PROPOSAL

CLAIM PACKAGE III

FIXED TYPE GAS ENGINE POWER PLANT PACKAGE III


PLTMG LANGGUR 20 MW

PERJANJIAN KONTRAK
No. 0177.PJ/DAN.02.01/DIR/2017
TANGGAL 18 MEI 2017

KONSORSIUM
PT WIJAYA KARYA (Persero) Tbk -
PT WIJAYA KARYA REKAYASA KONSTRUKSI
SEPTEMBER 2020
ROPOSAL
CLAIM PACKAGE III

FIXED TYPE GAS ENGINE POWER PLANT PACKAGE III


PLTMG LANGGUR 20 MW

PERJANJIAN KONTRAK
No. 0177.PJ/DAN.02.01/DIR/2017
TANGGAL 18 MEI 2017

KONSORSIUM
PT WIJAYA KARYA (Persero) Tbk -
PT WIJAYA KARYA REKAYASA KONSTRUKSI
SEPTEMBER 2020
DAFTAR ISI

BAB I KATA PENGANTAR...................................................................................

BAB II CLAIM PACKAGE III …………………………......................................................

A. PENAMBAHAN AIR INSTRUMENT TANK PADA COMPRESSED AIR SYSTEM


1. Dasar Pertimbangan .........................................................................
2. Korespondensi……………………............................................................
3. Referensi………………………………..........................................................
4. Dasar Pengajuan Claim/Justifikasi…..……………………….......................
5. Dasar Perhitungan ............................................................................

BAB III KESIMPULAN...............................................................................................


BAB I
KATA PENGANTAR
BAB I
KATA PENGANTAR

Penjanjian Kontrak No. 0177.PJ/DAN.02.01/DIR/2017 Proyek Mobile Power Plant and Fixed
Type Gas Engine Power Plant Package III (Fixed Power Plant), meliputi:
a) PLTMG Tanjung Selor 15 MW
b) PLTMG Biak 15 MW
c) PLTMG Merauke 20 MW
d) PLTMG Seram Peaker 20 MW
e) PLTMG Langgur 20 MW

telah ditanda tangani pada 18 Mei 2017 antara PT PLN (Persero) sebagai Pemilik Pekerjaan dan
Konsorsium PT Wijaya Karya (Persero) – PT Wijaya Karya Rekayasa Konstruksi sebagai
Kontraktor.

Butir 7 dari Perjanjian Kontrak tersebut di atas mengatur tentang : Tanggal Effektif Kontrak atau
tanggal dimana Kontrak telah mempunyai kekuatan hukum, yaitu pada saat prasayarat-prasayarat
di bawah ini tercapai:

1. Kontrak telah ditandatangani dan


2. Konfirmasi dari Pemilik Pekerjaan bahwa semua Site telah diserah terimakan untuk
konstruksi.

Selama masa konstruksi, terdapat beberapa hal, yang berubah terhadap isi kontrak, yaitu :
1. Penambahan Air Instrument Tank pada Compressed Air System

Sehubungan dengan hal-hal tersebut di atas, maka Kontraktor mangajukan proposal Claim ini,
beserta impact yang menyertainya.
BAB II
CLAIM PACKAGE III
PT PLN (PERSERO)
CLAIM
UNIT INDUK PEMBANGUNAN MALUKU
PLTMG LANGGUR 20 MW PROPOSAL
CP No. : CL-ME-LGR-011 Tanggal CP : 30/09/2020
Perihal : Penambahan Air Instrument
Tank pada Compressed Air
System
Nama Proyek : Fixed Type Gas Engine Power No. Kontrak : 0177.PJ/DAN.02.01/DIR/2017
Plant Package III – PLTMG Tanggal 17 Mei 2017
Langgur 20 MW T
No. Proyek : Sub Total : Rp 17.940.000
Proposal
Claim
Lokasi : PLN, PLTMG 20 MW, Desa
Dullah, Kecamatan Dullah
Utara, Kota Tual, Maluku
Tenggara.
Kepada ORIGINAL : PLN Kontraktor
PT PLN (Persero) Diajukan : A.A.N Angga Okadinata
Unit Induk Pembangunan Maluku Oleh
Jabatan : Project Director
Dasar Pertimbangan
Contract Book II Part 4 Technical Requirement Section 4.2 Summary of Work

a. Contract Book III Part 4 Technical Requirement Section 4.5 Mechanical Works
The compressed air system shall have a connection to air starting system. The air starting
system can supply to compressed air system. The compressed air system may also be used
as control air for instrumentation.
b. Contract Book I Part 2 General Conditions of Contract. 2.1 Definition
'Variation' means any modifications to the Works, approved by the Owner, which cause an
increase or decrease in the cost of, or the time required for, the execution of the Contract or part
thereof.

Korespondensi/Referensi yang berkaitan


1. ENG-DED- LGR-PR-03-SCA-010_REV.1 EQUIP SIZING OF COMPRESSED AIR SYSTEM_STATUS A
2. Specification instrument tank.
3. PID compress Air System No. ENG-DED-LGR-PR-52-SCA-006_Rev.2
DASAR CLAIM/JUSTIFIKASI
1. Berdasarkan Contract Book III Part 4 Technical Requirement Section 4.5 Mechanical Works, PLN
mensyaratkan bahwa untuk kebutuhan instrument bisa diambil dari tangki starting.
2. Berdasarkan Design proposal yang ditunjukkan di book 5 of 5 section 7.2.4 compressed air system,
kontraktor tidak mensupply instrument tank, karena secara teknis untuk kebutuhan instrument air bisa
langsung diambil dari tangki starting air dengan menambah pressure reducer valve.
3. Berdasarkan document ENG-DED-LGR-PR-03-SCA-010_REV.1 EQUIP SIZING OF COMPRESSED AIR
SYSTEM_STATUS A, untuk kebutuhan instrument dan service sudah ditambahkan ke design perhitungan
untuk kapasitas air starting tank.
4. Berdasar butir 1, 2 dan 3, kontraktor meminta claim atas kelebihan supply untuk tank instrument sebesar
0.5 m3 plus accesoris yang terpasang sesuai dengan specification instrument tank dan PID compress Air
System No. ENG-DED-LGR-PR-52-SCA-006_Rev.2

RINGKASAN BIAYA
Proposal Biaya Claim : Rp 17.940.000