Data Teknis :
PLV (P2) pada sta 0+400 di elevasi 2450 m
PPV (P3) pada sta 0+600 di elevasi 2450 m
PTV (P4) pada sta 1+800 di elevasi 2450 m
Elevasi : 2450 m
VR : 60 km/jam
S JPH : 87,143 m
S JPM : 387,911 m
Menentukan G1 dan G2
G1 = ( EI PPV – EI PLV ) / Jarak x 100%
= (2450 – 2450)/ 100 x 100%
=0%
G2 = ( EI PPV – EI PTV ) / Jarak x 100%
= (2450 – 2450) / 100 x 100%
=0%
Perhitungan Kelandaian :
A = |G1 – G2 |
=|0–0 |
=0%
Perhitungan LV berdasarkan Jarak Pandang Henti (JPH)
1. Untuk S < LV
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
LV =
,
=
=0m
S < LV = 87,143 > 19,080 ( tidak memenuhi)
LV =
( , )
=
=0m
S < LV = 387,911>156,745 (tidak memenuhi)
LV =
=0m
LV berdasarkan syarat drainase :
LV = 50 x A
= 50 x 0
=0m
LV berdasarkan syarat kenyamanan :
LV = 3 x
,
=3x
,
= 50 m
Maka LV yang diambil adalah 50 m.
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
E=
=0
1. PLV
STA = 0+600- x 50
= 0+575
Elevasi = 2450 - x 50 x 0
= 2450 m
2. PPV
STA = 0+600
Elevasi = 2450 + E
= 2450 + 0
= 2450 m
3. PTV
STA = 0 + 600+ ( x 50)
= 0 + 625
Elevasi = 2450 + ( x 50x 0)
= 2450 m
∗
y=
∗
x = ¼ LV
= ¼ (50)
= 12,5 m
∗
y=
∗
∗ ,
=
∗
= 0m
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
x = ¼ LV
STA = 0+600 - x 50
= 0+587,5
Elevasi = 2450– (¼ x 50x 0,0122)
= 2449,847 m
x = ¾ LV
STA = 0+600 + (3/4 x 50)
= 0+637,5
Elevasi = 2450 + (3/4 x 50 x 0,0306)
= 2451,147 m
0% -2,5%
PLV PTV
%
PPV
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
LV =
( , )
, ,
=
( , , )
= 8,934 m
S < LV = 87,143 >8,934 ( tidak memenuhi)
LV =
( , )
, ( , )
=
( , , )
= 50,916 m
S < LV = 387,911 >50,916 ( tidak memenuhi)
LV berdasarkan bentuk visual lengkung vertikal :
LV =
,
=
= 4,747 m
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
LV = 3 x
,
=3x
,
= 50 m
Maka LV yang diambil adalah 50 m.
Stationing dan Elevasi :
E=
,
=
= 0,031
1. PLV
STA = 1+200– ( x 50)
= 1+175
Elevasi = 2450+( x 50 x 0,0306)
= 2450,765 m
2. PPV
STA = 1+200
Elevasi = 2500 + E
= 2500+ 0,031
= 2500,031 m
3. PTV
STA = 1+200+( x 50)
= 1+225
Elevasi = 2400 + ( x 50 x 0,0159)
= 2400,397 m
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
∗
y=
∗
x = ¼ LV
= ¼ (50)
= 12,5 m
∗
y =
∗
, ∗ ,
=
∗
= 0,781 m
x = ¼ LV
STA = 1+200 - (¼ x 50 )
= 1+212,5
Elevasi = 2500 + (¼ x 50 x 0,0306)
= 2500,765 m
x = ¾ LV
STA = 1+200 + (3/4 x 50)
= 1+237,5
Elevasi = 2500 + (3/4 x 50 x 0,0159)
= 2500,596 m
1% 1%
PLV PTV
%
PPV
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
Data Teknis :
PLV (P14) pada sta 2+800 di elevasi 2000 m
PPV (P15) pada sta 3+000 di elevasi 1880 m
PTV (P16) pada sta 3+200 di elevasi 1780 m
Elevasi : 2450 m
VR : 60 km/jam
S JPH : 87,143 m
S JPM : 387,911 m
Menentukan G1 dan G2
G1 = ( EI PPV – EI PLV ) / Jarak x 100%
= (1880– 2000)/ 100 x 100%
= -1,8 %
G2 = ( EI PPV – EI PTV ) / Jarak x 100%
= (1880– 1780)/ 100 x 100%
=1%
Perhitungan Kelandaian :
A = |G1 – G2 |
= | -1,8 – 1 |
= 2,8 %
LV =
( , )
, ,
=
( , , )
= 50,030 m
S < LV = 87,143 >50,030 ( tidak memenuhi)
LV =
( , )
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
, ( , )
=
( , , )
= 285,128 m
S < LV = 387,911>285,128 (tidak memenuhi)
LV berdasarkan bentuk visual lengkung vertikal :
LV =
,
=
= 26,526 m
LV = 3 x
,
=3x
,
= 50 m
Maka LV yang diambil adalah 50 m.
Stationing dan Elevasi :
E=
,
=
= 0,175
1. PLV
STA = 3+000 – ( x 50)
= 2+975
Elevasi = 2000 + ( x 50 x 0,0306)
= 2000,765 m
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)
Tubes Geometrik Jalan Raya
2. PPV
STA = 3+000
Elevasi = 1880 + E
= 1880 + 0,175
= 1880,175 m
3. PTV
STA = 3+000+( x 50)
= 3+025
Elevasi = 1780 + ( x 50 x 0,0159)
= 1780,397 m
∗
y=
∗
x = ¼ LV
= ¼ (50)
= 12,5 m
∗
y =
∗
, ∗ ,
=
∗
= 4,375 m
x = ¼ LV
STA = 3+000 - (¼ x 50 )
= 2+987,5
Elevasi = 1880 + (¼ x 50 x 0,0306)
= 1880,765 m
x = ¾ LV
STA = 3+000 + (3/4 x 50)
= 3+037,5
Elevasi = 1880 + (3/4 x 50 x 0,0159)
= 1880,596 m
Kelompok 1 :
Bagus Kurniawan (30202000040)
Eko Muharifin (30202000061)