Temuan Inspeksi PJ-TEK

Rekomendasi Instalasi
Item Instalasi EPF SOW Status Tipe PIC
A1 Dokumen EPF Westkampar
1 Penelaahan Design / Basic Design B close Dokumen Rohim
2 Procedure/Manual : B
a Emergency Evacuation Procedure, A close Dokumen Wawan/Hanif
b Pre-Com & Commisioning Procedure B Dokumen Bayu/Arief
c Start-up Operational Procedure B Dokumen Bayu/Arief
d Piping hydrotest B Dokumen Bayu/Arief
e filling & dewatering Procedure B Dokumen Bayu/Arief
3 Drawing :
a Civil & Stucture drawing, B close Dokumen Tarno
b Hazardous Area Clasification, B close Dokumen Tarno
c Grounding & Lightning Protection Layout B close Dokumen Tarno
d Safe Chart B Dokumen Tarno/Wawan
e Fire & safety equipment layout B close Dokumen Tarno
f escape route layout, B close Dokumen Tarno/Wawan
g Instrument Diagram B close Dokumen Tarno
4 RKL/RPL / Izin Lingkungan A close Dokumen Hanif
5 Laporan izin Lingkungan A Dokumen Hanif
6 Material Certificate dan Equipment Instrument Calibration Certificates B Dokumen Rohim
7 COI equipment B Dokumen Rohim
8 QA/QC Manual B Dokumen Rohim
9 WPS/PQR B close Dokumen Rohim
10 Welder Certificate, B close Dokumen Rohim
11 Welding Inspector Personel Certificate B close Dokumen Rohim/Laili
12 NDT Procedure, B Dokumen Sulthon
13 NDT Personel Certificate B close Dokumen Sulthon
During Construction Report (Civil, Construction, Mechanical, Electrical
14 Instrument) B Dokumen
Final Report :
15 As Built Drawing B Dokumen Tarno
16 Safety Management System (SMS) B Dokumen Wawan
17 Start Up and Operational Manual Commissioning Report B Dokumen Bayu/Arief
Item Instalasi EPF SOW Status Tipe PIC

A2 Visual Inspeksi EPF


1 Belum ada tanda jalur evakuasi ke muster point A Fisik/Visual Hanif
2 Merapihkan dan membersihkan sisa-sisa material hasil kontruksi sipil B 50% Fisik/Visual Boy
3 Muster point masih dalam tempat sementara/ semi permanent A Close Fisik/Visual Hanif
4 Jalur kabel tray masih belum tertutup B close Fisik/Visual Oky
5 Gedung panel masih dalam proses perapihan B close Fisik/Visual Boy
close
6 Jalur kabel masih terbuka pada Gedung Air compressor dan ruangan panel B Fisik/Visual Boy
Peralatan Listrik pada instalasi
B.1 Visual Inspeksi Panel LVMDP
1 Belum ada Name plate pada panel LVMDP B Fisik/Visual Rohim
2 Belum ada penamaan identifikasi Incoming generator pada panel B close Fisik/Visual Oky
3 Jalur kabel pada panel room masih dalam kondisi terbuka B close Fisik/Visual Boy
4 Belum ada ada Air Conditioner/pendingin ruangan panel B Fisik/Visual Boy
5 Masih dalam perapihan ruangan panel B close Fisik/Visual Boy
6 Belum ada label alarm hazard pada digital panel B close Fisik/Visual Oky
B.2 Visual Inspeksi Diesel Generator
1 Belum ada Tag No pada Generator B close Fisik/Visual Boy
2 Belum dilakukan Anchor bolts dari Skid ke Foundation pada generator B Fisik/Visual Boy
3 Kabel grounding terbuka pada 2 unit Diesel Generator B close Fisik/Visual Boy
4 Jalur kabel tray masih terbuka B close Fisik/Visual Oky

C Peralatan Putar pada instalasi EPF


Visual Inspeksi Air Compressor (AC-01A ; AC-01B)
a Belum ada Tag No yang terpasang B close Fisik/Visual Boy
b Kabel grounding terbuka B close Fisik/Visual Boy
1 Belum dilakukan Anchor Bolts dari Skid ke Foundation B Fisik/Visual Boy
d Jalur kabel masih terbuka pada gedung compressor B close Fisik/Visual Boy
Visual Loading Pump
a Memberikan Tag No pada masing masing peralatan B close Fisik/Visual Boy
b Pada 2 unit transfer pump tidak ada kabel grounding B close Fisik/Visual Boy
c Belum ada shelter pada transfer pump B close Fisik/Visual Boy
2 Belum dilakukan Anchor Bolts dari Skid ke Foundation B Fisik/Visual Boy
Item Instalasi EPF SOW Status Tipe PIC
belum terpasang piping clamp pada jalur piping pada semua piping support close
e di loading pump B Fisik/Visual Boy
Visual Diesel fire water pump Fisik/Visual
a Memberikan Tag No pada diesel fire water pump B close Fisik/Visual Boy
b Belum dilakukan Anchor Bolts dari Skid ke Foundation B Fisik/Visual Boy
c Indicator dari box panel tidak ada yang berfungsi B Fisik/Visual Oky
Visual Electric fire water pump
a Memberikan Tag No pada electric fire water pump B close Fisik/Visual Boy
b Belum dilakukan Anchor Bolts dari Skid ke Foundation B Fisik/Visual Boy
c Kabel grounding terbuka B close Fisik/Visual Boy
d Jalur kabel masih terbuka pada gedung pump B close Fisik/Visual Boy
D Vessel pada instalasi EPF
Visual Waterseal (V-102)
a Tidak ada nameplate B close Fisik/Visual Rohim
b Tidak ada tangga B Fisik/Visual
c Kabel grounding terbuka B close Fisik/Visual Boy
d Anchor bolts tidak ada B Fisik/Visual Boy
e Tidak ada support pipa B Fisik/Visual Boy
Visual Air Receiver Tank (V-201)
a Nameplate terhalang dinding bangunan B close Fisik/Visual
b Kabel grounding terbuka B close Fisik/Visual Boy
c Anchor bolts tidak ada B Fisik/Visual Boy
Visual Production Gas Boot (V-100)
a Tidak ada nameplate B close Fisik/Visual Rohim
b Kabel grounding terbuka B close Fisik/Visual Boy
c Anchor bolts tidak ada B Fisik/Visual Boy
d Tidak ada pressure gauge B close Fisik/Visual Bayu/Juwanto/Arief
Visual Test Gas Boot (V-500)
a Tidak ada nameplate B close Fisik/Visual Rohim
b Kabel grounding terbuka B close Fisik/Visual Boy
c Anchor bolts tidak ada B Fisik/Visual Boy
d Tidak ada pressure gauge B Fisik/Visual Bayu/Juwanto/Arief

E Pressure Savety Valve pada instalasi EPF


Visual PSV (PSV100)
Item Instalasi EPF SOW Status Tipe PIC
a Tidak ada Tag No B Fisik/Visual Boy
b Tidak ada name plate B Fisik/Visual rohim
c Tidak ada valve di inlet B Fisik/Visual
Visual Storage Tank (T-501, T-502, T-503, T-504 & T-505)
a Kabel grounding terbuka B close Fisik/Visual Boy
Visual Diesel Storage Tank (T-801)
a Tidak ada Tag No yang terpasang B close Fisik/Visual Boy
b Drawing tidak sesuai dengan visual B Fisik/Visual Tarno
c Tidak ada nameplate B Fisik/Visual Rohim
d Kabel grounding terbuka B close Fisik/Visual Boy
e Sambungan nozzle tidak terlapis coating B Fisik/Visual Boy
Folder File Name

PLO EPF APG West Kampar\1. Umum\ 1.b BSU-PRC-1669-RPT-015 Owner Specification

PLO EPF APG West Kampar\1. Umum\ 1.g BSU - SMK3L - P - 39 of EMERGENCY RESPONS

Closing File BSU-CIV-1669-DWG-001-00, Civil and Structural Standard Drawing (1)


Closing File BSU-PSF-1669-RPT-001 - PHA HAZID Report
Closing File BSU-ELC-1669-DWG-007 - General Layout Lighting & small power
Closing File
Closing File BSU-PPG-1669-DWG-001 - General Layout-Safety Equipment
Closing File 4.e.iii escape route layout
PLO EPF APG West Kampar\2. Gambar Teknis

Belum ada
MDR
COI APG West Kampar semua yang terdapat didalam folder tersebut

COI APG West Kampar\Wash Storage Tank - T-501 (T5CH3401) 4. LIST WPS
COI APG West Kampar\Wash Storage Tank - T-501 (T5CH3401) 5. Welder Certificate

COI APG West Kampar\Wash Storage Tank - T-501 (T5CH3401) 8. NDE Procedure
COI APG West Kampar\Wash Storage Tank - T-501 (T5CH3401) 9. NDE Personnel Register

1.g BSU - SMK3L - P - 39 of EMERGNECY RESPONS


Folder File Name

On Progress

Sudah ada layout muster point permanent

Pasang pintu + jendela

Siku + Bordes

minta ke vendor
Sticker Maker
Siku + Bordes

Pasang pintu + jendela


Sticker Maker

white marker
dynabolt + bor
pasang konduit

white marker
pasang konduit
dynabolt + bor
siku + bordes

white marker
pasang grounding + konduit
terpasang
dynabolt + bor
Folder File Name

ubolt / clamp dengan siku

white marker
dynabolt + bor

white marker
dynabolt + bor
pasang konduit
siku + bordes

pasang konduit
dynabolt + bor
ubolt / clamp dengan siku

tidak dapat diputar, nozzle mentok dinding


pasang konduit
dynabolt + bor

pasang konduit
dynabolt + bor

pasang konduit
dynabolt + bor
Tap 1/2 npt pada blind flg 2"#150
Folder File Name
white marker

unit sedang beroperasi, modif oulet line,

pasang konduit

white marker
Generate As Build

pasang konduit
painting
Temuan Inspeksi PJ-TEK
Rekomendasi Peralatan
Item Peralatan Listrik SOW Status PIC Keterangan
Dokumen Panel LVMDP
1 Design Specification / Data Sheet B
2 Procedure Test B
3 Report Test B
4 Operating & Maintenance Manual B
Visual Inspeksi Panel LVMDP
1 Belum ada Name plate pada panel LVMDP B

2 Belum ada penamaan identifikasi Incoming generator pada panel B


3 Jalur kabel pada panel room masih dalam kondisi terbuka B
4 Belum ada ada Air Conditioner/pendingin ruangan panel B
5 Masih dalam perapihan ruangan panel B
6 Belum ada label alarm hazard pada digital panel B
Dokumen Diesel Generator
1 Design Specification / Data Sheet B
2 Drawing (GA Drawing) B
3 Procedure Test B
4 Operating & Maintenance Manual B
Visual Inspeksi Diesel Generator
1 Belum ada Tag No pada Generator B

2 Belum dilakukan Anchor bolts dari Skid ke Foundation pada generator B


3 Kabel grounding terbuka pada 2 unit Diesel Generator B
4 Jalur kabel tray masih terbuka B
B Peralatan Rotating Equipment
Dokumen Air Compressor (AC-01A; AC-01B)
1 Design specification / Data Sheet B
2 Procedure Test B
3 Drawing (GA Drawing, PID) B
4 Operating & Maintenance Manual B
Visual Inspeksi Air Compressor (AC-01A; AC-01B)
1 Belum ada Tag No yang terpasang B
Item Peralatan Listrik SOW Status PIC Keterangan
2 Kabel grounding terbuka B
3 Belum dilakukan Anchor Bolts dari Skid ke Foundation B
4 Jalur kabel masih terbuka pada gedung compressor B
Dokumen Loading Pump (P-201; P-202)
1 Design Specification B
2 Drawing (GA Drawing, PID) B
3 Procedure Test B
4 Report Test B
5 Operating & Maintenance Manual B
Visual Loading Pump (P-201; P-202)
1 Memberikan Tag No pada masing masing peralatan B
2 Pada 2 unit transfer pump tidak ada kabel grounding B
3 Belum ada shelter pada transfer pump B
4 Belum dilakukan Anchor Bolts dari Skid ke Foundation B
belum terpasang piping clamp pada jalur piping pada semua piping
5 support di loading pump B
Dokumen Oil Catcher Pump (P-401) and Unload Pump (P-301)
1 Design Specification B
2 Drawing (GA Drawing, PID, SLD) B
3 Procedure Test B
4 Report Test B
Dokumen Electric fire water pump dan Diesel fire water pump
1 Belum ada Dokumen Tersedia B
Visual Electric fire water pump
1 Memberikan Tag No pada electric fire water pump B
2 Belum dilakukan Anchor Bolts dari Skid ke Foundation B
3 Kabel grounding terbuka B
4 Jalur kabel masih terbuka pada gedung pump B
Visual Diesel fire water pump
1 Memberikan Tag No pada diesel fire water pump B
2 Belum dilakukan Anchor Bolts dari Skid ke Foundation B
3 Indicator dari box panel tidak adayang berfungsi B
Dokumen Waterseal (V-102)
1 Penelusuran & sertifikat material B
Visual Waterseal (V-102)
Item Peralatan Listrik SOW Status PIC Keterangan
1 Tidak ada nameplate B
2 Tidak ada tangga B
3 Kabel grounding terbuka B
4 Anchor bolts tidak ada B
5 Tidak ada support pipa B
Dokumen Air Receiver Tank (V-201)
1 Penelusuran & sertifikat material B
2 WPS / PQR B
3 Kualifikas juru las B
4 Weldimh & NDE map / tracebility B
5 Prosedur, laporan & kualifikasi personel NDT B
6 Laporan final dimensi B
7 Prosedur, laporan/Berita acara uji hydrostatik dan kebocoran B
8 As built drawing B
Visual Air Receiver Tank (V-201)
1 Nameplate terhalang dinding bangunan B
2 Kabel grounding terbuka B
3 Anchor bolts tidak ada B
Dokumen Production Gas Boot (V-100)
1 Penelusuran & sertifikat material B
Visual Production Gas Boot (V-100)
1 Tidak ada nameplate B
2 Kabel grounding terbuka B
3 Anchor bolts tidak ada B
4 Tidak ada pressure gauge B
Dokumen Test Gas Boot (V-500)
1 Penelusuran & sertifikat material B
Visual Test Gas Boot (V-500)
1 Tidak ada nameplate B
2 Kabel grounding terbuka B
3 Anchor bolts tidak ada B
4 Tidak ada pressure gauge B
Dokumen PSV (PSV100)
1 Prosedur leak test dan poping test B
2 Report leak test dan poping test B
Item Peralatan Listrik SOW Status PIC Keterangan
Visual PSV (PSV100)
1 Tidak ada Tag No B
2 Tidak ada name plate B
3 Tidak ada valve di inlet B
Dokumen PSV (PSV500)
1 Prosedur leak test dan poping test B
2 Report leak test dan poping test B
Visual PSV (PSV500)
1 Tidak ada Tag No B
2 Tidak ada valve di inlet B
Dokumen Test Tank (T-206)
1 Dokumen belum tersedia B
Visual Test Tank (T-200)
Terdapat perbedaan serial nomer pada tag nomor aktual (T-206) dan
1 dokumen (T-200) B
2 Kabel grounding terbuka B
Visual Storage Tank (T-501, T-502, T-503, T-504 & T-505)
1 Kabel grounding terbuka B
Dokumen Diesel Storage Tank (T-801)
1 Painting( Procedure and report) B
2 Leak test (procedure and report) B
3 NDE Procedure, NDE report, NDE personel register B
4 Report (Visual report, Dimensional report) B
5 Welding history summary B
6 Fit up report B
7 Weld map B
8 Material (tracebility map, Receiving record) B
9 Welder certificate B
10 List wps B
11 Nameplate B
12 Pad eye design calc. B
13 Mechanical calc. B
14 G.A drawing B
15 MDR B
Visual Diesel Storage Tank (T-801)
Item Peralatan Listrik SOW Status PIC Keterangan
1 Tidak ada Tag No yang terpasang B
2 Drawing tidak sesuai dengan visual B
3 Tidak ada nameplate B
4 Kabel grounding terbuka B
5 Sambungan nozzle tidak terlapis coating B