SUBMIT PLAN 7 JUL-23

DOCUMENT SUBMIT
NO DOCUMENT NUMBER DOCUMENT TITLE TANGGAL KETERANGAN
STATUS PLAN
SWITCHYARD 150 KV
ELECTROMECHANIC
TPG
1 0004.PJ-SUB-TPG-E-GI-004 TPG for Clamps and Connectors AIS 150 kV 13-Jun-23 EN 7-Jul-23 Melampirkan type test terbaru
2 0004.PJ-SUB-TPG-E-GI-009 TPG for Post Insulator AIS 150 kV 15-May-23 EN 7-Jul-23 Melampirkan surat keterangan sukses operasi dari PLN
3 0004.PJ-SUB-TPG-E-GI-021 TPG for 20 kV Switchgear with Panels AIS 150 kV - Bus Riser 13-Jun-23 EN 7-Jul-23 Melampirkan type test terbaru
1. Lampirkan type test terbaru
4 0004.PJ-SUB-TPG-E-GI-022 TPG for 20 kV Switchgear with Panels AIS 150 kV - Incoming 13-Jun-23 RFC 7-Jul-23
2. Lampirkan Berita Acara Energize Terbaru
5 0004.PJ-SUB-TPG-E-GI-024 TPG for 20 kV Switchgear with Panels AIS 150 kV - Local Distribution Transformer 13-Jun-23 EN 7-Jul-23 Melampirkan type test terbaru
1. Lampirkan type test terbaru
6 0004.PJ-SUB-TPG-E-GI-025 TPG for 20 kV Switchgear with Panels AIS 150 kV - Bus VT LA 13-Jun-23 RFC 7-Jul-23
2. Lampirkan Berita Acara Energize Terbaru
7 0004.PJ-SUB-TPG-E-GI-026 TPG for 110 V DC Battery AIS 150 kV 15-May-23 EN 7-Jul-23 Menyesuaikan jumlah cell dengan calculation notes
8 0004.PJ-SUB-TPG-E-GI-027 TPG for 48 V DC Battery AIS 150 kV 15-May-23 EN 7-Jul-23 Menyesuaikan jumlah cell dengan calculation notes
9 0004.PJ-SUB-TPG-E-GI-030 TPG for 110 V DC Switchboard AIS 150 kV 15-May-23 EN 7-Jul-23 Melampirkan katalog
10 0004.PJ-SUB-TPG-E-GI-031 TPG for 48 V DC Switchboard AIS 150 kV 15-May-23 EN 7-Jul-23 Melampirkan katalog
1. Busbars cross section area agar disesuaikan dengan kontrak
11 0004.PJ-SUB-TPG-E-GI-033 TPG for 400/230 VAC Switchboard AIS 150 kV 15-May-23 RFC 7-Jul-23 yaitu 40 x 10 mm2
2. Agar dilampirkan katalog

CALCULATION
1 0004.PJ-SUB-CAL-E-GI-002 Calculation for Current Transformer Belum submit Belum submit
1. Transiend and instantaneous load agar diasumsikan menjadi
the end of 7 hours
2. Load list pada bay agar ditambahkan local mimic
3. Agar ditambahkan beban sisi 20 KV (Incoming, outgoing, Bus
section, dan SAS 20 KV)
2 0004.PJ-SUB-CAL-E-GI-003 Calculation for 110 V DC Battery & Charger 19-Jun-23 RFC 7-Jul-23 4. Battery instantaneous load agar dibuat perhitungan first trip,
first closing, dan final trip
5. Discharge load profile dibuat beban konstan dan beban
inverter selama 8 jam
6. Agar digambarkan Grafik discharge load profile untuk instant
load pada 2 jam pertama selama 1 menit
1. Transiend and instantaneous load agar diasumsikan menjadi
3 0004.PJ-SUB-CAL-E-GI-004 Calculation for 48 V DC Battery & Charger 19-Jun-23 RFC 7-Jul-23 the end of 7 hours
2. Load list agar ditambahkan IP Phone
4 0004.PJ-SUB-CAL-E-GI-005 Calculation for Inverter 19-Jun-23 RFC 7-Jul-23 Agar ditambahkan load gateway, monitor, dan GPS

150 kV SINGLE LINE DIAGRAM


1. Rated nominal current Circuit Breaker pada bay
transformator agar disesuaikan dengan TPG
1 0004.PJ-SUB-SLD-E-GI-001 150 KV Single Line Diagram 29-May-23 RFC 7-Jul-23
2. Class dan core CT pada Bay Coupler agar disesuaikan dengan
TPG

LV AC/DC SYSTEM
Untuk supply AC/DC agar dikelompokkan sesuai dengan hasil
1 0004.PJ-SUB-LVS-E-GI-001 Single Line Diagram LV AC System 19-Jun-23 RFC 7-Jul-23
DRM terakhir
2 0004.PJ-SUB-LVS-E-GI-002 400 / 230 V AC Distribution Board Belum submit Belum submit 7-Jul-23
3 0004.PJ-SUB-LVS-E-GI-003 110 V DC Distribution Board Belum submit Belum submit 7-Jul-23
4 0004.PJ-SUB-LVS-E-GI-004 48 V DC Distribution Board Belum submit Belum submit 7-Jul-23
5 0004.PJ-SUB-LVS-E-GI-007 Rectifier 110 V DC Belum submit Belum submit 7-Jul-23
6 0004.PJ-SUB-LVS-E-GI-008 Rectifier 48 V DC Belum submit Belum submit 7-Jul-23

HV EQUIPMENT
1 0004.PJ-SUB-HVE-E-GI-008 Technical Drawing for Power Transformer Belum submit Belum submit 7-Jul-23

EARTHING SYSTEM
Untuk customer scope menjadi satu kesatuan dengan item NGR
1 0004.PJ-SUB-GRD-E-GI-004 Assembly and Detail Drawing for 20 kV Neutral Grounding Resistors 13-Jun-23 EN 7-Jul-23
dalam BOQ dan tidak menjadi kerja tambah

STRING INSULATOR
1 0004.PJ-SUB-SIN-E-GI-001 Detail Drawing for Disc Insulator Belum submit Belum submit 6-Jul-23
2 0004.PJ-SUB-SIN-E-GI-002 Assembly and Detail Drawing for String Insulator Belum submit Belum submit 6-Jul-23
3 0004.PJ-SUB-SIN-E-GI-003 Assembly and Detail Drawing for Clamp and Connector Belum submit Belum submit 7-Jul-23

CCTV SYSTEM
1 0004.PJ-SUB-CTV-E-GI-001 CCTV Layout 13-Jun-23 RFC 7-Jul-23 Menyesuaikan posisi CCTV
2 0004.PJ-SUB-CTV-E-GI-002 CCTV Single Line Diagram 13-Jun-23 RFC 7-Jul-23 Menyesuaikan dengan perubahan layout CCTV

CIVIL / STRUCTURE
SITE PREPARATION
1 0004.PJ-SUB-PRE-C-GI-004 Retaining Wall Layout and Detail Belum submit Belum submit 6-Jul-23

CALCULATION
Koordinasi dengan REN UIP apakah masih perlu submit karena
1 0004.PJ-SUB-CAL-C-GI-002-1 Calculation for Control Building Foundation Belum submit Belum submit
control building foundation sudah NEN
2 0004.PJ-SUB-CAL-C-GI-019 Calculation for Drainage Belum submit Belum submit Koordinasi dengan REN UIP apakah perlu submit

SUTT SUBANG - INCOMER


GENERAL
ROUTE
1 0004.PJ-SUB-INC-GEN-G-TL-004 Diagonal Profile Belum submit Belum submit 7-Jul-23

CIVIL / STRUCTURE
MISCELLANEOUS
1 0004.PJ-SUB-INC-MSC-C-TL-001 Tower Name Plate Belum submit Belum submit 7-Jul-23
2 0004.PJ-SUB-INC-MSC-C-TL-002 Danger Plate Belum submit Belum submit 7-Jul-23

TOTAL DRAWING 35