SUMBER BIAYA
NO RENCANA KEGIATAN VOLUME SATUAN HARGA SATUAN JUMLAH BIAYA
BANTUAN SWADAYA
1. BAHAN
1.1 BATU BELAH 12 M³ 175,000 2,100,000 2,100,000
1.2 BASE CORSE 18 M³ 150,000 2,700,000 2,700,000
1.3 BATU SPLIT 2/3 25 M³ 225,000 5,625,000 5,625,000
1.4 BATU SPLIT 1/2 15 M³ 225,000 3,375,000 3,375,000
1.5 ABU BATU 10 M³ 175,000 1,750,000 1,750,000
1.6 ASPAL 15 DRUM 1,700,000 25,500,000 25,500,000
1.7 KAYU BAKAR 7 M³ 75,000 525,000 525,000
SUB TOTAL 1 38,950,000 2,625,000 41,575,000
2. ALAT
2.1 STOOM WALLS 5 Hari 600,000 3,000,000 3,000,000
2.2 MOBILISASI STOOM 2 Jalan 1,500,000 3,000,000 3,000,000
2.4 TALI RAPIA 1 Roll 20,000.00 20,000 20,000
2.5 SKOP 2 Buah 120,000 240,000 240,000
2.6 CANGKUL 3 Buah 75,000 225,000 225,000
2.7 PENGKI 3 Buah 25,000 75,000 75,000
2.8 MARTIL 5 Kg 2 Buah 120,000 240,000 240,000
SUB TOTAL 2 6,000,000 800,000 6,800,000
3. UPAH KERJA
MANDOR 5 HOK 100,000 500,000 500,000.00
PEKERJA TUKANG X 15 75 HOK 75,000 4,050,000 1,575,000 5,625,000.00
SUB TOTAL 3 4,550,000 - 6,125,000
TOTAL (1+2+3) 49,500,000 3,425,000 54,500,000.0
RENCANA ANGGARAN BIAYA (RAB)
PENGASPALAN JALAN KP. CIPADALI RW.20
DESA CIKALONG KECAMATAN CIKALONGWETAN