KEGIATAN DOKUMEN KETERANGAN

MULAI Penyiap (Prepare) Dokumen


1. Central Workshop
2. PMO
3. Engineering Design
CENTRAL WORKSHOP FORM PP
Menerima WO dan (Project Proposal) Penyetuju (Approved Dokumen)
Mengisi Project Proposal 1. Grup Manager Bangsal Aceh
CENTRAL WORKSHOP
2. Sr Manager Proyek
3. Head of Downstream
Merevisi Dokumen
GRUP MANAGER BANGSAL
ACEH

Approved Dokumen Routing & Distribution Dokumen


1. PMO

Sr MANAGER PROYEK
Distribution Dokumen to :
1. Grup Manager Bangsal Aceh
Approved Dokumen PMO 2. Sr Manager Proyek
PMO BERKOORDINASI 3. Procurement
DENGAN CENTRAL 4. Head of DS
WORKSHOP
HEAD OF DS

Recording Dokumen
Approved Dokumen
1. PMO
YES

NO
SETUJU Revisi ?

YES

Engineering Dept

Site Survey

DOKUMEN TENDER
1. BoQ
Engineering Dept
2. Gambar For - Tender
Dokumen Tender 3. Spesifikasi TEknis
4. TOR

Sr Manager Proyek

Approval Dok Tender

NO

PMO FORM PR
(Project Request)
Isi Form PR

PMO

Distribusi Dokumen
Tender

Procurement

Proses Tender

Procurement

SPK Release

SELESAI
PROJECT PROPOSAL (PP)

No PP : ( ) Baru ( ) Revisi____
Tanggal :
Nama Pekerjaan :
Estimasi Selesai Pekerjaan :
Lokasi Proyek :
Biaya Pekerjaan : Budget / Non Budgeted
Deksripsi Proyek : (Dituliskan secara detail Deskripsi Proyek yang akan dilakukan)
1.
2.

LINGKUP KERJA: (SCOPE OF WORK)

LAMPIRAN (JIKA ADA):

1.

2.

DIAJUKAN DISETUJUI DIKETAHUI

(DEDE DERMAWAN) (HENDRI CANDRA) (WILLY SUSANTO) (STANLEY SYAMTORI)


MANAGER CENTRAL GRUP MANAGER SENIOR MANAGER
HEAD OF DOWNSTREAM
WORKSHOP BANGSAL ACEH PROJECT