,500.00 750,000.00
- PP-AC2, NYY 4 x 10 mm² + NYA 6 mm2 20.00 M¹ 37,500.00 750,000.00
JUMLAH - III 10,342,000.00
IV. PENERANGAN LUAR DAN GARDU
Lampu Jalan HPIT 125W, tiang 9 meter, lengan 3 mtere, pondasi 48.00 bh 2,250,000.00 108,000,000.00
terminal box.
Lampu Sorot HPI-T 125 W, dan dudukan 24.00 bh 750,000.00 18,000,000.00
Lampu Taman HPLN 80W, tiang GIP, pondasi 25.00 bh 340,000.00 8,500,000.00
terminal box.
Instalasi peneragan luar, NYFGbY 3x4mm2, dalam pipa 72.00 bh 360,000.00 25,920,000.00
PVC Hi 20mm2, ditaman di tanah, dan kelengkapannya
galian tanah dan urugan kembali
Fitting E27, Lampu PL 14 W 25.00 bh 31,600.00 790,000.00
Instalasi lampu, NYY 3x2,5mm2, dalam pipa konduit bh 180,000.00 -
PVC Hi 20mm2, inbow dos, dan kelengkapannya 45.00
Saklar ganda 36.00 bh 24,100.00 867,600.00
Outlet daya dinding dng instalasi NYM 3x2,5mm2 45.00 bh 210,000.00 9,450,000.00
dalam pipa conduit PVC Hi. dia.20mm
JUMLAH - IV 171,527,600.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
VII. SISTEM TATA SUARA
1 Mixer Pre Amplfier 4 input 6.00 bh 3,250,000.00 19,500,000.00
2 Power Amplifier 60 Watt RMS 4.00 bh 4,500,000.00 18,000,000.00
3 Dynamic Microphone dng desk stand 4.00 bh 275,000.00 1,100,000.00
4 Hand Microphone 6.00 bh 175,000.00 1,050,000.00
5 Speaker kolom 10 Watt 36.00 bh 950,000.00 34,200,000.00
6 Instalasi Speaker dng kabel NYMHY 2x2,5mm2 dlm 36.00 ttk 150,000.00 5,400,000.00
pipa konduit PVC 20mm
7 Conference system untuk ruang rapat 4.00 set 10,000,000.00 40,000,000.00
kap. 10 delegates, perkabelan dan power supllay
JUMLAH -VIII 119,250,000.00
SUB TOTAL - ELEKTRIKAL NON STANDARD 395,302,565.30
F. PEK. MEKANIKAL NON STANDARD
I. TANGKI AIR DAN PEMIPAAN AIR BERSIH
1 Tangki air fiber bulat, kapasitas 1000 liter, lengkap dengan 6.00 unit 10,801,800.00 64,810,800.00
dudukan penyangga dengan struktur besi siku
2 Pemipaan tangki air, header, gate valve, foating valve
dan drain beserta kelengkapannya sesuai gambar
• Gate valve ø 25 mm 8.00 Bh 100,000.00 800,000.00
• Gate valve ø 32 mm 8.00 Bh 150,000.00 1,200,000.00
• Gate valve ø 40 mm 8.00 Bh 200,000.00 1,600,000.00
• Gate valve ø 50 mm 8.00 Bh 250,000.00 2,000,000.00
• Header GIP ø 75 mm 8.00 Bh 600,000.00 4,800,000.00
• Floating Valve ø 40 mm 8.00 Bh 450,000.00 3,600,000.00
3 Pemipaan air bersih utama
Pengadaan dan pemasangan pipa distribusi air bersih, GIP Medium A,
Pipa dicat warna biru.Lengkap dengan fitting dan asesories yang diperlukan
Pipa utama dari Tangki atas sampai toilet
• GIP ø 40 mm dari meter air PDAM ke reservoir 45.00 m 168,600.00 7,587,000.00
• GIP ø 32 mm dari reservoir ke roof tank 45.00 m 111,500.00 5,017,500.00
• GIP ø 25 mm dari roof tank ke toilet 45.00 m 97,800.00 4,401,000.00
JUMLAH - I 95,816,300.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
II. RESERVOIR, SEPTIC TANK, RESAPAN DAN PEMIPAAN KE DRAINASE
• Septic tank kapasitas 5 m3 16.00 unit 6,071,900.00 97,150,400.00
• Bak Kontrol, 0.6mx0,6m, sesuai gambar 56.00 unit 450,000.00 25,200,000.00
• PVC AW ø 75 mm 280.00 m 30,900.00 8,652,000.00
• PVC AW ø 100 mm 280.00 m 51,900.00 14,532,000.00
JUMLAH - II 145,534,400.00
III. PENGKONDISIAN UDARA (AC)
Pemipaan refrigerant dari indoor ke outdoor
Pipa Liquid dan Gas, ukuran sesuai rekomendasi pabrik, pipa tembaga kualitas tinggi, Type L atau jenis oxidized
phosphorous seamless copper pipe, merk Crane Enfiled atau setara. Lengkap dng aseories yang diperlukan, sesuai
spesifikasi teknis. isolasi pipa refrigerant bagian gas (gas side) dengan thermaflex, bagian liquid tidak diisolasi.
1 Indoor unit Lt. 2 ke Outdoor unit masing-masing m 53,000.00 -
2 Indoor unit Lt. 1 ke Outdoor unit masing-masing m 53,000.00 -
Pemipaan pengembunan (drain) indoor
Pipa PVC AW, lengkap penggantung sesuai spesifikasi teknis, U-trap, sambungan solvent cemnet, konektor, slope 1%
Isolasi pipa pengembunan (termasuk pipa dalam dinding), dengan flexible closed cell elastomeric insulation
merk Amstrong (armaflex) atau setara.
Ukuran pipa minimal dia. 20 mm, atau sesuai rekomendasi pabrik.
3 Pipa PVC AW ø 20 mm, dng isolasi m 8,400.00 -
4 Pipa PVC AW ø 25 mm, dng isolasi m 9,900.00 -
JUMLAH - III -
SUB TOTAL - MEKANIKAL NON STANDARD 241,350,700.00
TOTAL JUMLAH NON STANDARD 2,378,612,480.41
IV. PEKERJAAN POS JAGA
I. PEKERJAAN GALIAN
1 Pek. Pasang Papan Bouwplang 6.00 m1 52,739.42 316,436.55
2 Galian tanah pondasi batu kali 7.20 m3 24,400.00 175,680.00
3 Urugan pasir urug t=10 cm 1.44 m3 127,600.00 183,744.00
SUB JUMLAH 675,860.55
II. PEKERJAAN PONDASI & BETON
1 Pekerjaan aanstamping batu kosong 2.40 m3 195,400.00 468,960.00
2 Pek. Pondasi Batu kali camp. 1Pc : 4Psr 18.00 m3 440,200.00 7,923,600.00
3 Urugan tanah ex galian pondasi 7.20 m3 8,000.00 57,600.00
4 Beton Sloof 15/20 0.72 m3 3,346,900.00 2,409,768.00
5 Beton Kolom 15/15 12.00 m1 93,553.18 1,122,638.16
6 Beton Balok Dak 15/20 0.72 m1 110,543.90 79,591.61
SUB JUMLAH 12,062,157.77
III. PEKERJAAN DINDING & PLESTERAN
1 Pasangan dinding bata 1 : 5 72.00 m2 65,400.00 4,708,800.00
2 Pekerjaan plester dan acian dinding 1 : 5 144.00 m2 22,600.00 3,254,400.00
3 Pekerjaan plester dan acian ban 1 : 2 24.00 m1 32,500.00 780,000.00
SUB JUMLAH 8,743,200.00
IV. PEKERJAAN KUSEN PINTU.JENDELA & ASESORIES
1 Pasang Pintu Type-P1 1.00 Unit 2,504,000.00 2,504,000.00
2 Jendela Type - J1 3.00 Unit 1,500,000.00 4,500,000.00
SUB JUMLAH 7,004,000.00
V. PEKERJAAN ATAP & PLAFOND
1 Pek. Kuda-kuda rangka baja ringan 15.00 m2 250,000.00 3,750,000.00
2 Pek. Penutup Atap Matal 15.00 m2 123,750.00 1,856,250.00
3 Pek. Pasdang Nok Genteng Metal 12.00 m1 127,445.00 1,529,340.00
4 Lisplang Plat GRC Lbr.30cm tebat 12 mm 15.00 m1 - -
5 Pek. Pasang Plafong Gypsum rangka Hollow 6.00 m2 250,000.00 1,500,000.00
6 Pek. Pasang Plafong GRC rangka Hollow 16.80 m2 245,000.00 4,116,000.00
7 Pek. Pasang List Plafong 24.00 m1 13,000.00 312,000.00
SUB JUMLAH 13,063,590.00
TOTAL JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN HARGA
(RP.) (RP.)
1 2 3 4 5 6=5X3
VI. PEKERJAAN LANTAI , FINISHING & PENGECATAN
1 Urugan pasir bawah lantai t=10 cm 2.40 m3 127,600.00 306,240.00
2 Lantai kerja t = 5 cm 1.20 m2 109,795.28 131,754.34
3 Pekerjaan lantai keramik 30x30 24.00 m2 206,930.80 4,966,339.20
4 Pekerjaan Pengecatan Dinding 144.00 m2 17,539.30 2,525,659.20
5 Pekerjaan Pengecatan Plafond 24.00 m2 17,539.30 420,943.20
6 Lantai Rabat t = 5 cm 0.30 m3 109,795.28 32,938.58
7 Saluran Gravel U 20 cm 6.00 m1 160,500.00 963,000.00
SUB JUMLAH 9,346,874.52
VII. PEKERJAAN INSTALASI LISTRIK
1 Titik cahaya 2.00 titik 196,260.22 392,520.44
2 Titik stop kontak 1 fasa 1.00 titik 215,886.24 215,886.24
3 Stop Kontak 1.00 bh 24,100.00 24,100.00
4 Saklar Ganda 1.00 bh 24,100.00 24,100.00
5 Pasang Lampu SL 25 watt 2.00 bh 45,000.00 90,000.00
SUB JUMLAH 746,606.68
SUB TOTAL - A 51,642,289.52

Anda mungkin juga menyukai