Y R X

2.5 50 0.14 357.1429 0.99 353.5714 883.9286 8839.286 10


3.3 50 0.14 357.1429 0.99 353.5714 1166.786 8839.286 7.575758
TEBAL BB (m) Dip (α) Pit Limit (m) SR
1 10 13 1 5

X 73.726663655 M
R 74.864016281 M

β 60
Y 7.5055534995

TEBAL α

PIT LIMIT
R
0.174533 0.174 1.047197551 1.732050808
0.985

Luas BB Panjang BB BJ Tonase


Luas BB 74.86 500 1.3 48,662 38,929
Luas OB 1 479
Luas OB 2 48.79
Luas OB Total 528.0094115
Tonase BB 97.32322117 500 48,662 38929.28847

No. Nama Seam Panjang (m) Lebar (m) Tebal (m)


1 SEAM A 60 74.86401628 2.46
2 SEAM B 1900 87 3.30
3 SEAM C 2200 100 2.00

5943 1.3 10043.67


5943 2.7 20859.93
30903.6 24722.88
Berat Jenis Tonase S/R
1.3 14364.91
1:5
1.3 709137
1.3 572000 1:11
PERHITUNGAN CADANGAN DAN STRIPING RATIO SEAM BATUBARA THE BERAU BAHAGIA

Lebar (m) Pit


No. Nama Seam Panjang (m) Tebal (m) Berat Jenis Tonase
Limit 50m

1 SEAM 1 1700 90 0.90 1.3 179,010


2 SEAM 2 1900 90 3.30 1.3 733,590
3 SEAM 3 2200 100 2.00 1.3 572,000
2 SEAM 4 1000 90 2.60 1.3 304,200
3 SEAM 5 1000 90 2.00 1.3 234,000
Total Cadangan 2,022,800
E BERAU BAHAGIA

S/R

1:5
1:10
1:8
1:10