INFORMASI PROYEK DAN DATA TEKNIS
Keterangan :
9
3 1. Bendungan Utama (main dam)
2. Bangunan Pelimpah (spillway)
1 3. Bangunan Pelimpah Samping (side
spillway)
2 4. Menara Pengambilan (Intake Tower)
11
12 5. Inlet Terowongan Pengelak
6. Outlet Terowongan Pengelak
7. Entrance Gate
8. Taman View Waduk
9. Kantor UPB
10. Plaza Ceremonial Court
11. Rumah Dinas Pengelola
12. Helipad Area
6 3
PROJECT TECHNICAL INFORMATION
Keterangan :
1.1 Saddle Dam 1
1.2 Saddle Dam 2
1.3 Saddle Dam 3
Main Dam
4
PROJECT TECHNICAL INFORMATION
GRAND VIEW CONSTRUCTION AREA (SITE OF CIUYAH)
OUTLET
15
16
13
14
INLET
Keterangan :
13. Intake Tower Ciuyah
14. Inlet Ciuyah Tunnel
15. Outlet Ciuyah Tunnel
16. Booster Pump KSCS 5
PROGRES PENGADAAN TANAH
No Status Rincian
SPILLWAY
7
Debit Rencana (inflow) : 3,671 m3/s (PMF)
Saluran Transisi
Saluran Peluncur
7 Lebar : 50 m
Kemiringan :1/4
Elevasi Puncak : 67.5 m (NWL)
Panjang : 87.12 m
Lebar : 49.00 m
Kolam Olak
Panjang : 86.56 m
2 3
Lebar : 49.00 m
4 5
Keterangan :
1 1. Pelimpah samping (side spillway)
2. Pelimpah dengan Pintu Radial (gated spillway)
3. Saluran Luncur (chute way)
6 4. Kolam olak (plunge pool)
5. Saluran transisi (transition channel)
6. Terowongan pengelak (diversion tunnel)
7. Bendungan utama (main dam)
KARIAN
DAM
Intake Tower
PINTU INTAKE
Intake Structure
Connected to Tunnel No. 1
4 Gate System
Top Elevation +73,65 Back
KARIAN
DAM
River Diversion
Inlet
Lokasi : sisi kanan tebing
Diameter : 4.5 m
Dimensi : Horseshoe-shaped tunnel
Tipe : Steel sliding gate
Elevasi bawah inlet portal : Elv. 19.0 m
Elevasi bawah outlet portal : Elv. 20.0 m
Panjang Plug Concrete : 20.0 m
Pintu Diversion
- Tipe : Slide Gate
- Jumlah : 2 (dua) set
- Lebar : 4,5 m
- Tinggi : 4,5 m
- FWL : +71,00 m
- Elevasi Sill beam : +20,00 m
- Tinggi Air Desain : 6 m (Elv. 26, 00 – Elv. 20,00 m)
- Hoisting Equipment : Chain Block
- Kapasitas : 2 x 5 ton
Back
LANDSCAPE KARIAN
DAM
Dam Control Office Building (UPB)
Back 12
Kurva Kapasitas Waduk Karian DAM
A (Mm2)
20.00 18.00 16.00 14.00 12.00 10.00 8.00 6.00 4.00 2.00 -
80.00
50.00
50.00 71.94 6.26
55.00 109.90 8.92
40.00 60.00 161.30 11.64
63.00 206.04 13.93
65.00 227.69 14.94
30.00 67.50 266.68 16.26
70.00 308.98 17.58
72.50 355.73 19.83
20.00
- 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00
V (Mm3)
REALISASI S.D 06 JANUARI 2024 (elv. 49.35)
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT JENDERAL SUMBER DAYA AIR
BBWS CIDANAU-CIUJUNG-CIDURIAN
SNVT PEMBANGUNAN BENDUNGAN